BidAbstract.pdf

PDF 987 KB Posted

Attached to
Environmental Remediation Services, Stratford Army Engine Plant, Stratford, CT
Solicitation number
W912WJ21B0017
Issued by

About this file

This abstract of offers summarizes bids received in response to Solicitation Number W912WJ21B0017, issued by the U.S. Army Corps of Engineers, New England District, for environmental remediation services at the Stratford Army Engine Plant in Stratford, Connecticut. Ten contractors submitted bids for dredging and disposal of approximately 13,000 cubic yards of sediment from an outfall drainage channel to remediate metals and PCBs. The small business set-aside contract has a period of performance of 375 calendar days. Bids ranged from $3,895,000 to $11,195,044 for the base work and option quantities. The work includes mechanical dredging, dewatering and solidification of most material for on-site reuse, and off-site disposal of a portion at approved landfills. The successful contractor must complete all work within 12.5 months.

View the file

Other files

Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES 7/16/2021 8/25/2021 1 3

4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. SIGNATURE DATE SIGNED

9. OFFERS

5. PROJECT TITLE (IFB) 8. GOVERNMENT ESTIMATE NO. 1 NO. 2

(Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR

A. HIRED LABOR

B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) X (Without Profit)

6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED (Including Profit)

7A. ITEM

NUMBER

7B. DESCRIPTION OF OFFERED

ITEM

7C. EST.

QUANTITY

D.

UNIT E. UNIT PRICE

F. ESTIMATED

AMOUNT D. UNIT PRICE

E. ESTIMATED

AMOUNT D. UNIT PRICE

E. ESTIMATED

AMOUNT

Site Preparation and Restoration 1 JOB $2,561,400.00 $2,561,400.00 $3,330,000.00 $3,330,000.00 $1,825,000.00 $1,825,000.00

0002 Excavate Outfall 08 (OF-08) 1 JOB $3,753,500.00 $3,753,500.00 $2,482,000.00 $2,482,000.00 $5,300,000.00 $5,300,000.00

Service Contract Reporting Formerly known as Contractor Manpower Reporitng Application 1 JOB $1,310.00 $1,310.00 $100.00 $100.00 $10,000.00 $10,000.00

ESTIMATED TOTAL AMOUNT $6,316,210.00 $5,812,100.00 $7,135,000.00

Off-Site Disposal (RCRA D Disposal Facility)

0004AA First 5,000 Tons 5,000 TON $256.33 $1,281,650.00 $100.00 $500,000.00 $125.00 $625,000.00 00004AB Over 5,000 Tons 16,000 TON 256.33$ $4,101,280.00 $100.00 $1,600,000.00 $120.00 $1,920,000.00

ESTIMATED TOTAL AMOUNT OPTIONS $5,382,930.00 $2,100,000.00 $2,545,000.00

ESTIMATED TOTAL AMOUNT BASE+OPTION $11,699,140.00 $7,912,100.00 $9,680,000.00

W912WJ21B0017

Environmental Restoration of Outfall 008, Stratford Army Engine Plant, Stratford, Connecticut

Sevenson Environmental Services, Inc

Erin E. Bradley Bid Opening OfficerUS ARMY ENGINEER DISTRICT, NEW ENGLAND

696 VIRGINIA ROAD

CONCORD, MA 01742

N/A N/A

Loureiro Contractors, Inc

1. SOLICITATION NUMBER PAGE OF PAGES

2 3

ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.

2. PROJECT TITLE

NO. 3 NO. 4 NO. 5 NO. 6

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED A. B. C.

ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED

NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 1 JOB $3,450,000.00 $3,450,000.00 $3,590,694.00 $3,590,694.00 $2,020,000.00 $2,020,000.00 $2,500,000.00 $2,500,000.00 0002 1 JOB $2,850,000.00 $2,850,000.00 $4,452,850.00 $4,452,850.00 $1,850,000.00 $1,850,000.00 $3,490,000.00 $3,490,000.00 0003 1 JOB $25,000.00 $25,000.00 $1,500.00 $1,500.00 $25,000.00 $25,000.00 $3,360.00 $3,360.00

ESTIMATED TOTAL AMOUNT $6,325,000.00 $8,045,044.00 $3,895,000.00 $5,993,360.00

0004AA 5,000 TON $155.00 $775,000.00 $150.00 $750,000.00 $135.00 $675,000.00 $263.50 $1,317,500.00 0004AB 16,000 TON $155.00 $2,480,000.00 $150.00 $2,400,000.00 $135.00 $2,160,000.00 $135.00 $2,160,000.00

ESTIMATED TOTAL AMOUNT OPTIONS $3,255,000.00 $3,150,000.00 $2,835,000.00 $3,477,500.00

ESTIMATED TOTAL AMOUNT BASE+OPTIONS $9,580,000.00 $11,195,044.00 $6,730,000.00 $9,470,860.00

W912WJ21B0017

N/A N/A N/A

Charter Contracting Company, LLC

Environmental Restoration of Outfall 008, Stratford Army Engine Plant, Stratford, Connecticut

12 12

N/A

12 12

Lucianos Excavation, IncConti Federal Service, LLC Mohawk Northeast, Inc

1. SOLICITATION NUMBER PAGE OF PAGES

3 3

ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.

2. PROJECT TITLE

NO. 7 NO: 8 NO: 9 NO: 10

A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR

B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED A. B. C.

ITEM ESTIMATED UNIT D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED D. UNIT E. ESTIMATED

NO. QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT

0001 1 JOB $3,515,000.00 $3,515,000.00 $0.00 $0.00 $0.00

0002 1 JOB $2,060,000.00 $2,060,000.00 $0.00 $0.00 $0.00

0003 1 JOB $12,500.00 $12,500.00 $0.00 $0.00 $0.00

ESTIMATED TOTAL AMOUNT $5,587,500.00 $0.00 $0.00 $0.00

0004AA 5,000 TON $139.00 $695,000.00 $0.00 $0.00 $0.00

0004AB 16,000 TON $139.00 $2,224,000.00 $0.00 $0.00 $0.00

ESTIMATED TOTAL AMOUNT OPTIONS $2,919,000.00 $0.00 $0.00 $0.00

ESTIMATED TOTAL AMOUNT BASE+OPTIONS $8,506,500.00 $0.00 $0.00 $0.00

Environmental Restoration of Outfall 008, Stratford Army Engine Plant, Stratford, Connecticut

W912WJ21B0017

N/AN/A

Land Remediation, Inc

FRONT
CONTINUATION
CONTINUATION (2)
2021-08-26T07:02:58-0400
BRADLEY.ERIN.ELIZABETH.1386908440

File details come from the government source that posted it. Updated .