Bid Abstract- SF 1419.pdf
Standard Form PDF 2 MB Posted
- Solicitation number
- W912P725BA003
About this file
This Abstract of Offers - Construction document details bids for the San Joaquin/Port of Stockton FY25 Maintenance Dredging Project (Solicitation Number W912P725BA003). Five companies submitted bids: J.F. Brennan Company, Manson Construction Co., Curtin Maritime Corp., HME Construction, Inc., and The Dutra Group. The project involves maintenance dredging of the San Joaquin River/Port of Stockton Deep Water Ship Channel (DWSC) to specified depths, with 15 separate dredging reaches totaling approximately 134,000 cubic yards.
The government estimate for the project was $6,014,556.31, with bid prices ranging from $5,924,354.60 (Curtin Maritime Corp.) to $8,792,795 (J.F. Brennan Company). The solicitation includes line items for mobilization and demobilization plus dredging across 12 different reaches, with unit prices varying significantly between bidders. Bid security was provided by each company in the form of SF24 with 20% coverage, and all bidders acknowledged the amendments to the solicitation. The bids were opened on 05/19/2025 by the USACE San Francisco District, with the contracting officer being Mary Fronck.
View the file
Other versions and copies of SF 1419
Show all 20
Who attaches SF 1419
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 5ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED
PAGES
4. ISSUING OFFICE
5. PROJECT TITLE
6. NUMBER OF AMENDMENTS ISSUED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE DATE SIGNED
7B. DESCRIPTION OF OFFERED ITEM 7C. EST.
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
A. HIRED LABOR
B. REASONABLE CONTRACT
(Without Profit)
C. REASONABLE CONTRACT
(Including Profit)
9. OFFERS
NO. 1 NO. 2
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)
USACE, SAN FRANCISCO DISTRICT
450 GOLDEN GATE
SAN FRANCISCO CA 94102
San Joaquin/ Port of Stockton FY25 Maintenance Dredging Project
Mobilization & Demobilization
Reach 1 Dredging
Reach 2 Dredging
Reach 3 Dredging
Reach 4 Dredging
Reach 5 Dredging
Reach 6 Dredging
Reach 7 Dredging
Reach 8 Dredging
Reach 9 Dredging
Reach 10 Dredging
Reach 11 Dredging
Reach 12 Dredging
JOB
CY
CY
CY
CY
CY
CY
CY
CY
CY
CY
CY
CY
8,357
2,652
2,102
8,052
52,506
3,587
3,851
1,013
2,280
1,110
5,095
3,340
1,913,106.00
23.30
45.27
51.04
38.88
22.29
39.59
39.29
85.76
49.02
86.10
33.24
39.67
1,913,106.00
194,718.10
120,056.04
107,286.08
313,061.76
1,170,358.74
142,009.33
151,305.79
86,874.88
111,765.60
95,571.00
169,357.80
132,497.80
2,036,000.00
300,852.00
249,288.00
399,380.00
603,900.00
1,575,180.00
538,050.00
462,120.00
232,990.00
296,400.00
183,150.00
305,700.00
303,940.00
2,036,000.00
36.00
94.00
190.00
75.00
30.00
150.00
120.00
230.00
130.00
165.00
60.00
91.00
3,800,000.00
28.00
28.00
28.00
28.00
28.00
28.00
28.00
28.00
28.00
28.00
28.00
28.00
3,800,000.00
233,996.00
74,256.00
58,856.00
225,456.00
1,470,168.00
100,436.00
107,828.00
28,364.00
63,840.00
31,080.00
142,660.00
93,520.00
W912P725BA003
Mary Fronck - Contracting Officer
J.F. Brennan Company, Inc. Manson Construction Co.
SF24 and 20% SF24 and 20%
YES YES
05/19/202504/18/2025
7A.
ITEM
NO.
2 Bids 13 CLINs 3-6 Bids 13 CLINs39 CLINs26 CLINs 39 CLINs26 CLINsReset Form
Page 2 of 5ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED
PAGES
4. ISSUING OFFICE
5. PROJECT TITLE
6. NUMBER OF AMENDMENTS ISSUED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE DATE SIGNED
7B. DESCRIPTION OF OFFERED ITEM 7C. EST.
QUANTITY
D.
UNIT
E. UNIT
PRICE
F. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
A. HIRED LABOR
B. REASONABLE CONTRACT
(Without Profit)
C. REASONABLE CONTRACT
(Including Profit)
9. OFFERS
NO. 1 NO. 2
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88)
USACE, SAN FRANCISCO DISTRICT
450 GOLDEN GATE
SAN FRANCISCO CA 94102
San Joaquin/ Port of Stockton FY25 Maintenance Dredging Project
Reach 13 Dredging
Reach 14 Dredging
Reach 15 Dredging
CY
CY
CY
7,691
23,814
21,593
29.01
23.79
23.94
223,115.91
566,535.06
516,936.42
607,589.00
309,582.00
388,674.00
79.00
13.00
18.00
28.00
28.00
28.00
215,348.00
666,792.00
604,604.00
W912P725BA003
Mary Fronck - Contracting Officer
J.F. Brennan Company, Inc. Manson Construction Co.
SF24 and 20% SF24 and 20%
YES YES
05/19/202504/18/2025
7A.
ITEM
NO.
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)2. PROJECT TITLE
NO.: NO.: NO.: NO.:
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
W912P725BA003
San Joaquin/ Port of Stockton FY25 Maintenance Dredging Project
SF24 and 20% SF24 and 20% SF24 and 20%
YES YES YES
66,800.0020.0097,695.0029.2573,346.4021.96CY3,3400013
101,900.0020.00149,028.7529.25109,746.3021.54CY5,0950012
22,200.0020.0032,467.5029.2524,098.1021.71CY1,1100011
45,600.0020.0066,690.0029.2547,401.2020.79CY2,2800010
20,260.0020.0029,630.2529.2521,485.7321.21CY1,0130009
77,020.0020.00112,641.7529.2583,682.2321.73CY3,8510008
71,740.0020.00104,919.7529.2584,079.2823.44CY3,5870007
1,667,065.5031.751,942,722.0037.001,290,597.4824.58CY52,5060006
161,040.0020.00235,521.0029.25179,157.0022.25CY8,0520005
42,040.0020.0061,483.5029.2544,373.2221.11CY2,1020004
53,040.0020.0077,571.0029.2556,726.2821.39CY2,6520003
167,140.0020.00244,442.2529.25186,528.2422.32CY8,3570002
1 JOB 2,606,719.49 2,606,719.49 3,450,000.00 3,450,000.00 2,200,000.00 2,200,000.00
3 4
Curtin Maritime Corp. HME Construction, Inc. The Dutra Group
CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)2. PROJECT TITLE
NO.: NO.: NO.: NO.:
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
W912P725BA003
San Joaquin/ Port of Stockton FY25 Maintenance Dredging Project
SF24 and 20% SF24 and 20% SF24 and 20%
YES YES YES
685,577.7531.75798,941.0037.00438,337.9020.30CY21,5930016
756,094.5031.75881,118.0037.00502,951.6821.12CY23,8140015
7,691 CY 22.77 175,124.07 29.25 224,961.75 20.00 153,820.00
3 4
Curtin Maritime Corp. HME Construction, Inc. The Dutra Group
TOTALS
6,014,556.31GOVERNMENT ESTIMATE
8,792,795J.F. Brennan Company, Inc.
7,917,204Manson Construction Co.
5,924,354.6Curtin Maritime Corp.
8,509,833.5HME Construction, Inc.
6,291,337.75The Dutra Group
Page of
1. SOLICITATION NUMBER
2. DATE ISSUED
3. DATE OPENED
PAGES
4. ISSUING OFFICE
5. PROJECT TITLE
6. NUMBER OF AMENDMENTS ISSUED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE
DATE SIGNED
7B. DESCRIPTION OF OFFERED ITEM
7C. EST. QUANTITY
D. UNIT
E. UNIT
PRICE
F. ESTIMATED AMOUNT
D. UNIT
PRICE
E. ESTIMATED AMOUNT
D. UNIT
PRICE
E. ESTIMATED AMOUNT
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
A. HIRED LABOR
B. REASONABLE CONTRACT (Without Profit) C. REASONABLE CONTRACT (Including Profit)
9. OFFERS
NO. 1
NO. 2
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
AUTHORIZED FOR LOCAL REPRODUCTION Previous edition is usable NOTE: If more than two offers are received, continue on OF 1419A.
OPTIONAL FORM 1419 (11-88)
\\iaimain\apps1\Pam_Ward\Logos\Pointer.jpg
7A. ITEM NO.
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
2. DATE ISSUED
3. DATE OPENED
PAGES
4. ISSUING OFFICE
5. PROJECT TITLE
6. NUMBER OF AMENDMENTS ISSUED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE
DATE SIGNED
7B. DESCRIPTION OF OFFERED ITEM
7C. EST. QUANTITY
D. UNIT
E. UNIT
PRICE
F. ESTIMATED AMOUNT
D. UNIT
PRICE
E. ESTIMATED AMOUNT
D. UNIT
PRICE
E. ESTIMATED AMOUNT
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
A. HIRED LABOR
B. REASONABLE CONTRACT (Without Profit) C. REASONABLE CONTRACT (Including Profit)
9. OFFERS
NO. 1
NO. 2
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
AUTHORIZED FOR LOCAL REPRODUCTION Previous edition is usable NOTE: If more than two offers are received, continue on OF 1419A.
OPTIONAL FORM 1419 (11-88)
\\iaimain\apps1\Pam_Ward\Logos\Pointer.jpg
7A. ITEM NO.
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
2. DATE ISSUED
3. DATE OPENED
PAGES
4. ISSUING OFFICE
5. PROJECT TITLE
6. NUMBER OF AMENDMENTS ISSUED
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
NAME AND TITLE OF CERTIFYING OFFICIAL (Type)
SIGNATURE
DATE SIGNED
7B. DESCRIPTION OF OFFERED ITEM
7C. EST. QUANTITY
D. UNIT
E. UNIT
PRICE
F. ESTIMATED AMOUNT
D. UNIT
PRICE
E. ESTIMATED AMOUNT
D. UNIT
PRICE
E. ESTIMATED AMOUNT
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F)
A. HIRED LABOR
B. REASONABLE CONTRACT (Without Profit) C. REASONABLE CONTRACT (Including Profit)
9. OFFERS
NO. 1
NO. 2
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
A. OFFEROR
B. BID SECURITY (Type and amount)
C. AMENDMENTS ACKNOWLEDGED
AUTHORIZED FOR LOCAL REPRODUCTION Previous edition is usable NOTE: If more than two offers are received, continue on OF 1419A.
OPTIONAL FORM 1419 (11-88)
\\iaimain\apps1\Pam_Ward\Logos\Pointer.jpg
7A. ITEM NO.
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)
2. PROJECT TITLE
NO.:
NO.:
NO.:
NO.:
A. OFFEROR
A. OFFEROR
A. OFFEROR
A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)
2. PROJECT TITLE
NO.:
NO.:
NO.:
NO.:
A. OFFEROR
A. OFFEROR
A. OFFEROR
A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
ABSTRACT OF OFFERS - CONSTRUCTION
CONTINUATION SHEET
1. SOLICITATION NUMBER
PAGES
INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF 1419A) as needed.
4. OFFERS (Continued)
2. PROJECT TITLE
NO.:
NO.:
NO.:
NO.:
A. OFFEROR
A. OFFEROR
A. OFFEROR
A. OFFEROR
B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount) B. BID SECURITY (Type and amount)
3. CONTRACT ITEMS
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
C. AMENDMENTS ACKNOWLEDGED
A.
ITEM
NO.
B.
ESTIMATED
QUANTITY
C.
UNIT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
E. ESTIMATED
AMOUNT
D. UNIT
PRICE
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition is usable
OPTIONAL FORM 1419A (11-88)
TOTALS
8.2.1.3144.1.471865.466429
| CurrentPage: |
| PageCount: |
| SignatureField1: |
| 4. ISSUING OFFICE: USACE, SAN FRANCISCO DISTRICT |
450 GOLDEN GATE
SAN FRANCISCO CA 94102
| 2. PROJECT TITLE: San Joaquin/ Port of Stockton FY25 Maintenance Dredging Project |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 1 of 13.: 0001 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 2 of 13.: 0002 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 3 of 13.: 0003 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 4 of 13.: 0004 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 5 of 13.: 0005 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 6 of 13.: 0006 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 7 of 13.: 0007 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 8 of 13.: 0008 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 9 of 13.: 0009 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 10 of 13.: 0010 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 11 of 13.: 0011 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 12 of 13.: 0012 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 13 of 13.: 0013 |
| 7B. DESCRIPTION OF OFFERED ITEM: Mobilization & Demobilization |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 1 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 2 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 3 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 4 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 5 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 6 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 7 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 8 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 9 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 10 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 11 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 12 Dredging |
| 3C. CONTRACT ITEMS. UNIT: JOB |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3B. ESTIMATED QUANTITY: 1.00000000 |
| 3B. ESTIMATED QUANTITY: 8357.00000000 |
| 3B. ESTIMATED QUANTITY: 2652.00000000 |
| 3B. ESTIMATED QUANTITY: 2102.00000000 |
| 3B. ESTIMATED QUANTITY: 8052.00000000 |
| 3B. ESTIMATED QUANTITY: 52506.00000000 |
| 3B. ESTIMATED QUANTITY: 3587.00000000 |
| 3B. ESTIMATED QUANTITY: 3851.00000000 |
| 3B. ESTIMATED QUANTITY: 1013.00000000 |
| 3B. ESTIMATED QUANTITY: 2280.00000000 |
| 3B. ESTIMATED QUANTITY: 1110.00000000 |
| 3B. ESTIMATED QUANTITY: 5095.00000000 |
| 3B. ESTIMATED QUANTITY: 3340.00000000 |
| E. UNIT PRICE: 1913106.00000000 |
| E. UNIT PRICE: 29.01000000 |
| E. UNIT PRICE: 23.30000000 |
| E. UNIT PRICE: 23.79000000 |
| E. UNIT PRICE: 45.27000000 |
| E. UNIT PRICE: 23.94000000 |
| E. UNIT PRICE: 51.04000000 |
| E. UNIT PRICE: 38.88000000 |
| E. UNIT PRICE: 22.29000000 |
| E. UNIT PRICE: 39.59000000 |
| E. UNIT PRICE: 39.29000000 |
| E. UNIT PRICE: 85.76000000 |
| E. UNIT PRICE: 49.02000000 |
| E. UNIT PRICE: 86.10000000 |
| E. UNIT PRICE: 33.24000000 |
| E. UNIT PRICE: 39.67000000 |
| F. ESTIMATED AMOUNT: 1913106.00000000 |
| F. ESTIMATED AMOUNT: 194718.10000000 |
| F. ESTIMATED AMOUNT: 120056.04000000 |
| F. ESTIMATED AMOUNT: 107286.08000000 |
| F. ESTIMATED AMOUNT: 313061.76000000 |
| F. ESTIMATED AMOUNT: 1170358.74000000 |
| F. ESTIMATED AMOUNT: 142009.33000000 |
| F. ESTIMATED AMOUNT: 151305.79000000 |
| F. ESTIMATED AMOUNT: 86874.88000000 |
| F. ESTIMATED AMOUNT: 111765.60000000 |
| F. ESTIMATED AMOUNT: 95571.00000000 |
| F. ESTIMATED AMOUNT: 169357.80000000 |
| F. ESTIMATED AMOUNT: 132497.80000000 |
| F. ESTIMATED AMOUNT: 223115.91000000 |
| F. ESTIMATED AMOUNT: 566535.06000000 |
| F. ESTIMATED AMOUNT: 516936.42000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 2036000.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 300852.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 249288.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 399380.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 603900.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 1575180.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 538050.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 462120.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 232990.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 296400.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 183150.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 305700.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 303940.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 607589.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 309582.00000000 |
| 9. OFFERS. NUMBER. 1. E. ESTIMATED AMOUNT: 388674.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 2036000.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 79.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 36.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 13.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 94.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 18.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 190.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 75.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 30.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 150.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 120.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 230.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 130.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 165.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 60.00000000 |
| 9. OFFERS. NUMBER. 1. D. UNIT PRICE: 91.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 3800000.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. D. UNIT PRICE: 28.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 3800000.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 233996.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 74256.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 58856.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 225456.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 1470168.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 100436.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 107828.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 28364.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 63840.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 31080.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 142660.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 93520.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 215348.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 666792.00000000 |
| 9. OFFERS. NUMBER. 2. E. ESTIMATED AMOUNT: 604604.00000000 |
| 6. NUMBER OF AMENDMENTS ISSUED: 3 |
| 1. SOLICITATION NUMBER: W912P725BA003 |
| NAME AND TITLE OF CERTIFYING OFFICIAL (Type): Mary Fronck - Contracting Officer |
| OFFEROR1: J.F. Brennan Company, Inc. |
| OFFEROR2: Manson Construction Co. |
| 9. OFFERS. NUMBER. 1. B. BID SECURITY (Type and amount): SF24 and 20% |
| 9. OFFERS. NUMBER. 2. B. BID SECURITY (Type and amount): SF24 and 20% |
| 9. OFFERS. NUMBER. 1. C. AMENDMENTS ACKNOWLEDGED: YES |
| 9. OFFERS. NUMBER. 2. C. AMENDMENTS ACKNOWLEDGED: YES |
| 3. DATE OPENED. Enter 2 digit month, 2 digit day and 4 digit year.: 2025-05-19 |
| 2. DATE ISSUED. Enter 2 digit month, 2 digit day and 4 digit year.: 2025-04-18 |
| Enter 2 digit month, 2 digit day and 4 digit year.: |
| 8. GOVERNMENT ESTIMATE |
(Check A, B or C and complete D, E, and F). A. HIRED LABOR: 0
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F). B. REASONABLE CONTRACT (Without Profit): 0
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F). C. REASONABLE CONTRACT (Including Profit): 1
| : |
| ResetButton1: |
| IGE: 4707968.92000000 |
| IGE: 1306587.39000000 |
| IGE: 0.00000000 |
| Offer1: 7486950.00000000 |
| Offer1: 1305845.00000000 |
| Offer1: 0.00000000 |
| Offer2: 6430460.00000000 |
| Offer2: 1486744.00000000 |
| Offer2: 0.00000000 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 1 of 13.: 0014 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 2 of 13.: 0015 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 3 of 13.: 0016 |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 4 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 5 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 6 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 7 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 8 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 9 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 10 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 11 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 12 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 13 of 13.: |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 13 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 14 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: Reach 15 Dredging |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: CY |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: 7691.00000000 |
| 3B. ESTIMATED QUANTITY: 23814.00000000 |
| 3B. ESTIMATED QUANTITY: 21593.00000000 |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| SIGNATURE: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 1 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 2 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 3 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 4 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 5 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 6 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 7 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 8 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 9 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 10 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 11 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 12 of 13.: |
| 3A. CONTRACT ITEMS. ITEM NUMBER. Line 13 of 13.: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 7B. DESCRIPTION OF OFFERED ITEM: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3C. CONTRACT ITEMS. UNIT: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 3B. ESTIMATED QUANTITY: |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): SF24 and 20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): SF24 and 20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): SF24 and 20% |
| 4B. OFFERS (Continued) BID SECURITY (Type and amount): |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: YES |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: YES |
| 4C. OFFERORS (Continued) AMENDMENTS ACKNOWLEDGED.: YES |
| 4C. OFFERS (Continued) AMENDMENTS ACKNOWLEDGED.: |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 0.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: |
| 4E. OFFERS (Continued) ESTIMATED.: 66800.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 101900.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 22200.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 45600.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 20260.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 77020.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 71740.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 1667065.50000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 161040.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 42040.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 53040.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 167140.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 2200000.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 685577.75000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 756094.50000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 153820.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: 20.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 97695.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 149028.75000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 32467.50000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 66690.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 29630.25000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 112641.75000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 104919.75000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 1942722.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 235521.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 61483.50000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 77571.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 244442.25000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 3450000.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 798941.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 881118.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 224961.75000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13: 29.25000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 73346.40000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 109746.30000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 24098.10000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 47401.20000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 21485.73000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 83682.23000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 84079.28000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 1290597.48000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 179157.00000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 44373.22000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 56726.28000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 186528.24000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 2606719.49000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 438337.90000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 502951.68000000 |
| 4E. OFFERS (Continued) ESTIMATED.: 175124.07000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 13 of 13.: 21.96000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 12 of 13.: 21.54000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 11 of 13.: 21.71000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 10 of 13.: 20.79000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 9 of 13.: 21.21000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 8 of 13.: 21.73000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 7 of 13.: 23.44000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: 31.75000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13: 37.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 6 of 13.: 24.58000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 5 of 13.: 22.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 4 of 13.: 21.11000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: 31.75000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13: 37.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13.: 21.39000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 3 of 13.: 20.30000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 31.75000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13: 37.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13.: 22.32000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 2 of 13.: 21.12000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 Of 13.: 2606719.49000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 Of 13.: 22.77000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 3450000.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 29.25000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 2200000.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: 20.00000000 |
| 4D. OFFERS (Continued) UNIT PRICE. Line 1 of 13: |
| Offeror number. Column 1 of 4.: 3 |
| Offeror number. Column 2 of 4.: 4 |
| Offeror number. Column 3 of 4.: |
| Offeror number. Column 4 of 4.: |
| OFFEROR3: Curtin Maritime Corp. |
| OFFEROR4: HME Construction, Inc. |
| OFFEROR5: The Dutra Group |
| OFFEROR6: |
| Offer3: 4807940.95000000 |
| Offer3: 1116413.65000000 |
| Offer3: 0.00000000 |
| Offer4: 6604812.75000000 |
| Offer4: 1905020.75000000 |
| Offer4: 0.00000000 |
| Offer5: 4695845.50000000 |
| Offer5: 1595492.25000000 |
| Offer5: 0.00000000 |
| Offer6: 0.00000000 |
| Offer6: 0.00000000 |
| Offer6: 0.00000000 |
| NumericField1: |
| TextField1: |
File details come from the government source that posted it. Updated .