AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 6 OF 7 (PKG 1B SEC 01 50 00) JAN 22.pdf

PDF 667 KB Posted

Attached to
Amendment 0015 to Super Hornet Procurement B, Package 005 (Organizational Level Maintenance Hangar) and Package 001A/B (Base Infrastructure)
Solicitation number
W912ER21R0025
Issued by

About this file

This solicitation requests proposals for the construction of an organizational level maintenance hangar, corrosion control hangar, vehicle parking sunshades, and related site improvements at Al Jaber Air Base in Kuwait. The scope of work includes building an organizational level maintenance hangar with eight aircraft bays and associated shop spaces, as well as an adjacent corrosion control hangar with two additional aircraft bays for corrosion control and washing. Proposals are due through the ProjNet system by the date specified in the solicitation. The Department of the Army Corps of Engineers Engineering District Middle East will award the contract. Offerors should follow the instructions and terms provided in the solicitation document.

View the file

Other files

File Type Posted
A154_Amendment 0015 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0014 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0013 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2022_0106_Pkg 5_ Rev A 0013_All Drawings.pdf PDF
2021_1229_Pkg 1A_ A 0013_All Drawings.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 2 OF 7 (PKG 1A) - JAN 22.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 4 OF 7 (PKG 5) JAN 22.pdf PDF
AMENDMENT 0013 NARRATIVE - 21R0025 Superhornet Procurement B -JAN 22.pdf PDF
A154_Amendment 0012 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1220_Pkg 1B A_12_All Drawings.pdf PDF
2021_1214_Pkg 1A_ A11_All Drawings.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 6 OF 7 - PACKAGE 1B.PDF PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 2 OF 7 - PACKAGE 1A.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 4 OF 7 - PACKAGE 5.pdf PDF
A154_Amendment 0011 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1214__Pkg 5_A11_All Drawings.pdf PDF
Amendment 0011 PROPOSAL SCHEDULE AND COST BREAKDOWN Super Hornet Kuwait.xls XLS spreadsheet
A154_Amendment 0010 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
DRAWING DOCUMENT VOL 3 FOR PKG 1B.pdf PDF
REVISED COVER - VOL 4 OF 5 (NOW 7) PKG 5 SPECS ORG LEVEL MAINT HANGAR.pdf PDF
VOL 6 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm SPECIFICATIONS.pdf PDF
480088 480569_Ku Super Hornet COST PROPOSAL - 11-19-2021 Amendment 0009.pdf PDF
480088 480569_Ku Super Hornet COST BREAKDOWN - 11-19-2021 Amendment 0009.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 4 OF 7 (PKG 5).pdf PDF
REVISED COVER - VOL 2 OF 5 (NOW 7) SPECS PKG 1A BASE INFRSTR FOR FAC AT CLIN5 4800881A.pdf PDF
REVISED COVER - VOL 5 OF 5 (NOW 7) SPECS FOR PKG 5 SUPP DOCS - SPECS_CLIN 5_VOL2.pdf PDF
A154_Amendment 0009 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 2 OF 7 (PKG 1A).pdf PDF
REVISED COVER - VOL 3 OF 5 (NOW 7) PKG 1A BASE INFRA (FOR PKG 5) SUPP DOCS - 480088 AE-SPECS_CLIN 5_VOL2 FROM ORIG FILE.pdf PDF
VOL 7 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm Supplemental Docs.pdf PDF
A154_Amendment 0008 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT SEC 33 16 15 FOR PKG 1A.pdf PDF
2021_1015_Proc B_Pkg 1A_Amendment 0008_All Drawings.pdf PDF
2021_1007_Proc B_Pkg 1A_Rev Amendment 0007_All Drawings - 04NOV21.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT FOR PKG 5 (3 SECTIONS).pdf PDF
2021_1015_Proc B_Pkg 5_Amendment 0008_All Drawings.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 5.pdf PDF
2021_1014_Proc B_Pkg 5_Rev Amendment 0007_All Drawings.pdf PDF
A154_Amendment 0007 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 1A.pdf PDF
A154_Amendment 0006 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_0827_Proc B_Package 1A_Amendment 0005_All Drawings.pdf PDF
2021_0827_Proc B_Package 5_Amendment 0005_All Drawings.pdf PDF
A154_Amendment 0005 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0004 W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
Package 1A_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
Proposal Schedule Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Package 5_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
APPENDIX A (RFP Attachments) W912ER21R0025 Super Hornet Procurement B Kuwait.docx DOCX document
Cost Breakdown Sheet Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Show 40 more

Latest 50 of 84 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SH Pkg 1B Base Infrastructure Improvements-Elec & Telecoms 480088PKG1B

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS -- REVISED BY AMENDMENT NO.

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 AREA USE PLAN

1.3.1 Security Provisions

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board

2.1.2 Project Identification Signs

2.1.3 Warning Signs

2.2 TEMPORARY TRAFFIC CONTROL

2.2.1 Haul Roads

2.2.2 Barricades

2.3 FENCING

2.3.1 Polyethylene Mesh Safety Fencing

2.3.2 Chain Link Panel Fencing

2.3.3 Post-Driven Chain Link Fencing

2.4 TEMPORARY WIRING

2.5 BACKFLOW PREVENTERS

PART 3 EXECUTION

3.1 EMPLOYEE PARKING

3.2 TEMPORARY BULLETIN BOARD

3.3 AVAILABILITY AND USE OF UTILITY SERVICES

3.3.1 Temporary Utilities

3.3.2 Sanitation

3.3.3 Telephone

3.3.4 Obstruction Lighting of Cranes

3.3.5 Fire Protection

3.4 TRAFFIC PROVISIONS

3.4.1 Maintenance of Traffic

3.4.2 Protection of Traffic

3.4.3 Rush Hour Restrictions

3.4.4 Dust Control

3.5 CONTRACTOR'S TEMPORARY FACILITIES

3.5.1 Safety Systems

3.5.2 Administrative Field Offices

3.5.3 Storage Area

3.5.4 Supplemental Storage Area

3.5.5 Appearance of Trailers

3.5.6 Maintenance of Storage Area

SECTION 01 50 00 Page 1

W912ER21R0025 AMENDMENT 0013

3.5.7 Security Provisions

3.5.8 Weather Protection of Temporary Facilities and Stored Materials

3.5.8.1 Building and Site Storm Protection

3.6 GOVERNMENT FIELD OFFICE

3.6.1 Resident Engineer's Office

3.6.2 Trailer-Type Mobile Office

3.7 PLANT COMMUNICATIONS

3.8 TEMPORARY PROJECT SAFETY FENCING

3.9 CLEANUP

3.10 RESTORATION OF STORAGE AREA

-- End of Section Table of Contents --

SECTION 01 50 00 Page 2

SECTION 01 50 00

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS -- REVISED BY AMENDMENT NO.

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2015; Rev L) Obstruction Marking and Lighting

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2015) Manual on Uniform Traffic Control Devices

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Site Plan Area Use Plan ; G M/R

Security Provisions; G M/R

SECTION 01 50 00 Page 3

Traffic Control Plan; G M/R

Haul Road Plan; G M/R

SD-06 Test Reports

Backflow Preventer Tests

SD-07 Certificates

Backflow Tester Certification

Backflow Preventers Certificate of Full Approval

1.3 CONSTRUCTION SITE PLANAREA USE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas. The Contractor shall submit to the Contracting Officer, within 15 calendar days after issuance of Notice to Proceed (NTP), an Area Use Plan designating intended use of all areas within the project boundaries. This plan shall include, but not necessarily be limited to the following: the proposed location and dimensions of any area to be fenced and used by the Contractor;

construction plant and building installations/the number of trailers and facilities to be used; avenues of ingress/egress to the fenced areas and details of the fence installation; drawings showing temporary electrical installations; temporary water and sewage disposal installations; material storage areas; hazardous storage areas. Any areas which may have to be graveled shall also be identified. The plan shall also include a narrative description of the building structural system, the site utility system;

and the office or administration facilities. The Contractor shall also indicate if the use of a supplemental or other staging area is desired.

The Contractor shall not begin construction of the mobilization or any Area Use prior to approval by the Contracting Officer.

1.3.1 Security Provisions

a. Prior to mobilization, submit a plan for providing project security to prevent unauthorized access to equipment, facilities, materials and documents, and to safeguard them against sabotage, damage and theft. The Contractor shall be responsible for physical security of all personnel, materials, supplies, and equipment of every description, including property which may be Government-furnished or owned, for all areas occupied jointly by the Contractor and the Government, as well as for all work areas.

b. The Contractor shall comply with security regulations imposed by the installation commander and/or the agency occupying the space where work is to be performed. The Contractor shall secure buildings where construction is being performed at the end of each work day.

SECTION 01 50 00 Page 4

1.4 BACKFLOW PREVENTERS CERTIFICATE

Certificate of Full Approval from FCCCHR List , University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval will not be acceptable.

1.4.1 Backflow Tester Certificate

Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with any company participating in any other phase of this Contract.

1.4.2 Backflow Prevention Training Certificate

Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.

1.5 DOD CONDITION OF READINESS (COR)

DOD will set the Condition of Readiness (COR) based on the weather forecast for sustained winds 50 knots (60mph or 95 km/hr) or greater.

Contact the Contracting Officer for the current COR setting.

Monitor weather conditions a minimum of twice a day and take appropriate actions according to the aproved Emergency Plan in the accepted Accident Prevention Plan, EM 385-1-1 Section 01 Emergency Planning and the instructions below.

Unless otherwise directed by the Contracting Officer, comply with:

a. Condition FOUR (Sustained winds of 93 km/hr or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than one m high. Remove all debris, trash, or objects that could become missile hazards.

b. Condition THREE (Sustained winds of 93 km/hr or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.

c. Condition TWO (Sustained winds of 93 km/hr or greater expected within 24 hours): Curtail or cease routine activities until securing operation is complete. Reinforce or remove form work and scaffolding. Secure machinery, tools, equipment, materials, or remove from the jobsite. Expend every effort to clear all missile hazards and loose equipment from general base areas.

SECTION 01 50 00 Page 5

d. Condition ONE. (Sustained winds of 93 km/hr or greater expected within 12 hours): Secure the jobsite, and leave Government premises.

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board

Within 7 calendar days of mobilization on site and prior to the commencement of work activities, provide a clear weatherproof covered bulletin board not less than 915 by 1220 mm in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, Safety and Health Information as required by EM 385-1-1 Section 01 and other information approved by the Contracting Officer. Coordinate requirements herein with

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.

2.1.2 Project Identification Signs

The requirements for the signs, their content, and location are as specified in Section 01 58 00 PROJECT IDENTIFICATION. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.

2.1.3 Warning Signs

Post temporary signs, tags, and labels to give workers and the public adequate warning and caution of construction hazards according to the EM 385-1-1 Section 04. Attach signs to the perimeter fencing every 150 feet warning the public of the presence of contruction hazards. Signs must require unauthorized persons to keep out of the construction site.

Correct the data required by safety signs daily.

2.2 TEMPORARY TRAFFIC CONTROL

2.2.1 Haul Roads

Construct access and haul roads necessary for proper prosecution of the work under this contract in accordance with EM 385-1-1 Section 04.

Construct with suitable grades and widths; sharp curves, blind corners, and dangerous cross traffic are be avoided. Submit haul road plan for approval. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.

2.2.2 Barricades

Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades

SECTION 01 50 00 Page 6 clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.

2.3 FENCING

Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic.

Specific fencing requirements are as described herein. All fencing will meet the requirements of EM 385-1-1 .

2.3.1 Polyethylene Mesh Safety Fencing

Temporary safety fencing must be a high visibility orange colored, high density polyethylene grid, a minimum of 48 inches high and maximum mesh size of 2 inches. Fencing must extend from the grade to a minimum of 48 inches above the grade and be tightly secured to T-posts spaced as necessary to maintain a rigid and taut fence. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.

2.3.2 Chain Link Panel Fencing

Temporary panel fencing must be galvanized steel chain link panels 6 feet high. Multiple fencing panels may be linked together at the bases toform long spens as needed. Each panel base must be weighted down using sand bags or other suitable materials in order for the fencing to withstand anticipated winds while remaining upright. Fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection.

2.3.3 Post-Driven Chain Link Fencing

Temporary post-driven fencing must be galvanized chain link fencing 6 feet high supported by an tightly secured to galvanized steel posts driven below grade. Fence posts must be located on minimum 10 foot centers.

Posts may be set in various sufaces such as sand, soil, ashpalt or concrete as necessary. Chain link fencing must remain rigid and taut with a minimum of 200 pounds of force exerted on it from any direction with less than 4 inches of deflection. Fencing and posts must be completely removed at the completion of construction and any surfaces disturbed or damaged must be restored to its original condition. Underground utilities must be located and identified prior to setting fence posts. Fence must be equipped with a lockable gate. Gate must remain locked when construction personnel are not present.

2.4 TEMPORARY WIRING

Provide temporary wiring in accordance with EM 385-1-1 Section 11, NFPA 241 and NFPA 70 . Include monthly inspection and testing of all equipment and apparatus.

2.5 BACKFLOW PREVENTERS

In the case of any contractor-initiated connection to the existing domestic water system, the contractor must furnish and install backflow prevention devices as required by local code and the Al Jaber Air Base Military Engineering Projects (MEP) Manager.

SECTION 01 50 00 Page 7

PART 3 EXECUTION

3.1 EMPLOYEE PARKING

Construction contract employees will park privately owned vehicles in an area designated by the Contracting Officer. This area will be within reasonable walking distance of the construction site. Employee parking must not interfere with existing and established parking requirements of the government installation.

3.2 TEMPORARY BULLETIN BOARD

Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.

3.3 AVAILABILITY AND USE OF UTILITY SERVICES

3.3.1 Temporary Utilities

The Government will provide no temporary utilities. The Contractor shall provide temporary utilities required for construction. Materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.

3.3.2 Sanitation

Provide and maintain within the construction area minimum field-type sanitary facilities approved by the Contracting Officer and periodically empty wastes into a municipal, district, or station sanitary sewage system, or remove waste to a commercial facility. Obtain approval from the system owner prior to discharge into any municipal, district, or commercial sanitary sewer system. Any penalties or fines associated with improper discharge will be the responsibility of the Contractor.

Coordinate with the Contracting Officer and follow station regulations and procedures when discharging into the station sanitary sewer system.

Maintain these conveniences at all times. Include provisions for pest control and elimination of odors. Government toilet facilities will not be available to Contractor's personnel.

3.3.3 Telephone

Make arrangements and pay all costs for telephone facilities desired.

3.3.4 Obstruction Lighting of Cranes

The provisions of this clause "Obstruction Lighting of Cranes" are a minimum. The Contractor shall coordinate with and comply with all requirements imposed local authorities and/or Flight Operations management responsible for operations at Ahmed Al Jaber Air Base.

Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 30 meter above ground level. Light construction and installation must comply with FAA AC 70/7460-1 . Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer.

3.3.5 Fire Protection

Provide temporary fire protection equipment for the protection of

SECTION 01 50 00 Page 8 personnel and property during construction. Remove debris and flammable materials weekly to minimize potential hazards.

3.4 TRAFFIC PROVISIONS

3.4.1 Maintenance of Traffic

a. Conduct operations in a manner that will not close any thoroughfare or interfere in any way with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval. The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.

b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.

c. Provide, erect, and maintain, at contractors expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.

3.4.2 Protection of Traffic

Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.

3.4.3 Rush Hour Restrictions

Do not interfere with the peak traffic flows preceding and during normal operations for Ahmed Al Jaber Air Base without notification to and approval by the Contracting Officer.

3.4.4 Dust Control

Dust control methods and procedures must be approved by the Contracting Officer. Coordinate dust control methods with 01 57 19 TEMPORARY

ENVIRONMENTAL CONTROLS.

3.5 CONTRACTOR'S TEMPORARY FACILITIES

Contractor-owned or -leased trailers must be identified by Government assigned numbers. Size and location of the number will comply with base requirements. Apply the number to the trailer within 14 calendar days of

SECTION 01 50 00 Page 9 notification, or sooner, if directed by the Government. Temporary facilities will meet requirements as identified in EM 385-1-1 Section 04.

3.5.1 Safety Systems

Protect the integrity of any installed safety systems or personnel safety devices. Obtain prior approval from Contracting Officer if entrance into systems serving safety devices is required. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.

3.5.2 Administrative Field Offices

Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will be available to the Contractor's personnel.

3.5.3 Storage Area

Construct a temporary 1.8 m high chain link fence around trailers and materials. Include plastic strip inserts so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.

3.5.4 Supplemental Storage Area

Upon request, and pending availability, the Contracting Officer will designate another or supplemental area for the use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. The area will be maintained in an clean and orderly fashion and secured if needed to protect supplies and equipment. Utilities will not be provided to this area by the Government.

3.5.5 Appearance of Trailers

a. Trailers which are rusted, have peeling paint or are otherwise in need of repair will not be allowed on Installation property. Trailers must present a clean and neat exterior appearance and be in a state of good repair.

b. and maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.

3.5.6 Maintenance of Storage Area

a. Keep fencing in a state of good repair and proper alignment. Grassed

SECTION 01 50 00 Page 10 or unpaved areas, which are not established roadways, and will be traversed with construction equipment or other vehicles, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.

3.5.7 Security Provisions

Provide adequate outside security lighting at the temporary facilities.

The Contractor will be responsible for the security of its own equipment.

3.5.8 Weather Protection of Temporary Facilities and Stored Materials

Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.

3.5.8.1 Building and Site Storm Protection

When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.

Precautions must include, but are not limited to, closing openings;

removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.

3.6 GOVERNMENT FIELD OFFICE

3.6.1 Resident Engineer's Office

Provide the Government Resident Engineer with an office, approximately 19 square meters in floor area, located where directed and providing space heat, air conditioning unit, electric light and power, and toilet facilities consisting of one lavatory and one water closet complete with connections to water and sewer mains. Provide a mail slot in the door or a lockable mail box mounted on the surface of the door. Include a 1200 by 2400 mm plan table, computer work space a standard size office desk and chair, and telephone. At completion of the project, the office will remain the property of the Contractor and be removed from the site. Utilities will be connected and disconnected in accordance with local codes and to the satisfaction of the Contracting Officer. Compliance with safety and appearance requirements for temporary facilities stated in previous paragraphs is required.

3.6.2 Trailer-Type Mobile Office

The option is available to, furnish and maintain a trailer-type mobile office acceptable to the Contracting Officer to meet the requirements of the minimum facilities specified above. Securely anchor the trailer to the ground at all four corners to guard against movement during high winds. Coordinate requirements for proper anchoring with EM 385-1-1

SECTION 01 50 00 Page 11

Section 04.

3.7 PLANT COMMUNICATIONS

Whenever the individual elements of the plant are located so that operation by normal voice between these elements is not satisfactory, install a satisfactory means of communication, such as telephone or other suitable devices and make available for use by Government personnel.

3.8 TEMPORARY PROJECT SAFETY FENCING

As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project safety fencing at the work site. Maintain the safety fencing during the life of the contract and, upon completion and acceptance of the work, removefrom the work site.

3.9 CLEANUP

Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store any salvageable materials resulting from demolition activities within the fenced area described above or at the supplemental storage area. Neatly stack stored materials not in trailers, whether new or salvaged.

3.10 RESTORATION OF STORAGE AREA

Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site.

After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the contract to the original or better condition. Remove gravel used to traverse grassed areas and restore the area to its original condition, including top soil and seeding as necessary.

-- End of Section --