Amendment 0011 PROPOSAL SCHEDULE AND COST BREAKDOWN Super Hornet Kuwait.xls

XLS spreadsheet 69 KB Posted

Attached to
Amendment 0015 to Super Hornet Procurement B, Package 005 (Organizational Level Maintenance Hangar) and Package 001A/B (Base Infrastructure)
Solicitation number
W912ER21R0025
Issued by

About this file

This file contains a proposal schedule and cost breakdown for Amendment 0011 to Solicitation W912ER21R0025. The solicitation is for the construction of a new Organizational Level Maintenance Hangar with eight aircraft bays and associated shop spaces at Al Jaber Air Base in Kuwait. Also included is an adjacent Organizational Level Corrosion Control Hangar with two additional aircraft bays, corrosion control shop spaces, vehicle parking sunshades, and related site improvements. The proposal schedule lays out 15 base bid items and 8 optional CLINs for sitework, utilities, buildings, electrical infrastructure, and telecommunications work. The cost breakdown requires the contractor to provide labor, equipment, material, subcontractor, overhead, profit, and total proposed costs for each item. Inquiries must be submitted through ProjNet as specified in the solicitation. The agency is the Department of the Army Corps of Engineers Engineering District Middle East.

View the file

Other files

File Type Posted
A154_Amendment 0015 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0014 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 6 OF 7 (PKG 1B SEC 01 50 00) JAN 22.pdf PDF
A154_Amendment 0013 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2022_0106_Pkg 5_ Rev A 0013_All Drawings.pdf PDF
2021_1229_Pkg 1A_ A 0013_All Drawings.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 2 OF 7 (PKG 1A) - JAN 22.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 4 OF 7 (PKG 5) JAN 22.pdf PDF
AMENDMENT 0013 NARRATIVE - 21R0025 Superhornet Procurement B -JAN 22.pdf PDF
A154_Amendment 0012 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1220_Pkg 1B A_12_All Drawings.pdf PDF
2021_1214_Pkg 1A_ A11_All Drawings.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 6 OF 7 - PACKAGE 1B.PDF PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 2 OF 7 - PACKAGE 1A.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 4 OF 7 - PACKAGE 5.pdf PDF
A154_Amendment 0011 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1214__Pkg 5_A11_All Drawings.pdf PDF
A154_Amendment 0010 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
DRAWING DOCUMENT VOL 3 FOR PKG 1B.pdf PDF
REVISED COVER - VOL 4 OF 5 (NOW 7) PKG 5 SPECS ORG LEVEL MAINT HANGAR.pdf PDF
VOL 6 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm SPECIFICATIONS.pdf PDF
480088 480569_Ku Super Hornet COST PROPOSAL - 11-19-2021 Amendment 0009.pdf PDF
480088 480569_Ku Super Hornet COST BREAKDOWN - 11-19-2021 Amendment 0009.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 4 OF 7 (PKG 5).pdf PDF
REVISED COVER - VOL 2 OF 5 (NOW 7) SPECS PKG 1A BASE INFRSTR FOR FAC AT CLIN5 4800881A.pdf PDF
REVISED COVER - VOL 5 OF 5 (NOW 7) SPECS FOR PKG 5 SUPP DOCS - SPECS_CLIN 5_VOL2.pdf PDF
A154_Amendment 0009 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 2 OF 7 (PKG 1A).pdf PDF
REVISED COVER - VOL 3 OF 5 (NOW 7) PKG 1A BASE INFRA (FOR PKG 5) SUPP DOCS - 480088 AE-SPECS_CLIN 5_VOL2 FROM ORIG FILE.pdf PDF
VOL 7 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm Supplemental Docs.pdf PDF
A154_Amendment 0008 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT SEC 33 16 15 FOR PKG 1A.pdf PDF
2021_1015_Proc B_Pkg 1A_Amendment 0008_All Drawings.pdf PDF
2021_1007_Proc B_Pkg 1A_Rev Amendment 0007_All Drawings - 04NOV21.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT FOR PKG 5 (3 SECTIONS).pdf PDF
2021_1015_Proc B_Pkg 5_Amendment 0008_All Drawings.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 5.pdf PDF
2021_1014_Proc B_Pkg 5_Rev Amendment 0007_All Drawings.pdf PDF
A154_Amendment 0007 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 1A.pdf PDF
A154_Amendment 0006 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_0827_Proc B_Package 1A_Amendment 0005_All Drawings.pdf PDF
2021_0827_Proc B_Package 5_Amendment 0005_All Drawings.pdf PDF
A154_Amendment 0005 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0004 W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
Package 1A_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
Proposal Schedule Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Package 5_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
APPENDIX A (RFP Attachments) W912ER21R0025 Super Hornet Procurement B Kuwait.docx DOCX document
Cost Breakdown Sheet Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Show 40 more

Latest 50 of 84 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposal Schedule

PROPOSAL SCHEDULE
RFP:W912ER21R0025P2#480088 & 480569
PROJECT:Super Hornet Packages 001A, 001B, & 005Amendment 0011
LOCATION:Kuwait12-Aug-08
ITEM NO.DESCRIPTIONQTYUNITAMOUNTTOTALTOTAL
Base Bid Items
Primary Facilities
0001Mobilization and Demobilization
Mobilization and Demobilization in accordance with the Contract Documents.1JA
0002Sitework and Utility Infra. Fac. A
Construct Sitework and Utility Infrastructure, identified as Facility A in Package 1A, in accordance with the Contract Documents. This work includes but may not be limited to demolition of existing facilities, rough grading, stormwater improvements, and all utility infrastructure (domestic water, sanitary sewer, and fire water) identified as Facility A in Package 1A.1JA
0003Pump House, Water Storage Tanks
Construct Pump House and Water Storage Tanks in accordance with the Contract Documents. This work is identified as Facility P in Package 1A.1JA$5,886,463
0004Org. Level Corrosion Control Hangar
Construct Organizational Level Corrosion Control Hangar in accordance with the Contract Documents. This work is further identified as Facility D in Package 5.1JA$$$
0005Org. Level Maintenance Hangar
Construct Organizational Level Maintenance Hangar in accordance with the Contract Documents. This work is further identified as Facility J in Package 5.1JA$805,900
0006Guard House
Construct Guard House in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include Vehicle Parking Sunshades and Equipment Shelters, which is included in a different CLIN.1JA
0007Sitework and Utility Infra. Fac D, J, N
Construct Associated Sitework and Utility Infrastructure to support Package 5 Facilities D, J, and N in accordance with the Contract Documents. This work includes, but is not limited to, utility tie-ins, fine grading, site concrete, asphalt pavement, and other incidental site improvements associated with Facilities D (Organizational Level Corrosion Control Hangar), J (Organizational Level Maintenance Hangar), and N (Guard House, Parking Area, etc).1JA$805,900
0008Electrical Switching Station
Construct Electrical Switching Station in accordance with the Contract Documents. This work is identified as part of Facility R in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Switching Station and electrical gear. This work does not include site electrical medium voltage ductbank or cabling, which is included in a different CLIN.1JA
0009Electrical Substation #1
Construct Electrical Substation #1 in accordance with the Contract Documents. This work is identified as Facility S in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #1 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.1JA
0010Electrical Substation #2
Construct Electrical Substation #2 in accordance with the Contract Documents. This work is identified as Facility T in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #2 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.1JA
0011MV Ductbank & Cabling to Substa #1 & #2
Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.1JA
0012LV Ductbank & Cabling From Substa #1 & #2
Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) to all new or existing facilities serviced by either substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.1JA
0013LV Ductbank & Cabling to Warehouse
Construct Site Electrical Low Voltage Ductbank and Cabling from Existing Substation S/S N5 to new facility Package 3 General Purpose Warehouse in accordance with the Contract Documents. This work includes tie-in to existing S/S N5 and termination at Package 3 General Purpose Warehouse. This Contract does not include construction of Package 3 General Purpose Warehouse (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.1JA
0014Telecom Infra at Existing Vault
Construct Telecommunications Infrastructure at Existing Communications Vault in accordance with the Contract Documents. This work is identified as part of Facility R Electrical Switching Station in Package 1B. This work includes, but may not be limited to, all equipment, cabling, and terminations within the existing Communications Vault, Handhole HH-01, and all site telecommunications ductbank and cabling from the Communications Vault to HH-01.1JA
0015Telecom Ductbank and Cabling
Construct Site Telecommunications Ductbank and Cabling identified as part of Facility R in Package 1B in accordance with the Contract Documents. The scope of this CLIN includes all site telecommunications ductbank and cabling as shown, EXCEPT for any telecommunications ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Aircrew Training Facility Building). Work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.1JA
TOTAL BASE (ITEMS 0001 - 0015)
OPTIONAL CLINS
0016Power Check and Compass Calibration Pads
Option #1: Construct Power Check Pad and Compass Calibration Pad complete in accordance with the Contract Documents. The work includes, but is not limited to, any sitework and utilities specifically associated with these facilities. This work is identified as Facilities B and C in Package 1A.1JA
0017Parking Sunshades & Equipment Shelters
Option #2: Construct Vehicle Parking Sunshades and Equipment Shelters in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include the Guard House, which is included a different CLIN.1JA
0018Electrical Substation #3
Option #3: Construct Electrical Substation #3 in accordance with the Contract Documents. This work is identified as Facility V in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #3 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.1JA
0019MV Ductbank & Cabling to Substa #3
Option #4: Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #3 (Facility V in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.1JA
0020LV Ductbank & Cabling From Substa #3
Option #5: Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #3 (Facility V in Package 1B) to all new or existing facilities serviced by this substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.1JA
0021LV Ductbank & Cabling to CALA
Option #6: Construct Site Electrical Low Voltage Ductbank and Cabling from Existing UDS1 to new facility Package 2 Combat Aircraft Loading Area (CALA) in accordance with the Contract Documents. This work includes tie-in to existing UDS1 and termination at Package 2 CALA. This Contract does not include construction of Package 2 CALA (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.1JA$805,900
0022Telecom Ductbank & Cabling to Training Fac
Option #7: Construct Site Telecom Ductbank and Cabling to Package 6 Aircrew Training Facility in accordance with the Contract Documents. This work is part of Facility R in Package 1B. This CLIN includes telecom ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Training Facility). This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, infrastructure within the existing facility, and incidental work.1JA
0023Enhanced Turnover Assistance
Option #8: Provide Enhanced Turnover Assistance for all work completed in this Contract as described in Specification Section 01 15 00.12 10, Paragraph 1.11, in accordance with the Contract Documents.1JA
TOTAL OPTIONS (ITEMS 0016 THRU 0023)
TOTAL BASE BID ( ITEMS 0001 - 0015) & OPTIONS (ITEM 0016 - 0023)
$8,611,972

&C&9&P of &N

Cost Breakdown Sheet

COST BREAKDOWN
RFP:W912ER21R0025P2#480088 & 480569
PROJECT:Super Hornet Packages 001A, 001B, & 005Amendment 0011PROPOSER:
LOCATION:KuwaitDATE:
ITEMDESCRIPTIONUnit of Measure and QtyDIRECT LABOR COSTDIRECT EQUIPMENT COSTDIRECT MATERIALS COSTSUB CONTRACTOR COSTTOTAL DIRECT COSTINDIRECT COST JOOH (G&A)*INDIRECT COST HOOH (G&A)*BONDTOTAL OVERHEAD/INDIRECT COSTPROFITTOTAL PROPOSED COST
Primary Facilities
0001Mobilization and Demobilization
Mobilization and Demobilization in accordance with the Contract Documents.0
0002Sitework and Utility Infra. Fac. A

Construct Sitework and Utility Infrastructure, identified as Facility A in Package 1A, in accordance with the Contract Documents. This work includes but may not be limited to demolition of existing facilities, rough grading, stormwater improvements, and all utility infrastructure (domestic water, sanitary sewer, and fire water) identified as Facility A in Package 1A.

0003 Pump House, Water Storage Tanks

Construct Pump House and Water Storage Tanks in accordance with the Contract Documents. This work is identified as Facility P in Package 1A.0
0004Org. Level Corrosion Control Hangar

Construct Organizational Level Corrosion Control Hangar in accordance with the Contract Documents. This work is further identified as Facility D in Package 5.

0005 Org. Level Maintenance Hangar

Construct Organizational Level Maintenance Hangar in accordance with the Contract Documents. This work is further identified as Facility J in Package 5.

0006 Guard House

Construct Guard House in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include Vehicle Parking Sunshades and Equipment Shelters, which is included in a different CLIN.

0007 Sitework and Utility Infra. Fac D, J, N

Construct Associated Sitework and Utility Infrastructure to support Package 5 Facilities D, J, and N in accordance with the Contract Documents. This work includes, but is not limited to, utility tie-ins, fine grading, site concrete, asphalt pavement, and other incidental site improvements associated with Facilities D (Organizational Level Corrosion Control Hangar), J (Organizational Level Maintenance Hangar), and N (Guard House, Parking Area, etc).

0008 Electrical Switching Station

Construct Electrical Switching Station in accordance with the Contract Documents. This work is identified as part of Facility R in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Switching Station and electrical gear. This work does not include site electrical medium voltage ductbank or cabling, which is included in a different CLIN.

0009 Electrical Substation #1

Construct Electrical Substation #1 in accordance with the Contract Documents. This work is identified as Facility S in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #1 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.

0010 Electrical Substation #2

Construct Electrical Substation #2 in accordance with the Contract Documents. This work is identified as Facility T in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #2 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.

0011 MV Ductbank & Cabling to Substa #1 & #2

Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

0012 LV Ductbank & Cabling From Substa #1 & #2

Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) to all new or existing facilities serviced by either substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.

0013 LV Ductbank & Cabling to Warehouse

Construct Site Electrical Low Voltage Ductbank and Cabling from Existing Substation S/S N5 to new facility Package 3 General Purpose Warehouse in accordance with the Contract Documents. This work includes tie-in to existing S/S N5 and termination at Package 3 General Purpose Warehouse. This Contract does not include construction of Package 3 General Purpose Warehouse (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

0014 Telecom Infra at Existing Vault

Construct Telecommunications Infrastructure at Existing Communications Vault in accordance with the Contract Documents. This work is identified as part of Facility R Electrical Switching Station in Package 1B. This work includes, but may not be limited to, all equipment, cabling, and terminations within the existing Communications Vault, Handhole HH-01, and all site telecommunications ductbank and cabling from the Communications Vault to HH-01.

0015 Telecom Ductbank and Cabling

Construct Site Telecommunications Ductbank and Cabling identified as part of Facility R in Package 1B in accordance with the Contract Documents. The scope of this CLIN includes all site telecommunications ductbank and cabling as shown, EXCEPT for any telecommunications ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Aircrew Training Facility Building). Work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.

TOTAL BASE (ITEMS 0001 - 0015)
OPTIONAL CLINS
0016Power Check and Compass Calibration Pads

Option #1: Construct Power Check Pad and Compass Calibration Pad complete in accordance with the Contract Documents. The work includes, but is not limited to, any sitework and utilities specifically associated with these facilities. This work is identified as Facilities B and C in Package 1A.

0017 Parking Sunshades & Equipment Shelters

Option #2: Construct Vehicle Parking Sunshades and Equipment Shelters in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include the Guard House, which is included a different CLIN.

0018 Electrical Substation #3

Option #3: Construct Electrical Substation #3 in accordance with the Contract Documents. This work is identified as Facility V in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #3 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.

0019 MV Ductbank & Cabling to Substa #3

Option #4: Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #3 (Facility V in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

0020 LV Ductbank & Cabling From Substa #3

Option #5: Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #3 (Facility V in Package 1B) to all new or existing facilities serviced by this substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

0021 LV Ductbank & Cabling to CALA

Option #6: Construct Site Electrical Low Voltage Ductbank and Cabling from Existing UDS1 to new facility Package 2 Combat Aircraft Loading Area (CALA) in accordance with the Contract Documents. This work includes tie-in to existing UDS1 and termination at Package 2 CALA. This Contract does not include construction of Package 2 CALA (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

0022 Telecom Ductbank & Cabling to Training Fac

Option #7: Construct Site Telecom Ductbank and Cabling to Package 6 Aircrew Training Facility in accordance with the Contract Documents. This work is part of Facility R in Package 1B. This CLIN includes telecom ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Training Facility). This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, infrastructure within the existing facility, and incidental work.

0023 Enhanced Turnover Assistance

Option #8: Provide Enhanced Turnover Assistance for all work completed in this Contract as described in Specification Section 01 15 00.12 10, Paragraph 1.11, in accordance with the Contract Documents.

TOTAL OPTIONS (ITEMS 0016 THRU 0023)
TOTAL BASE BID ( ITEMS 0001 - 0015) & OPTIONS (ITEM 0016 - 0023)

&C&"Arial,Bold"&12EXHIBIT 1&RPage &P of &N