Amendment 0011 PROPOSAL SCHEDULE AND COST BREAKDOWN Super Hornet Kuwait.xls
XLS spreadsheet 69 KB Posted
- Solicitation number
- W912ER21R0025
About this file
This file contains a proposal schedule and cost breakdown for Amendment 0011 to Solicitation W912ER21R0025. The solicitation is for the construction of a new Organizational Level Maintenance Hangar with eight aircraft bays and associated shop spaces at Al Jaber Air Base in Kuwait. Also included is an adjacent Organizational Level Corrosion Control Hangar with two additional aircraft bays, corrosion control shop spaces, vehicle parking sunshades, and related site improvements. The proposal schedule lays out 15 base bid items and 8 optional CLINs for sitework, utilities, buildings, electrical infrastructure, and telecommunications work. The cost breakdown requires the contractor to provide labor, equipment, material, subcontractor, overhead, profit, and total proposed costs for each item. Inquiries must be submitted through ProjNet as specified in the solicitation. The agency is the Department of the Army Corps of Engineers Engineering District Middle East.
View the file
Other files
Show 40 more
Latest 50 of 84 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Proposal Schedule
| PROPOSAL SCHEDULE | ||||||
| RFP: | W912ER21R0025 | P2# | 480088 & 480569 | |||
| PROJECT: | Super Hornet Packages 001A, 001B, & 005 | Amendment 0011 | ||||
| LOCATION: | Kuwait | 12-Aug-08 | ||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | AMOUNT | TOTAL | TOTAL |
| Base Bid Items | ||||||
| Primary Facilities | ||||||
| 0001 | Mobilization and Demobilization |
| Mobilization and Demobilization in accordance with the Contract Documents. | 1 | JA |
| 0002 | Sitework and Utility Infra. Fac. A |
| Construct Sitework and Utility Infrastructure, identified as Facility A in Package 1A, in accordance with the Contract Documents. This work includes but may not be limited to demolition of existing facilities, rough grading, stormwater improvements, and all utility infrastructure (domestic water, sanitary sewer, and fire water) identified as Facility A in Package 1A. | 1 | JA |
| 0003 | Pump House, Water Storage Tanks |
| Construct Pump House and Water Storage Tanks in accordance with the Contract Documents. This work is identified as Facility P in Package 1A. | 1 | JA | $5,886,463 |
| 0004 | Org. Level Corrosion Control Hangar |
| Construct Organizational Level Corrosion Control Hangar in accordance with the Contract Documents. This work is further identified as Facility D in Package 5. | 1 | JA | $ | $ | $ |
| 0005 | Org. Level Maintenance Hangar |
| Construct Organizational Level Maintenance Hangar in accordance with the Contract Documents. This work is further identified as Facility J in Package 5. | 1 | JA | $805,900 |
| 0006 | Guard House |
| Construct Guard House in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include Vehicle Parking Sunshades and Equipment Shelters, which is included in a different CLIN. | 1 | JA |
| 0007 | Sitework and Utility Infra. Fac D, J, N |
| Construct Associated Sitework and Utility Infrastructure to support Package 5 Facilities D, J, and N in accordance with the Contract Documents. This work includes, but is not limited to, utility tie-ins, fine grading, site concrete, asphalt pavement, and other incidental site improvements associated with Facilities D (Organizational Level Corrosion Control Hangar), J (Organizational Level Maintenance Hangar), and N (Guard House, Parking Area, etc). | 1 | JA | $805,900 |
| 0008 | Electrical Switching Station |
| Construct Electrical Switching Station in accordance with the Contract Documents. This work is identified as part of Facility R in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Switching Station and electrical gear. This work does not include site electrical medium voltage ductbank or cabling, which is included in a different CLIN. | 1 | JA |
| 0009 | Electrical Substation #1 |
| Construct Electrical Substation #1 in accordance with the Contract Documents. This work is identified as Facility S in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #1 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN. | 1 | JA |
| 0010 | Electrical Substation #2 |
| Construct Electrical Substation #2 in accordance with the Contract Documents. This work is identified as Facility T in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #2 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN. | 1 | JA |
| 0011 | MV Ductbank & Cabling to Substa #1 & #2 |
| Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work. | 1 | JA |
| 0012 | LV Ductbank & Cabling From Substa #1 & #2 |
| Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) to all new or existing facilities serviced by either substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work. | 1 | JA |
| 0013 | LV Ductbank & Cabling to Warehouse |
| Construct Site Electrical Low Voltage Ductbank and Cabling from Existing Substation S/S N5 to new facility Package 3 General Purpose Warehouse in accordance with the Contract Documents. This work includes tie-in to existing S/S N5 and termination at Package 3 General Purpose Warehouse. This Contract does not include construction of Package 3 General Purpose Warehouse (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work. | 1 | JA |
| 0014 | Telecom Infra at Existing Vault |
| Construct Telecommunications Infrastructure at Existing Communications Vault in accordance with the Contract Documents. This work is identified as part of Facility R Electrical Switching Station in Package 1B. This work includes, but may not be limited to, all equipment, cabling, and terminations within the existing Communications Vault, Handhole HH-01, and all site telecommunications ductbank and cabling from the Communications Vault to HH-01. | 1 | JA |
| 0015 | Telecom Ductbank and Cabling |
| Construct Site Telecommunications Ductbank and Cabling identified as part of Facility R in Package 1B in accordance with the Contract Documents. The scope of this CLIN includes all site telecommunications ductbank and cabling as shown, EXCEPT for any telecommunications ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Aircrew Training Facility Building). Work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work. | 1 | JA |
| TOTAL BASE (ITEMS 0001 - 0015) | ||
| OPTIONAL CLINS | ||
| 0016 | Power Check and Compass Calibration Pads |
| Option #1: Construct Power Check Pad and Compass Calibration Pad complete in accordance with the Contract Documents. The work includes, but is not limited to, any sitework and utilities specifically associated with these facilities. This work is identified as Facilities B and C in Package 1A. | 1 | JA |
| 0017 | Parking Sunshades & Equipment Shelters |
| Option #2: Construct Vehicle Parking Sunshades and Equipment Shelters in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include the Guard House, which is included a different CLIN. | 1 | JA |
| 0018 | Electrical Substation #3 |
| Option #3: Construct Electrical Substation #3 in accordance with the Contract Documents. This work is identified as Facility V in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #3 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN. | 1 | JA |
| 0019 | MV Ductbank & Cabling to Substa #3 |
| Option #4: Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #3 (Facility V in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work. | 1 | JA |
| 0020 | LV Ductbank & Cabling From Substa #3 |
| Option #5: Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #3 (Facility V in Package 1B) to all new or existing facilities serviced by this substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work. | 1 | JA |
| 0021 | LV Ductbank & Cabling to CALA |
| Option #6: Construct Site Electrical Low Voltage Ductbank and Cabling from Existing UDS1 to new facility Package 2 Combat Aircraft Loading Area (CALA) in accordance with the Contract Documents. This work includes tie-in to existing UDS1 and termination at Package 2 CALA. This Contract does not include construction of Package 2 CALA (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work. | 1 | JA | $805,900 |
| 0022 | Telecom Ductbank & Cabling to Training Fac |
| Option #7: Construct Site Telecom Ductbank and Cabling to Package 6 Aircrew Training Facility in accordance with the Contract Documents. This work is part of Facility R in Package 1B. This CLIN includes telecom ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Training Facility). This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, infrastructure within the existing facility, and incidental work. | 1 | JA |
| 0023 | Enhanced Turnover Assistance |
| Option #8: Provide Enhanced Turnover Assistance for all work completed in this Contract as described in Specification Section 01 15 00.12 10, Paragraph 1.11, in accordance with the Contract Documents. | 1 | JA | |
| TOTAL OPTIONS (ITEMS 0016 THRU 0023) | |||
| TOTAL BASE BID ( ITEMS 0001 - 0015) & OPTIONS (ITEM 0016 - 0023) | |||
| $8,611,972 |
&C&9&P of &N
Cost Breakdown Sheet
| COST BREAKDOWN | |||||||||||||
| RFP: | W912ER21R0025 | P2# | 480088 & 480569 | ||||||||||
| PROJECT: | Super Hornet Packages 001A, 001B, & 005 | Amendment 0011 | PROPOSER: | ||||||||||
| LOCATION: | Kuwait | DATE: | |||||||||||
| ITEM | DESCRIPTION | Unit of Measure and Qty | DIRECT LABOR COST | DIRECT EQUIPMENT COST | DIRECT MATERIALS COST | SUB CONTRACTOR COST | TOTAL DIRECT COST | INDIRECT COST JOOH (G&A)* | INDIRECT COST HOOH (G&A)* | BOND | TOTAL OVERHEAD/INDIRECT COST | PROFIT | TOTAL PROPOSED COST |
| Primary Facilities | |||||||||||||
| 0001 | Mobilization and Demobilization |
| Mobilization and Demobilization in accordance with the Contract Documents. | 0 | ||
| 0002 | Sitework and Utility Infra. Fac. A |
Construct Sitework and Utility Infrastructure, identified as Facility A in Package 1A, in accordance with the Contract Documents. This work includes but may not be limited to demolition of existing facilities, rough grading, stormwater improvements, and all utility infrastructure (domestic water, sanitary sewer, and fire water) identified as Facility A in Package 1A.
0003 Pump House, Water Storage Tanks
| Construct Pump House and Water Storage Tanks in accordance with the Contract Documents. This work is identified as Facility P in Package 1A. | 0 | ||
| 0004 | Org. Level Corrosion Control Hangar |
Construct Organizational Level Corrosion Control Hangar in accordance with the Contract Documents. This work is further identified as Facility D in Package 5.
0005 Org. Level Maintenance Hangar
Construct Organizational Level Maintenance Hangar in accordance with the Contract Documents. This work is further identified as Facility J in Package 5.
0006 Guard House
Construct Guard House in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include Vehicle Parking Sunshades and Equipment Shelters, which is included in a different CLIN.
0007 Sitework and Utility Infra. Fac D, J, N
Construct Associated Sitework and Utility Infrastructure to support Package 5 Facilities D, J, and N in accordance with the Contract Documents. This work includes, but is not limited to, utility tie-ins, fine grading, site concrete, asphalt pavement, and other incidental site improvements associated with Facilities D (Organizational Level Corrosion Control Hangar), J (Organizational Level Maintenance Hangar), and N (Guard House, Parking Area, etc).
0008 Electrical Switching Station
Construct Electrical Switching Station in accordance with the Contract Documents. This work is identified as part of Facility R in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Switching Station and electrical gear. This work does not include site electrical medium voltage ductbank or cabling, which is included in a different CLIN.
0009 Electrical Substation #1
Construct Electrical Substation #1 in accordance with the Contract Documents. This work is identified as Facility S in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #1 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.
0010 Electrical Substation #2
Construct Electrical Substation #2 in accordance with the Contract Documents. This work is identified as Facility T in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #2 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.
0011 MV Ductbank & Cabling to Substa #1 & #2
Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
0012 LV Ductbank & Cabling From Substa #1 & #2
Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) to all new or existing facilities serviced by either substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.
0013 LV Ductbank & Cabling to Warehouse
Construct Site Electrical Low Voltage Ductbank and Cabling from Existing Substation S/S N5 to new facility Package 3 General Purpose Warehouse in accordance with the Contract Documents. This work includes tie-in to existing S/S N5 and termination at Package 3 General Purpose Warehouse. This Contract does not include construction of Package 3 General Purpose Warehouse (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
0014 Telecom Infra at Existing Vault
Construct Telecommunications Infrastructure at Existing Communications Vault in accordance with the Contract Documents. This work is identified as part of Facility R Electrical Switching Station in Package 1B. This work includes, but may not be limited to, all equipment, cabling, and terminations within the existing Communications Vault, Handhole HH-01, and all site telecommunications ductbank and cabling from the Communications Vault to HH-01.
0015 Telecom Ductbank and Cabling
Construct Site Telecommunications Ductbank and Cabling identified as part of Facility R in Package 1B in accordance with the Contract Documents. The scope of this CLIN includes all site telecommunications ductbank and cabling as shown, EXCEPT for any telecommunications ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Aircrew Training Facility Building). Work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.
| TOTAL BASE (ITEMS 0001 - 0015) | |
| OPTIONAL CLINS | |
| 0016 | Power Check and Compass Calibration Pads |
Option #1: Construct Power Check Pad and Compass Calibration Pad complete in accordance with the Contract Documents. The work includes, but is not limited to, any sitework and utilities specifically associated with these facilities. This work is identified as Facilities B and C in Package 1A.
0017 Parking Sunshades & Equipment Shelters
Option #2: Construct Vehicle Parking Sunshades and Equipment Shelters in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include the Guard House, which is included a different CLIN.
0018 Electrical Substation #3
Option #3: Construct Electrical Substation #3 in accordance with the Contract Documents. This work is identified as Facility V in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #3 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.
0019 MV Ductbank & Cabling to Substa #3
Option #4: Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #3 (Facility V in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
0020 LV Ductbank & Cabling From Substa #3
Option #5: Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #3 (Facility V in Package 1B) to all new or existing facilities serviced by this substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
0021 LV Ductbank & Cabling to CALA
Option #6: Construct Site Electrical Low Voltage Ductbank and Cabling from Existing UDS1 to new facility Package 2 Combat Aircraft Loading Area (CALA) in accordance with the Contract Documents. This work includes tie-in to existing UDS1 and termination at Package 2 CALA. This Contract does not include construction of Package 2 CALA (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
0022 Telecom Ductbank & Cabling to Training Fac
Option #7: Construct Site Telecom Ductbank and Cabling to Package 6 Aircrew Training Facility in accordance with the Contract Documents. This work is part of Facility R in Package 1B. This CLIN includes telecom ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Training Facility). This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, infrastructure within the existing facility, and incidental work.
0023 Enhanced Turnover Assistance
Option #8: Provide Enhanced Turnover Assistance for all work completed in this Contract as described in Specification Section 01 15 00.12 10, Paragraph 1.11, in accordance with the Contract Documents.
| TOTAL OPTIONS (ITEMS 0016 THRU 0023) |
| TOTAL BASE BID ( ITEMS 0001 - 0015) & OPTIONS (ITEM 0016 - 0023) |
&C&"Arial,Bold"&12EXHIBIT 1&RPage &P of &N