A154_Amendment 0009 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf

PDF 563 KB Posted

Attached to
Amendment 0015 to Super Hornet Procurement B, Package 005 (Organizational Level Maintenance Hangar) and Package 001A/B (Base Infrastructure)
Solicitation number
W912ER21R0025
Issued by

About this file

This document is an amendment to a solicitation for construction services. The amendment revises specifications and drawings for packages 1A, 1B, and 5 of the solicitation. Package 1A includes base infrastructure such as sitework, utilities, a pump house, and water storage tanks. Package 1B adds electrical switching stations, substations, and associated ductwork and cabling. Package 5 includes an organizational level maintenance hangar, corrosion control hangar, guard house, and related site improvements. The amendment extends the proposal due date to December 9, 2021 and replaces the proposal schedule and cost breakdown with revised versions. The solicitation is for construction of facilities at Al Jaber Air Base in Kuwait and is issued by the Department of the Army Corps of Engineers Engineering District Middle East.

View the file

Other files

File Type Posted
A154_Amendment 0015 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0014 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 6 OF 7 (PKG 1B SEC 01 50 00) JAN 22.pdf PDF
A154_Amendment 0013 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2022_0106_Pkg 5_ Rev A 0013_All Drawings.pdf PDF
2021_1229_Pkg 1A_ A 0013_All Drawings.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 2 OF 7 (PKG 1A) - JAN 22.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 4 OF 7 (PKG 5) JAN 22.pdf PDF
AMENDMENT 0013 NARRATIVE - 21R0025 Superhornet Procurement B -JAN 22.pdf PDF
A154_Amendment 0012 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1220_Pkg 1B A_12_All Drawings.pdf PDF
2021_1214_Pkg 1A_ A11_All Drawings.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 6 OF 7 - PACKAGE 1B.PDF PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 2 OF 7 - PACKAGE 1A.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 4 OF 7 - PACKAGE 5.pdf PDF
A154_Amendment 0011 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1214__Pkg 5_A11_All Drawings.pdf PDF
Amendment 0011 PROPOSAL SCHEDULE AND COST BREAKDOWN Super Hornet Kuwait.xls XLS spreadsheet
A154_Amendment 0010 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
DRAWING DOCUMENT VOL 3 FOR PKG 1B.pdf PDF
REVISED COVER - VOL 4 OF 5 (NOW 7) PKG 5 SPECS ORG LEVEL MAINT HANGAR.pdf PDF
VOL 6 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm SPECIFICATIONS.pdf PDF
480088 480569_Ku Super Hornet COST PROPOSAL - 11-19-2021 Amendment 0009.pdf PDF
480088 480569_Ku Super Hornet COST BREAKDOWN - 11-19-2021 Amendment 0009.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 4 OF 7 (PKG 5).pdf PDF
REVISED COVER - VOL 2 OF 5 (NOW 7) SPECS PKG 1A BASE INFRSTR FOR FAC AT CLIN5 4800881A.pdf PDF
REVISED COVER - VOL 5 OF 5 (NOW 7) SPECS FOR PKG 5 SUPP DOCS - SPECS_CLIN 5_VOL2.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 2 OF 7 (PKG 1A).pdf PDF
REVISED COVER - VOL 3 OF 5 (NOW 7) PKG 1A BASE INFRA (FOR PKG 5) SUPP DOCS - 480088 AE-SPECS_CLIN 5_VOL2 FROM ORIG FILE.pdf PDF
VOL 7 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm Supplemental Docs.pdf PDF
A154_Amendment 0008 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT SEC 33 16 15 FOR PKG 1A.pdf PDF
2021_1015_Proc B_Pkg 1A_Amendment 0008_All Drawings.pdf PDF
2021_1007_Proc B_Pkg 1A_Rev Amendment 0007_All Drawings - 04NOV21.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT FOR PKG 5 (3 SECTIONS).pdf PDF
2021_1015_Proc B_Pkg 5_Amendment 0008_All Drawings.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 5.pdf PDF
2021_1014_Proc B_Pkg 5_Rev Amendment 0007_All Drawings.pdf PDF
A154_Amendment 0007 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 1A.pdf PDF
A154_Amendment 0006 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_0827_Proc B_Package 1A_Amendment 0005_All Drawings.pdf PDF
2021_0827_Proc B_Package 5_Amendment 0005_All Drawings.pdf PDF
A154_Amendment 0005 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0004 W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
Package 1A_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
Proposal Schedule Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Package 5_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
APPENDIX A (RFP Attachments) W912ER21R0025 Super Hornet Procurement B Kuwait.docx DOCX document
Cost Breakdown Sheet Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Show 40 more

Latest 50 of 84 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

480569

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment 0009 is to (1) amend the specifications and add the package 1B specif ication packages, (2) add the package 1B draw ings, (3) replace the proposal schedule and cost breakdow n sheet, and (4) extend the proposal due date.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Nov-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ER21R0025

X 9B. DATED (SEE ITEM 11)

19-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Nov-2021

CODE

US ARMY CORPS OF ENGINEERS-CETAM-CT

MIDDLE EAST DISTRICT, CETAM-CT

PO BOX 2250

WINCHESTER VA 22604-1450

W912ER 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ER21R0025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

CONTINUATION PAGE

SUBJECT: Amendment 0009 to W912ER21R0025 Super Hornet Procurement B, Kuwait has been issued to revise the following:

1. Specifications: Revised sections are replaced in their entirety. Revisions to the specification pages are shown on the pages in the following manner: New text is underlined, and deleted text is shown using strikeout. The amendment number appears in the bottom margin on all pages of the new or revised sections.

The following have been revised/added:

VOLUME 2 (Package 1A, Base Infrastructure (for Package 5)):

COVER DOCUMENT (to change the title from Vol 2 of 5 to Vol 2 of 7)

Table of Contents – replaced in its entirety

Section 01 11 00

Paragraph 1.1, page 2 Paragraph 1.1.1, page 2 Paragraphs 1.1.1.1 thru 1.1.1.3, pages 2 thru 3 Paragraphs 1.4 thru 1.6, pages 3 thru 7

Section 01 15 00.12 10

Paragraph 1.20, page 9

Section 01 35 26 – replaced in its entirety to include an additional Exhibit B

Section 01 45 00.00 10

Paragraph 3.2.1.j, page 5

Section 01 50 00

Paragraph 3.3.1, page 7 Paragraphs 3.3.2 thru 3.3.5, pages 7 thru 8

Section 01 78 00. 49 – replaces Section 01 78 00 in its entirety

VOLUME 3 (Package 1A, Supplemental Volume (for Package 5)):

COVER DOCUMENT (to change the title from Vol 3 of 5 to Vol 3 of 7)

VOLUME 4 (Package 5, Organizational Level Maintenance Hangar):

COVER DOCUMENT (to change the title from Vol 4 of 5 to Vol 4 of 7)

Table of Contents – replaced in its entirety

Section 01 11 00

Paragraph 1.1, page 2 Paragraph 1.1.1, page 2 Paragraphs 1.1.1.1 thru 1.1.1.3, pages 2 thru 3 Paragraphs 1.4 thru 1.6, pages 3 thru 7

Section 01 15 00.12 10

Paragraph 1.20, page 9

Section 01 35 26 – replaced in its entirety to include an additional Exhibit B

Section 01 45 00.00 10

Paragraph 3.2.1.j, page 5

Section 01 50 00

Paragraph 3.3.1, page 7 Paragraphs 3.3.2 thru 3.3.5, pages 7 thru 8

Section 01 78 00. 49 – replaces Section 01 78 00 in its entirety

VOLUME 5 (Package 5, Supplemental Volume:

COVER DOCUMENT (to change the title from Vol 5 of 5 to Vol 5 of 7)

VOLUME 6 OF 7 (Package 1B, Base Infrastructure Electrical and Telecommunication Distribution – Specifications

– added in its entirety

VOLUME 7 OF 7 (Package 1B, Base Infrastructure Electrical and Telecommunication Distribution – Supplemental Documents – added in its entirety

2. Drawings: The proposal schedule and cost breakdown have been revised in their entirety.

DRAWING DOCUMENT VOL 3 FOR PKG 1B – added in its entirety

3. Proposal Schedule and Cost Breakdown: The proposal schedule and cost breakdown have been revised in its entirety and are provided.

4. Solicitation:

Section 00 21 00 Section II – Solicitation Provisions, C PROPOSAL SUBMISSION INSTRUCTIONS:

The proposal due date has been extended from December 6th, 2021 by 4:00PM Eastern Standard Time to December 9th, 2021 by 4:00PM Eastern Standard Time.

All other terms and conditions remain unchanged.

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Mobilization and Demobilization

FFP

Mobilization and Demobilization in accordance with the Contract Documents.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job

Sitework and Utility Infra. Fac. A

FFP

Construct Sitework and Utility Infrastructure, identified as Facility A in Package 1A, in accordance with the Contract Documents. This work includes but may not be limited to demolition of existing facilities, rough grading, stormwater improvements, and all utility infrastructure (domestic water, sanitary sewer, and fire water) identified as Facility A in Package 1A.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Job

Pump House, Water Storage Tanks

FFP

Construct Pump House and Water Storage Tanks in accordance with the Contract Documents. This work is identified as Facility P in Package 1A.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0004 1 Job

Org. Level Corrosion Control Hangar

FFP

Construct Organizational Level Corrosion Control Hangar in accordance with the Contract Documents. This work is further identified as Facility D in Package 5.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0005 1 Job

Org. Level Maintenance Hangar

FFP

Construct Organizational Level Maintenance Hangar in accordance with the Contract Documents. This work is further identified as Facility J in Package 5.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0006 1 Job

Guard House

FFP

Construct Guard House in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include Vehicle Parking Sunshades and Equipment Shelters, which is included in a different CLIN.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0007 1 Job

Sitework and Utility Infra. Fac D, J, N

FFP

Construct Associated Sitework and Utility Infrastructure to support Package 5 Facilities D, J, and N in accordance with the Contract Documents. This work includes, but is not limited to, utility tie-ins, fine grading, site concrete, asphalt pavement, and other incidental site improvements associated with Facilities D (Organizational Level Corrosion Control Hangar), J (Organizational Level Maintenance Hangar), and N (Guard House, Parking Area, etc).

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0008 1 Job

Electrical Switching Station

FFP

Construct Electrical Switching Station in accordance with the Contract Documents.

This work is identified as part of Facility R in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Switching Station and electrical gear. This work does not include site electrical medium voltage ductbank or cabling, which is included in a different CLIN.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0009 1 Job

Electrical Substation #1

FFP

Construct Electrical Substation #1 in accordance with the Contract Documents.

This work is identified as Facility S in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #1 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0010 1 Job

Electrical Substation #2

FFP

Construct Electrical Substation #2 in accordance with the Contract Documents.

This work is identified as Facility T in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #2 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0011 1 Job

MV Ductbank & Cabling to Substa #1 & #2

FFP

Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0012 1 Job

LV Ductbank & Cabling From Subst #1 & #2

FFP

Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) to all new or existing facilities serviced by either substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0013 1 Job

LV Ductbank & Cabling to Warehouse

FFP

Construct Site Electrical Low Voltage Ductbank and Cabling from Existing Substation S/S N5 to new facility Package 3 General Purpose Warehouse in accordance with the Contract Documents. This work includes tie-in to existing S/S N5 and termination at Package 3 General Purpose Warehouse. This Contract does not include construction of Package 3 General Purpose Warehouse (by others).

This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0014 1 Job

Telecom Infra at Existing Vault

FFP

Construct Telecommunications Infrastructure at Existing Communications Vault in accordance with the Contract Documents. This work is identified as part of Facility R Electrical Switching Station in Package 1B. This work includes, but may not be limited to, all equipment, cabling, and terminations within the existing Communications Vault, Handhole HH-01, and all site telecommunications ductbank and cabling from the Communications Vault to HH-01.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0015 1 Job

Telecom Ductbank and Cabling

FFP

Construct Site Telecommunications Ductbank and Cabling identified as part of Facility R in Package 1B in accordance with the Contract Documents. The scope of this CLIN includes all site telecommunications ductbank and cabling as shown, EXCEPT for any telecommunications ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Aircrew Training Facility Building). Work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0016 1 Job OPTION Power Check and Compass Calibration Pads

FFP

Construct Power Check Pad and Compass Calibration Pad complete in accordance with the Contract Documents. The work includes, but is not limited to, any sitework and utilities specifically associated with these facilities. This work is identified as Facilities B and C in Package 1A.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0017 1 Job OPTION Parking Sunshades & Equipment Shelters

FFP

Construct Vehicle Parking Sunshades and Equipment Shelters in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5.

The work of this CLIN does not include the Guard House, which is included a different CLIN.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0018 1 Job OPTION Electrical Substation #3

FFP

Construct Electrical Substation #3 in accordance with the Contract Documents.

This work is identified as Facility V in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #3 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different CLIN.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0019 1 Job OPTION MV Ductbank & Cabling to Substa #3

FFP

Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #3 (Facility V in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0020 1 Job OPTION LV Ductbank & Cabling From Substa #3

FFP

Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #3 (Facility V in Package 1B) to all new or existing facilities serviced by this substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0021 1 Job OPTION LV Ductbank & Cabling to CALA

FFP

Construct Site Electrical Low Voltage Ductbank and Cabling from Existing UDS1 to new facility Package 2 Combat Aircraft Loading Area (CALA) in accordance with the Contract Documents. This work includes tie-in to existing UDS1 and termination at Package 2 CALA. This Contract does not include construction of Package 2 CALA (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.

FOB: Destination

PSC CD: Y1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0022 1 Job OPTION Telecom Ductbank & Cabling to Training F

FFP

Construct Site Telecom Ductbank and Cabling to Package 6 Aircrew Training Facility in accordance with the Contract Documents. This work is part of Facility R in Package 1B. This CLIN includes telecom ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Training Facility). This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, infrastructure within the existing facility, and incidental work.

FOB: Destination

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0023 1 Job OPTION Enhanced Turnover Assistance

FFP

Provide Enhanced Turnover Assistance for all work completed in this Contract as described in Specification Section 01 15 00.12 10, Paragraph 1.11, in accordance with the Contract Documents.

FOB: Destination

PSC CD: Y1BZ

NET AMT

INCORPORATE PROPOSAL

1. The Government reserves the right to incorporate the successful contractor’s proposal fully or in portions into the contract and distribute the proposal as deemed necessary.

2. The successful contractor’s cost breakdown sheet will be incorporated into the award and will be used as the basis of negotiation for future modifications and schedule purposes.