This cost breakdown document provides pricing details for a federal construction contract to build facilities at Al Jaber Air Base in Kuwait. Key work includes an Organizational Level Maintenance Hangar, Organizational Level Corrosion Control Hangar, guard house, utility infrastructure, electrical switching and substations, telecommunications infrastructure, and associated site work. Fifteen base line items and eight optional line items are outlined with direct costs broken down by materials, subcontractors, labor, equipment, overhead and profit. The Army Corps of Engineers Middle East District is the contracting agency. The solicitation number is W912ER21R0025 and the document relates to Amendment 0009 of the Super Hornet Procurement B project.
View the file
Other files
Show 40 more
Latest 50 of 84 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP: W912ER21R0025 P2# 480088 & 480569
PROJECT: Super Hornet Packages 001A, 001B, & 005 Amendment 0009 PROPOSER:
LOCATION: Kuwait DATE:
Primary Facilities
Mobilization and Demobilization
Mobilization and Demobilization in accordance with the Contract Documents.
Sitework and Utility Infra. Fac. A
Construct Sitework and Utility Infrastructure, identified as Facility A in Package 1A, in accordance with the Contract Documents. This work includes but may not be limited to demolition of existing facilities, rough grading, stormwater improvements, and all utility infrastructure (domestic water, sanitary sewer, and fire water) identified as Facility A in Package 1A.
Pump House, Water Storage Tanks
Construct Pump House and Water Storage Tanks in accordance with the Contract Documents. This work is identified as Facility P in Package 1A.
Org. Level Corrosion Control Hangar
Construct Organizational Level Corrosion Control Hangar in accordance with the Contract Documents. This work is further identified as Facility D in Package 5.
Org. Level Maintenance Hangar
Construct Organizational Level Maintenance Hangar in accordance with the Contract Documents. This work is further identified as Facility J in Package 5.
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
EXHIBIT 1 Page 1 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
Guard House
Construct Guard House in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include Vehicle Parking Sunshades and Equipment Shelters, which is included in a different CLIN.
Sitework and Utility Infra. Fac D, J, N
Construct Associated Sitework and Utility Infrastructure to support Package 5 Facilities D, J, and N in accordance with the Contract Documents. This work includes, but is not limited to, utility tie-ins, fine grading, site concrete, asphalt pavement, and other incidental site improvements associated with Facilities D (Organizational Level Corrosion Control Hangar), J (Organizational Level Maintenance Hangar), and N (Guard House, Parking Area, etc).
Electrical Switching Station
Construct Electrical Switching Station in accordance with the Contract Documents.
This work is identified as part of Facility R in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Switching Station and electrical gear.
This work does not include site electrical medium voltage ductbank or cabling, which is included in a different
CLIN.
EXHIBIT 1 Page 2 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
Electrical Substation #1
Construct Electrical Substation #1 in accordance with the Contract Documents.
This work is identified as Facility S in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #1 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different
CLIN.
Electrical Substation #2
Construct Electrical Substation #2 in accordance with the Contract Documents.
This work is identified as Facility T in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #2 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different
CLIN.
MV Ductbank & Cabling to Substa #1 & #2
Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
EXHIBIT 1 Page 3 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
LV Ductbank & Cabling From Substa #1 & #2
Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #1 (Facility S in Package 1B) and Electrical Substation #2 (Facility T in Package 1B) to all new or existing facilities serviced by either substation, in accordance with the Contract Documents. This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.
LV Ductbank & Cabling to Warehouse
Construct Site Electrical Low Voltage Ductbank and Cabling from Existing Substation S/S N5 to new facility Package 3 General Purpose Warehouse in accordance with the Contract Documents. This work includes tie-in to existing S/S N5 and termination at Package 3 General Purpose Warehouse. This Contract does not include construction of Package 3 General Purpose Warehouse (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
EXHIBIT 1 Page 4 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
Telecom Infra at Existing Vault
Construct Telecommunications Infrastructure at Existing Communications Vault in accordance with the Contract Documents. This work is identified as part of Facility R Electrical Switching Station in Package 1B. This work includes, but may not be limited to, all equipment, cabling, and terminations within the existing Communications Vault, Handhole HH-01, and all site telecommunications ductbank and cabling from the Communications Vault to HH-01.
Telecom Ductbank and Cabling
Construct Site Telecommunications Ductbank and Cabling identified as part of Facility R in Package 1B in accordance with the Contract Documents. The scope of this CLIN includes all site telecommunications ductbank and cabling as shown, EXCEPT for any telecommunications ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Aircrew Training Facility Building).
Work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, and incidental related work.
TOTAL BASE (ITEMS 0001 - 0015)
EXHIBIT 1 Page 5 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
OPTIONAL CLINS
Power Check and Compass Calibration Pads
Construct Power Check Pad and Compass Calibration Pad complete in accordance with the Contract Documents. The work includes, but is not limited to, any sitework and utilities specifically associated with these facilities. This work is identified as Facilities B and C in Package 1A.
Parking Sunshades & Equipment Shelters
Construct Vehicle Parking Sunshades and Equipment Shelters in accordance with the Contract Documents. This work is identified as part of Facility N in Package 5. The work of this CLIN does not include the Guard House, which is included a different CLIN.
Electrical Substation #3
Construct Electrical Substation #3 in accordance with the Contract Documents.
This work is identified as Facility V in Package 1B. This work includes, but may not be limited to, grading, concrete and/or asphalt pavements, and construction of the new Electrical Substation #3 and electrical gear. This work does not include site electrical medium or low voltage ductbank or cabling, which is included in a different
CLIN.
EXHIBIT 1 Page 6 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
MV Ductbank & Cabling to Substa #3
Construct Site Electrical Medium Voltage Ductbank and Cabling from the Electrical Switching Station (Facility R in Package 1B) to Electrical Substation #3 (Facility V in Package 1B) in accordance with the Contract Documents. This Site Electrical Medium Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
LV Ductbank & Cabling From Substa #3
Construct Site Electrical Low Voltage Ductbank and Cabling from Electrical Substation #3 (Facility V in Package 1B) to all new or existing facilities serviced by this substation, in accordance with the Contract Documents.
This Site Electrical Low Voltage Ductbank and Cabling is identified as part of Facility R in Package 1B. This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
LV Ductbank & Cabling to CALA
Construct Site Electrical Low Voltage Ductbank and Cabling from Existing UDS1 to new facility Package 2 Combat Aircraft Loading Area (CALA) in accordance with the Contract Documents. This work includes tie-in to existing UDS1 and termination at Package 2 CALA. This Contract does not include construction of Package 2 CALA (by others). This work includes any associated excavation, backfill and compaction, utility or pavement crossings, pavement replacement, and any other incidental related work.
EXHIBIT 1 Page 7 of 8
LOCATION: Kuwait DATE:
BOND
DIRECT
MATERIALS COST
SUB CONTRACTOR
COST
TOTAL
DIRECT
COST
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
TOTAL
OVERHEAD/INDIRECT
COST
PROFIT
TOTAL PROPOSED
COST
COST BREAKDOWN
ITEM DESCRIPTION
INDIRECT COST
JOOH (G&A)*
INDIRECT COST
HOOH (G&A)*
Telecom Ductbank & Cabling to Training Fac
Construct Site Telecom Ductbank and Cabling to Package 6 Aircrew Training Facility in accordance with the Contract Documents. This work is part of Facility R in Package 1B. This CLIN includes telecom ductbank and cabling from handhole HH-07 to Package 6 Aircrew Training Facility (HH-08, HH-09, and new infrastructure within the existing Training Facility). This work includes excavation, backfill, compaction, utility or pavement crossings, pavement replacement, infrastructure within the existing facility, and incidental work.
Enhanced Turnover Assistance
Provide Enhanced Turnover Assistance for all work completed in this Contract as described in Specification Section 01 15
00.12 10, Paragraph 1.11, in accordance with the Contract Documents.
TOTAL OPTIONS (ITEMS 0016 THRU 0023)
TOTAL BASE BID ( ITEMS 0001 - 0015) &
OPTIONS (ITEM 0016 - 0023)
EXHIBIT 1 Page 8 of 8