This amendment to a federal solicitation revises the specifications and drawings for a project to construct an organizational level maintenance hangar and associated infrastructure at Al Jaber Air Base in Kuwait. Revisions include updated sections and drawings for site work, concrete, asphalt paving, utilities, electrical systems, and facility construction. The proposal due date is extended to December 6, 2021. Additional guidance related to COVID-19 safety protocols for federal contractors is also included.

View the file

Other files

File Type Posted
A154_Amendment 0015 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0014 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 6 OF 7 (PKG 1B SEC 01 50 00) JAN 22.pdf PDF
A154_Amendment 0013 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2022_0106_Pkg 5_ Rev A 0013_All Drawings.pdf PDF
2021_1229_Pkg 1A_ A 0013_All Drawings.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 2 OF 7 (PKG 1A) - JAN 22.pdf PDF
AMENDMENT 0013 SPECIFICATIONS DOC FOR VOL 4 OF 7 (PKG 5) JAN 22.pdf PDF
AMENDMENT 0013 NARRATIVE - 21R0025 Superhornet Procurement B -JAN 22.pdf PDF
A154_Amendment 0012 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1220_Pkg 1B A_12_All Drawings.pdf PDF
2021_1214_Pkg 1A_ A11_All Drawings.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 6 OF 7 - PACKAGE 1B.PDF PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 2 OF 7 - PACKAGE 1A.pdf PDF
AMENDMENT 0011 - SPECIFICATIONS DOC FOR VOL 4 OF 7 - PACKAGE 5.pdf PDF
A154_Amendment 0011 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_1214__Pkg 5_A11_All Drawings.pdf PDF
Amendment 0011 PROPOSAL SCHEDULE AND COST BREAKDOWN Super Hornet Kuwait.xls XLS spreadsheet
A154_Amendment 0010 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
DRAWING DOCUMENT VOL 3 FOR PKG 1B.pdf PDF
REVISED COVER - VOL 4 OF 5 (NOW 7) PKG 5 SPECS ORG LEVEL MAINT HANGAR.pdf PDF
VOL 6 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm SPECIFICATIONS.pdf PDF
480088 480569_Ku Super Hornet COST PROPOSAL - 11-19-2021 Amendment 0009.pdf PDF
480088 480569_Ku Super Hornet COST BREAKDOWN - 11-19-2021 Amendment 0009.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 4 OF 7 (PKG 5).pdf PDF
REVISED COVER - VOL 2 OF 5 (NOW 7) SPECS PKG 1A BASE INFRSTR FOR FAC AT CLIN5 4800881A.pdf PDF
REVISED COVER - VOL 5 OF 5 (NOW 7) SPECS FOR PKG 5 SUPP DOCS - SPECS_CLIN 5_VOL2.pdf PDF
A154_Amendment 0009 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0009 SPEC DOCUMENT FOR VOL 2 OF 7 (PKG 1A).pdf PDF
REVISED COVER - VOL 3 OF 5 (NOW 7) PKG 1A BASE INFRA (FOR PKG 5) SUPP DOCS - 480088 AE-SPECS_CLIN 5_VOL2 FROM ORIG FILE.pdf PDF
VOL 7 OF 7 - SPEC PKG 1B 480088 Base Infrastr Elec and Telecomm Supplemental Docs.pdf PDF
A154_Amendment 0008 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT SEC 33 16 15 FOR PKG 1A.pdf PDF
2021_1015_Proc B_Pkg 1A_Amendment 0008_All Drawings.pdf PDF
2021_1007_Proc B_Pkg 1A_Rev Amendment 0007_All Drawings - 04NOV21.pdf PDF
AMENDMENT 0008 - SPEC DOCUMENT FOR PKG 5 (3 SECTIONS).pdf PDF
2021_1015_Proc B_Pkg 5_Amendment 0008_All Drawings.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 5.pdf PDF
2021_1014_Proc B_Pkg 5_Rev Amendment 0007_All Drawings.pdf PDF
AMENDMENT 0007 SPECIFICATION DOC FOR PKG 1A.pdf PDF
A154_Amendment 0006 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
2021_0827_Proc B_Package 1A_Amendment 0005_All Drawings.pdf PDF
2021_0827_Proc B_Package 5_Amendment 0005_All Drawings.pdf PDF
A154_Amendment 0005 to Solicitation W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
A154_Amendment 0004 W912ER21R0025 Super Hornet Procurement B Kuwait.pdf PDF
Package 1A_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
Proposal Schedule Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Package 5_Amendment 0004_All Drawings Super Hornet Procurement B Kuwait.pdf PDF
APPENDIX A (RFP Attachments) W912ER21R0025 Super Hornet Procurement B Kuwait.docx DOCX document
Cost Breakdown Sheet Amendment 0004 Super Hornet Procurement B Kuwait.pdf PDF
Show 40 more

Latest 50 of 84 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

480569

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment 0007 is to (1) amend the specifications, (2) amend the draw ings, (3) include the Class Deviation 2021-O0009, and (4) extend the proposal due date.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Oct-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ER21R0025

X 9B. DATED (SEE ITEM 11)

19-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Oct-2021

CODE

US ARMY CORPS OF ENGINEERS-CETAM-CT

MIDDLE EAST DISTRICT, CETAM-CT

PO BOX 2250

WINCHESTER VA 22604-1450

W912ER 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912ER21R0025

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

CONTINUATION PAGE

SUBJECT: Amendment 0007 to W912ER21R0025 Super Hornet Procurement B, Kuwait has been issued to revise the following:

1. Specifications: Revised sections are replaced in their entirety. Revisions to the specification pages are shown on the pages in the following manner: New text is underlined, and deleted text is shown using strikeout. The amendment number appears in the bottom margin on all pages of the new or revised sections.

The following have been revised/added:

VOLUME 2 (Package 1A, Base Infrastructure (for Package 5)):

Table of Contents Replaced in its entirety.

Section 03 30 00

Paragraph 2.4.6, page 26 Paragraph 2.5.1.i, page 28

Section 32 01 11.51

Added in its entirety.

Section 32 01 19 Paragraph 3.1.1.5, page 6

Section 32 11 23

Paragraph 2.1.3, pages 7-8

Section 32 12 15.13

Paragraph 1.5, page 10 Paragraph 1.6, page 10 Paragraph 2.2.4, page 17 Paragraph 2.4.1.s, page 19

Section 32 13 14.13

Paragraph 1.1.5, page 6 Paragraph 1.2, page 7 Paragraph 1.4, page 11 Paragraph 1.5.1.g, page 12 Paragraph 1.5.2.c, page 12 Paragraph 1.5.6.1, page 15 Paragraph 2.5, page 29 Paragraph 2.11.1.2, page 31 Paragraph 2.13.1, page 37 Paragraph 3.1.1, page 40 Paragraph 3.1.2.a. and g., page 41

Section 33 16 15

Paragraph 2.1.3, page 6 Paragraph 2.1.5, pages 6-7

Paragraph 3.4, page 10 Paragraph 3.5, page 10

Section 33 40 00

Paragraph 2.1.1, page 6

Section 34 73 16 Paragraph 2.3, page 3 Paragraph 3.1.2.3, page 4 Paragraph 3.1.3, page 4

VOLUME 4 (Package 5, Organizational Level Maintenance Hangar):

Section 03 30 00 Paragraph 2.4.6, page 26 Paragraph 2.5.1.i, page 28

Section 26 35 43

Section Title Paragraph 1.3, page 5 Paragraph 1.4.2, page 6 Paragraph 2.1, page 8 Paragraph 2.1.1.6, page 9 Paragraph 2.1.1.15, page 11 Paragraph 2.1.3.2.g, page 12 Paragraph 2.1.4, page 13 Paragraph 2.1.4.1, page 13 Paragraph 2.1.4.4, page 13 Paragraph 2.1.4.5, page 13 Paragraphs 2.1.5.e and h, page 14 Paragraph 2.2, page 15 Paragraph 2.4.3.a, page 18 Paragraph 3.1.3.1, page 20 Paragraph 3.2.1, page 20

Section 32 01 19

Paragraph 3.1.1.5, page 5

Section 32 11 23 Paragraph 2.1.3, pages 7-8

Section 32 12 16

Paragraph 3.11, page 24

Section 32 13 14.13 Paragraph 1.1.5, page 6 Paragraph 1.2, page 7 Paragraph 1.4, page 11 Paragraph 1.5.1.g, page 12 Paragraph 1.5.2.c, page 12 Paragraph 1.5.6.1, page 15 Paragraph 2.5, page 29 Paragraph 2.11.1.2, page 31 Paragraph 2.11.5.1, page 34 Paragraph 2.11.5.4, page 35

Paragraph 2.13.1, page 37 Paragraph 3.1.1, page 41 Paragraph 3.1.2.a. and g., page 41 Paragraph 3.4, page 44 Paragraph 3.5.2, page 45 Paragraph 3.5.3, page 45

Section 33 40 00

Paragraph 2.1.1, page 6

2. Drawings: The following drawings have been revised per this amendment. Revisions are identified by a triangle placed on the drawing near each revision and a "cloud" drawn around both the triangle and change.

Package 1A, Base Infrastructure (for Package 5):

G-011 G-013

Site Design – Civil

GC001

CD151

CG115

CG151

CG152

CG153

CG503

CS115

CS151

CS161

CS401

CP151

CP161

CP162

CP163

CP401

CP501

CP551

Facility P

A-101 F-003 F-601

Package 5, Organizational Level Maintenance Hangar:

G-010 G-011 G-015 G-020 G-025

Site Design

CG111

CG112

CG113

CG114

CS111

CS112

CS113

CS114

CS401

CS602

CS603

Facility D

A-102 A-103 A-112 A-312 A-402 A-405 A-501 A-510 A-601 A-602 I-102 I-103 I-130 F-001 M-641

Facility J

A-102 A-103 A-104 A-105 A-106 A-107 A-112 A-113 A-114 A-202 A-304 A-402 A-403 A-501 A-602 A-603 A-607 I-102 I-103 I-104 I-105 I-106 I-107

I-130 F-001

Facility N

A-110

Standard Details

SS-505

SA-521

3. Section 00 73 00: Class Deviation 2021-O0009 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors was added in its entirety.

252.223-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021- O0009)

(a) Definition. As used in this clause –

United States or its outlying areas means—

(1) The fifty States;

(2) The District of Columbia;

(3) The commonwealths of Puerto Rico and the Northern Mariana Islands;

(4) The territories of American Samoa, Guam, and the United States Virgin Islands; and

(5) The minor outlying islands of Baker Island, Howland Island, Jarvis Island, Johnston Atoll, Kingman Reef, Midway Islands, Navassa Island, Palmyra Atoll, and Wake Atoll.

(b) Authority. This clause implements Executive Order 14042, Ensuring Adequate COVID Safety Protocols for Federal Contractors, dated September 9, 2021 (published in the Federal Register on September 14, 2021, 86 FR 50985).

(c) Compliance. The Contractor shall comply with all guidance, including guidance conveyed through Frequently Asked Questions, as amended during the performance of this contract, for contractor or subcontractor workplace locations published by the Safer Federal Workforce Task Force (Task Force Guidance) at https:/www.saferfederalworkforce.gov/contractors/.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts at any tier that exceed the simplified acquisition threshold, as defined in Federal Acquisition Regulation 2.101 on the date of subcontract award, and are for services, including construction, performed in whole or in part within the United States or its outlying areas.

(End of clause)

4. Proposal Due Date: Section 00 21 00, Section II, C - Proposal Submission Instructions: The proposal due date has been extended from November 5th, 2021 by 4:00PM Eastern Daylight Time to December 6th, 2021 by 4:00PM Eastern Standard Time.