This document is Amendment 0003 to a solicitation for the Maintenance Dredging of Fire Island Inlet and Shores Westerly to Jones Inlet Beach Erosion Control and Navigation Project, Solicitation Number W912DS24B0003.

The amendment provides clarification and updates to the solicitation, including revisions to the bid schedule, plans, and various specification sections. It notes the bid opening date remains April 25, 2024 at 2:00 PM. The amendment also includes additional information on potential obstructions in the dredge area based on prior survey data. The total estimated quantity of material to be dredged and placed is approximately 1,450,000 cubic yards, with the anticipated placement volume between Station 93+00 and 0+00 being 750,000 cubic yards. Contractors are required to survey the placement area prior to starting work. The amendment also provides detailed requirements for the government-furnished field office to be provided by the contractor.

View the file

Other files

File Type Posted
Bid Abstract W912DS-24-B-0003.pdf PDF
Amendment 0015.pdf PDF
Amendment 0014.pdf PDF
Amendment 0013.pdf PDF
Amendment-0012.pdf PDF
Amendment 0011.pdf PDF
Amendment 11_f - Revised Section 31 24 00_00 18 Beach Fill Placement 5-7-24.pdf PDF
Amendment 11_d - Revised Section 00 01 15 List of Drawings 5-7-24.pdf PDF
Amendment 11_h - NYSDEC Permit - Town of Oyster Bay Tobay Beach.pdf PDF
Amendment 11_c - Tobay Beach WQC - F-2021-0073 CCR - NYSDOS Approval.pdf PDF
Amendment 11_e - Revised Section 01 11 00 Summary of Work 5-7-24.pdf PDF
Amendment 11_g - DA Permit - Town of Oyster Bay Tobay Beach.pdf PDF
Amendment 11_b - Tobay Beach Drawings for 2024 Beach Fill from Fire Island.pdf PDF
Amendment 0010.pdf PDF
Amendment 0009.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amnedment 0004.pdf PDF
Amendment 0003_m - Map 3 - 15771 Fire Island Inlet.pdf PDF
Amendment 0003_b - W912DS24B0003 FIIJI24 Revised Plans.pdf PDF
Amendment 0003_f - Revised Section 31 24 00_00 18 Beach Fill Placement.pdf PDF
Amendment 0003_g - 00 90 03 Composite Grain Size Distribution Curves.pdf PDF
Amendment 0003_n - Revised 01 50 00 Temporary Construction Facilities and Controls.pdf PDF
Amendment 0003_c2 - 5367-60 sort-mllw-ELEVATION.pdf PDF
Amendment 0003_d - Revised Section 00 01 15 List of Drawings.pdf PDF
Amendment 0003_c3 - 5406-30sort-ele.pdf PDF
Amendment 0003_i - Utility Permit 1980-00225_11453_13160.pdf PDF
Amendment 0003_h - 00 90 04 WENTWORTH SCALE.pdf PDF
Amendment 0003_a - Revised Bid Schedule.pdf PDF
Amendment 0003_e - Revised Section 01 11 00 Summary of Work.pdf PDF
Amendment 0003_j - Utility Permit 1990-01009_16305_12907.pdf PDF
Amendment 0003_c1 - 5367-3 med-mllw-ELEVATION.pdf PDF
Amendment 0003_k - Map 1- Project_15771 Fire Island Inlet.pdf PDF
Amendment 0003_l - Map 2 - 015995 Fire Island Inlet Contract 1.pdf PDF
Amendment 0002_b -W912DS24B0003 FIIJI24 Revised Plans.pdf PDF
Amendment 0002_c2 - 5367-60 sort-mllw-ELEVATION.pdf PDF
Amendment 0002_m - Map 3 - 15771 Fire Island Inlet.pdf PDF
Amendment 0002_f - Revised Section 31 24 00_00 18 Beach Fill Placement.pdf PDF
Amendment 0002_l - Map 2 - 015995 Fire Island Inlet Contract 1.pdf PDF
Amendment 0002_c3 - 5406-30sort-ele.pdf PDF
Amendment 0002_j - Utility Permit 1990-01009_16305_12907.pdf PDF
Amendment 0002_g - 00 90 03 Composite Grain Size Distribution Curves.pdf PDF
Amendment 0002_h - 00 90 04 WENTWORTH SCALE.pdf PDF
Amendment 0002_k - Map 1- Project_15771 Fire Island Inlet.pdf PDF
Amendment 0002_c1 - 5367-3 med-mllw-ELEVATION.pdf PDF
Amendment 0002_n - Revised 01 50 00 Temporary Construction Facilities and Controls.pdf PDF
Amendment 0002_d - Revised Section 00 01 15 List of Drawings.pdf PDF
Amendment 0002_i - Utility Permit 1980-00225_11453_13160.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of Amendment 0003:

1) Bid opening remains 25 April 2024 at 2:00 P.M.

2) Provide missing clarification not noted in Amendment 0002. Please see continuation page.

3) All attachments for Amendment 0002 w ill be reloaded w ith this Amendment.

NOTE: Bidders must acknow ledge receipt of this amendment by date specified in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THELATE BID, LATE MODIFICATION OF BID, OR LATE

WITHDRAWAL OF BID (FAR 14.3041

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Apr-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS24B0003

X 9B. DATED (SEE ITEM 11)

19-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Apr-2024

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS24B0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0003

AMENDMENT 0003

Fire Island Inlet and Shores Westerly to Jones Inlet, New York Beach Erosion Control and

Navigation Project

- Option 4: Beach Placement at Overlook Beach

- Amendment 0002 updated the Bid Schedule, the Beach Placement section of the Project

Plans based on the most recent topographic and hydrographic survey data (XYZ) for the Gilgo Beach placement area, in addition to providing a revised Overlook Beach Option(s), including updated plans. As a result, Amendment 0002 provides revisions to Section 00 01

15, Section 01 11 00, and Section 31 24 00.00 18 of the Project Specifications, in addition to specific paragraphs in other sections (Section 01 22 00.00 10, Section 01 30 00, Section 01 50 00, Section 01 57 20.00 10 and Section 35 20 23) of the specifications that have been revised.

Amendment 0002 also added two additional sections (Section 00 90 03 and Section 00 90 04), in addition to grab sample requirements and two utility permits (1980-00225_11453_13160 and 1990-01009_16305_12907), to the solicitation.

This amendment also provides information from the contractor who performed work for the Corps during the last two dredging cycles of Fire Island Inlet in 2018/2019 and 2021/2022/2023 concerning lost buoy moorings in the Fire Island Inlet channel and deposition basins. Map 1 (Project: 015771 Fire Island Inlet) survey dated March 3, 2019, shows the magnetometer survey results of 2018, the given U.S. Coast Guard potential obstructions, and the 14-foot contour MLLW. Map 2 (Project: 015995 Fire Island Inlet Contract 1), dated March 21, 2023, shows the magnetometer survey results of 2018, the given U.S. Coast Guard potential obstructions, the 14-foot grade contour, and the areas where the contractor hit something hard highlighted in blue. Map 3 (Project: 015771 Fire Island Inlet) shows the magnetometer survey results of 2018, the given U.S. Coast Guard potential obstructions, and the areas where the contractor hit something hard highlighted in blue.

Amendment 0002 attachments are as follows:

a – Revised Bid Schedule b -W912DS24B0003 FIIJI24 Revised Plans c1 - 5367-3 med-mllw-ELEVATION c2 - 5367-60 sort-mllw-ELEVATION c3 - 5406-30sort-ele d - Revised Section 00 01 15 List of Drawings e - Revised Section 01 11 00 Summary of Work f - Revised Section 31 24 00_00 18 Beach Fill Placement g - 00 90 03 Composite Grain Size Distribution Curves h - 00 90 04 WENTWORTH SCALE i - Utility Permit 1980-00225_11453_13160 j - Utility Permit 1990-01009_16305_12907 k - Map 1- Project_15771 Fire Island Inlet l - Map 2 - 015995 Fire Island Inlet Contract 1 m - Map 3 - 15771 Fire Island Inlet n - Revised 01 50 00 Temporary Construction Facilities and Controls

Revisions of specific paragraphs in other sections of the Project Specifications are as follow:

In SECTION 01 22 00.00 10, MEASUREMENT AND PAYMENT, the following paragraph has been revised:

1.3 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

The total amount of material acceptably placed on the beach (from designated areas of Fire Island Inlet) to be paid for at the contract unit price as shown on the price schedule (Section 00 10 00), must be measured by the cubic yards in place on the beach by computing the volume between the beach shown by a survey made before filling and beach surface shown on a survey after filling. The reference datum must be NAVD. No payment must be made for material placed:

(1) In excess of the quantity to the design grade plus the 0.5-foot tolerance. Refer to the Compensated Slope paragraph in section 31 24 00.00 18 BEACH FILL PLACEMENT for exception regrading compensated slope.

(2) Above EL. +8 ft. NAVD plus tolerance.

(3) Which was obtained from outside the designated dredged area or below the maximum dredging limit of the dredged area, except as directed by the Contracting Officer.

(4) Beyond the point where the 1 on 20 slope line intersects the -1-foot elevation and beyond the point where the 1 on 15 slope line, which starts at -1.0 feet intersects the ocean bottom.

Original and Final Surveys:

The Contractor must make original and final surveys under the supervision of the Contracting Officer's representative and must make computations to determine the quantities of materials placed on the beach for acceptance.

Surveys for Progress Payments:

The Contractor will make any surveys for periods for which progress payments are requested and must make the computations based on these surveys.

In SECTION 01 30 00, ADMINISTRATIVE REQUIREMENTS, the following paragraph has been

1.8 ESTIMATED QUANTITIES

The total estimated quantities of material necessary to be removed from the specified limits to complete the work described in these specifications are computed from the plans and specifications survey performed in the Fire Island Inlet project area in DEC 2023 and

JAN AND FEB 2024.

Distribution of volumes is summarized below:

WORK AREA REQUIRED

DREDGING

DEPTH (FT.)

MEAN

LOWER

LOW

WATER

(MLLW)

CHANN

EL AND

DEPO

BASINS

TO

GRADE

(CY)

CHANNEL

AND DEPO

BASINS

OVERDEPT

H

2 FEET

(CY)

SLOPE

TO

GRAD

E (CY)

SLOPE

OVERDEPT

H

2 FOOT

(CY)

ESTIMATED

TOTAL (CY)

DREDGING

AREA

Basic Work

14 1,232,140 501,755 35,675 17,250 1,786,820

Total Estimated Quantity Available: 1,786,820 CY

The anticipated volume to be dredged and placed is approximately 1,450,000 CY. An updated survey will be performed prior to starting work.

The total estimated quantities of fill material needed to be removed from the channel and deposition basins and placed as fill in the project area within the specified limits to complete the work described in these specifications, as computed from the information shown on the contract drawings, are as indicated on the price schedule.

Fire Island Inlet and Shores Westerly to Jones Inlet, New York Beach Erosion Control and Navigation Project

SURVEY STATION ANTICIPATED PLACEMENT

VOLUME (CY)

BASIC WORK 93+00 - 0+00 750,000

The Contractor shall be required to survey the placement area prior to starting work (dredging and placement).

The contractor will be required to survey an option placement area prior to starting the work if an option is exercised.

Above estimated quantities were computed from the data shown on the contract drawings. The quantities that may be removed and paid for will be computed by the Triangulated Irregular Network (TIN) method or average end area method as indicated in the Technical Specifications, Section 01 22 00.00 10, entitled "MEASUREMENT AND

PAYMENT."

In SECTION 01 50 00, TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS, Part 2, the following paragraph has been revised:

2.2 FIELD OFFICE

a) The Contractor shall provide at the job site a separate field office for the exclusive use by the Government representatives for the duration of the contract. Field office and contents remain the property of the Contractor. The desired location will be designated by the Contracting Officer or Contracting Officer Representative. The designated location shall be coordinated to ensure that sufficient parking is available for the Government representative’s vehicle as well as the required contract provided vehicle and up to 2 visitor vehicles. The field office shall be removed from the project site when and as directed by the Contracting Officer. No separate payment will be made for providing the items contained in this section and all costs in connection therewith will be considered the obligation of the Contractor.

b) The field office shall meet the following minimum requirements:

i. Office space shall be a minimum of 800 SF, with lockable interior doors. The space (if rented in a building) shall be in good condition. The office shall contain at least four (4) operable windows with screens.

ii. One (1) enclosed bathrooms with hot and cold water.

iii. Two (2) enclosed office of minimum dimensions of 10 feet x 12 feet.

iv. Open flat area to accommodate one meeting area and one workspace/miscellaneous use area.

v. Two (2) office desks with lockable drawers (60 inches x 30 inches), laminated top and high-back cloth swivel chairs.

vi. One (1) fire-proof, 4-drawer, legal-size lockable filing cabinets.

vii. Two (2) shelf sets, four-shelves high x 12 inches deep x 3 feet long (attachable to wall).

viii. One (1) 21" Color TV with basic cable service with the Weather Channel included.

ix. Wall TV swivel mount with outlet surge protector.

x. Office conference table capable of seating 6 people

xi. Six (6) straight high back office chairs with wheels.

xii. One (1) bulletin board, 3 feet x 5 feet, mounted by contractor at COR designated location.

xiii. Four (4) wastebaskets with supply of bags.

xiv. One (1) drafting table for E-size drawings and chair.

xv. One (1) paper towel dispenser with towels.

xvi. One (1) paper cup dispenser with cups.

xvii. One (1) water cooler/heater with water.

xviii. Toilet facilities as specified.

c) All structures installed under this paragraph FIELD OFFICE shall be provided with, as a minimum, the following services:

i. Provide one (1) Combination Smoke/Carbon Monoxide Alarm with battery back-up.

ii. Lighting: electric light, non-glare types luminaries to provide a minimum illumination level of 50-foot candles at desk height level.

iii. Sufficient supply of electrical outlets meeting NEC code for residential construction, or no less than 6, whichever is greater.

iv. Heating and Cooling: adequate equipment to maintain an ambient air temperature of 70 degrees F +/- 3 degrees.

v. Window Blinds.

vi. Potable bottled water- Provide sufficient supply of bottled 16.9oz water for field office.

vii. Fire Extinguisher - Provide two (2): non-toxic, dry chemical, fire extinguishers meeting Underwriters Laboratories, Inc. approval for Class A, Class B and Class C fires with a minimum rating of 10A; 20B, 10C.

viii. For each bathroom: power-ventilated, heated and complying with applicable sanitary codes including hot and cold running water and flush-type toilet.

ix. DSL or Cable Modem Service: Business DSL or cable modem service with all required equipment (modems, filters, Ethernet NIC cards, etc.) shall be provided for the entire duration of the contract. DSL service shall be 940 Mbps downstream/ upstream. Service shall utilize a Static IP address for the connection. Contractor shall pay all costs associated with this service including ISP fees. DSL or Cable Modem service shall be a 'dedicated' service, and this line shall not be shared with other Users (i.e., Contractors Field Office Trailer and USACE Field Office Trailer shall not utilize the same DSL or Cable Modem line via an Ethernet Switch/Hub). The Contractor shall provide and install all required equipment (i.e., Switch, Hub, Ethernet NIC Cards, modems, etc.) for use with Government-furnished field office computers.

x. If contractor utilizes VHF or similar radio communication, provide base station and one (1) portable unit on the Contractor's frequency, all with desk chargers.

xi. The contractor shall be responsible for the monthly utility and telephone payment and installation cost of the above service and equipment.

xii. If trailer type mobile office, securely anchor the trailer to the ground at all four corners to guard against movement during high winds. Coordinate requirements for proper anchoring with EM 383-1-1 (March 2024).

xiii. Janitorial services on a weekly basis including, but not limited to, sweeping, emptying baskets, weekly mopping, dusting all surfaces, servicing of toilets and washing and waxing floors, cleaning all windows (inside and out) and re-supply of paper goods and soap.

xiv. Snow and ice removal in the vicinity of the field office may be required during and after storm events.

d) Upon completion of the project remove the bulletin board, signs, barricades, haul roads, and any other temporary products from the site. After removal of trailers, materials, and equipment from within the fenced area, remove the fence. Restore areas used during the performance of the contract to the original or better condition.

Remove gravel used to traverse grassed areas and restore the area to its original condition, including topsoil and seeding as necessary.

e) Provide 1 vehicle with 4-wheel drive, less than 2 years old (minimum 6 passengers) with gas cards sufficient to cover the duration of the project for Government’s official use for Government's use. Maintenance of the vehicles including all fuel, insurance, registration, and fuel and maintenance of the vehicle including State Inspections shall be the contractor’s responsibility.

f) First Aid Kit: Provide two (2) kits, one for field office and one for the contract required vehicle. First aid kits should meet EM 385-1-1 requirements. At a minimum, each kit shall include antiseptic kit, eyewash solution, bandages, insect sting medication, aspirin and acetaminophen, and cold pack, and at the minimum shall conform to ANSI Z308.1

g) Two hard copy sets of the conformed plans (1 full size ANSI D and 1 half size) and 1 copy of the conformed specifications.

In SECTION 01 57 20.00 10, ENVIRONMENTAL PROTECTION, the following paragraph has been

1.14.1 Protection of Endangered and Threatened Species

a. Piping Plover, Least and Roseate Terns (NO WORK WILL BE PERFORMED DURING

THE ENVIRONMENTAL WINDOW OF April 1 TO September 30)

b. Seabeach Amaranth

During each construction cycle, the Contractor will provide a qualified biologist(s) or botanist(s) to survey the work sites for the Federally threatened plant species, seabeach amaranth on a weekly basis to determine the presence of any plants. The Contractor shall take all reasonable precautions to ensure that his work is not conducted in a manner harmful to the seabeach amaranth. The Contractor's personnel shall be aware of the presence of such species and be sufficiently familiar with them so as to minimize contact with them during normal construction hours. If no such sites are identified, then no further action will be required. However, all such sites that are identified will be fenced off by the Contractor within 24 hours of notification. The fencing shall remain in place through the end of construction. The fence will consist of snow fencing at a height of three feet around a 10-foot diameter.

The biologist or botanists will determine the adequacy of fencing so erected and determine the need for additional protection. The zone within the fencing shall be OFF LIMITS to all personnel at all times. In the event, that the plants cannot be avoided due to their spatial distribution and/or abundance, the Contracting Officer will contact the USFWS and New York Department of Environmental Conservation (NYSDEC) to obtain the necessary permits to allow for plant transplantation to nearby suitable habitat (within the action area if possible) and seed collection (which would later be rebroadcasted)

c. Red Knot

For dredging and/or placement of material occurring between September 1 and November 30 of any calendar year: Not more than seven (7) days prior to the commencement of dredging or beach placement activities, the Contractor shall conduct and provide a Red Knot survey by a qualified biologist. In the event that Red Knot are observed within this period, prior to the start of work, or while work is being performed, the contractor shall maintain a 300-meter buffer surrounding the location of the Red Knot and notify the U.S. Fish & Wildlife Service (USFWS), Long Island Field Office (Region 5) at (631) 286- 0485 for further consultation and instructions. The surveys shall be conducted in the following manner:

(1) Inclement Weather: The Contractor shall not conduct surveys in weather with strong winds (>24 mph), heavy fog (<200 m visibility), or steady rain.

(2) Survey Protocol and Data Collection: The Contractor shall begin each survey of each area by indicating the start time. The Contractor shall count and identify Red Knot (and other species) in the survey area. This includes birds that enter or leave the survey area during the survey. For shorebirds to be considered "using" the survey area, the birds need to be on the ground within the defined survey area for at least part of the time it takes to do the survey. Shorebirds that fly over the survey area but do not land in it should NOT be counted. The USACE shall record numbers as the survey is continued. The Contractor shall complete surveys within the optimal 3-hour survey window around peak high tide. Once the area has been thoroughly searched and all birds seen have been recorded, the count is considered complete.

In SECTION 35 20 23, DREDGING, the following paragraph has been revised:

1.3 MATERIAL TO BE REMOVED

The material to be removed is more than 95% sand.

Under the Basic Work, maintenance dredging of approximately 750,000 cubic yards of sand which would be placed along 9,300 linear feet of Gilgo Beach shoreline, between baseline survey stations 93+00 and 00+00.

The Basic Work will require dredging to a plane of -14 feet mean lower low water plus 2 feet allowable overdepth.

All Optional Work will require dredging to a plane of -14 feet mean lower low water plus 2 feet allowable overdepth if exercised.

Grad Sample Requirements:

The contractor must obtain grab samples of the placed fill from: the beach backshore; edge of berm; mean high water (MHW); and mean low water (MLW). One set of samples must be taken every 200 feet along the placed fill area. A grain size analysis of each sand sample will be made using sieve sizes comparable to the Wentworth size classifications (shown in Section 00 90 04 WENTWORTH SCALE) and the results plotted on an appropriate curve format. The laboratory analysis results, and plotted grain size distribution curves must be furnished with the Daily

Construction Quality Reports.

The contractor must obtain a minimum of three (3) grab samples from the channel, three (3) from the eastern deposition basin, and three (3) from the ebb shoal area. Samples must be spaced throughout these areas, and locations must be provided along with grain size analysis. A grain size analysis of each sand sample will be made using sieve sizes comparable to the Wentworth size classifications (shown in Section 00 90 04 WENTWORTH SCALE) and the results plotted on an appropriate curve format. The laboratory analysis results, and plotted grain size distribution curves must be furnished with the Daily Construction Quality Reports.

NOTE: The Contractor is required to conduct a daily toolbox safety meet and include what was discuss on the daily report submitted to the U.S. Army Corps of Engineers.

The following have been deleted:

AMENDMENT 0002

(End of Summary of Changes)