W912DS-17-R-0001-AMENDMENT_0012.pdf

PDF 23 KB Posted

Attached to
Non-Commissioned Officer (NCO) Academy Complex, Fort Drum, New York
Solicitation number
W912DS-17-R-0001
Issued by

About this file

W912DS-17-R-0001-AMENDMENT 0012

View the file

Other files

File Type Posted
C-751.pdf PDF
CP_NCOA-DMMA-CF.pdf PDF
W912DS-17-R-0001-0011.pdf PDF
W912DS-17-R-0001-AMENDMENT_0010.pdf PDF
W912DS-17-R-0001-0010_ET-602_Card_Access_System.pdf PDF
W912DS-17-R-0001-AMENDMENT_0009.pdf PDF
Plan_Set_-_REV1.pdf PDF
W912DS-17-R-0001-AMENDMENT_0008.pdf PDF
NCOA-STRUCT_Amendment7_31Jan2017.pdf PDF
Appendix_J_-_NOI__100__RTA_NCOA_SWPPP_rev01-31-2017-2.pdf PDF
Amend__7_SPECs_Reissued_02-01-17.pdf PDF
100__NCOA_SWPPP_rev01-31-2017_(No_Appendix).pdf PDF
W912DS-17-R-0001-AMENDMENT_0007.pdf PDF
NCOA_Plumbing_Revised_Dwgs_Amend_7.pdf PDF
100pcnt_LEED_Checklist_20160930.pdf PDF
ADDITIONAL_RFIs_20170126_REV.pdf PDF
NCOA_Civil_Dwgs_Amend_7.pdf PDF
W912DS-17-R-0001-0006.pdf PDF
W912DS-17-R-0001-0006.pdf PDF
W912DS-17-R-0001-AMENDMENT_0005.pdf PDF
Fort_Drum_Lab_Data-_500_Area_Buildings_excerpt.pdf PDF
Copy_of_Asbestos_DataRequest_20160315.pdf PDF
Amend__5_SPECs_Reissued_1-22-17.pdf PDF
Amend__5_Arch_Drawings_Reissued_1-20-17_.pdf PDF
C-GP0001_NCOA_Grading_Plan_bound.dwg DWG drawing
PLAN_SET.pdf PDF
C-GP0001_NCOA_Grading_Plan_converted.dgn —
Amend__5_Civil_drawings_reissued.pdf PDF
Fort_Drum_ACM_Report_-_500_Area_Buildings_excerpt.pdf PDF
Copy_of_Lead_DataRequest_20160315.pdf PDF
1-10-17_Site_Visit_Sign_In_roster.pdf PDF
W912DS-17-R-0001-AMENDMENT_0004.pdf PDF
NCOA_INT_REV1.pdf PDF
W912DS-17-R-0001-AMENDMENT_0003.pdf PDF
NCOA_revCivilSheets_12-29-2016.pdf PDF
Sign_In_Roster_for_NCOA_Site_Visit_20_DEC_2016.pdf PDF
W912DS-17-R-0001-AMENDMENT_0002.pdf PDF
RFI-0001_NCOA_DR-WDs.pdf PDF
W912DS-17-R-0001-0001.pdf PDF
Site_Visit_Map.pdf PDF
RTA_100PCNT_DESIGN_-_SPECS_SUBMISSION.pdf PDF
W912DS-17-R-0001_SOLICITATION_FOR_NCO_ACADEMY_COMPLEX_FORT_DRUM_NEW_YORK.pdf PDF
RTA_100PCNT_DESIGN_-_DRAWINGS_SUBMISSION.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912DS-17-R-0001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

a. Revise the Specifications

b. Revise the Draw ings

c. Answ er to Offerors Questions for only information Proposal due date remains 17 February 2017 at 2:00 P.M. Eastern Standard Time

NOTE: Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Feb-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-17-R-0001

X 9B. DATED (SEE ITEM 11)

14-Dec-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Feb-2017

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 73 00 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

AMENDMENT 0012

FY16 NCO Academy Complex Fort Drum, NY

W921DS-17-R-0001

Amendment 0012

AMENDMENT 0012 to DRAWINGS and SPECIFICATIONS for NCO Academy Complex, Fort Drum, NY.

TO OFFERERS

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- Drawing A-104: Add the following General Note: “6. In areas where roof slopes shown on this drawing cannot be achieved utilizing mechanically fastened tapered insulation, the contractor shall provide light gauge metal framing to meet the required slopes. See SK-XXX

2. The following DRAWINGS have been REVISED and REISSUED:

- Drawing C-751

3. The following DRAWINGS have been ADDED:

- SK-1, SK-2 and SK-3.

4. The following DRAWINGS have been DELETED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- None

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- None.

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- Section 02 82 13, para. 1.4.1: Change the following after the last sentence; "Government-provided surveys for asbestos containing materials are likely incomplete and may not meet New York State requirements.

Contractor shall complete new surveys in accordance with New York State Subpart 56-5.1 to determine presence of Asbestos Containing Material and condition. This activity is to be reflected in the schedule."

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

(Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and Answers are issued to the Offerors for information only).

1. With the R60 Insulation you are at a depth of 10" then add the 1"/12' tapered insulation on-top of that and in some places you're at 19" deep if this is mechanically fastened the way the plans and specs indicate they do not make a fastener that long due to shear strength. Is this system supposed to foam applied after the vapor barrier?

Response: Drawing revised with this amendment to address this issue.