NCO ACADEMY COMPLEX DRUMNCOAC
ADDITIONAL RFIS REVS. AFTER AMEND #5
SECTION 01 45 00.00 10
QUALITY CONTROL
02/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D3740 (2012a) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E329 (2014a) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program, and all associated costs will be included in the applicable Bid Schedule prices.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan ; G, RO
SD-06 Test Reports
Verification Statement
PART 2 PRODUCTS
Not Used
SECTION 01 45 00.00 10 Page 1
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system that complies with the Contract Clause titled "Inspection of Construction." QC consist of plans, procedures, and organization necessary to produce an end product which complies with the contract requirements. The QC system must cover all construction operations, both onsite and offsite, and be keyed to the proposed construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
3.2 QUALITY CONTROL PLAN
Submit no later than 90 days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction."
The Government will consider an interim plan for the first 90 days of operation. Construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.
3.2.1 Content of the CQC Plan
Include, as a minimum, the following to cover all construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents :
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Copies of these letters must be furnished to the Government.
d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents . These procedures must be in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SECTION 01 45 00.00 10 Page 2
e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer must be used.)
f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
g. Procedures for tracking construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.
h. Reporting procedures, including proposed reporting formats.
i. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. This list will be agreed upon during the coordination meeting.
j. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections.
3.2.2 Acceptance of Plan
Acceptance of the Contractor's plan is required prior to the start of construction . Acceptance is conditional and will be predicated on satisfactory performance during the construction . The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
3.2.3 Notification of Changes
After acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
3.3 COORDINATION MEETING
After the Preconstruction Conference, before start of construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer or Authorized Representative and discuss the Contractor's quality control system. Submit the CQC Plan a minimum of 14 calendar days prior to the Coordination Meeting. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations , control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the Government, signed by both the Contractor and the Contracting
SECTION 01 45 00.00 10 Page 3
Officer and will become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures which may require corrective action by the Contractor.
3.4 QUALITY CONTROL ORGANIZATION
3.4.1 Personnel Requirements
The requirements for the CQC organization are a Safety and Health Manager, CQC System Manager and sufficient number of additional qualified personnel to ensure safety and contract compliance. The Safety and Health Manager must report directly to a senior project (or corporate) official independent from the CQC System Manager. The Safety and Health Manager will also serve as a member of the CQC Staff Personnel identified in the technical provisions as requiring specialized skills to assure the required work is being performed properly will also be included as part of the CQC organization. The Contractor's CQC staff must maintain a presence at the site at all times during progress of the work and have complete authority and responsibility to take any action necessary to ensure contract compliance. The CQC staff will be subject to acceptance by the Contracting Officer. Provide adequate office space, filing systems and other resources as necessary to maintain an effective and fully functional CQC organization. Promptly complete and furnish all letters, material submittals, shop drawing submittals, schedules and all other project documentation to the CQC organization. The CQC organization is responsible to maintain these documents and records at the site at all times, except as otherwise acceptable to the Contracting Officer.
3.4.2 CQC System Manager
Identify as CQC System Manager an individual within the onsite work organization who is responsible for overall management of CQC and have the authority to act in all CQC matters for the Contractor. The CQC System Manager must be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 2 years construction experience on construction similar to this contract. This CQC System Manager must be on the site at all times during construction and be employed by the prime Contractor. The CQC System Manager must be assigned no other duties .
Identify in the plan an alternate to serve in the event of the CQC System Manager's absence. The requirements for the alternate are the same as the CQC System Manager.
3.4.3 CQC Personnel
In addition to CQC personnel specified elsewhere in the contract, provide as part of the CQC organization specialized personnel to assist the CQC System Manager for the following areas: electrical, mechanical, Cx Agent/LEED Specialist, . These individuals or specialized technical companies must be directly employed by the prime Contractor and may not be employed by a supplier or subcontractor on this project ; be responsible to the CQC System Manager; be physically present at the construction site during work on their areas of responsibility; have the necessary education and/or experience in accordance with the experience matrix listed herein.
These individuals may perform other duties but must be allowed sufficient time to perform their assigned quality control duties as described in the Quality Control Plan.
SECTION 01 45 00.00 10 Page 4
Experience Matrix
Area Qualifications
Civil Graduate Civil Engineer or Construction Manager with 2 years experience in the type of work being performed on this project or technician with 5 yrs related experience
Mechanical Graduate Mechanical Engineer with 2 yrs experience or person with 5 years of experience supervising mechanical features of work in the field with a construction company
Electrical Graduate Electrical Engineer with 2 years related experience or person 5 years of experience supervising electrical features of work in the field with a construction company
Structural Graduate Civil Engineer (with Structural Track or Focus) or Construction Manager with 2 years experience or person 5 years of experience supervising structural features of work in the field with a construction company
Architectural Graduate Architect with 2 years experience or person with 5 years related experience
Environmental Graduate Environmental Engineer with 3 years experience
Submittals Submittal Clerk with 1 year experience
Concrete, Pavements and Soils Materials Technician with 2 years experience for the appropriate area
Testing, Adjusting and Balancing (TAB) Personnel
Specialist must be a member of AABC or an experienced technician of the firm certified by the NEBB
3.4.4 Additional Requirement
In addition to the above experience and education requirements, the CQC System Manager must have completed the Construction Quality Management (CQM) for Contractors course. If the CQC System Manager does not have a current certification, obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.
SECTION 01 45 00.00 10 Page 5
The Construction Quality Management Training certificate expires after 5 years. If the CQC System Manager's certificate has expired, retake the course to remain current.
3.4.5 Organizational Changes
Maintain the CQC staff at full strength at all times. When it is necessary to make changes to the CQC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.
3.5 SUBMITTALS AND DELIVERABLES
Submittals, if needed, must comply with the requirements in Section 01 33 00 SUBMITTAL PROCEDURES. The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the contract requirements. When Section 23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS are included in the contract, the submittals required by those sections must be coordinated with Section 01 33 00 SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required.
3.6 CONTROL
Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control must be conducted by the CQC System Manager for each definable feature of the construction work as follows:
3.6.1 Preparatory Phase
This phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:
a. A review of each paragraph of applicable specifications, reference codes, and standards. Make available during the preparatory inspection a copy of those sections of referenced codes and standards applicable to that portion of the work to be accomplished in the field. Maintain and make available in the field for use by Government personnel until final acceptance of the work.
b. Review of the contract drawings.
c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.
d. Review of provisions that have been made to provide required control inspection and testing.
e. Review Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections.
f. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.
g. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.
SECTION 01 45 00.00 10 Page 6
h. Review of the appropriate activity hazard analysis to assure safety requirements are met.
i. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.
j. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.
k. Discussion of the initial control phase.
l. The Government must be notified at least 48 hours in advance of beginning the preparatory control phase. Include a meeting conducted by the CQC System Manager and attended by the superintendent, other CQC personnel (as applicable), and the foreman responsible for the definable feature. Document the results of the preparatory phase actions by separate minutes prepared by the CQC System Manager and attach to the daily CQC report. Instruct applicable workers as to the acceptable level of workmanship required in order to meet contract specifications.
3.6.2 Initial Phase
This phase is accomplished at the beginning of a definable feature of work. Accomplish the following:
a. Check work to ensure that it is in full compliance with contract requirements. Review minutes of the preparatory meeting.
b. Verify adequacy of controls to ensure full contract compliance.
Verify required control inspection and testing are in conpliance with the contract.
c. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.
d. Resolve all differences.
e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.
f. The Government must be notified at least 48 hours in advance of beginning the initial phase for definable feature of work. Prepare separate minutes of this phase by the CQC System Manager and attach to the daily CQC report. Indicate the exact location of initial phase for definable feature of work for future reference and comparison with follow-up phases.
g. The initial phase for definable feature of work should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.
h. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections.
SECTION 01 45 00.00 10 Page 7
3.6.3 Follow-up Phase
Perform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS, the Statement of Special Inspections and the Schedule of Special Inspections.
3.6.4 Additional Preparatory and Initial Phases
Conduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.
3.7 TESTS
3.7.1 Testing Procedure
Perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements.
Upon request, furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and/or acceptance tests when specified. Procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. Perform the following activities and record and provide the following data:
a. Verify that testing procedures comply with contract requirements.
b. Verify that facilities and testing equipment are available and comply with testing standards.
c. Check test instrument calibration data against certified standards.
d. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
e. Record results of all tests taken, both passing and failing on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. If approved by the Contracting Officer, actual test reports may be submitted later with a reference to the test number and date taken. Provide an information copy of tests performed by an offsite or commercial test facility directly to the Contracting Officer. Failure to submit timely test reports as stated may result in nonpayment for related work performed and disapproval of the test facility for this contract.
3.7.2 Testing Laboratories
The listing of validated testing laboratories is available at
SECTION 01 45 00.00 10 Page 8 http://gsl.erdc.usace.army.mil/SL/MTC/ .
3.7.2.1 Capability Check
The Government reserves the right to check laboratory equipment in the proposed laboratory for compliance with the standards set forth in the contract specifications and to check the laboratory technician's testing procedures and techniques. Laboratories utilized for testing soils, concrete, asphalt, and steel must meet criteria detailed in ASTM D3740 and
ASTM E329.
3.7.2.2 Capability Recheck
If the selected laboratory fails the capability check, the Contractor will be assessed a charge of $7,200 to reimburse the Government for each succeeding recheck of the laboratory or the checking of a subsequently selected laboratory. Such costs will be deducted from the contract amount due the Contractor.
3.7.3 Onsite Laboratory
The Government reserves the right to utilize the Contractor's control testing laboratory and equipment to make assurance tests, and to check the Contractor's testing procedures, techniques, and test results at no additional cost to the Government.
3.8 COMPLETION INSPECTION
3.8.1 Punch-Out Inspection
Conduct an inspection of the work by the CQC System Manager near the end of the work, or any increment of the work established by a time stated in the SPECIAL CONTRACT REQUIREMENTS Clause, "Commencement, Prosecution, and Completion of Work", or by the specifications. Prepare and include in the CQC documentation a punch list of items which do not conform to the approved drawings and specifications, as required by paragraph DOCUMENTATION. Include within the list of deficiencies the estimated date by which the deficiencies will be corrected. Make a second inspection the CQC System Manager or staff to ascertain that all deficiencies have been corrected. Once this is accomplished, notify the Government that the facility is ready for the Government Pre-Final inspection.
3.8.2 Pre-Final Inspection
The Government will perform the pre-final inspection to verify that the facility is complete and ready to be occupied. A Government Pre-Final Punch List may be developed as a result of this inspection. Ensure that all items on this list have been corrected before notifying the Government, so that a Final inspection with the customer can be scheduled. Correct any items noted on the Pre-Final inspection in a timely manner. These inspections and any deficiency corrections required by this paragraph must be accomplished within the time slated for completion of the entire work or any particular increment of the work if the project is divided into increments by separate completion dates.
3.8.3 Final Acceptance Inspection
The Contractor's Quality Control Inspection personnel, plus the superintendent or other primary management person, and the Contracting
SECTION 01 45 00.00 10 Page 9
Officer's Representative must be in attendance at the final acceptance inspection. Additional Government personnel including, but not limited to, those from Base/Post Civil Facility Engineer user groups, and major commands may also be in attendance. The final acceptance inspection will be formally scheduled by the Contracting Officer based upon results of the Pre-Final inspection. Notify the Contracting Officer at least 14 days prior to the final acceptance inspection and include the Contractor's assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date scheduled for the final acceptance inspection. Failure of the Contractor to have all contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the contract clause titled "Inspection of Construction".
3.9 DOCUMENTATION
Maintain current records providing factual evidence that required quality control activities and/or tests have been performed. Include in these records the work of subcontractors and suppliers on an acceptable form that includes, as a minimum, the following information:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Work performed each day, giving location, description, and by whom.
When Network Analysis (NAS) is used, identify each phase of work performed each day by NAS activity number.
d. Test and/or control activities performed with results and references to specifications/drawings requirements. Identify the control phase (Preparatory, Initial, Follow-up). List of deficiencies noted, along with corrective action.
e. Quantity of materials received at the site with statement as to acceptability, storage, and reference to specifications/drawings requirements.
f. Submittals and deliverables reviewed, with contract reference, by whom, and action taken.
g. Offsite surveillance activities, including actions taken.
h. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
i. Instructions given/received and conflicts in plans and/or specifications.
k. Contractor's Verification Statement .
Indicate a description of trades working on the project; the number of personnel working; weather conditions encountered; and any delays encountered. Cover both conforming and deficient features and include a statement that equipment and materials incorporated in the work and
SECTION 01 45 00.00 10 Page 10 workmanship comply with the contract. Furnish the original and one copy of these records in report form to the Government daily within 16 hours after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit one report for every 7 days of no work and on the last day of a no work period. All calendar days must be accounted for throughout the life of the contract. The first report following a day of no work will be for that day only. Reports must be signed and dated by the CQC System Manager. Include copies of test reports and copies of reports prepared by all subordinate quality control personnel within the CQC System Manager Report.
3.10 SAMPLE FORMS
Sample forms enclosed at the end of this section.
3.11 NOTIFICATION OF NONCOMPLIANCE
The Contracting Officer will notify the Contractor of any detected noncompliance with the foregoing requirements. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification. If the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders will be made the subject of claim for extension of time or for excess costs or damages by the Contractor.
-- End of Section --
SECTION 01 45 00.00 10 Page 11
SECTION 01 45 20.00 18
TESTING FOR MECHANICAL AND ELECTRICAL SYSTEMS
NY Dist. Sept. 2003
PART 1 GENERAL
1.1 APPLICABILITY
This section applies to all mechanical and electrical systems and all systems using electromagnetically driven equipment, pneumatic or electronic systems; high and low voltage electrical distribution systems (except branch panels) and to any system which incorporates this section into other parts of the specification by reference. For purposes of this section a "system" is an entity comprised of a series of closely related interdependent components and which is capable of independent performance of a useful function. System components shall include all software and programming as applicable for the system. Some typical examples include:
a. Independently functioning HVAC Systems.
b. Fire Alarm Systems.
c. Public Address Systems.
d. Sprinkler Systems including alarms.
e. Telephone Systems including line protectors, splices cables, switching equipment, outlets and instruments.
f. Intrusion Detection System.
g. High Voltage Equipment including cable, splices, switchgear, relays, circuit breakers, fuses, transformers, instrumentation, etc.
h. Low Voltage Switchboard including incoming and outgoing feeders, circuit protection and all accessories.
1.2 TEST PLAN
a. Not later than sixty days after Notice to Proceed, in accordance with Section "Submittals" and other paragraphs of the technical provisions, the Contractor shall submit a list for approval consisting of all systems for which test plans are required. This list will be reviewed by the Government and any systems found to be missing will be required to be added by the Contractor, and appropriate test plans submitted. No work will be permitted on any of the above systems until this list is submitted.
b. The Contractor shall develop test plans and schedule operational testing for the systems in the approved list. The testing shall be in accordance with the requirements in the appropriate technical provisions and shall include as a minimum the requirements below. All testing required by applicable codes, standards, utility companies, manufacturers, suppliers, etc. shall be incorporated into the Contractor's test plans.
Test plans shall list all equipment required to perform the tests, and any Government support required. It shall be in sufficient detail to permit a step by step approach to the test and to demonstrate that the systems
SECTION 01 45 20.00 18 Page 1 operate as intended by the contract documents. It shall describe as a minimum:
1. What system is being tested including a listing of all components to be tested.
2. What individual or organization will perform testing, who will certify the tests, and qualifications of test personnel.
3. A step by step narrative of the testing procedure to be used to demonstrate contract compliance including all governing standards, such as "sequence of controls", "ASTM Standard XXX"; or IEEE Standard XXX", etc.
4. What testing equipment will be utilized.
5. What operator interaction is required.
6. What results are to be expected.
7. Seasonal limitations, if any, including date(s) of proposed testing.
8. A complete schematic diagram (electrical, pneumatic) showing all components, and block diagram.
9. A checklist shall be developed to be used during the operational test.
c. Test plans shall be submitted for approval for all systems contained on the list submitted per paragraph 2a above. It is also desirable to submit all test plans as soon as possible so that the progress of the project and corresponding payments will proceed on schedule.
1.3 TESTING PROCESS
a. Outlined below are a number of events relating to the status of the test plan and testing. The corresponding percentages indicate the maximum percentage of the value of the system which will be permitted to be installed after the successful completion of the corresponding event indicated, for all systems to which this section applies. Events must be completed sequentially. Any work performed in excess of the permitted percentages will be at the Contractor's own risk and will not be paid until the event corresponding to the percentage of system value permitted to be installed is successfully completed:
EVENT MAX. % of SYSTEM
VALUE PERMITTED TO BE INSTALLED
1. Contractor has submitted list 50 of systems that require test plans to be approved, and system work is ongoing but no test plan submitted.
2. Test Plan Submitted 65
3. *Test Plan Approved 80
4. Successful completion of tests **100 including submission of required
SECTION 01 45 20.00 18 Page 2 documents, reports (i.e. balancing reports for all HVAC Systems), Operation and Maintenance Manuals spare parts, and spare parts data.
* The Government will process the submittal in accordance with the time frames indicated in the specification section "Submittals". If the test plan is disapproved the Government has an additional 30 days to review the resubmittal from the date it receives the resubmittal.
**If a system involves both heating and cooling modes and one mode has been successfully tested this percentage shall be reduced to 90% until the testing is completed.
b. The Contractor may proceed with events as indicated in the above table for each system separately.
1.4 OPERATIONAL TESTS
Operational tests including performance tests shall be conducted for an entire system, not component parts only. Tests may be conducted only after an entire system has been completely installed. Contractor shall provide a minimum of 14 days notice to the Contracting Officer of scheduled tests.
This notice must include the Contractor's assurance that all installed work previously identified to the Contractor as being unacceptable along with all remaining work associated with the respective system will be complete and acceptable by the date scheduled for the operational test.
Failure of the Contractor to have all contract work acceptably complete for this test will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection costs.
1.5 TESTING QUALIFICATIONS
For each system the Contractor shall obtain the services of an experienced professional who shall certify that the operational test was conducted in accordance with the approved test plan and the results of this test meet all the contract requirements. These individuals must have a minimum of eight years experience in the testing of the particular system being tested and shall also meet qualifications (if any) set forth in other technical sections of the contract specifications.
1.6 DESIGNER OF RECORD PARTICIPATION
Designer of Record for the system shall participate in HVAC System Commissioning.
1.7 COMPONENTS
When considering the value of a system for payment purposes the following components shall be counted as part of a "system": All electromagnetically driven equipment; pneumatic or electric control system; gauges, dampers, valves, actuators, controllers, pipes, test sensing elements, logic/processors, CPU's, ducts, insulation, wiring, conduit, switchgear, and all other mechanical or electrical components, devices or equipment which are essential to the proper function of the system such as pumps, motors, air handling units, chillers, cooling towers, etc. Software programs and any refrigerants are also considered "parts" of a system.
SECTION 01 45 20.00 18 Page 3
1.8 TESTING CONFLICTS
The requirements contained in this section supplement other testing requirements contained in the contract documents. If a conflict exists between the requirements of this section and other parts of the contract documents, the requirements of this section shall take precedence.
1.9 COMMISSIONING FUNCTIONAL TESTING
Completion of commissioning functional testing shall be accomplished as a pre-requisite for the final inspection. See Section 01 80 00 COMMISSIONING, 23 08 00.00 10 COMMISSIONING OF HVAC SYSTEMS and
26 08 00.00 23 COMMISSIONING OF ELECTRICAL SYSTEMS.
PART 2 PRODUCTS Not Applicable
PART 3 EXECUTION Not Applicable
-- End of Section --
SECTION 01 45 20.00 18 Page 4
SECTION 03 30 00.00 10
CAST-IN-PLACE CONCRETE
05/14
PART 1 GENERAL
1.1 LUMP SUM CONTRACT
Under this type of contract, concrete items will be paid for by lump sum and will not be measured. The work covered by these items consists of furnishing all concrete materials, reinforcement, miscellaneous embedded materials, and equipment, and performing all labor for the forming, manufacture, transporting, placing, finishing, curing, and protection of concrete in these structures.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO
ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete
ACI 211.2 (1998; R 2004) Standard Practice for Selecting Proportions for Structural Lightweight Concrete
ACI 213R (2014) Guide for Structural Lightweight-Aggregate Concrete
ACI 214R (2011) Evaluation of Strength Test Results of Concrete
ACI 301 (2010; ERTA 2015) Specifications for Structural Concrete
ACI 302.1R (2004; Errata 2006; Errata 2007) Guide for Concrete Floor and Slab Construction
ACI 304.2R (1996; R 2008) Placing Concrete by Pumping Methods
ACI 304R (2000; R 2009) Guide for Measuring, SECTION 03 30 00.00 10 Page 1
Mixing, Transporting, and Placing Concrete
ACI 305.1 (2014) Specification for Hot Weather Concreting
ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting
ACI 309R (2005) Guide for Consolidation of Concrete
ACI 318 (2014; Errata 1-2 2014; Errata 3-4 2015) Building Code Requirements for Structural Concrete and Commentary
ACI SP-15 (2011) Field Reference Manual: Standard Specifications for Structural Concrete ACI 301-05 with Selected ACI References
ASTM INTERNATIONAL (ASTM)
ASTM C1017/C1017M (2013; E 2015) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete
ASTM C1064/C1064M (2011) Standard Test Method for Temperature of Freshly Mixed Hydraulic-Cement Concrete
ASTM C1077 (2015) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation
ASTM C1107/C1107M (2014a) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
ASTM E1155 (2014) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers
ASTM C1260 (2014) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C136/C136M (2014) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM C143/C143M (2012) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2015) Standard Specification for Portland Cement
ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
SECTION 03 30 00.00 10 Page 2
ASTM C172/C172M (2014a) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C192/C192M (2015) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory
ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C309 (2011) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C31/C31M (2012) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C311/C311M (2013) Sampling and Testing Fly Ash or Natural Pozzolans for Use as a Mineral Admixture in Portland-Cement Concrete
ASTM C33/C33M (2013) Standard Specification for Concrete Aggregates
ASTM C330/C330M (2014) Standard Specification for Lightweight Aggregates for Structural Concrete
ASTM C39/C39M (2015a) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C42/C42M (2013) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C494/C494M (2015a) Standard Specification for Chemical Admixtures for Concrete
ASTM C552 (2015) Standard Specification for Cellular Glass Thermal Insulation
ASTM C567/C567M (2014) Determining Density of Structural Lightweight Concrete
ASTM C578 (2015b) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
ASTM C591 (2015) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation
SECTION 03 30 00.00 10 Page 3
ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C78/C78M (2015a) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)
ASTM C937 (2010) Grout Fluidifier for Preplaced-Aggregate Concrete
ASTM C94/C94M (2015) Standard Specification for Ready-Mixed Concrete
ASTM C989/C989M (2014) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM D5759 (2012) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses
ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates
ASTM E1643 (2011) Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs
ASTM E1745 (2011) Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs
ASTM E1993/E1993M (1998; R 2013; E 2013) Standard Specification for Bituminous Water Vapor Retarders Used in Contact with Soil or Granular Fill Under Concrete Slabs
ASTM E96/E96M (2014) Standard Test Methods for Water Vapor Transmission of Materials
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
CRSI 10MSP (2009; 28th Ed) Manual of Standard Practice
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST HB 44 (2013) Specifications, Tolerances, and Other Technical Requirements for Weighing and Measuring Devices
NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)
NRMCA CPMB 100 (2000; R 2006) Concrete Plant Standards
NRMCA QC 3 (2011) Quality Control Manual: Section 3, Plant Certifications Checklist:
Certification of Ready Mixed Concrete
SECTION 03 30 00.00 10 Page 4
Production Facilities
NRMCA TMMB 100 (2001; R 2007) Truck Mixer, Agitator and Front Discharge Concrete Carrier Standards
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 104 (1980) Method of Calculation of the Fineness Modulus of Aggregate
1.3 Definitions
1.3.1 Cementitious Material
As used herein, includes all portland cement, pozzolan, fly ash, ground granulated blast-furnace slag.
1.3.2 Chemical Admixtures
Materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.
1.3.3 Complementary Cementing Materials (CCM)
Coal fly ash, silica fume, granulated blast-furnace slag, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in considerable improvement to sustainability, durability.
1.3.4 Design Strength (f'c)
The specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.
1.3.5 Mass Concrete
Any concrete system that approaches a maximum temperature of 158 degrees F within the first 72 hours of placement. In addition, it includes all concrete elements with a section thickness of 3 feet or more regardless of temperature.
1.3.6 Mixture Proportioning
The process of designing concrete mixture proportions to enable it to meet the strength, service life and constructability requirements of the project.
1.3.7 Mixture Proportions
The masses or volumes of individual ingredients used to make a unit measure (cubic yard ) of concrete.
1.3.8 Pozzolan
Siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.
SECTION 03 30 00.00 10 Page 5
1.3.9 Workability or Consistency
The ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality. Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Quality Control Plan ; G, RO Laboratory Accreditation Sampling Plan ; G
SD-03 Product Data
Recycled Content Products ; (LEED) Cementitious Materials Vapor Retarder Vapor Barrier Floor Finish Floor Hardener Chemical Admixtures
SD-04 Samples
Surface Retarder
SD-05 Design Data
Mixture Proportions ; G, DO Lightweight Aggregate Concrete
SD-06 Test Reports
Mixture Proportions ; G, DO Testing and Inspection for CQC ; G, RO Fly Ash Ground Granulated Blast-Furnace (GGBF) Slag Aggregates Air Content Slump Compressive Strength Water
SD-07 Certificates
Contractor Quality Control personnel
SECTION 03 30 00.00 10 Page 6
Ready-Mix Plant
1.5 QUALITY ASSURANCE
Submit qualifications for Contractor Quality Control personnel assigned to concrete construction as American Concrete Institute (ACI) Certified Workmen in one of the following grades or show written evidence of having completed similar qualification programs:
Concrete Field Testing Technician Grade I
Concrete Laboratory Testing Technician Grade I or II
Concrete Construction Inspector Level II
Concrete Transportation Construction Inspector or Reinforced Concrete Special Inspector
Jointly certified by American Concrete Institute (ACI), Building Official and Code Administrators International (BOCA), International Code Council (ICC), and Southern Building Code Congress International (SBCCI)
Foreman or Lead Journeyman of the flatwork finishing crew
Similar qualification for ACI Concrete Flatwork Technician/Finisher or equal, with written documentation
1.5.1 Laboratory Accreditation
Provide laboratory and testing facilities. The laboratories performing the tests must be accredited in accordance with ASTM C1077, including ASTM C78/C78M and ASTM C1260. The accreditation must be current and must include the required test methods, as specified. Furthermore, the testing must comply with the following requirements:
1.5.1.1 Aggregate Testing and Mix Proportioning
Perform aggregate testing and mixture proportioning studies in an accredited laboratory, under the direction of a registered professional engineer in a U.S. state or territory who is competent in concrete materials. This person is required to sign all reports and designs.
1.5.1.2 Acceptance Testing
Furnish all materials, labor, and facilities required for molding, curing, testing, and protecting test specimens at the site and in the laboratory.
Furnish and maintain boxes or other facilities suitable for storing and curing the specimens at the site while in the mold within the temperature range stipulated by ASTM C31/C31M.
1.5.1.3 Contractor Quality Control
All sampling and testing must be performed by an approved, onsite, independent, accredited laboratory.
SECTION 03 30 00.00 10 Page 7
1.5.2 Quality Control Plan
Submit a concrete quality control program in accordance with the guidelines of ACI 121R and as specified herein. Identify the approved laboratories. Provide direct oversight for the concrete qualification program inclusive of associated sampling and testing. Provide all quality control reports to the Quality Manager, Concrete Supplier and the Contracting Officer. Maintain a copy of ACI SP-15 and CRSI 10MSP at the project site.
1.5.3 Pre-installation Meeting
A pre-installation meeting with the Contracting Officer is required at least 10 days prior to start of construction of concrete elements.
Conduct the meeting with the Project Superintendent and active installation personnel present.
1.5.4 Special Properties and Products
Concrete may contain admixtures other than air entraining agents, such as water reducers, superplasticizers, or set retarding agents to provide special properties to the concrete, if specified or approved. Include any of these materials to be used on the project in the mix design studies.
1.5.5 Government Assurance Inspection and Testing
Day-to day inspection and testing is the responsibility of the Contractor Quality Control (CQC) staff. However, representatives of the Contracting Officer can and will inspect construction as considered appropriate and will monitor operations of the CQC staff. Government inspection or testing will not relieve any CQC responsibilities.
1.5.5.1 Materials
The Government will sample and test aggregates, cementitious materials, other materials, and concrete to determine compliance with the specifications as considered appropriate. Provide facilities and labor as may be necessary for procurement of representative test samples. Samples of aggregates will be obtained at the point of batching in accordance with ASTM D75/D75M. Other materials will be sampled from storage at the jobsite or from other locations as considered appropriate. Samples may be placed in storage for later testing when appropriate.
1.5.5.2 Fresh Concrete
Fresh concrete will be sampled as delivered in accordance with ASTM C172/C172M and tested in accordance with these specifications, as considered necessary.
1.5.5.3 Hardened Concrete
Tests on hardened concrete will be performed by the Government when such tests are considered necessary.
1.5.5.4 Inspection
Concrete operations may be tested and inspected by the Government as the project progresses. Failure to detect defective work or material will not prevent rejection later when a defect is discovered nor will it obligate
SECTION 03 30 00.00 10 Page 8 the Government for final acceptance.
1.6 DELIVERY, STORAGE, AND HANDLING
Follow ACI 301 and ACI 304R requirements and recommendations.