Section_J_-_VA0092771_Modified_Permit_May_2017.pdf

PDF 1 MB Posted

Attached to
Environmental Remediation Services at Fort Belvoir, Virginia
Solicitation number
W912DR-19-R-0015
Issued by

About this file

This document contains a modified Virginia Pollutant Discharge Elimination System permit and a pre-solicitation notice for an environmental remediation services contract.

The modified VPDES permit corrects a typographical error to the quantification limit for iron at Outfall 019 for the U.S. Army Garrison at Fort Belvoir. The pre-solicitation notice indicates that the U.S. Army Corps of Engineers Baltimore District intends to issue a request for proposal for environmental remediation services at Fort Belvoir, Virginia in July 2019. The services will include environmental compliance, restoration, conservation, pollution prevention and management. The single-award task order contract will have a ceiling of $45 million over a base year and four option years. Offerors must register in SAM to participate. The pre-solicitation provides notice that the solicitation will have a total small business set-aside and identifies the NAICS code and size standard.

VA0092771 Modified Permit

View the file

Other files

File Type Posted
B.08.03_Solicitation_Amendment_4_07NOV2019.pdf PDF
B.08.03_Solicitation_Amendment_3_06NOV2019.pdf PDF
RFI_questions_and_responses_10-31-19_.pdf PDF
Section_J_-_Calibration_Protocols.pdf PDF
Section_J_-_SAA_DPW-ENRD_Inspection_Checklist_rev7MAY14.pdf PDF
Section_J_-_SAA_ECO_Inspection_Checklist_rev11JUN14.pdf PDF
B.08.03_Solicitation_Amendment_30OCT2019.pdf PDF
Section_J_-_Datasheet_template.pdf PDF
Section_J_-_APP_N_-_CFR-2012-title49-vol2-sec172-400.pdf PDF
Section_J_-_HWMMP_Dec_2014.pdf PDF
Section_J_-_Turn-in_Form.pdf PDF
Section_J_-_Guide_for_SamplingRedacted_Redacted.pdf PDF
Section_J_-_APP_M_-_90-Day_HWAS_Management_Flowchart-rev4APR14.pdf PDF
Section_J_-_APP_I_-Permitted_Facility_Inventory.pdf PDF
Section_J_-_81599_Fort_Belvoir_-_Rivanna_Station_Minor_NSR_Permit_Redacted.pdf PDF
Section_J_-_MS4_Permit_VAR040093_29_November_2018_-_31_October_2023.pdf PDF
Section_J_-16_AUG_16_-_NSR_-_North_Area_73630_Redacted.pdf PDF
Section_J_-_Visual_Assessment_template.pdf PDF
Section_J_-_Label_Reference_Sheet.pdf PDF
Section_J_-_APP_L_-_HM_HW_Compatability_Chart.pdf PDF
Section_J_-_APP_K_-_SAA_Flowcharts.pdf PDF
Section_J_-_REP_Analytes.pdf PDF
Section_J_-_21_MAR_03_-_Title_V_Permit_70550_Redacted.pdf PDF
Section_J_-_APP_H_-_Inspection_Forms.pdf PDF
CAA_Response_to_Comments_FTBL_SATOC_Solicitation_2019.docx DOCX document
Section_J_-_Fort_Belvoir_SPCC_Plan_Signed_and_Approved_-_updated_September_2017.pdf PDF
Section_J_-_Field_Note_Reference_Sheet.pdf PDF
Section_J_-_RCRA_Final_Permit_with_Class_1_Modification_May2019.pdf PDF
Section_J_-_17_JUN_16_-_NSR_-_Consolidated_Permit_70550_Redacted.pdf PDF
Section_J_-_APP_J_-_HW_Identification_And_Classification_Flowchart.pdf PDF
B.08.02_Solicitation_W912DR19R0015-0001_24OCT2019.pdf PDF
Price_Schedule_16OCT2019.pdf PDF
Solicitation_W912DR19R0015_09OCT2019.pdf PDF
SF_LLL.pdf PDF
Past_Performance_Questionnaire_Template.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH of VIRGINIA

DEPARTMENT OF ENVIRONMENTAL QUALITY

NORTHERN REGIONAL OFFICE

13901 Crown Court, Woodbridge, Virginia 22193

(703) 583-3800 www.deq.virginia.gov

Molly Joseph Ward

Secretary of Natural Resources David K. Paylor

Director

Thomas A. Faha

Regional Director

May 8, 2017

Colonel Angelia K. Holbrook

Garrison Commander

Department of the Army

U.S. Army Garrison, Fort Belvoir

Command Group

9820 Flagler Road

Fort Belvoir, VA 22060-5932

CERTIFIED MAIL

RETURN RECEIPT REQUESTED

Re: Minor Modification of Virginia Pollutant Discharge Elimination System (VPDES) Permit No. VA0092771

U.S. Army Garrison - Fort Belvoir, Fairfax County

Dear Colonel Holbrook:

In response to requests dated March 23, 2017, from Fort Belvoir staff please find enclosed the modified permit for the U.S. Army

Garrison - Fort Belvoir. Pursuant to 9VAC25-151-400, minor modifications of the permit may be made to make corrections to typographical errors. Such minor modifications are not subject to the requirements for development of a draft permit or public review

(9VAC25-31-370).

The following typographical error was corrected with this modification:

Part I.A.18 – Outfall 019: The quantification limit for Iron was corrected as follows:

January 1, 2017 (Issuance) May 8, 2017 (Modification)

Parameter QL Parameter QL

Iron 1.0 µg/L Iron 1.0 mg/L

The above modification does not affect any effluent limitations or monitoring requirements previously established for the above referenced permit. Should you have any questions about the permit, please contact Susan Mackert at (703) 583-3853, or by E-mail at susan.mackert@deq.virginia.gov.

mailto:susan.mackert@deq.virginia.gov

VA0092771

Modified Permit to Facility May 8, 2017

Respectfully, <g J

Bryant Thomas Water Permits & Planning Manager

Enc. : Permit for VA0092771

Ec: Bill Sanders (william. l. sanders34. civ(5:;mail. mil) Sybille Vega (sybille. r. vega. civ(%mail. mil) Wilamena Harback (wilamena.g.harback.civ(%mail.mil) DEQ-Water, OWPP EPA-RegionIII,3WP12 Department of Health, Culpeper Water Compliance, NRO

COMMONWEALTH of VIRGINIA

DEPARTMENT OF ENVIRONMENTAL QUALITY

Permit No. VA0092771 Effective Date: January 1, 2017

Minor Modification Date: May 8, 2017 Expiration Date: December 31, 2021

AUTHORIZATION TO DISCHARGE UNDER THE

VIRGINIA POLLUTANT DISCHARGE ELIMINATION SYSTEM

AND THE VIRGINIA STATE WATER CONTROL LAW

In compliance with the provisions of the Clean Water Act as amended and pursuant to the State Water Control Law and regulations adopted pursuant thereto, the following owner is authorized to discharge in accordance with the information submitted with the permit application, and with this permit cover page, Part I - Effluent Limitations and Monitoring Requirements, and Part II - Conditions Applicable To All VPDES Permits, and Part Ill - Industrial Stormwater Management as set forth herein.

Owner Name: United States Department of the Army

Facility Name: U.S. Army Garrison - Fort Belvoir

County: Fairfax

Facility Location: U.S. Route 1 , Fort Belvoir, VA 22060

The owner is authorized to discharge to the following receiving streams:

Stream Name:

River Basin:

River Subbasin:

Section:

Class:

Special Standards:

Accotink Bay, UT; Accotink Creek, UT; Dogue Creek, UT Gunston Cove, UT; Mason Run; Mason Run, UT

Potomac River

Potomac River in b (Not Applicable)

Dogue Creek; Gunston Cove

Potomac River

Potomac River

II

b, y (Not Applicable)

Thomas A. Faha

Director, Northern Regional Office rv I a A. 8^ , ^i-^

Part I

A. Stormwater Monitoring Requirements

1. Outfall 001 – Davison Army Airfield North

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 001. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 001 is substantially identical to Outfall 4942. Discharge data from Outfall 001 may be submitted to represent this outfall.

Parameter Discharge Limitations Monitoring Requirements

Monthly Average (1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(7) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,8) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Copper, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(6) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

(2) The average flow is variable. NA = Not applicable.

NL = No limit; monitor and report.

S.U. = Standard units.

(3) Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5) Samples shall be collected during each of the first four semi-annual monitoring periods.

(6)

Samples for metals and hardness shall be collected concurrently.

(7) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L;

Dissolved Copper – 14 ug/L.

(8) The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Copper – 2.8 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 th day of the month following the monitoring period (July 10 and January 10, respectively).

Grab = An individual sample collected over a period of time not to exceed 15-minutes.

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

2. Outfall 002 – Davison Army Airfield East

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 002. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 002 is substantially identical to Outfalls 4715, 4842, 4843, 4844, 4847, 4852, 4868, 4870, 4910, 4911, 4928, 4940, 4948, 4954, 4956, and 4958. Discharge data from Outfall 002 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Propylene Glycol(8) NA NA NA NL (mg/L) 1/6M Grab

Specific Conductance(8) NA NA NA NL (µmhos/cm) 1/6M Grab

Dissolved Oxygen (D.O.)(8) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

(2) The average flow is variable. NA = Not applicable.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5) Samples shall be collected during each of the first four semi-annual monitoring periods.

(6) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L.

(7) The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L.

(8) Samples for propylene glycol, specific conductance, and dissolved oxygen shall be collected during the months of October – April within the semi-annual monitoring period (January 1 – June 30 and July 1 – December 31) when a runoff event occurs and deicing activities have taken place.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

3. Outfall 003 – Davison Army Airfield South

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 003. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 003 is substantially identical to Outfalls 4668, 4669, 4670, 4671, 4696, and 4706. Discharge data from Outfall 003 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5) Samples shall be collected during each of the first four semi-annual monitoring periods.

(6) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L.

(7) The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

4. Outfall 004 – Belvoir Training Area

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 004. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 004 is substantially identical to Outfalls 3302, 3992, 3993, 4430, 4432, 4434, 4435, 4442, 4444, 4446, 4450, and 4452.

Discharge data from Outfall 004 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,3) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(4,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(4) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,4) NA NA NA NL (mg/L) 1/6M Grab

Lead, Dissolved(5,7) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(4)

Samples shall be collected during each of the first four semi-annual monitoring periods.

(5)

Samples for metals and hardness shall be collected concurrently.

(6)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L.

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TKN – 0.50 mg/L; Lead – 0.5 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

5. Outfall 005 –HazWaste Facility (<90 day)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 005. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 005 is substantially identical to Outfall 2759. Discharge data from Outfall 005 may be submitted to represent this outfall.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(7) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Organic Carbon (TOC)(7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(8) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Arsenic, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Cadmium, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Chromium, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Lead, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Lead, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Magnesium, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Mercury, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Selenium, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Silver, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(6) NA NA NA NL (mg/L) 1/6M Grab

Cyanide, Total(7) NA NA NA NL (µg/L) 1/6M Grab

NL (µg/L) NL (µg/L) NA NA 1/6M Grab (1)

See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5) Samples shall be collected during each of the first four semi-annual monitoring periods.

(6) Samples for metals and hardness shall be collected concurrently.

(7) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TKN – 1.5 mg/L;

TOC – 110 mg/L; Total Recoverable Arsenic – 50 µg/L; Total Recoverable Cadmium – 2.1 µg/L; Dissolved Copper – 14 µg/L; Dissolved Lead – 16 µg/L;

Total Recoverable Lead – 120 µg/L; Total Recoverable Magnesium – 64 µg/L; Total Recoverable Mercury – 1.4 µg/L; Dissolved Nickel – 32 µg/L;

Total Recoverable Selenium – 5.0 µg/L; Total Recoverable Silver – 3.8 µg/L; Total Cyanide – 22 µg/L.

(8)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TKN – 0.50 mg/L; Arsenic - 90 µg/L; Cadmium – 0.39 µg/L;

Copper – 2.8 µg/L; Lead – 3.4 µg/L; Mercury – 1.0 µg/L; Nickel – 6.8 µg/L; Selenium – 3.0 µg/L; Silver – 0.42 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

6. Outfall 006 – National Guard Motor Pool

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 006. Such discharges shall be monitored by the permittee as specified below.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected each of the first four semi-annual monitoring periods.

(6)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L.

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

7. Outfall 007 – 21 st Waste Facility

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 007. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 007 is substantially identical to Outfalls 2823, 2829, and 2832. Discharge data from Outfall 007 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,3) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(4,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(4) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,4) NA NA NA NL (mg/L) 1/6M Grab

Copper, Dissolved(5,6,7) NA NA NA NL (µg/L) 1/6M Grab

Lead, Dissolved(5,6,7) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(5,7) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(4)

Samples shall be collected each of the first four semi-annual monitoring periods.

(5)

Samples for metals and hardness shall be collected concurrently.

(6)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; Dissolved Copper – 14 µg/L;

Dissolved Lead – 16 µg/L.

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TKN – 0.50 mg/L; Copper – 2.8 µg/L; Lead – 3.4 µg/L; Nickel – 6.8 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

8. Outfall 008 – Aerospace Data Facility (NE)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 008. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 008 is substantially identical to Outfalls 5015, 5017, 5018, 5021, 5026, 5028, and 5038. Discharge data from Outfall 008 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(8) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(8,9) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,8,9) NA NA NA NL (mg/L) 1/6M Grab

Total Organic Carbon (TOC)(8) NA NA NA NL (mg/L) 1/6M Grab

Chloride(7) NA NA NA NL (mg/L) 1/6M Grab

Total Dissolved Solids (TDS)(7) NA NA NA NL (mg/L) 1/6M Grab

Specific Conductance(7) NA NA NA NL (µmhos/cm) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(8,9) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Arsenic, Total Recoverable(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Cadmium, Total Recoverable(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Lead, Total Recoverable(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Magnesium, Total Recoverable(6,8) NA NA NA NL (µg/L) 1/6M Grab

Mercury, Total Recoverable(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Selenium, Total Recoverable(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Silver, Total Recoverable(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

Cyanide, Total(8) NA NA NA NL (µg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4) Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected during each of the first four semi-annual monitoring periods.

(6)

Samples for metals and hardness shall be collected concurrently.

(7) Samples for chloride, total dissolved solids, and specific conductance shall be collected during the winter months associated with the semi-annual monitoring period

(January 1 – June 30 and July 1 – December 31) when salt movements are occurring and/or salt is being applied.

(8)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L; TKN – 1.5 mg/L;

TOC – 110 mg/L; Total Recoverable Arsenic – 50 µg/L; Total Recoverable Cadmium – 2.1 µg/L; Dissolved Copper – 14 µg/L; Total Recoverable Lead – 120 µg/L;

Total Recoverable Magnesium – 64 µg/L; Total Recoverable Mercury – 1.4 µg/L; Total Recoverable Selenium – 5.0 µg/L; Total Recoverable Silver – 3.8 µg/L;

Total Cyanide – 22 µg/L.

(9)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Arsenic - 90 µg/L; Cadmium – 0.39 µg/L;

Copper – 2.8 µg/L; Lead – 3.4 µg/L; Mercury – 1.0 µg/L; Nickel – 0.5 µg/L; Selenium – 3.0 µg/L; Silver – 0.42 µg/L.

A. Stormwater Monitoring Requirements

8. Outfall 008 – Aerospace Data Facility (NE) Continued

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 1 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

9. Outfall 009 – Swank-Snyder Golf Course

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 009. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 009 is substantially identical to Outfalls 4040, 4042, 4044, 4050, 4052, 4054, 4300, 5318, 5320, 5321, 5594, 5596, 5597, 5726, 5729, 5767, 5768, 5779, 5782, 5784, 5788, and 5844. Discharge data from Outfall 009 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(7) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Chloride(6) NA NA NA NL (mg/L) 1/6M Grab

Total Dissolved Solids (TDS)(6) NA NA NA NL (mg/L) 1/6M Grab

Specific Conductance(6) NA NA NA NL (µmhos/cm) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(8) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1) NA NA NA NL (mg/L) 1/6M Grab

Copper, Dissolved(5,7,8) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(5,7,8) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests.

(5)

Samples for metals and hardness shall be collected concurrently.

(6)

Samples for chloride, total dissolved solids, and specific conductance shall be collected during the winter months associated with the semi-annual monitoring period (January 1 – June 30 and July 1 – December 31) when salt movements are occurring and/or salt is being applied.

(7) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L;

Dissolved Copper – 14 µg/L; Dissolved Nickel – 32 µg/L.

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Copper – 2.8 µg/L; Nickel – 6.8 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

10. Outfall 010 – 249 th

Prime Power Motor Pool (Meade Road)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the outfall is removed due to construction or the expiration date, whichever comes first, the permittee is authorized to discharge from Outfall Number 010. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 010 is substantially identical to Outfalls 3243, 3258, and 3260. Discharge data from Outfall 010 may be submitted to

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected each of the first four semi-annual monitoring periods.

(6)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L.

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

11. Outfall 011 – 12 th

Aviation Motor Pool / Washrack

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 011. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 011 is substantially identical to Outfalls 3209, 3211, 3215, 3220, and 3222. Discharge data from Outfall 011 may be

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected during each of the first four semi-annual monitoring periods.

(6)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L.

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

12. Outfall 012 – Mosby Center

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 012. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 012 is substantially identical to Outfalls 5510, 5512, 5514, 5521, 5737, and 5740. Discharge data from Outfall 012 may be

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(7) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Organic Carbon (TOC)(7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Arsenic, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Cadmium, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Chromium, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Lead, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Magnesium, Total Recoverable(6,7) NA NA NA NL (µg/L) 1/6M Grab

Mercury, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Selenium, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Silver, Total Recoverable(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

Cyanide, Total(7) NA NA NA NL (µg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4) Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected during each of the first four semi-annual monitoring periods.

(6)

Samples for metals and hardness shall be collected concurrently.

(7) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L; TKN – 1.5 mg/L:

TOC – 110 mg/L; Total Recoverable Arsenic – 50 µg/L; Total Recoverable Cadmium – 2.1 µg/L; Dissolved Copper – 14 µg/L; Total Recoverable Lead – 120 µg/L;

Total Recoverable Magnesium – 64 µg/L; Total Recoverable Mercury – 1.4 µg/L; Total Recoverable Selenium – 5.0 µg/L; Total Recoverable Silver – 3.8 µg/L;

Total Cyanide – 22 µg/L.

(8)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Arsenic - 90 µg/L; Cadmium – 0.39 µg/L;

Chromium – 0.5 µg/L; Copper – 2.8 µg/L; Lead – 3.4 µg/L; Mercury – 1.0 µg/L; Nickel – 0.5 µg/L; Selenium – 3.0 µg/L; Silver – 0.42 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

13. Outfall 013 – Arby’s / Army and Air Force Exchange Station (AAFES)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 013. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 013 is substantially identical to Outfalls 3762, 3763, and 3771. Discharge data from Outfall 013 may be submitted to

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(7) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,7,8) NA NA NA NL (mg/L) 1/6M Grab

Oil and Grease NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,8) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Chromium, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Lead, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(6) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected during each of the first four semi-annual monitoring periods.

(6)

Samples for metals and hardness shall be collected concurrently.

(7)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L;

Dissolved Copper – 14 µg/L.

(8)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Chromium – 0.5 µg/L; Copper – 2.8 µg/L;

Lead – 0.5 µg/L; Nickel – 0.5 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

14. Outfall 014 –Army and Air Force Exchange Station (AAFES)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 014. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 014 is substantially identical to Outfalls 3745, 3752, 3753, 3756, 3757, 3758, 3759, and 3773. Discharge data from Outfall

014 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(7) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,7,8) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,8) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Chromium, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(6,7,8) NA NA NA NL (µg/L) 1/6M Grab

Lead, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(6,8) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

(6) NA NA NA NL (mg/L) 1/6M Grab

(1) See Part I.B. MGD = Million gallons per day. 1/6M = Once every six months.

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5)

Samples shall be collected during each of the first four semi-annual monitoring periods.

(6)

Samples for metals and hardness shall be collected concurrently.

(7)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L; Dissolved Copper

– 14 µg/L.

(8)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Chromium – 0.5 µg/L; Copper – 2.8 µg/L;

Lead – 0.5 µg/L; Nickel – 0.5 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

15. Outfall 015 – 16 th

Street Storage Area (Base Operations)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 015. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 015 is substantially identical to Outfalls 1611, 1636, 1696, 2176, 2941, 5818, 5889, and 5892. Discharge data from Outfall

015 may be submitted to represent these outfalls.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(8) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(8,9) NA NA NA NL (mg/L) 1/6M Grab

Total Petroleum Hydrocarbons (TPH)(3,8,9) NA NA NA NL (mg/L) 1/6M Grab

Oil and Grease NA NA NA NL (mg/L) 1/6M Grab

Chloride(7) NA NA NA NL (mg/L) 1/6M Grab

Total Dissolved Solids (TDS)(7) NA NA NA NL (mg/L) 1/6M Grab

Specific Conductance(7) NA NA NA NL (µmhos/cm) 1/6M Grab

Total Nitrogen(1,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5,9) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,5) NA NA NA NL (mg/L) 1/6M Grab

Chromium, Dissolved(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Lead, Dissolved(6,8,9) NA NA NA NL (µg/L) 1/6M Grab

Hardness, Total (as CaCO3)

Total Petroleum Hydrocarbons (TPH) is the sum of individual gasoline range organics and diesel range organics or TPH-GRO and TPH-DRO to be measured by

EPA SW 846 Method 8015 for gasoline and diesel range organics, or by EPA SW 846 Methods 8260 Extended and 8270 Extended.

(4)

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four semi-annual monitoring periods.

(5) Samples shall be collected during each of the first four semi-annual monitoring periods.

(6) Samples for metals and hardness shall be collected concurrently.

(7) Samples for chloride, total dissolved solids, and specific conductance shall be collected during the winter months associated with the semi-annual monitoring period

(January 1 – June 30 and July 1 – December 31) when salt movements are occurring and/or salt is being applied.

(8)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; TPH – 15 mg/L; Dissolved

Chromium – 28 µg/L; Dissolved Copper – 14 µg/L; Dissolved Lead – 16 µg/L.

(9)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TPH – 0.5 mg/L; TKN – 0.50 mg/L; Chromium – 6.4 µg/L; Copper – 2.8 µg/L;

Lead – 0.5 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

16. Outfall 016 – Dogue Creek Marina

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 016. Such discharges shall be monitored by the permittee as specified below.

c. Outfall 016 is substantially identical to Outfalls 4467, 4469, and 4474. Discharge data from Outfall 016 may be submitted to

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(6) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(6,7) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,3) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(4,7) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3)

(4) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,4) NA NA NA NL (mg/L) 1/6M Grab

Chromium, Dissolved(5,7) NA NA NA NL (µg/L) 1/6M Grab

Copper, Dissolved(5,6,7) NA NA NA NL (µg/L) 1/6M Grab

Copper, Total Recoverable(5,6,7) NA NA NA NL (µg/L) 1/6M Grab

Lead, Dissolved(5,6,7) NA NA NA NL (µg/L) 1/6M Grab

Nickel, Dissolved(5,7) NA NA NA NL (µg/L) 1/6M Grab

Zinc, Total Recoverable(5,6,7) NA NA NA NL (µg/L) 1/6M Grab

(5) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests during each of the first four sei-annual monitoring periods.

(4) Samples shall be collected during each of the first four semi-annual monitoring periods.

(5) Samples for metals and hardness shall be collected concurrently.

(6) The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; Dissolved Copper – 28 µg/L;

Total Recoverable Copper – 18 µg/L; Dissolved Lead – 13 µg/L; Total Recoverable Zinc – 120 µg/L.

(7)

The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; TKN – 0.50 mg/L; Chromium – 0.5 µg/L; Copper – 2.9 µg/L;

Lead – 6.7 µg/L; Nickel – 0.5 µg/L; Zinc – 29 µg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

17. Outfall 017 – Building 1809 (Recycling Center and Compost Yard)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number 017. Such discharges shall be monitored by the permittee as specified below.

(1)

Daily Maximum (1)

Minimum Maximum (1)

Frequency Sample Type

Flow (MGD)(2) NL NL NA NA 1/6M Estimate pH(4) NA NA NL (S.U.) NL (S.U.) 1/6M Grab

Total Suspended Solids (TSS)(4,5) NA NA NA NL (mg/L) 1/6M Grab

Biochemical Oxygen Demand (BOD5) (4,5) NA NA NA NL (mg/L) 1/6M Grab

Chemical Oxygen Demand (COD)(4,5) NA NA NA NL (mg/L) 1/6M Grab

Ammonia, as N(4,5) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen(1,3,4) NA NA NA NL (mg/L) 1/6M Calculated

Total Kjeldahl Nitrogen (TKN)(5) NA NA NA NL (mg/L) 1/6M Grab

Nitrate+Nitrite (NO2+NO3) NA NA NA NL (mg/L) 1/6M Grab

Total Phosphorus(1,4) NA NA NA NL (mg/L) 1/6M Grab

Total Nitrogen is the sum of Total Kjeldahl Nitrogen and NO2+NO3 Nitrogen and shall be calculated from the results of those tests.

(4)

The following benchmark concentrations are applicable: pH (Minimum) – 6.0 S.U.; pH (Maximum) – 9.0 S.U.; TSS – 100 mg/L; BOD5 – 30 mg/L; COD – 120 mg/L; Ammonia (as N) – 2.4 mg/L; Total Nitrogen – 2.2 mg/L; Total Phosphorus – 2.0 mg/L.

(5) The following Quantification Levels (QLs) are applicable: TSS – 1.0 mg/L; BOD – 2 mg/L; COD – 10 mg/L: Ammonia (as N) – 0.20 mg/L; TKN – 0.50 mg/L.

1/6M = The semi-annual monitoring periods shall be January 1 – June 30 and July 1 – December 31. The DMR shall be submitted no later than the 10 day of the month following the monitoring period (July 10 and January 10, respectively).

Estimate = Reported flow is to be based on the technical evaluation of the sources contributing to the discharge.

A. Stormwater Monitoring Requirements

18. Outfall 019 – 300 Area (Building 322 General Lab)

a. There shall be no discharge of floating solids or visible foam in other than trace amounts.

b. During the period beginning with the permit’s effective date and lasting until the expiration date the permittee is authorized to discharge from Outfall Number…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .