Attachment 7 Section M Evaluation Criteria FAR_52.212-2(W912D027QA003).pdf
FAR Clause PDF 245 KB Posted
- Attached to
- Repair and Maintenance of 10 Sprung Structures (8 WINMATs & 2 CRTFs) - Fort Wainwright, AK
- Solicitation number
- W912D027QA003
About this file
This document is an Evaluation Factors for Award attachment to a Request for Quotations (RFQ) for repair services at Fort Wainwright, Alaska.
The solicitation W912D027QA003 seeks labor, equipment, and materials for baseline and over-and-above repairs to Fort Wainwright Sprung Structures, specifically eight WINMATs (Wide-span Inflatable Maintenance and Training facilities) and two CRTFs (Containerized Rapid Training Facilities). The 413th Regional Contracting Office – Alaska is issuing this acquisition under FAR Part 12 and simplified procedures of FAR Subpart 13.5. Award will be made to the responsible offeror with the lowest evaluated price who meets acceptable quality standards across all non-price evaluation factors. The Government intends to award without discussions but reserves the right to conduct clarifications or verify pricing. Offerors must maintain active, valid registration in SAM.gov under NAICS 332311 with no active exclusions prior to award.
Quotations are evaluated against three primary factors: (1) Technical Capability on a Pass/Fail basis requiring Sprung Structures, Inc. OEM preferred contractor or certified installer qualification, a detailed technical execution plan addressing membrane thermal welding, insulation/vapor barrier procedures, doors and hardware maintenance, aerial equipment and safety compliance, with schedule confirmation of completion by January 31, 2027; (2) Past Performance rated as Acceptable, Unacceptable, or Neutral based on recency (last three years) and relevancy to large-scale tensioned-membrane fabric structure repair in cold-weather or sub-arctic conditions; and (3) Evaluated Price calculated as the sum of CLIN 0001 (baseline repairs lump-sum), CLIN 0002 evaluated labor (four trade categories at 380 total plug hours), and CLIN 0002 funded parts/materials set at $125,690.00 not-to-exceed. Price reasonableness is compared against the Independent Government Cost Estimate of $754,140.00. The Government will evaluate potential extension pricing by prorating baseline pricing for up to six months in accordance with FAR 52.217-8.
View the file
Other versions and copies of FAR 52.212-2
Show all 20
Who attaches FAR 52.212-2
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION W912D027QA003
ATTACHMENT 7: EVALUATION FACTORS FOR
AWARD
(TAILORED ADDENDUM TO FAR 52.212-2)
Requirement Title: Labor, Equipment, and Materials for Baseline and Over-and-Above
Repairs to Fort Wainwright Sprung Structures (8 WINMATs & 2 CRTFs)
Issuing Office: 413th Regional Contracting Office – Alaska (RCO-AK), Fort
Wainwright, AK
Procurement Method: Request for Quotations (RFQ) under FAR Part 12 and FAR
Subpart 13.5
1.0 BASIS FOR CONTRACT AWARD
(a) Source Selection Methodology:
The Government will award a single, Firm-Fixed-Price (FFP) contract resulting from this
Request for Quotations (RFQ) to the responsible offeror whose quote conforms to all solicitation requirements, meets the acceptable quality standards across all non-price evaluation factors, and offers the Lowest Evaluated Price (Lowest Price, Technically
Acceptable – LPTA).
(b) Simplified Acquisition Procedures (FAR Subpart 13.5):
This acquisition is conducted under FAR Part 12 in conjunction with the simplified procedures of FAR Subpart 13.5. In accordance with FAR 13.106:
1. Formal competitive ranges, formal technical evaluation panels, and the restrictive discussion/final proposal revision rules of FAR Part 15 do not apply.
2. The Government intends to award without discussions. However, the Contracting
Officer (KO) reserves the right to conduct clarifications, verify pricing, or engage in communications with any or all offerors if determined advantageous to the
Government.
3. The Government reserves the right to award to other than the lowest quote if the lowest quote is determined non-conforming, technically unacceptable, or poses unreasonable performance risk.
4. Offerors must have an active, valid registration in the System for Award
Management (SAM.gov) under NAICS 332311 with no active exclusions prior to award.
2.0 EVALUATION FACTORS & RATING METHODOLOGY
Quotations will be evaluated against three (3) primary factors:
• Factor 1: Technical Capability (Pass / Fail)
• Factor 2: Past Performance (Acceptable / Unacceptable / Neutral)
• Factor 3: Evaluated Price (Fairness, Reasonableness, and Realism Analysis)
Award will be made to the lowest-priced quote that achieves a rating of "Acceptable"
(Pass) in Factor 1 and "Acceptable" or "Neutral" in Factor 2. A rating of
"Unacceptable" in either Factor 1 or Factor 2 will render the quotation ineligible for award.
Evaluation Sequence:
• Step 1: All conforming quotations received by the deadline will be ranked by
Total Evaluated Price (TEP) from lowest to highest.
• Step 2: The lowest-priced quotation will be evaluated under Factor 1 (Technical
Capability). If evaluated as "Acceptable" (Pass), evaluation will proceed to Factor
2 (Past Performance).
• Step 3: If the lowest-priced quotation is evaluated as "Acceptable" or "Neutral" under Factor 2, and the price is determined fair, reasonable, and realistic, award will be made without further evaluation of higher-priced quotes.
• Step 4: If the lowest-priced quotation is found "Unacceptable" under Factor 1 or
Factor 2, it will be eliminated from consideration, and the next lowest-priced quotation will be evaluated following the same sequence.
3.0 FACTOR 1: TECHNICAL CAPABILITY (PASS / FAIL)
Technical capability will be evaluated on a Pass/Fail basis to determine whether the offeror demonstrates a complete understanding of the Performance Work Statement
(PWS) and possesses the requisite manufacturer credentials, equipment, and methodologies to execute high-bay architectural envelope repairs in an extreme sub-arctic environment.
To achieve an Acceptable (Pass) rating, the quotation must satisfy all three (3) subfactors:
Subfactor 1A: Sprung OEM Preferred Contractor / Certified Installer Qualification
• Standard: To preserve existing structural warranties and ensure engineering integrity across the ten (10) heavy tensioned-membrane facilities, the contractor must provide documented verification of qualification directly associated with
Sprung Structures, Inc.
• Acceptable Criteria: The offeror must provide one of the following:
1. Official documentation verifying current status as a Sprung Structures
"Preferred Contractor"; OR
2. Factory-authorized installer certification issued by Sprung Structures, Inc., confirming qualified installer status on large-span ( and ) tensioned-fabric architectural structures; OR
3. A formal, signed commitment letter establishing that an authorized Sprung
Technical Representative or certified installer will be present on-site to directly oversee and inspect all thermal membrane welding, structural hardware tensioning, and envelope restoration.
Subfactor 1B: Technical Execution Plan & MHE Access Strategy
• Standard: The offeror must provide a realistic operational narrative detailing how baseline repairs will be executed in accordance with OEM specifications and safety regulations.
• Acceptable Criteria: The technical narrative must satisfactorily address:
1. Membrane Thermal Welding: Sound methodology for performing hot-air extrusion or radio-frequency thermal welding to patch tears, holes, and skirts in sub-arctic conditions (including temporary heated enclosures if ambient temperatures fall below manufacturer adhesive/bonding limits).
2. Insulation & Vapor Barrier: Procedures for re-hanging, splicing, and securing dislodged R-30 fiberglass insulation blankets and continuous poly vapor barrier films along high-bay arches, end-walls, and ceilings.
3. Doors & Hardware Maintenance: Methodology for overhauling rolling overhead service door hood covers, track realignment, cable/roller lubrication, vestibule personnel door hinge weldment repairs, and weatherstripping.
4. Aerial Equipment & Safety (MHE): Identification of rough-terrain aerial lifts (e.g., 60-ft boom lifts, wide-deck scissor lifts) capable of reaching apex heights up to 45 feet, accompanied by OSHA-compliant fall protection plans.
5. Explicit Exclusions Acknowledgment: Affirmation confirming understanding that heating systems (furnaces/boilers), hydronic piping, ductwork, fire sprinkler loops, and fire alarm systems are explicitly excluded from this contract scope.
Subfactor 1C: Schedule Feasibility & Milestones
• Standard: Timely completion prior to deep winter freeze-up is mandatory to maintain troop readiness.
• Acceptable Criteria: The offeror must provide an operational timeline confirming that all on-site baseline repairs (CLIN 0001) will commence promptly upon award, achieve post-award deliverable submissions within ten (10) working days, and reach final physical completion and Government acceptance no later than 31 January 2027.
4.0 FACTOR 2: PAST PERFORMANCE (ACCEPTABLE /
UNACCEPTABLE / NEUTRAL)
The Government will evaluate the offeror's record of recent and relevant past performance to assess confidence in the contractor’s ability to perform the contract successfully.
4.1 Evaluation Criteria:
• Recency: Performance on contracts completed or ongoing within the last three
(3) years from the issuance date of this solicitation.
• Relevancy: Performance involving the repair, erection, re-covering, or structural envelope maintenance of large-scale relocatable tensioned-membrane fabric structures, with particular emphasis on work performed under extreme cold-weather or sub-arctic environmental conditions.
4.2 Information Sources:
In accordance with FAR 13.106-2(b)(3), the Contracting Officer is not limited to references provided in the quotation and may evaluate past performance using:
1. Contractor-submitted past performance reference data.
2. Contractor Performance Assessment Reporting System (CPARS).
3. Supplier Performance Risk System (SPRS) risk scores.
4. Direct personal knowledge of the Contracting Officer and Contract Specialist regarding previous agency contracts.
5. Other federal, state, or commercial sources.
4.3 Ratings & Definitions:
Past
Performance
Rating
Definition
Acceptable
Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Unacceptable
Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will successfully perform the required effort (e.g., history of severe schedule slippage, default, or uncorrected structural deficiencies).
Neutral The offeror lacks a record of recent and relevant past performance, or performance information is not available. A neutral rating will be evaluated as Acceptable in accordance with FAR 15.305(a)(2)(iv) and
FAR 13.106.
5.0 FACTOR 3: EVALUATED PRICE
Price will be evaluated to ensure it is fair, reasonable, and balanced in accordance with
FAR 13.106-3.
5.1 Total Evaluated Price (TEP) Calculation:
To determine the lowest evaluated quote, the Government will calculate the Total
Evaluated Price using the following formula:
Where:
• CLIN 0001 (Baseline Repairs): The lump-sum firm-fixed-price proposed by the offeror for all ten (10) structures.
• CLIN 0002 Evaluated Labor: The sum of the offeror's proposed fully burdened hourly labor rates for each required trade, multiplied by the Government’s standardized evaluation plug hours:
Labor Category
(CLIN 0002)
Government Plug
Hours
Proposed Fully
Burdened Hourly Rate
Evaluated
Amount
Sprung Certified Lead
Installer 100 hrs
Membrane Technician
/ Welder 150 hrs
Mechanical / Rigging
Technician 80 hrs
General Laborer /
Helper 50 hrs
Total Evaluated
Labor Pool 380 hrs —
• CLIN 0002 Funded Parts/Materials NTE Ceiling: Set by the Government at
$125,690.00. (All offerors must incorporate this exact plug value; do not alter).
5.2 Price Reasonableness & Realism:
1. Price Reasonableness: Evaluated using price analysis techniques pursuant to
FAR 13.106-3(a), including comparison of proposed prices received, comparison with previous competitive awards for similar services, and comparison against the
Independent Government Cost Estimate (IGCE) of $754,140.00.
2. Price Realism / Scope Verification: Unrealistically low prices will be evaluated to determine whether the offeror fails to comprehend the complexity of high-bay tensioned-fabric repair, omitted mandatory sub-tier labor/equipment, or poses an unacceptable risk of default. The Contracting Officer reserves the right to request price verification under FAR 13 before making an award determination.
3. Unbalanced Pricing: The Government will analyze line items and hourly rates to identify materially unbalanced pricing. Quotations containing significantly overstated or understated rates may be rejected if creating unreasonable risk.
6.0 OPTIONS AND EXTENSIONS (FAR 52.217-8)
In accordance with FAR 52.217-8 (Option to Extend Services), the Government will evaluate potential extension pricing by prorating the evaluated baseline pricing to cover up to a six-month duration. Evaluation of options does not obligate the Government to exercise any option.
SOLICITATION SECTION J: LIST OF
ATTACHMENTS
The following documents are attached and incorporated into Solicitation
W912D027QA003:
Attachment
No.
Document Title /
Description Date Source File
Attachment
FWA Sprung Shelter
Locations (Site Map &
Layouts)
Oct
Attachment 1 - FWA Sprung
Shelter Locations.pdf
Attachment
Itemized List of WINMAT and CRTF Structure Faults
Oct
Attachment 2 - List of
WINAMT, CRTF Faults.pdf
Attachment
CRTF 01 Detailed
Inspection Photos and Fault
Log
Oct
Attachment 3 - CRTF01
Faults.pdf
Attachment
WINMAT RWS 07
Detailed Inspection Photos
& Fault Log
Oct
Attachment 4 - WINMAT RWS07
Faults.pdf
Attachment
WINMAT 01–04, 08–10,
and CRTF 02 Photo Log
Oct
Attachment 5 - WINMAT
1,2,3,4,8,9,10 CRTF02
Faults.pdf
Attachment
Performance Work
Statement (PWS) – FWA
Sprung Repairs
Oct
PWS Fort_Wainwright Sprung
Structures Repairs Oct
2026.pdf
Attachment
Evaluation Factors for
Award (Addendum to FAR
52.212-2)
Oct
Attachment 7 Text as set forth above
Attachment
SCA Wage Determination
No. 2015-5683 (Rev. No.
29)
Aug
SCA Wage Determination No.
2015-5683 Rev No. 29
(27Aug2026).pdf
| SOLICITATION W912D027QA003 |
| ATTACHMENT 7: EVALUATION FACTORS FOR AWARD |
| (TAILORED ADDENDUM TO FAR 52.212-2) |
| 1.0 BASIS FOR CONTRACT AWARD |
| 2.0 EVALUATION FACTORS & RATING METHODOLOGY |
| Evaluation Sequence: |
| 3.0 FACTOR 1: TECHNICAL CAPABILITY (PASS / FAIL) |
| Subfactor 1A: Sprung OEM Preferred Contractor / Certified Installer Qualification |
| Subfactor 1B: Technical Execution Plan & MHE Access Strategy |
| Subfactor 1C: Schedule Feasibility & Milestones |
| 4.0 FACTOR 2: PAST PERFORMANCE (ACCEPTABLE / UNACCEPTABLE / NEUTRAL) |
| 4.1 Evaluation Criteria: |
| 4.2 Information Sources: |
| 4.3 Ratings & Definitions: |
| 5.0 FACTOR 3: EVALUATED PRICE |
| 5.1 Total Evaluated Price (TEP) Calculation: |
| 5.2 Price Reasonableness & Realism: |
6.0 OPTIONS AND EXTENSIONS (FAR 52.217-8)
SOLICITATION SECTION J: LIST OF ATTACHMENTS