Attachment 6 - PWS Fort_Wainwright Sprung Structures Repairs Oct 2026.pdf
PDF 338 KB Posted
- Attached to
- Repair and Maintenance of 10 Sprung Structures (8 WINMATs & 2 CRTFs) - Fort Wainwright, AK
- Solicitation number
- W912D027QA003
About this file
This is a Performance Work Statement (PWS) for labor, equipment, and materials to perform baseline and over-and-above repairs to ten Sprung Structures (tensioned-membrane shelters) located at Fort Wainwright, Alaska. The contract covers eight warm maintenance facility shelters (WINMATs) measuring 110' × 255' and two combat readiness training facility shelters (CRTFs) measuring 60' × 100'. The contractor must be an authorized Sprung Structures "Preferred Contractor" with manufacturer certification for heavy-envelope tensioned structures.
The scope encompasses comprehensive exterior and interior repairs including architectural fabric membrane patches, interior R-30 insulation blankets, vapor barriers, personnel doors, and cargo door mechanical assemblies. All repairs must comply with Original Equipment Manufacturer (OEM) specifications and procedures using genuine Sprung Structures OEM components for proprietary items, while commercial-grade sub-arctic rated materials (rated to −65°F) may be used for standard items with technical representative approval. The contractor must provide skilled labor, heavy access equipment (scissor lifts, telescoping boom lifts), and mobilization, with all exterior envelope work and tension bolt replacements completed by the January 31, 2027 winter freeze deadline. Required deliverables include staffing and operational work plans, Sprung certification verification, equipment and safety manifests, weekly progress reports, over-and-above work requests within 48 hours of deficiency discovery, and final quality and warranty closeout documentation signed by the Sprung Technical Representative. The contract includes an Over-and-Above (O&A) mechanism compliant with DFARS 252.217-7028 for latent deficiencies discovered during baseline performance. Personnel must undergo NCIC-III and Terrorist Screening Database vetting and comply with all Fort Wainwright security and access control requirements. No Government-Furnished Property, Equipment, or Materials are provided, though the Government will coordinate access and provide restroom facilities.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
(PWS)
PROJECT TITLE: Labor, Equipment, and Materials for Baseline and Over-and-Above
Repairs to Fort Wainwright Sprung Structures
REVISED DATE: 26 October 2026
LOCATION: Fort Wainwright, Alaska
1. BACKGROUND
1.1 Contract Characterization: This is a non-personal services contract to provide qualified labor, equipment, and materials to conduct comprehensive repairs to existing Sprung Structures located on Fort Wainwright, Alaska. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn, is responsible to the Government.
1.2 Facility History & Regulatory Posture: In 2019, Army Materiel Command
(AMC) erected ten (10) tensioned-membrane Sprung Shelters on Fort Wainwright in support of Army Quality of Life initiatives to improve soldier living and maintenance working conditions under extreme sub-arctic conditions. AMC erected eight (8) warm maintenance facility shelters (WINMATs) and two (2) combat readiness training facility shelters (CRTFs) utilizing the Logistics Civil Augmentation
Program (LOGCAP). LOGCAP coverage, including its one-year initial preventative maintenance period, has expired. The Sprung shelters are classified as non-real property (equipment/relocatable facilities); consequently, the Fort Wainwright
Directorate of Public Works (DPW) is barred from providing ongoing maintenance or repair support to these structures pursuant to Installation Management
Command (IMCOM) regulations.
1.3 Operational Requirement: All ten (10) Sprung structures require critical exterior and interior repairs to the architectural fabric membrane, interior insulation systems, doors, and related mechanical/hardware components to ensure structural integrity, prevent extreme weather damage, preserve soldier safety, and protect facility service life.
1.4 Warranty & Technical Oversight: The Sprung Structures retain an active manufacturer warranty covering specific materials and on-site technical representative support. While select faults are covered under manufacturer warranty, most existing structural deficiencies are non-warranted conditions resulting from sub-arctic operational wear. Repairs must be executed in compliance with OEM procedures and materials. Complex repairs, as determined by the contractor and Sprung Structures, Inc, may require direct technical oversight of an on-site Sprung Structures Technical Representative to maintain manufacturer certification and warranty validity.
1.5 Contractor Qualification: To ensure compliance with manufacturer technical standards, the Contractor must be an authorized Sprung Structures "Preferred
Contractor" (or possess documented manufacturer certification verifying authorized installer status on heavy-envelope Sprung tensioned structures).
2. OBJECTIVES
2.1 Provide skilled labor, necessary heavy access equipment (e.g., all-terrain scissor lifts, telescoping boom lifts), and approved materials to execute baseline repairs to the exterior architectural membrane/skin, interior R-30 insulation blankets, vapor barriers, personnel doors, and cargo door mechanical assemblies across:
• Eight (8) 110′ × 255′ WINMAT Sprung Structures
• Two (2) 60′ × 100′ CRTF Sprung Structures
2.2 Integrate and collaborate directly with the Sprung Structures Technical
Representative to ensure all repair methodologies, materials, and workmanship comply with Original Equipment Manufacturer (OEM) engineering specifications.
2.3 Provide an agile, fully compliant Firm-Fixed-Price (FFP) Over-and-Above (O&A) mechanism in accordance with DFARS 252.217-7028 to inspect, propose, authorize, and repair latent deficiencies discovered during baseline performance without causing project delays or administrative gridlock.
2.4 Complete all baseline and authorized over-and-above repair actions prior to the sub-arctic winter freeze deadline of 31 January 2027.
2.5 Explicit System Exclusions: This contract does not include maintenance, servicing, or repairs to any furnace, hydronic heating systems, HVAC units, fire suppression/sprinkler systems, or building fire alarm systems.
3. SCOPE OF WORK
3.1 Facility Inventory & Designation
Repairs shall be executed at the following ten (10) facility locations on Fort
Wainwright, AK:
• WINMAT Facilities (8 Units, 110′ × 255′): RWS-01, RWS-02, RWS-03, RWS-04, RWS-07, RWS-08, RWS-09, and RWS-10.
• CRTF Facilities (2 Units, 60′ × 100′): CRTF-01 and CRTF-02. (Facility layout, footprints, and physical coordinates are set forth in Attachment 1).
3.2 Baseline Fault Documentation (CLIN 0001)
• Attachment 2 provides the validated baseline deficiency schedule for each individual structure.
• Attachments 3 through 5 provide technical photographs, elevations, and architectural call-outs for each identified baseline defect.
• Baseline work consists of all labor, mobilization, access equipment, and OEM materials required to remediate every item cited in Attachments 2–5.
3.3 Material Standards & OEM Integrity
The Contractor shall furnish all materials required for authorized repairs:
• Mandatory OEM Components: All exterior architectural membrane fabric patches, tensioning bolt hardware, arch splice hardware, spreader assemblies, and tension cables must be genuine Sprung Structures OEM components to preserve manufacturer structural warranties.
• Non-Proprietary Standard Materials: Standard insulation fasteners, weather-stripping, commercial door latches, and standard sealants may consist of commercial grade, sub-arctic rated (rated to −65∘F) materials approved by the
Sprung Technical Representative and Government Technical Point of Contact
(TPOC).
3.4 Operational Schedule & Milestones
• Period of Performance: Contract Award through 31 January 2027.
• Physical Work Window: Due to extreme winter conditions in Fairbanks, Alaska, all exterior envelope work, fabric heat-welding, and tension bolt replacements must be completed and accepted before 31 January 2027.
4. GENERAL SERVICE & PERFORMANCE
REQUIREMENTS
4.1 On-Site Labor & Staffing
• The Contractor shall provide a self-sufficient, manufacturer-qualified traveling crew consisting of certified Sprung structure installation specialists, riggers, and mechanical repair personnel.
• The Contractor shall maintain dedicated on-site supervisory management to coordinate daily work schedules with the Government TPOC, facility building managers, and the on-site Sprung Technical Representative.
4.2 Material Handling Equipment (MHE) & Aerial Access
• The Contractor shall assess, procure, deliver, operate, and maintain all aerial access equipment required to perform repairs up to the maximum apex height of the structures (35′ to 45′ ridge height).
• Required equipment typically includes rough-terrain 4x4 scissor lifts, 60-ft articulating/telescoping boom lifts, and rigging equipment rated for sub-arctic outdoor operations.
• Equipment must be operated strictly by OSHA-certified personnel with active fall protection certification.
4.3 Workmanship & Environmental Considerations
• Thermal Welding Standards: Exterior membrane repairs must be executed utilizing hot-air extrusion or radio-frequency handheld welding equipment calibrated to manufacturer thermal specifications, ensuring homogeneous molecular bonding without scorching or weakening adjacent membrane material.
• Tensioning Calibration: Structural tensioning bolts must be tightened and verified against Sprung Structures torque specifications using calibrated torque instruments.
• Sub-Arctic Weather Constraints: Hot-air membrane welding and adhesive curing cannot occur below OEM temperature thresholds unless temporary heated containment enclosures are established by the Contractor.
5. DELIVERABLES
The Contractor shall provide the following technical and operational deliverables to the Government:
Deliverable Ref
Deliverable Description
Technical Criteria & Content Requirements
Delivery Due Date
Recipient(s)
DEL-01 Staffing & Operational Work Plan
Detailed on-site manning roster, crew safety certifications, lift operator qualifications, and badging/installation access compliance plan.
Within 10 working days of contract award
TPOC, COR,
Contracting Officer
DEL-02 Sprung Preferred Contractor Certification
Written formal verification from Sprung Structures, Inc. verifying Contractor is a certified/preferred installer.
Within 10 working days of contract award
Contracting Officer, COR
DEL-03 Equipment & Safety Inspection Manifest
Complete inventory of aerial work platforms (scissor/boom lifts), OEM hot-air welding equipment, and fall protection gear.
5 days prior to on-site work start
TPOC
DEL-04 Weekly Execution Progress Report
Summary of structures completed, active bays under repair, percent completion against schedule, and planned upcoming work.
Weekly by close of business Friday
TPOC, COR
DEL-05 Over-and- Above (O&A) Work Requests
Completed bilateral Exhibit A documentation, including photo logs, OEM concurrence, and pre-priced unit itemization.
Within 48 hours of deficiency discovery
COR,
Contracting Officer
DEL-06 Final Quality & Warranty Closeout Dossier
Comprehensive structure-by-structure completion report signed by Sprung Tech Rep verifying OEM warranty continuity.
Within 10 working days of final inspection
TPOC, COR,
Contracting Officer
6. QUALITY ASSURANCE SURVEILLANCE PLAN
(QASP)
The Government shall monitor Contractor performance using the standards, acceptable quality levels (AQLs), and surveillance methods detailed below:
PWS Task / Paragraph
Performance Standard
Acceptable Quality Level
(AQL)
Method of Surveillance
Performance Incentive / Deduction
PWS 4.1 –
4.3: Baseline Structural
Complete all documented repairs in
100% compliance;
zero defect
Joint physical inspection by
TPOC, COR,
Non-compliant work rejected.
Contractor
Repairs (CLIN 0001)
Attachments 2–5 in accordance with Sprung
OEM
standards.
unsealed penetrations;
100% weather-tight seal.
and Sprung Tech Rep.
must re-perform at own cost prior to payment.
PWS 3.3:
OEM Material Compliance
All structural fabric, tension hardware, and splices must be genuine OEM certified materials.
100% compliance;
zero unauthorized substitutions.
Verification of OEM Bills of Lading and Sprung Tech Rep sign-off.
Non-compliant materials removed and replaced at Contractor expense;
potential stop-work order.
PWS 5.2 –
5.4: Over-and-Above Ordering Discipline
Zero performance of discovered work without prior written bilateral KO Work Order.
100% compliance;
zero unauthorized commitments.
Continuous audit of daily field operations by
TPOC/COR.
Unauthorized work performed at Contractor risk;
zero reimbursement;
negative CPARS rating.
PWS 5.5:
Quality of Discovered Repairs (CLIN 0002)
Workmanship on authorized O&A work conforms to manufacturer technical standards.
100% compliance with approved Work Order scope.
Post-completion physical inspection by TPOC and Sprung Tech Rep.
Work order re-inspection.
Invoices withheld until final sign-off.
PWS 3.4:
Project Milestone Schedule
All 10 facilities completed and fully accepted prior to winter freeze.
Final acceptance achieved on or before 1 November 2026.
Weekly milestone tracking against approved master schedule.
Negative CPARS rating;
assessment of liquidated or actual Government delay damages.
7. PLACE OF PERFORMANCE & PERIOD OF
PERFORMANCE
8.1 Place of Performance: Fort Wainwright, Alaska, within the cantonment area in the vicinity of Fairbanks, AK. Work is situated on active military maintenance and training pads housing WINMATs RWS-01 through RWS-04, RWS-07 through RWS-
10, and CRTFs CRTF-01 and CRTF-02.
8.2 Period of Performance: From date of contract award through 31 Jan
2027.
8.3 Working Hours & Base Access Coordination: Regular operational hours are
0730 to 1630 Monday through Friday. Due to northern daylight patterns during summer and the strict 31 January 2027 winter deadline, extended shifts or weekend operations may be authorized with forty-eight (48) hours advance coordination with the TPOC.
8. SECURITY & INSTALLATION ACCESS
REQUIREMENTS
9.1 Physical Security & Access Control: Contractor personnel and all associated subcontractors shall comply with all installation access control policies established by the Fort Wainwright Provost Marshal Office, Director of Emergency Services, and
Garrison Commander.
9.2 Personnel Vetting: All personnel performing under this contract must undergo
National Crime Information Center Interstate Identification Index (NCIC-III) and
Terrorist Screening Database checks (Army Directive 2014-05 / AR 190-13).
Personnel must present valid REAL ID-compliant identification to obtain installation pass credentials.
9.3 Force Protection Condition (FPCON): The Contractor shall comply with all
Force Protection Condition directives. In the event of an FPCON elevation, the
Government reserves the right to alter access routes, escalate security checks, or temporarily suspend access.
9. GOVERNMENT FURNISHED PROPERTY &
AVAILABLE SUPPORT
10.1 Government Furnished Property: No Government Furnished Property (GFP), Government Furnished Equipment (GFE), or Government Furnished Materials
(GFM) will be provided under this contract.
10.2 Government Logistical Support:
• The Government will ensure unimpeded physical access to the exterior and interior perimeter of all ten (10) Sprung structures by coordinating with military tenant units.
• The Government will provide designated on-site latrine/restroom facilities.
• Limited Government MHE support (e.g., forklift offloading of freight) may be provided strictly on a non-interference, as-available basis with prior COR coordination. Under no circumstances will Government equipment be operated by Contractor personnel.
| PERFORMANCE WORK STATEMENT (PWS) |
| 1. BACKGROUND |
| 2. OBJECTIVES |
| 3. SCOPE OF WORK |
| 3.1 Facility Inventory & Designation |
| 3.2 Baseline Fault Documentation (CLIN 0001) |
| 3.3 Material Standards & OEM Integrity |
| 3.4 Operational Schedule & Milestones |
| 4. GENERAL SERVICE & PERFORMANCE REQUIREMENTS |
| 4.1 On-Site Labor & Staffing |
| 4.2 Material Handling Equipment (MHE) & Aerial Access |
| 4.3 Workmanship & Environmental Considerations |
| 5. DELIVERABLES |
| 6. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP) |
| 7. PLACE OF PERFORMANCE & PERIOD OF PERFORMANCE |
| 8. SECURITY & INSTALLATION ACCESS REQUIREMENTS |
| 9. GOVERNMENT FURNISHED PROPERTY & AVAILABLE SUPPORT |
110 ′ × 255 ′
60 ′ × 100 ′
110 ′ × 255 ′
60 ′ × 100 ′
− 65 ∘ F
35 ′
45 ′