W9128F20R0002_Am0001_Final.pdf

PDF 538 KB Posted

Attached to
Consolidated Space Operations Facility, Schriever AFB, Colorado
Solicitation number
W9128F20R0002
Issued by

About this file

This solicitation package seeks proposals for the construction of a Consolidated Space Operations Facility at Schriever Air Force Base in Colorado. The project includes construction of a two-story facility with reinforced concrete foundation and steel structure, as well as a one-story entry control facility. Facilities must comply with DoD, Air Force, and base design standards and include cybersecurity and antiterrorism measures. Offerors must provide pricing for the base project and optional scopes. Proposals are due by April 21, 2021. The contractor will have 1200 calendar days from notice to proceed to complete the work, which is to commence within 10 days of notice. Performance and payment bonds are required. Liquidated damages will apply for delays in completion. The Army Corps of Engineers Engineering District Omaha is the contracting agency.

View the file

Other files

File Type Posted
Am-0012_W9128F20R0002.pdf PDF
Am-0011_W9128F20R0002.pdf PDF
Am-0010_W9128F20R0002.pdf PDF
Am-0009_W9128F20R0002.pdf PDF
Am-0009_W9128F20R0002_Drawings-Reissued.pdf PDF
Am-0008_W9128F20R0002_Drawings_(Reissued).pdf PDF
Am-0008_W9128F20R0002.pdf PDF
CSOF Part 1_Modeling Files_90 Percent Corrected Download Instructions.pdf PDF
Am-0007_W9128F20R0002.pdf PDF
Modeling Files - 90 Percent Corrected Disclaimer.pdf PDF
Am-0004_W9128F20R0002.pdf PDF
CSOF Part 9_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 2_Modeling Files_90 Percent Corrected.zip ZIP file
ECP_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 10_Modeling Files_90 Percent Corrected.zip ZIP file
Am-0005_W9128F20R0002.pdf PDF
Am-0006_W9128F20R0002.pdf PDF
CSOF Part 1_Modeling Files_90 Percent Corrected.pdf PDF
CSOF Part 7_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 3_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 6_Modeling Files_90 Percent Corrected.zip ZIP file
Am-0003_W9128F20R0002.pdf PDF
CSOF Part 5_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 8_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 4_Modeling Files_90 Percent Corrected.zip ZIP file
Am-0002_W9128F20R0002_Drawings-(Revised).pdf PDF
W9128F20R0002_Am0002_Final_Div00_Specs_Drawings.pdf PDF
CSOF Virtual Site Visit_Attendee POCs_01Apr2021.pdf PDF
CSOF_DRAWINGS_Volume 1_LS-Civil-Landscape.pdf PDF
90-Percent-Corrected_V3-SPECS_W9128F20R0002_ECP.pdf PDF
CSOF_DRAWINGS_Volume 8_Comm-Security.pdf PDF
ECP_DRAWINGS.pdf PDF
CSOF_DRAWINGS_Volume 4_Interiors.pdf PDF
Div00_W9128F20R0002.pdf PDF
90-Percent-Corrected_V1-SPECS_W9128F20R0002_CSOF-General.pdf PDF
90-Percent-Corrected_V2-SPECS_W9128F20R0002_CSOF.pdf PDF
CSOF_DRAWINGS_Volume 7_Electrical.pdf PDF
CSOF_DRAWINGS_Volume 6_Process-Mechanical.pdf PDF
CSOF Site Photo Package compressed.pdf PDF
CSOF_DRAWINGS_Volume 3_Architectural.pdf PDF
CSOF_DRAWINGS_Volume 5_Fire-Plumbing.pdf PDF
CSOF_DRAWINGS_Volume 2_Structural.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is to update option CLIN 0005 extended description, update the Price Schedule CLIN Notes [date in w hich to excerise option CLINs (Note 1), contract duration (Note 4) and revised language for Note 5], update SF 1442 and FAR clause 52.211-10 w ith contract duration, update FAR clause 52.217-7 and include revisions to technical specif ications Section 01 14 00. Volume I proposal due date and time remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Mar-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F20R0002

X 9B. DATED (SEE ITEM 11)

23-Mar-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Mar-2021

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9128F20R0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AM 0001 - SUMMARY OF CHANGES

March 25, 2021 Solicitation No. W9128F 20 R 0002

Date of Issue: 23 MAR 2021 Date of Receiving Proposals: 21 APR 2021

SUBJECT: Amendment No. 0001 to Request for Proposal Solicitation Package for Construction of CONSOLIDATED SPACE OPERATIONS FACILITY.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

(1) Section 00 10 00 CLIN SCHEDULE, revise the description of Item No. 0005; and revise Notes 1, 4 and 5. Revised CLIN SCHEDULE is attached to this amendment.

VOLUME 1 – GENERAL REQUIREMENTS

(2) Section 01 14 00, Page 21, paragraph 1.14 “Recording Devices”, delete entire paragraph and substitute the following:

“1.14 Recording Devices

The contractor will be authorized a reasonable, limited quantity of phones for use within the freezone or RA work area to complete the work and meet all safety, quality, and other contract requirements. Phones or recording devices for every individual entering the freezone/RA work area will not be allowed; devices will only be allowed for key contractor management, quality, safety, etc personnel. 5G bandwidth is not permitted for use within the RA or freezone perimeters. Cameras will be authorized in a reasonable limited quantity for use within the freezone/RA work area to complete the work and meet all safety, quality, and other contract requirements. As part of its SSAMP, the contractor must maintain a list of recording devices that is approved for use through the 50th CES Engineering Flight Security Manager and each device must be accounted for when entering and exiting the freezone.

Any photos recorded by cameras will be vetted through Engineering Flight Security Manager and/or the SSO prior to any use outside the project site or transfer from recording device to other electronic equipment or system.”

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Proposals. Provide proposals via the instructions provided in Section 00 21 00 of the Request for Proposal.

4. Offers will be received until 12:00 p.m., local time at place of receiving proposals, 21 APR 2021.

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102-4901

25 MAR 2021

nep/2160

SECTION 00 10 00 - SOLICITATION

The contractor period of performance end date has decreased by 200 days from 1400 days to 1200 days.

CLIN 0005

The CLIN extended description has changed from:

Interior Communications Prewiring: Entire work complete to procure and install all Inside Plant (ISP) horizontal cables, ISP cables, racks, patch panels not included in base bid for CSOF. See Note 5 below. (MILCON funded)

To:

Interior Communications Prewiring: Entire work complete to procure and install all Inside Plant (ISP) horizontal cables, ISP cables, patch panels not included in base bid for CSOF. See Note 5 below. (MILCON funded)

The following have been modified:

CLIN NOTES & PRICE BREAKDOWN

CLIN NOTES:

1. See SECTION 00 21 00, INSTRUCTIONS TO OFFERORS for evaluation of options. The Government reserves the right to exercise Options No. 0005 - 0006 within 90 days after issuance of Notice to Proceed and remaining options within 950 days of Notice to Proceed.

2. Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the lump-sum prices and the total amount, the lump-sum prices will be considered the price submitted.

3. A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump-sum price affected.

4. Contract duration is 1200 calendar days; no additional time will be provided upon award of any combination of option items.

5. Horizontal cabling from telecom rooms to the user outlet locations shall be considered part of the CLIN option 5 "Interior Communications Prewiring". All other scope described herein shall be considered part of the base bid scope, including premises backbone cabling, backbone cabling racks and terminations, pull strings to user outlet locations, all racks and cabinets, and outlet faceplates with jacks, and all outside plant scope. All horizontal prewiring for ECF and Auditorium are to be included in CLINs 0003 & 0006, respectively.

6. Submit a Supplemental Price Breakdown for the “TOTAL BASIC AMOUNT” in the Pricing Schedule.

Include Offeror name, project title and project location on each page of the price breakdown. See Supplemental Price Breakdown of Pricing Schedule template on the following page. See Section 00 22 00 PROPOSAL SUBMISSION REQUIREMENTS, EVALUATION CRITERIA AND BASIS OF AWARD for submission requirements.

SUPPLEMENTAL PRICE BREAKDOWN OF PRICING SCHEDULE TEMPLATE

TOTAL WITH MARKUPS AMOUNT TO EQUAL TOTAL BASIC AMOUNT

AS INDICATED ON PRICE SCHEDULE OF THIS SECTION 00 10 00

DIVISION MASTERFORMAT 2016 DESCRIPTION UNIT AMOUNT

01 GENERAL REQUIREMENTS (minus item 0101) LS $_______________

0101 01 33 29 Sustainability Documentation LS $_______________

02 EXISTING CONDITIONS LS $_______________

03 CONCRETE LS $_______________

04 MASONRY LS $_______________

05 METALS LS $_______________

06 WOOD, PLASTICS, AND COMPOSITES LS $_______________

07 THERMAL AND MOISTURE PROTECTION LS $______________

08 OPENINGS LS $_______________

09 FINISHES LS $_______________

10 SPECIALTIES LS $______________

11 EQUIPMENT LS $_______________

12 FURNISHINGS LS $_______________

13 SPECIAL CONSTRUCTION LS $_______________

14 CONVEYING EQUIPMENT LS $_______________

21 FIRE SUPPRESSION LS $_______________

22 PLUMBING LS $______________

23 HEATING, VENTILATING, AND AIR CONDITIONING LS $_______________

25 INTEGRATED AUTOMATION LS $_______________

26 ELECTRICAL LS $_______________

27 COMMUNICATIONS LS $_______________

28 ELECTRONIC SAFETY AND SECURITY LS $_______________

31 EARTHWORK LS $_______________

32 EXTERIOR IMPROVEMENTS LS $_______________

33 UTILITIES LS $_______________

34 TRANSPORTATION LS $_______________

Total Price Breakdown Amount

Prime Contractor Markups:

--G&A General and Administrative Expense $ ______________ --FOOH Field Office Overhead not defined by Division -01 $ ______________ --PROFIT Profit $ ______________ --P&PB Performance and Payment Bond $ ______________

TOTAL WITH MARKUPS

All items must be entered in dollars.

“TOTAL WITH MARKUPS” from this Price Breakdown must match the “TOTAL BASIC

AMOUNT”.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 90 days after issuance of Notice to Proceed fro CLINs 0005 – 0006 and remaining options within 950 days of Notice to Proceed. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of clause)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1200 days. * The time stated for completion shall include final cleanup of the premises.

(End of clause)

(End of Summary of Changes)