Consolidated Space Operations Facility, Schriever AFB, Colorado
Solicitation number
W9128F20R0002
Issued by

About this file

This solicitation is for the construction of a Consolidated Space Operations Facility at Schriever Air Force Base in Colorado. The project will consist of constructing a two-story facility with reinforced concrete, steel structure, and a low slope membrane roof, as well as a one-story entry control facility. The facilities must comply with DoD, Air Force, and base design standards, and incorporate cybersecurity measures. The contractor will be required to commence work within 10 days of the notice to proceed and complete construction within 1400 calendar days, with liquidated damages for failure to meet the deadline. Performance and payment bonds are required. The solicitation package includes the project specifications, drawings, and instructions to offerors.

View the file

Other files

File Type Posted
Am-0012_W9128F20R0002.pdf PDF
Am-0011_W9128F20R0002.pdf PDF
Am-0010_W9128F20R0002.pdf PDF
Am-0009_W9128F20R0002.pdf PDF
Am-0009_W9128F20R0002_Drawings-Reissued.pdf PDF
Am-0008_W9128F20R0002_Drawings_(Reissued).pdf PDF
Am-0008_W9128F20R0002.pdf PDF
CSOF Part 1_Modeling Files_90 Percent Corrected Download Instructions.pdf PDF
Am-0007_W9128F20R0002.pdf PDF
Modeling Files - 90 Percent Corrected Disclaimer.pdf PDF
Am-0004_W9128F20R0002.pdf PDF
CSOF Part 9_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 2_Modeling Files_90 Percent Corrected.zip ZIP file
ECP_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 10_Modeling Files_90 Percent Corrected.zip ZIP file
Am-0006_W9128F20R0002.pdf PDF
CSOF Part 1_Modeling Files_90 Percent Corrected.pdf PDF
CSOF Part 7_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 3_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 6_Modeling Files_90 Percent Corrected.zip ZIP file
Am-0003_W9128F20R0002.pdf PDF
CSOF Part 5_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 8_Modeling Files_90 Percent Corrected.zip ZIP file
CSOF Part 4_Modeling Files_90 Percent Corrected.zip ZIP file
Am-0002_W9128F20R0002_Drawings-(Revised).pdf PDF
W9128F20R0002_Am0002_Final_Div00_Specs_Drawings.pdf PDF
CSOF Virtual Site Visit_Attendee POCs_01Apr2021.pdf PDF
W9128F20R0002_Am0001_Final.pdf PDF
CSOF_DRAWINGS_Volume 1_LS-Civil-Landscape.pdf PDF
90-Percent-Corrected_V3-SPECS_W9128F20R0002_ECP.pdf PDF
CSOF_DRAWINGS_Volume 8_Comm-Security.pdf PDF
ECP_DRAWINGS.pdf PDF
CSOF_DRAWINGS_Volume 4_Interiors.pdf PDF
Div00_W9128F20R0002.pdf PDF
90-Percent-Corrected_V1-SPECS_W9128F20R0002_CSOF-General.pdf PDF
90-Percent-Corrected_V2-SPECS_W9128F20R0002_CSOF.pdf PDF
CSOF_DRAWINGS_Volume 7_Electrical.pdf PDF
CSOF_DRAWINGS_Volume 6_Process-Mechanical.pdf PDF
CSOF Site Photo Package compressed.pdf PDF
CSOF_DRAWINGS_Volume 3_Architectural.pdf PDF
CSOF_DRAWINGS_Volume 5_Fire-Plumbing.pdf PDF
CSOF_DRAWINGS_Volume 2_Structural.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

W9128F

CONSOLIDATED SPACE OPERATIONS FACILITY, PNGLEN203001 (FY20), SCHRIEVER AFB, COLORADO

See attached documentation for content of the amendment revisions to solicitation

New date for receipt of Volume II proposals is 03 JUN 2021 at 1400 hours

Government Point of Contact: Melissa Harlon, Contract Specialist, Melissa.R.Harlon@usace.army.mil

U.S.ARMY CORPS OF ENGINEERS, OMAHA DIST

Attn: CONTRACTING DIVISION (CENWO-CT-M)

1616 CAPITOL AVENUE

OMAHA, NE 68102-4901

See Item 6

W9128F20R0002

06 May 21

23-Mar-2021

06 May 21

Am #0005 - 1

Am #0005 - 2 (Continuation SF 30)

6 MAY 2021

Solicitation No. W9128F 20 R 0002

Date of Issue: 23 MAR 2021 New Date of Receiving Volume II Proposals: 03 JUN 2021

SUBJECT: Amendment No. 0005 to Request for Proposal Solicitation Package for Construction of CONSOLIDATED SPACE OPERATIONS FACILITY.

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications. (Descriptive Changes.)

DIVISION 00 SPECIFICATIONS:

(1) Section 00 10 00 - SOLICITATION, delete the required response date/time and substitute 03 Jun 2021, 02:00 PM.

b. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification sections as noted below. The substituted sections are revised and reissued with this amendment. For convenience, on the revised specification pages, changes have been identified with highlighting unless section is noted as new or completely reissued; all portions of the revised specification pages apply regardless of whether changes are shown with highlighting.

VOLUME 1 SPECIFICATIONS – GENERAL REQUIREMENTS:

Pages or Sections Deleted Pages or Sections Substituted or Added 01 91 00.15 10 01 91 00.15 10

VOLUME 2 SPECIFICATIONS – CSOF:

Pages or Sections Deleted Pages or Sections Substituted or Added 25 05 11.04 25 05 11.04

VOLUME 3 SPECIFICATIONS – ECP:

Pages or Sections Deleted Pages or Sections Substituted or Added 22 00 00 22 00 00 23 11 25 23 11 25 23 23 00 23 23 00 33 71 02 33 71 02

c. Drawings (Reissued). The following drawings are revised with latest revision date as shown in the drawing border and reissued with this amendment.

CSOF PACKAGE - VOLUME 3 OF 8 – ARCHITECTURAL:

(1) Sheet A-112, 1ST FLOOR - SECTOR 2 PLAN

(2) Sheet A-113, 1ST FLOOR - SECTOR 3 PLAN

(3) Sheet A-114, 1ST FLOOR - SECTOR 4 PLAN

Am #0005 - 3

(4) Sheet A-115, 1ST FLOOR - SECTOR 5 PLAN

(5) Sheet A-116, 1ST FLOOR - SECTOR 6 PLAN – BASE BID

(6) Sheet A-116A, 1ST FLOOR - SECTOR 6 PLAN – BID OPTION

(7) Sheet A-117, 1ST FLOOR - SECTOR 7 PLAN

(8) Sheet A-118, 1ST FLOOR - SECTOR 8 PLAN

(9) Sheet A-121, 2ND FLOOR - SECTOR 1 PLAN

(10) Sheet A-124, 2ND FLOOR - SECTOR 4 PLAN

(11) Sheet A-125, 2ND FLOOR - SECTOR 5 PLAN

(12) Sheet A-126, 2ND FLOOR - SECTOR 6 PLAN – BASE BID

(13) Sheet A-126A, 2ND FLOOR - SECTOR 6 PLAN – BID OPTION

(14) Sheet A-128, 2ND FLOOR - SECTOR 8 PLAN

(15) Sheet A-401, ENLARGED RESTROOM PLANS

CSOF PACKAGE - VOLUME 7 OF 8 – ELECTRICAL:

(1) Sheet ES102, CSOF SITE ELECTRICAL PLAN – SHEET 3

(2) Sheet EG111, GROUNDING PLAN LEVEL 1

(3) Sheet EG111A, GROUNDING PLAN LEVEL 1A

(4) Sheet EG121, GROUNDING PLAN LEVEL 2

(5) Sheet EG501, GROUNDING DETAILS

(6) Sheet EP113, ELECTRICAL POWER PLAN LEVEL 1 – SECTOR 3

(7) Sheet EP115, ELECTRICAL POWER PLAN LEVEL 1 – SECTOR 5

(8) Sheet EP502, POWER DETAILS

(9) Sheet EQ115, EQUIPMENT POWER PLAN LEVEL 1 – SECTOR 5

(10) Sheet EQ116, EQUIPMENT POWER PLAN LEVEL 1 – SECTOR 6

(11) Sheet EQ116A, EQUIPMENT POWR PLAN LEVEL 1 – SECTOR 6A

(12) Sheet EQ124, EQUIPMENT POWER PLAN LEVEL 2 – SECTOR 4

(13) Sheet E-602, MEDIUM-VOLTAGE ONE-LINE DIAGRAM

(14) Sheet E-620, SUB-METERING DIAGRAM

(15) Sheet E-639, PANEL SCHEDULES

(16) Sheet E-646, PANEL SCHEDULES

(17) Sheet E-647, PANEL SCHEDULES

(18) Sheet E-650, PANEL SCHEDULES

(19) Sheet E-662, PANEL SCHEDULES

(20) Sheet E-664, PANEL SCHEDULES

(21) Sheet E-667, PANEL SCHEDULES

Am #0005 - 4

CSOF PACKAGE - VOLUME 8 OF 8 – TELECOMMUNICATIONS, AUDIO VISUAL, SECURITY:

(1) Sheet TN-139A, COMMUNICATION CABLE TRAY PLAN FIRST FLOOR SECTOR 9 - BID

OPTION

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Proposals. Provide proposals via the instructions provided in Section 00 22 00 of the Request for Proposal.

4. Offers will be received until 2:00 p.m., local time at place of receiving proposals, 03 JUN 2021.

Attachments:

Specifications listed in 1.b., above Drawings listed in 1.c. and 1.d., above

U.S. Army Corps of Engineers, Omaha District 1616 Capitol Avenue Omaha, Nebraska 68102 4901

06 MAY 2021

nep/2160

Consolidated Space Operations Facility - Schriever AFB, CO SH50

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 91 00.15 10

TOTAL BUILDING COMMISSIONING

05/19

PART 1 GENERAL

1.1 SUMMARY

1.2 SYSTEMS TO BE COMMISSIONED

1.3 REFERENCES

1.4 COMMUNICATION WITH THE GOVERNMENT

1.5 SEQUENCING AND SCHEDULING

1.5.1 Sequencing

1.5.2 Project Schedule

1.6 SUSTAINABILITY REQUIREMENTS

1.7 SUBMITTALS

1.8 COMMISSIONING FIRM

1.8.1 Lead Commissioning Specialist

1.8.2 Technical Commissioning Specialists

1.8.3 Commissioning Standard

1.9 SUSTAINABILITY THIRD PARTY CERTIFICATION (TPC)

1.10 ISSUES LOG

1.11 CERTIFICATE OF READINESS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 CONSTRUCTION PHASE

3.1.1 Construction Commissioning Coordination Meeting

3.1.2 Construction Phase Commissioning Plan

3.1.2.1 Interim Construction Phase Commissioning Plan

3.1.2.1.1 Checklists

3.1.2.1.2 Template Building Envelope Inspection Checklists

3.1.2.2 Final Construction Phase Commissioning Plan

3.1.2.2.1 Pre-Functional Checklists

3.1.2.2.2 Functional Performance Test Checklists

3.1.2.2.3 Integrated Systems Test Checklists

3.1.3 Construction Submittals

3.1.4 Inspection and Testing

3.1.4.1 Commissioning Team

3.1.4.1.1 Building Envelope Inspections Team

3.1.4.1.2 Mechanical System Pre-Functional Checks Team

3.1.4.1.3 Electrical System Pre-Functional Checks Team

3.1.4.1.4 Mechanical Systems Test Team

3.1.4.1.5 Electrical Systems Test Team

3.1.4.1.6 Other Pre-Functional and Functional Performance

Participants

3.1.4.2 Building Envelope Inspection

3.1.4.3 Pre-Functional Checks

SECTION 01 91 00.15 10 Page 1Am #0005

3.1.4.4 Testing, Adjusting, and Balancing (TAB) Report and Field Acceptance Testing

3.1.4.5 HVAC Controls Test Reports

3.1.4.6 Tests

3.1.4.6.1 Functional Performance and Integrated Systems Tests

3.1.4.6.1.1 Checklist

3.1.4.6.1.2 Acceptance

3.1.4.6.2 HVAC Test Methods

3.1.4.6.2.1 Prior to Testing

3.1.4.6.2.2 Simulating Conditions

3.1.4.6.2.3 Setup

3.1.4.6.3 Integrated Systems Test Methods

3.1.4.6.3.1 Mechanical

3.1.4.6.3.1.1 Sustaining Mission to Mission Critical

3.1.4.6.3.1.2 Mission Critical to Sustaining

3.1.4.6.3.1.3 Failure Induced System Change

3.1.4.6.3.2 Electrical

3.1.4.6.3.2.1 Sustaining to Mission Critical

3.1.4.6.3.2.2 Mission Critical to Sustaining

3.1.4.6.3.2.3 Failure Induced System Change

3.1.4.6.4 Sample Strategy

3.1.4.6.5 Seasonal Tests

3.1.4.6.5.1 Initial Functional Performance Tests

3.1.4.6.5.2 Full-Load Conditions

3.1.4.6.5.3 System Acceptance

3.1.4.6.6 Aborted Tests and Re-Testing

3.1.4.6.6.1 100 Percent Sample

3.1.4.6.6.2 Less than 100 Percent Sample

3.1.5 Training Plan

3.1.6 Systems Manual

3.1.7 Maintenance and Service Life Plans

3.1.7.1 Maintenance Plan

3.1.7.2 Service Life Plan

3.2 COMMISSIONING REPORT

3.3 POST-CONSTRUCTION SUPPORT

3.3.1 Post-Construction Endurance Test

3.3.2 Post-Construction Site Visit

-- End of Section Table of Contents --

SECTION 01 91 00.15 10 Page 2Am #0005

SECTION 01 91 00.15 10

TOTAL BUILDING COMMISSIONING

05/19

PART 1 GENERAL

1.1 SUMMARY

Commission the building systems listed herein. Employ the services of an independent Commissioning Firm. The Commissioning Firm must be a 1st tier subcontractor of the General or Prime Contractor and must be financially and corporately independent of all other subcontractors. The Commissioning Firm must employ a Lead Commissioning Specialist that coordinates all aspects of the commissioning process. Conform to the commissioning procedures outlined in this specification.

1.2 SYSTEMS TO BE COMMISSIONED

Commission the following systems:

Heating, Ventilating, Air Conditioning, and Refrigeration Systems

(HVAC)

Building Automation System Utility Monitoring and Control System Lighting Systems Power Distribution Systems Power Generation Systems (CSOF only) Uninterrupted Power Supply (UPS) (CSOF only) Service Water Heating Systems Plumbing Systems Natural Gas Systems Water Pumping and Mixing Systems Energy and Water Utility Metering Systems and Sub-Meters Fenestration Control Systems (CSOF only) Building Envelope: include moisture, thermal integrity, and air tightness for the entire buidling envelope including systems such as walls, fenestration, roofing, roof openings, below grade perimeter walls, slabs-on-grade.

1.3 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 180 (2012) Standard Practice for Inspection and Maintenance of Commercial Building HVAC Systems

ASHRAE 202 (2013; Addenda B 2018) Commissioning Process for Buildings and Systems

SECTION 01 91 00.15 10 Page 3Am #0005

ASSOCIATED AIR BALANCE COUNCIL (AABC)

ACG Commissioning Guideline (2005) Commissioning Guideline

NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)

NEBB Commissioning Standard (2009) Procedural Standards for Whole Building Systems Commissioning of New Construction; 3rd Edition

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

SMACNA 1429 (1994) HVAC Systems Commissioning Manual, 1st Edition

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 25-345-1 (1991) Systems Operation and Maintenance Documentation

1.4 COMMUNICATION WITH THE GOVERNMENT

The Lead Commissioning Specialist (CxC) must submit all plans, schedules, reports, and documentation directly to the Contracting Officer Representative concurrent with submission to the CQC System Manager. The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Lead Commissioning Specialist.

1.5 SEQUENCING AND SCHEDULING

1.5.1 Sequencing

Complete the following prior to starting Functional Performance Tests of mechanical systems:

a. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.

b. Performance Verification Tests of the controls systems have been completed and the Performance Verification Test Report has been submitted and approved in accordance with Specification Section

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC.

c. Testing, Adjusting, and Balancing has been completed and the Testing, Adjusting, and Balancing Report, has been submitted and approved in accordance with Specification Section 23 05 93 TESTING, ADJUSTING, AND

BALANCING FOR HVAC.

d. The building envelope is enclosed according to contract documents with final construction completed, the Air Barrier Pressure Tests have been completed and the Air Leakage Test Reports and Diagnostic Test Reports have been submitted and approved in accordance with Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR

TIGHTNESS.

SECTION 01 91 00.15 10 Page 4Am #0005

e. The Pre-Functional Checklists have been submitted and approved.

f. The Certificate of Readiness for mechanical systems has been submitted and approved.

Complete the following prior to starting Functional Performance Tests of the electrical systems:

a. All electrical, power generation, and lighting equipment and systems have been completed, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.

b. The building envelope is enclosed according to contract documents with final construction completed.

c. Ceiling tiles, floor coverings, and window coverings are in place.

1.5.2 Project Schedule

Include the following tasks in the project schedule required by Section 01 32 01.00 10 PROJECT SCHEDULE. Ensure sufficient time is scheduled to accommodate the requirements of this specification section. The order of items listed below is not intended to imply a specified sequence:

a. Submission and approval of the Commissioning Firm and Commissioning Specialist

b. Submission and approval of the Testing, Adjusting, and Balancing (TAB) Firm and TAB Specialist specified in Specification Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC

c. Submission of the Design Review Report specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC.

d. Submission and approval of the Construction Phase Commissioning Plan

e. Installation of permanent utilities (gas, water, electric)

f. Building Envelope Construction

g. Submission of the Building Envelope Inspection Checklists

h. Air Barrier Pressure Tests specified in Specification Section 07 05 23

PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS

i. Factory Acceptance Testing for each of the systems to be commissioned as required by technical specifications

j. Manufacturer's Equipment Start-Up for each of the systems to be commissioned.

k. Submission and approval of Duct Air Leakage Test Procedures specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING

FOR HVAC

l. Duct Air Leakage Test Execution specified in Specification Section

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

m. Submission and approval of the Final Duct Air Leakage Test Report

SECTION 01 91 00.15 10 Page 5Am #0005 specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND

BALANCING FOR HVAC

n. Testing, Adjusting, and Balancing (TAB) Field Work required by Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR

HVAC

o. Submission and approval of the TAB Report specified in Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

p. TAB Field Acceptance Testing required by Specification Section 23 05 93

TESTING, ADJUSTING, AND BALANCING FOR HVAC

q. Pre-Functional Checklist Submittal

r. Functional Performance Testing for each system to be commissioned

s. Integrated Systems Tests

t. Post-Test Deficiency Correction for each system to be commissioned

u. Training for each of the systems to be commissioned

v. Systems Manual, Maintenance Plan, and Service Life Plan submission and approval

w. Submission and approval of the Commissioning Report

x. Seasonal Testing

y. Post-Construction Endurance Testing

z. Post-Construction Site Visit

1.6 SUSTAINABILITY REQUIREMENTS

Materials in this technical specification may contribute towards contract compliance with sustainability requirements. See Section 01 33 29 SUSTAINABILITY REPORTING for project requirements.

1.7 SUBMITTALS

Government approval is required for submittals with a "G" designation ubmittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Commissioning Firm; G, DO

Lead Commissioning Specialist; G, DO

Technical Commissioning Specialists; G, DO

SD-06 Test Reports

SECTION 01 91 00.15 10 Page 6Am #0005

Interim Construction Phase Commissioning Plan; G, DO

Final Construction Phase Commissioning Plan; G, DO

Template Building Envelope Inspection Checklists; G, DO

Building Envelope Inspection Checklists; G, DO

Pre-Functional Checklists; G, DO

Issues Log

Commissioning Report; G, DO

Post-Construction Trend Log Report; G, DO

SD-07 Certificates

Certificate of Readiness; G, DO

SD-10 Operation and Maintenance Data

Training Plan; G, RO

Training Attendance Rosters; G, RO

Systems Manual; G, DO

Maintenance and Service Life Plans; G, DO

SD-11 Closeout Submittals

Final Commissioning Report; G, DO

Final Construction Phase Commissioning Plan

1.8 COMMISSIONING FIRM

Provide a Commissioning Firm that is certified in commissioning by one of the following: the AABC Commissioning Group (ACG); the National Environmental Balancing Bureau (NEBB); the International Certification Board/Testing, Adjusting, and Balancing Bureau (ICB/TABB), the Building Commissioning Association (BCA); the Association of Energy Engineers (AEE).

The Commissioning Firm must be certified in all systems to be commissioned to the extent such certifications are available from the certifying body.

Describe any lapses in certification or disciplinary action taken by the certifying body against the proposed Commissioning Firm or Lead Commissioning Specialist in detail. Any firm or commissioning professional that has been the subject of disciplinary action by the certifying body within the five years preceding contract award is not eligible to perform any duties related to commissioning.

a. Submit the Commissioning Firm's certification of qualifications including the name of the firm and certifications no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.

SECTION 01 91 00.15 10 Page 7Am #0005

b. The Commissioning Firm's and Commissioning Specialists' certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the firm or a specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Commissioning Firm or Commissioning Specialist for approval. All work specified in this specification section performed by the Commissioning Firm or associated Commissioning Specialists is invalid if the Commissioning Firm or Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.

c. The Commissioning Firm must oversee and assist the General or Prime Contractor with the work specified herein.

d. The Commissioning Firm may act as the Pressure Test Agency required by Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS provided that all qualification requirements of that specification section are met.

1.8.1 Lead Commissioning Specialist

The Commissioning Firm must provide a Lead Commissioning Specialist (CxC) that has a minimum of five years of commissioning experience, including two projects of similar size and complexity, and that is one of the following: a NEBB qualified Systems Commissioning Administrator (SCA);

ACG Certified Commissioning Authority (CxA); ICB/TABB Certified Commissioning Supervisor; BCA Certified Commissioning Professional (CCP);

AEE Certified Building Commissioning Professional (CBCP); University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP); ASHRAE Commissioning Process Management Professional (CPMP).

a. Submit the Lead Commissioning Specialist's certification of qualifications including the name of the specialist and firm;

certifications; years of experience; and a listing of representative projects of similar size and complexit. Submit one electronic copy.

b. The Lead Commissioning Specialists certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, the specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Lead Commissioning Specialist for approval. All work specified in this specification section to be performed by the Lead Commissioning Specialist is invalid if the Lead Commissioning Specialist loses its certification prior to contract completion and must be performed by an approved successor.

c. The Lead Commissioning Specialist must lead and oversee the commissioning work specified herein and be the primary point of contact for the Government regarding the commissioning work. One of the Technical Commissioning Specialists may be the Lead Commissioning Specialist provided that all of the qualification requirements are met.

1.8.2 Technical Commissioning Specialists

Technical Commissioning Specialists, employed by the Commissioning Firm and that have the following qualifications, must perform the technical work specified herein associated with each system to be commissioned:

a. Mechanical Technical Commissioning Specialist: The technical work

SECTION 01 91 00.15 10 Page 8Am #0005 associated with mechanical systems including Heating, Ventilating, Air Conditioning, and Refrigeration Systems; Building Automation System;

Utility Monitoring and Control System ervice Water Heating Systems;

Plumbing Systems; Water Pumping Systems; Irrigation Systems; Energy and Water Utility Metering Systems must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.

b. Electrical Technical Commissioning Specialist: The technical work associated with electrical systems including Lighting Systems; Power Distribution Systems; Power Generation Systems; Electrical Utility Metering Systems must be performed by an engineering technician certified by the InterNational Electrical Testing Association (NETA) with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

c. Building Envelope Technical Commissioning Specialist technical work associated with the Building Envelope system must be performed by a registered architect with five years of building envelope design or construction experienceor a professional with training and certification as an Air Barrier Installer from the Air Barrier Association of America (ABAA) or other 3rd party air barrier association. The Building Envelope Technical Commissioning Specialist must have experience coordinating and instructing personnel involved in installation, joining, and sealing of air barrier materials and components. The Commissioning Firm team member with the required experience related to the building envelope may act as the Air Barrier Inspector required by Specification Section 07 27 10.00 10 BUILDING AIR BARRIER SYSTEM provided that all qualification requirements of that specification section are met. The Commissioning Firm team member with the required experience related to the building envelope may act as the thermographer required by Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS provided that all of the qualification requirements of that specification section are met.

d. Submit the Technical Commissioning Specialist's certification of qualifications including the name of the specialist and firm;

certifications; years of experience; and a listing of representative projects of similar size and complexity. Submit one electronic copy.

1.8.3 Commissioning Standard

Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of the acceptable standards unless otherwise stated herein. The acceptable standards are ACG Commissioning Guideline, NEBB Commissioning Standard, SMACNA 1429, or ASHRAE 202. Comply with applicable NETA testing standards for electrical systems.

a. Implement all recommendations and suggested practices contained in the Commissioning Standard and electrical test standards.

b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.

SECTION 01 91 00.15 10 Page 9Am #0005

c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.

d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.

e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.

f. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the Commissioning Standard.

1.9 SUSTAINABILITY THIRD PARTY CERTIFICATION (TPC)

The Commissioning Specialists must execute and document the commissioning activities required of the Commissioning Authority for the purposes of complying with the Third Party Certification (TPC) requirements for the project in accordance with Section 01 33 29 SUSTAINABILITY REPORTING.

Provide all commissioning documentation required to meet the TPC requirements.

1.10 ISSUES LOG

The Lead Commissioning Specialist must develop and maintain an Issues Log for tracking and resolution of all deficiencies discovered through submittal reviews, inspection, and testing. Include the date of final resolution of issues as confirmed by the Commissioning Specialist. Submit the Issues Log on a monthly basis at a minimum. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log.

1.11 CERTIFICATE OF READINESS

Prior to scheduling Functional Performance Tests for each system, issue a Certificate of Readiness for the system certifying that the system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports; Performance Verification Test Reports; completed Building Envelope Inspection Checklists; completed Pre-Functional Checklists; Testing, Adjusting, and Balancing (TAB) Report; HVAC Controls Start-Up Reports; and the Air Leakage Test Reports and Diagnostic Test Reports to the extent applicable to the system. The Contractor must sign and date the Certificate of Readiness. Submit the Certificate of Readiness for each system no later than 14 calendar days prior to Functional Performance Tests of that system. Submit one electronic copy.

Do not schedule Functional Performance Tests for a system until the Certificate of Readiness for that system receives approval by the Government.

PART 2 PRODUCTS

Not used

SECTION 01 91 00.15 10 Page 10Am #0005

PART 3 EXECUTION

3.1 CONSTRUCTION PHASE

3.1.1 Construction Commissioning Coordination Meeting

The Lead Commissioning Specialist must lead a Construction Commissioning Coordination Meeting no later than 14 days after approval of the Commissioning Firm and Commissioning Specialists to discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this specification section. The Contractor's Superintendent or Project Manager, the Contractor's Quality Control Representative, and the Government must attend this meeting. Invite the User and a Base Civil Engineer Office Representative to attend this meeting.

3.1.2 Construction Phase Commissioning Plan

3.1.2.1 Interim Construction Phase Commissioning Plan

The Lead Commissioning Specialist (CxC) must prepare the Interim Construction Phase Commissioning Plan. Submit the Interim Construction Phase Commissioning Plan no later than 30 calendar days after the Construction Commissioning Coordination Meeting and no later than 14 days prior to the start of construction of the building envelope. Submit one electronic copy.

Identify the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, documentation requirements for the construction phase of the project, and Template Building Envelope Inspection Checklists in the Interim Construction Phase Commissioning Plan.

3.1.2.1.1 Checklists

Download example Building Envelope Inspection Checklists, Pre-Functional Checklists, Integrated Systems Test Checklists, and Functional Performance Test Checklists for specification section 01 91 00.15 10 TOTAL BUILDING COMMISSIONING at the following location:

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphic The checklists submitted in the Interim and Final Construction Phase Commissioning Plans must contain the same level of detail shown in the examples. The submitted checklists are not required to match the format of the examples.

3.1.2.1.2 Template Building Envelope Inspection Checklists

The Building Envelope Technical Commissioning Specialist must develop the Template Building Envelope Inspection Checklists. Include all items that verify the building materials and construction maintain the required thermal and moisture integrity and air tightness of the building envelope system in the Building Envelope Inspection Checklists.

3.1.2.2 Final Construction Phase Commissioning Plan

The Lead Commissioning Specialist (CxC) must prepare the Final

SECTION 01 91 00.15 10 Page 11Am #0005

Construction Phase Commissioning Plan. Submit the Final Construction Phase Commissioning Plan no later than 30 calendar days prior to the start of Pre-Functional Checks. Submit one electronic copy. Once approved, file the approved plan in the Sustainability eNotebook.

Include the information provided in the Interim Construction Phase Commissioning Plan. In addition, the Technical Commissioning Specialist must develop the Pre-Functional Checklists, Integrated Systems Test Checklists, and Functional Performance Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the Final Construction Phase Commissioning Plan.

3.1.2.2.1 Pre-Functional Checklists

The Pre-Functional Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete.

3.1.2.2.2 Functional Performance Test Checklists

Functional Performance Test Checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract.

Include the following sections and details appropriate to the systems being tested in the Functional Performance Test Checklists:

a. Notable system features including information about controls to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be accepted by the Government.

c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions

d. Identification of the equipment involved in the test

e. Control system feature identification

f. Point-to-point observations including demonstrating system flow meters and sensors have been calibrated and are correctly displayed on the Operator work station

g. Actuator operation observations demonstrating actuator responses to commands from the control system

h. As-found condition of the system operation

3.1.2.2.3 Integrated Systems Test Checklists

Integrated Systems Test Checklists must include test procedures that explain, step-by-step, the actions and expected results that will demonstrate that the interactive operations between systems performs in accordance with the contract. Include the following sections in the Integrated Systems Test Checklists:

a. Notable features of the interconnected systems organized by discipline

SECTION 01 91 00.15 10 Page 12Am #0005 including information to facilitate understanding of system operation

b. Conclusions and recommendations. Conclusions must clearly indicate if the systems do or do not perform in accordance with contract requirements. Recommendation must clearly indicate that the systems should or should not be accepted by the Government

3.1.3 Construction Submittals

Provide all submittals associated with the systems to be commissioned, including shop drawings; equipment submittals; test plans, procedures, and reports; and resubmittal's to the Commissioning Specialists. The Technical Commissioning Specialist must review the submittals to the extent necessary verify that the equipment and system installation will comply with the contract requirements and the requirements of the Basis of Design and the Owner's Project Requirements Document.

3.1.4 Inspection and Testing

Demonstrate that all system components have been installed, that each control device and item of equipment operates, and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents and the Owner's Project Requirements.

Requirements in related specification sections are independent from the requirements of this section and do not satisfy any of the requirements specified in this specification section. Provide all materials, services, and labor required to perform the Functional Performance Tests.

3.1.4.1 Commissioning Team

Provide a commissioning representative for each sub-contractor associated with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section. The designers listed below are the designers of record for their respective systems. Substitutes must be approved by the Contracting Officer's Representative.

3.1.4.1.1 Building Envelope Inspections Team

The following team members must participate in building envelope inspections:

Designation Function

CxB Building Envelope Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

BEC Contractor's Building Envelope Commissioning Representative

SECTION 01 91 00.15 10 Page 13Am #0005

3.1.4.1.2 Mechanical System Pre-Functional Checks Team

The following team members must participate in Pre-Functional checks of mechanical systems:

Designation Function

CQC Contractor's Quality Control Personnel

MC Contractor's Mechanical Commissioning Representative

EC Contractor's Electrical Commissioning Representative

CC Contractor's Controls Commissioning Representative

TABC Contractor's TAB Commissioning Representative

PC Contractor's Plumbing Commissioning Representative

3.1.4.1.3 Electrical System Pre-Functional Checks Team

The following team members must participate in Pre-Functional checks of electrical systems:

Designation Function

CQC Contractor's Quality Control Personnel

EC Contractor's Electrical Commissioning Representative

3.1.4.1.4 Mechanical Systems Test Team

The following team members must participate in Functional Performance, Seasonal, and Integrated Systems Testing of mechanical systems:

Designation Function

CxM Mechanical System Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

MC Contractor's Mechanical Commissioning Representative

EC Contractor's Electrical Commissioning Representative

CC Contractor's Controls Commissioning Representative

TABC Contractor's TAB Commissioning Representative

PC Contractor's Plumbing Commissioning Representative

SECTION 01 91 00.15 10 Page 14Am #0005

3.1.4.1.5 Electrical Systems Test Team

The following team members must participate in Functional Performance and Integrated Systems Testing of electrical systems:

Designation Function

CxE Electrical System Technical Commissioning Specialist

QAR Contracting Officer's Quality Assurance Representative

CQC Contractor's Quality Control Personnel

EC Contractor's Electrical Commissioning Representative

3.1.4.1.6 Other Pre-Functional and Functional Performance Participants

The following may participate as team members during Pre-Functional Checks and Functional Performance Testing:

Designation Function

BCE Base Civil Engineer Office Representative

User Using Agent's Representative

3.1.4.2 Building Envelope Inspection

Document building envelope inspection by the commissioning team using the approved Template Building Envelope Inspection Checklists. Indicate commissioning team member inspection and acceptance of each Building Envelope Inspection Checklist item by initials at the time they are inspected and found to be in conformance with contract requirements.

Inspect checklist items before they become hidden as construction progresses.

a. Submit the completed and initialed Building Envelope Inspection Checklists no later than 7 calendar days after completion of inspection of all checklists items. Submit one electronic copy.

b. The Building Envelope Technical Commissioning Specialist must make at least two site visits to the site to observe construction of the building envelope in-progress. On each visit, the Building Envelope Commissioning Specialist must review the Contractor's in-progress checklists to ensure that the commissioning team is inspecting the building envelope as required.

c. The Building Envelope Technical Commissioning Specialist must witness the building envelope pressure tests and diagnostic tests specified in Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS. The Building Envelope Technical Commissioning Specialist must review the resulting reports and provide recommendations for correction of any deficiencies or further testing.

SECTION 01 91 00.15 10 Page 15Am #0005

3.1.4.3 Pre-Functional Checks

Pre-Functional Checklists from the approved Final Construction Phase Commissioning Plan must be completed by the commissioning team. Complete one Pre-Functional Checklist for each individual item of equipment or system for each system required to be commissioned including, but not limited to, ductwork, piping, equipment, fixtures (lighting and plumbing), and controls. Indicate commissioning team member inspection and acceptance of each Pre-Functional Checklist item by initials. Acceptance of each Pre-Functional Checklist item by each team member indicates that item conforms to the construction contract requirements in their area of responsibility. Technical Commissioning Specialist acceptance of each Pre-Functional Checklist item indicates that each item has been installed correctly and in accordance with contract documents and the Owner's Project Requirements. Submit the completed and initialed Pre-Functional Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system. Submit one electronic copy.

Include manufacturer start-up checklists associated with equipment with the submission of the Pre-Functional Checklists.

3.1.4.4 Testing, Adjusting, and Balancing (TAB) Report and Field Acceptance Testing

The Mechanical System Technical Commissioning Specialist must review the pre-final TAB Report required by Specification Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC. Identify any deficiencies to the Contracting Officer's Representative and the Contractor's Quality Control Personnel. Resolve all deficiencies prior to TAB Field Acceptance Testing.

3.1.4.5 HVAC Controls Test Reports

The Mechanical System Technical Commissioning Specialist must review the Start-Up Testing Report and the PVT Procedures and Reports required by Specification Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC.

Include a certification by the Mechanical System Technical Commissioning Specialist that the submittals contain no deficiencies or that the submittals do not indicate any deficiencies in the HVAC systems or HVAC control systems with each of these submittals.

3.1.4.6 Tests

3.1.4.6.1 Functional Performance and Integrated Systems Tests

Schedule Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Functional Performance Tests. Perform Integrated Systems Tests only after the Functional Performance Tests for each associated system are completed with all deficiencies resolved and after the related Functional Performance Test Checklists have been signed by each commissioning team member.

a. Functional Performance Tests and Integrated Systems Tests must be performed with the Contracting Officer's Quality Assurance Representative present.

b. Abort Functional Performance Tests or Integrated Systems Tests when any system deficiency prevents the successful completion of the test.

SECTION 01 91 00.15 10 Page 16Am #0005

c. Technical Commissioning Specialists must lead and document all Functional Performance Tests and Integrated Systems Tests for the systems to be commissioned with the Contractor and appropriate sub-contractors performing the Functional Performance Tests and Integrated Systems Tests. The representatives listed in the paragraph Commissioning Team must attend the tests. Abort Functional Performance Tests or Integrated Systems Tests when any required commissioning team member is not present for the test.

3.1.4.6.1.1 Checklist

Use the Functional Performance Test and Integrated Systems Test Checklists from the approved Final Construction Phase Commissioning Plan to guide the Functional Performance Tests and Integrated Systems Tests. Functional Performance Tests must be performed for each item of equipment and each system required to be commissioned and verify all sensor calibrations, control responses, safeties, interlocks, operating modes, sequences of operation, capacities, lighting levels, and all other performance requirements comply with construction contract regardless of the specific items listed within the Functional Performance Test and Integrated Systems Test Checklists provided. Testing must progress from equipment or components to subsystems to systems to interlocks and connections between systems. Integrated Systems Tests must be performed for the interactive operation between systems such as HVAC systems, fire protection systems, back-up electrical supply, energy generation systems, and other systems, and verify correct interactive operation, acceptable speed of response, and other contract requirements for both normal and failure modes.

Examples of Integrated Systems Tests include the correct operation of HVAC systems during emergency system activation, correct operation of uninterruptible power supplies or energy generators and connected systems, or lighting system operation during power outage or emergency system activation. The order of components and systems to be tested must be determined by the Technical Commissioning Specialists.

3.1.4.6.1.2 Acceptance

Indicate acceptance of each item of equipment and systems tested by signature of each commissioning team member for each Functional Performance Test or Integrated Systems Test Checklist. The Contractor's Quality Control Representative and the Technical Commissioning Specialists must indicate acceptance after the equipment and systems are free of deficiencies.

3.1.4.6.2 HVAC Test Methods

Perform Functional Performance Tests in accordance with the following:

3.1.4.6.2.1 Prior to Testing

Prior to testing operating modes, sequences of operation, interlocks, and safeties, complete control point-to-point observations, test sensor calibrations, and test actuator commands.

3.1.4.6.2.2 Simulating Conditions

Over-writing control input values through the controls system is not acceptable, unless approved by the Contracting Officer's Representative.

Identify proposed exceptions in a protocol submitted to the Contracting

SECTION 01 91 00.15 10 Page 17Am #0005

Officer's Representative for approval. Before simulating conditions, overwriting values (if approved), or changing set-points, calibrate all sensors, transducers and devices. Below are several examples of exceptions that would be considered acceptable:

a. When varying static pressures inside ductwork can not be simulated within the duct, and where a sensor signals the controls system to initiate sequences at various duct static pressures, it is acceptable to simulate the various pressures with a Pneumatic Squeeze-Bulb Type Signaling Device with gauge temporarily attached to the sensing tube leading to the transmitter. It is not acceptable to reset the various set-points, nor to simulate an electric analog signal (unless approved as noted above).

b. Dirty filter pressure drops can be simulated using sheets of cardboard at filter face.

c. Freeze-stat safeties can be simulated by packing portion of sensor with ice.

d. High outside air temperatures can be simulated with a hair blower.

e. High entering cooling coil temperatures can be used to simulate entering cooling coil conditions.

f. Do not use signal generators to simulate sensor signals unless approved by the Contracting Officer's Representative, as noted above, for special cases.

g. Control set points can be altered. For example, to see the air conditioning compressor lockout work at an outside air temperature below 55 degrees F, when the outside air temperature is above 55 degrees F, temporarily change the lockout set point to be 0 degrees F above the current outside air temperature. Caution: Set points are not to be raised or lowered to a point such that damage to the components, systems, or the building structure and/or contents will occur.

h. Test duct mounted smoke detectors in accordance with the manufacturer's recommendations. Perform the tests with air system at minimum airflow condition in ductwork.

i. Test current sensing relays used for fan and pump status signals to control system to indicate unit failure and run status by resetting the set point on the relay to simulate a lost belt or unit failure while the unit is running. Confirm that the failure alarm was generated and received at the control system. After the test is conducted, return the set point to its original set-point or a set-point as indicated by the Contracting Officer's Representative.

3.1.4.6.2.3 Setup

Perform each test under conditions that simulate actual conditions as close as is practically possible. Provide all necessary materials and system modifications to produce the necessary flows, pressures, temperatures, and other conditions necessary to execute the test according to the specified conditions. At completion of the test, return the affected building equipment and systems to their pre-test condition.

SECTION 01 91 00.15 10 Page 18Am #0005

3.1.4.6.3 Integrated Systems Test Methods

3.1.4.6.3.1 Mechanical

3.1.4.6.3.1.1 Sustaining Mission to Mission Critical

Confirm that the mechanical control system converts to Mission…