W9128A-18-B-0002_Am-0009.pdf

PDF 778 KB Posted

Attached to
FY16 MCAF KNMD043004, Fighter Alert Facility, Joint Base Pearl Harbor-Hickam (JBPHH), Oahu, Hawaii
Solicitation number
W9128A-18-B-0002
Issued by

About this file

Am-0009

View the file

Other files

File Type Posted
W9128A-18-B-0002_Abstract_of_Bids.pdf PDF
W9128A-18-B-0002_Am-0013.pdf PDF
W9128A-18-B-0002_Am-0013_Specifications.pdf PDF
W9128A-18-B-0002_Am-0013_Drawings.pdf PDF
W9128A-18-B-0002_Am-0012.pdf PDF
W9128A-18-B-0002_Am-0011_Drawings_(3_of_3).pdf PDF
W9128A-18-B-0002_Am-0011_Drawings_(2_of_3).pdf PDF
W9128A-18-B-0002_Am-0011_Drawings_(1_of_3).pdf PDF
W9128A-18-B-0002_Am-0011_Specifications.pdf PDF
W9128A-18-B-0002_Am-0011.pdf PDF
W9128A-18-B-0002_Am-0010_Specifications.pdf PDF
W9128A-18-B-0002_Am-0010.pdf PDF
W9128A-18-B-0002_Am-0010_Drawings_(1_of_3).pdf PDF
W9128A-18-B-0002_Am-0010_Drawings_(3_of_3).pdf PDF
W9128A-18-B-0002_Am-0010_Drawings_(2_of_3).pdf PDF
W9128A-18-B-0002_Am-0008.pdf PDF
W9128A-18-B-0002_Am-0008_Specifications.pdf PDF
W9128A-18-B-0002_Am-0007_Drawings_(2_of_6).pdf PDF
W9128A-18-B-0002_Am-0007_Drawings_(5_of_6).pdf PDF
W9128A-18-B-0002_Am-0007_Drawings_(6_of_6).pdf PDF
W9128A-18-B-0002_Am-0007_Drawings_(3_of_6).pdf PDF
W9128A-18-B-0002_Am-0007.pdf PDF
W9128A-18-B-0002_Am-0007_Drawings_(4_of_6).pdf PDF
W9128A-18-B-0002_Am-0007_Drawings_(1_of_6).pdf PDF
W9128A-18-B-0002_Am-0006.pdf PDF
W9128A-18-B-0002_Am-0005_Drawings_(2_of_3).pdf PDF
W9128A-18-B-0002_Am-0005_Drawings_(1_of_3).pdf PDF
W9128A-18-B-0002_Am-0005_Specifications.pdf PDF
W9128A-18-B-0002_Am-0005.pdf PDF
W9128A-18-B-0002_Am-0005_Drawings_(3_of_3).pdf PDF
W9128A-18-B-0002_Am-0004.pdf PDF
W9128A-18-B-0002_Am-0003_Drawings_(1_of_2).pdf PDF
W9128A-18-B-0002_Am-0003.pdf PDF
W9128A-18-B-0002_Am-0003_Drawings_(2_of_2).pdf PDF
W9128A-18-B-0002_Am-0003_Specifications.pdf PDF
W9128A-18-B-0002_Am-0002.pdf PDF
W9128A-18-B-0002_Am-0001.pdf PDF
W9128A-18-B-0002_Specifications.pdf PDF
W9128A-18-B-0002_Drawings_(2_of_2).pdf PDF
W9128A-18-B-0002_IFB.pdf PDF
W9128A-18-B-0002_Drawings_(1_of_2).pdf PDF
SECNAV_5512-1.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Continuation Page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9128A18B0002

X 9B. DATED (SEE ITEM 11)

01-Feb-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

Am-0009

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Jun-2018

CODE

CECT - CONTRACTING DIVISION

USACE, HONOLULU DISTRICT

BLDG 252 (CECT-POH)

FT. SHAFTER HI 96858-5440

W9128A 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9128A18B0002 Am-0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

1. CHANGES TO SPECIFICATIONS. Attached hereto are revised pages/paragraphs to the specifications. The revision mark “(Am-0009)” is shown on each revised page.

a. REVISED SECTIONS. The following are revised pages/paragraphs to the solicitation. Changes are marked in “*” asterisks or indicated in bold.

Standard Form 1442 – Page 1

b. NEW PAGES. The following are new pages to the solicitation.

Section 00 60 00, Appendix A – Requests for Information (#141 through 147)

2. The bid opening date and time is EXTENDED (see SF1442, Page 1, Block 13A).

FY16 MCAF KNMD043004, F-22 Fighter Alert Facility, Joint Base Pearl Harbor-Hickam (JBPHH), Oahu, Hawaii

X

COLIN K WAKI 808-835-4393

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

01-Feb-2018

(RFP)

(IFB)

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance within _______7 calendar days and complete it within ________721 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the work required are due at the place specified in Item 8 by ___________ local time ______________ 24 July 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______ 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

CECT - CONTRACTING DIVISION

USACE, HONOLULU DISTRICT

BLDG 252 (CECT-POH)

FT. SHAFTER HI 96858-5440

W9128A

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX: TEL: TEL: FAX:

W9128A18B0002 90

(Am-0009)

FY16 MCAF RNMD043004, F‐22 Fighter Alert Facility Joint Base Pearl Harbor Hickam (JBPHH), Oahu, Hawaii

RFI # References Question Government Response 141 Section 01 90 00, Paragraph 1.12.4 and CG001, Note 3

Note 3 on sheet CG001 indicates a required 45 day notice before an electrical or water outage. Spec Section 01 90 00 Page 8 says there is a minimum 30 day requirement for water and 30-180 days for electrical. Please confirm the minimum is 30 days, and not 45 days.

Please see revised Drawing CG001, per Am-0005, and revised Section 01 90 00 notes, per Am-0008.

142 Drawings A-600, A-601, A-801, and A-802

The floor types called out on the Interior Room Finish Schedule (A-600 and A-601) and the Finish Floor Plans (A-801 and A-

802) differ for several rooms. Please confirm the finish floor for the following rooms:

EP101 - Shows CS-1 on Dwg 600, shows VCT-1 on Dwg 801.

CQ204 - Shows CS-1 on Dwg 601, not tagged on Dwg 801.

CQ205 - Shows CS-1 on Dwg 601, not tagged on Dwg 801.

CQ213 - Shows CS-1 on Dwg 601, shows CPT-1 on Dwg 801.

CQ215 - Shows CS-1 on Dwg 601, not tagged on Dwg 801.

CQ222 - Shows CS-1 on Dwg 601, shows PCT-1 on Dwg 801

Please see the following the referenced revised drawings for each of the rooms identified:

Room EP-101: A-600 INTERIOR ROOM FINISH SCHEDULE - ENTRY CONTROL POINT, per Am-0005.

Rooms CQ204, CQ205, CQ215: A-801 A2 Crew Quarter - Finish Floor Plan, Per Am-0005.

Room CQ222: A-801 Crew Quarter - Finish Floor Plan, per Am- 0003. [NOTE: Room CQ213 has been deleted; see RFI 145 below].

143 Will the designers reclassify the requirements of the concrete aggregates as “Negligible Weather” (1N or 2N) as indicated by the definitions in ASTM C33?

Due to the critical nature of the project, the specified limits will not be changed.

144 A-801 No finish indicated in rooms CQ 204, 205, 215 please confirm concrete sealer only per finish schedule A-600

Confirmed, please see revised Drawing A-801, per Am-0003.

145 A-801 CQ 213 supply room is indicated for carpet, A-600 calls for concrete sealer CS-1, - Please clarify

Confirmed, Room 213 deleted on revised Drawing A-801, per Am-0003.

146 Drawing AD-100 Please provide guidance on required duration for government personnel to transition to the new facilities after acceptance (i.e.

time from acceptance/occupancy to when demo may begin on existing facilities).

Please see revised Drawing GI005, per Am-0007.

147 Specification 06 61 16 Page 7, paragraph 2.1.2 - note says "patterns and colors for all solid polymer components and fabrications shall be those indicated on the project drawings"; however we were not able to locate on drawings. Please advise.

Please see revised Drawing A-701 details (also called solid surface), per Am-0007.

Section 00 60 00, Appendix A (Am‐0009)