W9128A-18-B-0002_Am-0005_Specifications.pdf
PDF 12 MB Posted
- Attached to
- FY16 MCAF KNMD043004, Fighter Alert Facility, Joint Base Pearl Harbor-Hickam (JBPHH), Oahu, Hawaii
- Solicitation number
- W9128A-18-B-0002
About this file
Am-0005 - Specifications
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MCAF FIGHTER ALERT FACILITY, JBPHH, OAHU, HAWAII KNMD 043004
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 INTERIOR FIRE ALARM SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
31 31 16.19 TERMITE CONTROL BARRIERS
31 32 11 SOIL SURFACE EROSION CONTROL
31 63 33 DRILLED MICROPILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 11.51 RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS
32 01 19 FIELD MOLDED SEALANTS FOR SEALING JOINTS IN RIGID
PAVEMENTS
32 01 19.61 RESEALING OF JOINTS AND CRACKS IN RIGID PAVEMENT
32 01 29.61 PARTIAL DEPTH PATCHING OF RIGID PAVING
32 11 23 AGGREGATE BASE COURSES
32 12 13 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 HOT-MIX ASPHALT AIRFIELD PAVING
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 11 CONCRETE PAVEMENT FOR AIRFIELDS PAVEMENTS
32 16 13 CONCRETE SIDEWALKS AND CURBS
32 17 23 PAVEMENT MARKINGS
32 31 13 CHAIN LINK FENCES AND GATES
32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES
DIVISION 33 - UTILITIES
33 05 23.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 30 00 SANITARY SEWERS
33 32 16 PACKAGED UTILITY WASTEWATER PUMPING STATIONS
33 40 00 STORM DRAINAGE UTILITIES
33 52 10 SERVICE PIPING, FUEL SYSTEMS
33 61 14 EXTERIOR BURIED PREINSULATED WATER PIPING
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 34 - TRANSPORTATION
34 43 00.00 20 AIRFIELD LIGHTING
34 73 13 MOORING AND GROUNDING POINTS FOR AIRCRAFT
ATTACHMENTS
NOTICE OF INTENT (NOI)
STORMWATER POLLUTION PREVENTION PLAN (SWPPP)
TARGETED HAZARDOUS MATERIAL SURVEY
SOIL & GROUNDWATER SCREENING SURVEY REPORT
S-1: STANDARD AIR POLLUTION CONTROL PERMIT APPLICATION FORM
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4 raink Text Box
-- End of Project Table of Contents --raink Text Box (Am-0005) raink Text Box 34 71 13.19 raink Text Box
ACTIVE VEHICLE BARRIERS
raink Text Box
ATTACHMENTS
raink Text Box 28 10 05 raink Text Box
ELECTRONIC SECURITY SYSTEMS (ESS)
raink Text Box 28 31 76 raink Text Box
INTERIOR FIRE ALARM SYSTEM
raink Text Box 28 08 10 raink Text Box
ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING
raink Text Box
GEOTECHNICAL ENGINEERING EXPLORATION
2.8 SHOP/FACTORY FINISHING
Furnish all ferrous metal components, except stainless steel, primed for painting unless indicated otherwise. Finish painting shall be in accordance with Section 09 90 00 PAINTS AND COATINGS, unless otherwise indicated. When anodic coatings are specified, the coatings shall conform to AAMA 611, with coating thickness not less than that specified for protective and decorative type finish in AA DAF45. Items to be anodized shall receive a polished satin finish pretreatment and a clear lacquer overcoat. All factory or manufactured components shall be shop finished as indicated.
2.8.1 Ferrous Metal
Surfaces of ferrous metal, except galvanized and stainless steel surfaces, shall be cleaned and shop coated with the manufacturer's standard protective coating other than a bituminous protective coating, compatible with finish coats. Prior to shop painting, clean surfaces with solvents to remove grease and oil, and with power wire-brushing or sandblasting to remove loose rust, loose mill scale and other foreign substances. Surfaces of items to be embedded in concrete shall not be shop painted.
2.8.2 Galvanizing
Items specified to be galvanized shall be hot-dip processed after fabrication. Galvanizing shall be in accordance with ASTM A123/A123M or ASTM A653/A653M as applicable.
2.8.3 Aluminum
Unless otherwise specified, aluminum items shall be standard mill finish.
For anodic coatings see paragraph SHOP/FACTORY FINISHING above.
2.9 PRODUCT SUSTAINABILITY CRITERIA
For products in this section, where applicable and to the extent allowed by performance criteria, provide and document the following in accordance with GBI GP Compliance requirements:
2.9.1 Recycled Content
Provide bullet resistant components meeting the recycled content requirements as stated in UFC 1-200-02, Paragraph 2-6.1.1 and provide documentation in accordance with Section 01 33 29 SUSTAINABILITY REPORTING paragraph RECYCLED CONTENT.
PART 3 EXECUTION
3.1 EXAMINATION
Field verify dimensions of rough openings for components, and that surfaces of openings are plumb, true, and provide required clearances. Protect surrounding work prior to installation of bullet-resistant components.
Surrounding work which is damaged as a result of the installation of bullet-resistant components shall be restored to like-new condition prior to acceptance of the work described herein. Examine existing work to ensure that it is ready for installation or erection of the components.
Components shall be checked and corrected for racking, twisting, and other malformation prior to installation. Set frames true, plumb and aligned for
SECTION 08 34 02 Page 11 raink Text Box
(DELETED)
raink Rectangle raink Text Box (Am-0005) raink Rectangle raink Rectangle raink Rectangle raink Text Box All factory or manufactured components shall be shop finished as indicated.
raink indicated. When anodic coatings are specified, the coatings shall conform to AAMA 611, with costing thickness not less than that specified for protective and decorative type finish in AA DAF45.
the window frame or subframe must replicate the method of installation to be used for the project. The minimum airblast loading parameters for the test must be as follows: Peak positive pressure of 40 kPa and positive phase impulse of 285 kPa-msec. The hazard rating for the proposed window systems, as determined by the rating criteria of ASTM F1642/F1642M, must not exceed the "Very Low Hazard" rating (i.e. the "No Break", "No Hazard", "Minimal Hazard" and "Very Low Hazard" ratings are acceptable. "Low Hazard" and "High Hazard" ratings are unacceptable). Results of window systems previously tested by test protocols other than ASTM F1642/F1642M may be accepted provided the required loading, hazard level rating, and size limitations stated herein are met.
1.11.3 Air Infiltration
Air infiltration must not exceed the amount established by AAMA/WDMA/CSA 101/I.S.2/A440 for each window type.
1.11.4 Water Penetration
Water penetration must not exceed the amount established by AAMA/WDMA/CSA 101/I.S.2/A440 for each window type.
1.11.5 Thermal Performance
Non-residential aluminum windows (including frames and glass) must be certified by the National Fenestration Rating Council with a whole-window Solar Heat Gain Coefficient (SHGC) maximum of .23 determined according to
NFRC 200 procedures and a U-factor maximum of .28 Btu/hr-ft2-F in accordance with NFRC 100.
1.11.6 Sound Attenuation
The window unit must have a minimum OITC of 40 with the window glazed with two pieces of 1/4 inch thick laminated glass, for Crew Quarters Building only, 35 OITC with the window glazed with 1/2 inch air space between two pieces of 1/4 inch thick glass when tested in accordance with AAMA/WDMA/CSA 101/I.S.2/A440 acoustical performance (optional) for Sentry Aloha Building.
1.12 QUALIFICATION
Window manufacturer must specialize in designing and manufacturing the type of aluminum windows specified in this section, and have a minimum of 2 years of documented successful experience. Manufacturer must have the facilities capable of meeting contract requirements, single-source responsibility and warranty.
1.13 WARRANTY
Provide Manufacturer's standard performance guarantees or warranties that extend beyond a 1 year period.
PART 2 PRODUCTS
2.1 PRODUCT SUSTAINABILITY CRITERIA
For products in this section, where applicable and to the extent allowed by performance criteria, provide and document the following in accordance with GBI GP Compliance requirements:
SECTION 08 51 13 Page 9 raink Text Box (Am-0005) raink
STC ratings are not applicable for window ratings.
2.3.8 Accessories
Provide windows complete with necessary hardware, fastenings, clips, fins, anchors, glazing beads, and other appurtenances necessary for complete installation and proper operation.
2.3.8.1 Hardware
AAMA/WDMA/CSA 101/I.S.2/A440. The item, type, and functional characteristics must be the manufacturer's standard for the particular window type. Provide hardware of suitable design and of sufficient strength to perform the function for which it is used. Equip all operating ventilators with a lock or latching device which can be secured from the inside.
2.3.8.2 Fasteners
Provide concealed anchors of the type recommended by the window manufacturer for the specific type of construction. Anchors and fasteners must be compatible with the window and the adjoining construction. Provide a minimum of three anchors for each jamb located approximately 6 inches from each end and at midpoint.
2.3.8.3 Window Anchors
Anchoring devices for installing windows must be made of aluminum, cadmium-plated steel, stainless steel, or zinc-plated steel conforming to
AAMA/WDMA/CSA 101/I.S.2/A440.
2.3.9 Finishes
Exposed aluminum surfaces must be factory finished with an anodic coating.
Color must be black. All windows for each building must have the same finish.
2.3.9.1 Anodic Coating
Clean exposed aluminum surfaces and provide an anodized finish conforming to AA DAF45 and AAMA 611. Finish must be:
a. Architectural Class I ( 0.7 mil or thicker), designation AA-M10-C22-anodized.
2.3.9.2 Organic Coating
Clean and prime exposed aluminum surfaces. Provide a baked enamel finish in accordance with AAMA 2603 with total dry film thickness not less than
0.8 mil.
2.4 THERMAL-BARRIER WINDOWS
Provide thermal-barrier windows, complete with accessories and fittings, where indicated.
Specify material and construction except as follows:
a. Aluminum alloy must be 6063-T6.
SECTION 08 51 13 Page 12 raink Text Box (Am-0005) raink dark bronze. All windows for each building must have the same
SECTION 08 91 00 Page 3
(Am-0003)
SD-02 Shop Drawings Wall louvers
SD-03 Product Data Metal Wall Louvers; S
SD-04 Samples
Wall louvers; G
SD-11 Closeout Submittals Recycled Content;
1.3 DELIVERY, STORAGE, AND PROTECTION
Deliver materials to the site in an undamaged condition. Carefully store materials off the ground to provide proper ventilation, drainage, and protection against dampness. Louvers shall be free from nicks, scratches, and blemishes. Replace defective or damaged materials with new.
1.4 DETAIL DRAWINGS
Show all information necessary for fabrication and installation of wall louvers. Indicate materials, sizes, thicknesses, fastenings, and profiles.
1.5 COLOR SAMPLES
Colors of finishes for wall louvers shall closely approximate colors indicated. Where color is not indicated, submit the manufacturer's standard colors to the Contracting Officer for selection.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Aluminum Sheet
ASTM B209, alloy 3003 or 5005 with temper as required for forming.
2.1.2 Extruded Aluminum
ASTM B221, alloy 6063-T5 or -T52.
2.2 METAL WALL LOUVERS
Weather resistant type, with bird screens and made to withstand a wind load of not less than 80 pounds per square foot. Wall louvers shall bear the AMCA certified ratings program seal for air performance and water penetration in accordance with AMCA 500-D and AMCA 511. The rating shall show a water penetration of 0.01 or less ounce per square foot of free area at a free velocity of 1250 feet per minute.
2.2.1 Extruded Aluminum Louvers
Fabricated of extruded 6063-T5 or -T52 aluminum with a wall thickness of not less than 0.081 inch.
raink
MCAF FIGHTER ALERT FACILITY, JBPHH, OAHU, HAWAII
raink Text Box
KNMD 043004
raink Text Box (Am-0005) raink Text Box SD-11 Closeout Submittals Recycled Content; S
e. Details at floor perimeter and height above structural floor
f. Method of anchorage to structural subfloor
g. Lateral bracing
h. Typical cutout details
i. Description of factory coating
j. Floor finishes
k. Location of connection to building grounding electrode
2.3.3 Panel Construction
a. Base access floor system on a 24 by 24 inch square module providing minimum of 6 inch clearance between structural floor and underside of panel and stringer. Fabricate so accurate job cutting and fitting may be done using standard sizes for perimeters and around columns.
b. Do not expose metal on finished top surface of panels. Provide cutouts and cutout closures to accommodate utility systems and equipment intercabling. Reinforce cutouts to meet design load requirements.
Provide extra support pedestals at each corner of cutout for cutout panels that do not meet specified design load requirements.
c. Panel design must provide for convenient panel removal for underfloor servicing and for openings for new equipment. Use panels of uniform dimensions within specified tolerances. Permanently mark panels to indicate load rating and model number.
d. Machine square floor panels to within plus or minus 0.015 inch with edge straightness plus or minus 0.0025 inch. If plastic edging is applied to the panel, the tolerances apply to the panel before the plastic edging is applied.
2.3.3.1 Hollow Formed Steel
Steel panels must be of die-formed construction, consisting of a flat steel top sheet welded to one or more formed steel stiffener sheets or components. Panels must be chemically cleaned, bonderized, and painted with the manufacturer's standard finish.
2.3.4 Floor Covering
Surface floor panels with carpet tile installed in the field. The electrical resistance must remain stable over the life expectancy of the floor covering. Any anti-static agent used in the manufacturing process must be an integral part of the material, not surface applied. Bolt heads or similar attachments must not rise above the traffic surface. Submit three separate samples of each specified floor covering finish and color.
2.3.4.1 Carpet Tile
Reference Section 09 68 00 CARPETING for carpet tile specification requirements including additional flammability testing requirements for carpet tile. Carpet tile must be field installed and comply with the following:
SECTION 09 69 13 Page 10 raink Text Box part of the panel. The electrical resistance must remain stable over the life expectancy of the floor covering. Any anti-static agent used in the manufacturing process must be an integral part of the material, not surface applied. Bolt heads or similar attachments must not rise above the traffic surface. Submit three separate samples of each specified floor covering finish and color.
raink Text Box (Am-0005) raink Rectangle raink Text Box
(DELETED)
raink Text Box raink or integrated raink
(Am-0005)
b. Perform the control system installation work, including all field check-outs and tuning.
c. Provide support to TAB personnel as specified under the paragraph TEST
AND BALANCE SUPPORT.
d. Submit and receive approval of the Controls System Operators Manual specified under the paragraph CONTROLS SYSTEM OPERATORS MANUALS.
e. Submit and receive approval of the Performance Verification Testing Plan and the Pre-PVT Checklist specified under the paragraph
PERFORMANCE VERIFICATION TESTING.
f. Perform the Performance Verification Testing.
g. Submit and receive approval on the PVT Report.
h. Submit and receive approval on the Training Documentation specified under the paragraph INSTRUCTION TO GOVERNMENT PERSONNEL. Submit at least 30 days before training.
i. Deliver the final Controls System Operators Manuals.
j. Conduct the Phase I Training.
k. Conduct the Phase II Training.
l. Submit and receive approval of Closeout Submittals.
PART 2 PRODUCTS
2.1 DDC SYSTEM
a. Provide a networked DDC system for stand-alone control in compliance with the latest revision of the ASHRAE 135 BACnet standard. Include all programming, objects, and services required to meet the sequence of control. Provide BACnet communications between the DDC system and native BACnet devices furnished with HVAC equipment and plant equipment including chillers, and variable frequency drives. Devices provided shall be certified in the BACnet Testing Laboratories (BTL) Product Listing and in accordance with ASHRAE 135.1 Method of Test for Conformance to BACnet.
b. Provide an operator workstation with complete interface software capable of programming, configuring, and monitoring the digital controllers.
Interface the new DDC system with the site's existing server and operator workstation and software including graphic creation, scheduling, alarming, and trending. The server and workstation are located at Building.
2.1.1 BACnet Building Controller (B-BC)
ASHRAE 135 building controller that is the main interface for the building control system.New equipment finishing shall be factory provided.
2.1.2 Direct Digital Controllers
Direct digital controllers shall be UL 916 rated.
SECTION 23 09 23.13 20 Page 17 raink Text Box The existing server is Trane Ensemble raink Text Box V5.1 and is located is Building 3385.
raink
SECTION 28 08 10
ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING
05/16
PART 1 GENERAL
1.1 SUMMARY
This specification defines the process and procedures for initial acceptance testing of electronic security systems (ESS) to include intrusion detection, access control and video as well as associated power and communications. Requirements to plan, conduct, and document all testing activities are covered along with the Government responsibility to witness testing and review and approve submittals. During the course of the acceptance test, demonstrate that, without exception, the completed and integrated ESS complies with the contract requirements.
1.2 DEFINITIONS
The Government Representative is a qualified individual given specific authority to witness system acceptance testing and evaluate the results.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section
01 33 00 SUBMITTAL PROCEDURES:
SD-05 Design Data
Test Plan
SD-06 Test Reports
Draft Test Report
Final Test Report
SD-07 Certificates
Qualifications
1.4 QUALITY ASSURANCE
1.4.1 Qualifications
1.4.1.1 General
The Test Director, Operator, and Technician must have prior experience with the specific equipment, hardware and software installed under the contract.
SECTION 28 08 10 Page 1
1.4.1.2 Test Director
The Test Director must have at least five years of hands-on ESS experience to include any combination of design, installation, testing and maintenance.
1.4.1.3 Operator
The Operator must have at least two years of hands-on experience installing and maintaining ESS workstations to include both hardware and software. The Operator must be capable of demonstrating all workstation features and capabilities.
1.4.1.4 Technician
The technician must have at least two years of hands-on experience installing and maintaining ESS field equipment to include sensors, card readers, cameras, local processors, and communications equipment. The Technician must be capable of demonstrating all features and capabilities of ESS field equipment. Qualifications may be met by the individual experience of one technician or by the combined experience of a team of technicians.
1.4.1.5 Test Intruder
The purpose of the test intruder is to activate intrusion sensors in a realistic and repeatable manner. The test intruder must be between 72 inches tall and weigh between 190 pounds. The test intruder must possess sufficient physical strength, agility, and endurance to perform movements required for intrusion testing. These movements may include, but are not limited to, walking, running, crawling, jumping, and climbing.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 TEST PLAN
Clearly establish the scope for ESS testing prior to beginning testing.
Submit a Test Plan that addresses the following topics:
3.1.1 Personnel
Identify the Test Director, Operator, Technician, Test Intruder, and any other personnel that will be performing test activities.
3.1.2 Equipment
List all equipment that is required to support testing. State the purpose of each piece of equipment. Describe equipment that will be used to enable voice communications between the monitoring location and the field.
3.1.3 Procedures
Provide a step-by-step procedure for conducting each functional test.
Describe actions and expected results. Ensure that functional test procedures address performance standards described in contract
SECTION 28 08 10 Page 2 specifications.
Download example procedures from http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf and review for applicability and completeness. Adapt example procedures to meet specific project requirements and develop additional ones as needed. Follow TEST-MASTERTP0023-005 for Air Force projects.
3.1.4 Special Provisions
Discuss any special test provisions such as facility access, safety, integration with existing systems, and coordination with other work.
3.1.5 Test Logs
Provide logs for recording all data from functional testing and burn-in testing.
Download example logs from http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf and review for applicability and completeness. Adapt example logs to meet specific project requirements and develop additional ones as needed.
3.1.6 Schedule
Provide an overall schedule that includes all testing milestones.
3.2 PRE-ACCEPTANCE TESTING
Conduct a complete test of all field equipment, workstations, and central system hardware and software in accordance with the approved Test Plan.
The Test Director must be on site to conduct a pre-test inspection and oversee all testing activities. Prior to testing, visually inspect all ESS components and correct workmanship and neatness deficiencies as needed. During the pre-test inspection, verify the accuracy of redline drawings and update drawings as needed. Conduct testing in two phases -functional testing followed by burn-in testing.
3.2.1 Phased Testing
3.2.1.1 Functional Testing Phase
During the functional testing phase, verify system performance in accordance with approved Test Plan. Record results in approved Test Logs, and provide a written explanation of each failure to include cause, corrective action, and retest result. Continue functional testing until all tests have been successfully completed with no unresolved failures.
3.2.1.2 Burn-In Testing Phase
Begin burn-in testing after successful completion of all functional testing.During the burn-in testing phase, place the ESS in normal operating mode and evaluate system performance for a continuous Five-day burn-in test period. During this time, the ESS must be fully functional and programmed such that all features can be exercised and evaluated through normal use. Record all system anomalies in approved Test Logs.
Include a description of each anomaly along with any actions taken in response. Immediately correct minor deficiencies observed during the course of testing and continue with burn-in testing. Determine the root cause of any failures and make necessary repairs or modifications to
SECTION 28 08 10 Page 3 restore full functionality. After a failure is corrected repeat functional tests for components and features associated with the failure, and repeat the entire burn-in testing phase.
3.2.2 Draft Test Report
Prepare and submit a Draft Test Report detailing the results of the testing. Refer to paragraph FINAL TEST REPORT for required content.
Include a cover letter signed by the Test Director stating that pre-acceptance testing has been completed and that the system is ready for acceptance testing.
3.3 SYSTEM ACCEPTANCE
Test the ESS in accordance with the approved Test Plan in the presence of the Government Representative to certify acceptable performance. Verify that the total system meets all requirements of the specification and complies with the specified standards.
Begin acceptance testing upon arrival of the Government Representative at the project site. Place the ESS in normal operating mode and evaluate system performance during the testing period. Immediately report any deficiencies observed during testing to the Government Representative and discuss possible causes and corrective measures. Obtain Government approval prior to making any adjustments, repairs or modifications. The Government retains the right to terminate testing at any time the ESS is found to be incomplete or fails to perform as specified. Such termination of acceptance testing constitutes a FAILED system acceptance test.
3.3.1 Preparation
Nofity the Contracting Officer of system readiness 15 days prior to the expected start date of acceptance testing. Prior to acceptance testing, complete all clean-up and patch work requirements. Ensure that security equipment closets and similar areas are free of accumulation of waste materials or rubbish caused by prior installation work.
3.3.2 Personnel
Ensure that the following personnel are on site to perform test activities: Test Director, Operator, Technician, and Test Intruder.
Ensure that the Quality Control Manager is on site during acceptance testing.
3.3.3 Visual Inspection
Assist the Government Representative in conducting a visual inspection of ESS equipment and wiring. This inspection will focus on the general neatness and quality of workmanship and compliance with applicable codes and manufacturers' recommended installation methods. Provide a comprehensive listing of installed equipment and software along with a complete set of ESS red line drawings to be used during the inspection.
Document deficiencies identified during the inspection.
3.3.4 Functional Testing
Comply with requests from the Government Representative to repeat functional tests performed previously during pre-acceptance testing. The Government reserves the right to request the Contractor to repeat all
SECTION 28 08 10 Page 4 functional tests or a representative sampling thereof as a means of performance verification. Add all test results to approved Test Logs.
3.3.5 System Activity Reports
Retrieve archived data from the system and provide activity reports as requested by the Government Representative. Reports may address any type of activity to include alarms, portal transactions, and video archives.
Assist with analyzing reports to identify trends and anomalies.
3.3.6 Corrective Actions
Correct any deficiencies in coordination with the Government Representative. Maintain a punch list and review status at the end of each day. Work diligently to complete corrective actions the same day that deficiencies are observed. Add deficiencies not corrected on the same day to the rework items list maintained by the Quality Control Manager. Failure to resolve punch list items to the satisfaction of the Government constitutes a FAILED system acceptance test.
3.4 FINAL TEST REPORT
Submit a Final Test Report following the successful completion of acceptance testing to include resolution of all punch list items. Address the following topics in the Final Test Report:
3.4.1 Summary
Provide a chronological summary of all testing. Describe test activities and results in narrative form.
3.4.2 Personnel
Provide a list of all Contractor and Government personnel who participated in the testing.
3.4.3 Test Logs
Provide all completed test logs along with a test log verification signed by the Test Director.
-- End of Section --
SECTION 28 08 10 Page 5
SECTION 28 10 05
ELECTRONIC SECURITY SYSTEMS (ESS)
05/16
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ASC/X9 X9.52 (1998) Triple Data Encryption Algorithm Modes of Operation
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2015) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM B32 (2008; R 2014) Standard Specification for Solder Metal
ASTM D709 (2017) Standard Specification for Laminated Thermosetting Materials
ASTM E84 (2017) Standard Test Method for Surface Burning Characteristics of Building Materials
BUILDERS HARDWARE MANUFACTURERS ASSOCIATION (BHMA)
ANSI/BHMA A156.23 (2010) Electromagnetic Locks
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 802.3 (2015; CORR 2017) Ethernet
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code
INTELLIGENCE COMMUNITY STANDARD (ICS)
ICS 705-1 (2010) Physical and Technical Security Standard for Sensitive Compartmented Information Facilities
INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO)
ANSI ISO/IEC 7816 (R 2009) Identification Cards - Integrated Circuit Cards
SECTION 28 10 05 Page 1
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
NEMA 250 (2014) Enclosures for Electrical Equipment (1000 Volts Maximum)
NEMA ICS 1 (2000; R 2015) Standard for Industrial Control and Systems: General Requirements
NEMA ICS 2 (2000; R 2005; Errata 2008) Industrial Control and Systems Controllers, Contactors, and Overload Relays Rated 600 V
NEMA ICS 6 (1993; R 2016) Industrial Control and Systems: Enclosures
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3) National Electrical Code
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST FIPS 140-2 (2001) Security Requirements for Cryptographic Modules
NIST FIPS 197 (2001) Advance Encryption Standard
NIST FIPS 201-2 (2013) Personal Identity Verification (PIV) of Federal Employees and Contractors
OPEN NETWORK VIDEO INTERFACE FORUM (ONVIF)
ONVIF (2015) Core Specification Version 2.6
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
TIA-222 (2005G; Add 1 2007; Add 2 2009; Add 3 2014; Add 4 2014; R 2014; R 2016) Structural Standards for Steel Antenna Towers and Antenna Supporting Structures
TIA-568-C.2 (2009; Errata 2010; Add 2 2014; Add 1 2016) Balanced Twisted-Pair Telecommunications Cabling and Components Standards
TIA-606 (2017c) Administration Standard for the Telecommunications Infrastructure
U.S. DEPARTMENT OF DEFENSE (DOD)
DODI 8500.01 (2014) Cybersecurity
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
47 CFR 15 Radio Frequency Devices
SECTION 28 10 05 Page 2
UNDERWRITERS LABORATORIES (UL)
UL 1037 (2016; Reprint Sep 2017) UL Standard for Safety Antitheft Alarms and Devices
UL 1076 (1995; Reprint Mar 2015) Proprietary Burglar Alarm Units and Systems
UL 1610 (2016) UL Standard for Safety Central-Station Burglar-Alarm Units
UL 294 (2013; Reprint Feb 2015) Access Control System Units
UL 437 (2013) Key Locks
UL 50 (2015) UL Standard for Safety Enclosures for Electrical Equipment, Non-Environmental Considerations
UL 634 (2007; Reprint Mar 2015) Connectors and Switches for Use with Burglar-Alarm Systems
UL 636 (1996; Reprint Jan 2013) Holdup Alarm Units and Systems
UL 639 (2007; Reprint May 2012) Standard for Intrusion Detection Units
UL 681 (2014) Installation and Classification of Burglar and Holdup Alarm Systems
UL 796 (2016) UL Standard for Safety Printed-Wiring Boards
UL 969 (2017) UL Standard for Safety Marking and Labeling Systems
UL 972 (2006; Reprint Dec 2015) Standard for Burglary Resisting Glazing Material Type
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "L" are for inclusion in the Sustainability eNotebook.
The Joint Base Pearl Harbor Hickam, Security Forces Squadron via the contracting officer will approve submittals requiring special review in this section. Drawings and descriptive data shall be approved prior to procurement, fabrication, and installation. A schedule of required submittals shall be prepared to be integrated with the overall construction management schedule to ensure adequate review and necessary corrective work before installation.
Include wiring diagrams and installation details of equipment indicating proposed location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a
SECTION 28 10 05 Page 3 coordinated installation. Wiring diagrams shall identify circuit terminals and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment. Drawings shall indicate adequate clearance for operation, maintenance, and replacement of operating equipment devices. Submittals shall include the nameplate data, size, and capacity. Submittals shall also include applicable federal, military, industry, and technical society publication references.
SD-02 Shop Drawings
ESS Components; G
Overall System Schematic; G
SD-03 Product Data
Premise Control Unit; G
Detection Sensors; G
Access Control Unit; G
Access Control Devices; G
Cameras; G
Camera Lenses; G
Camera Housing and Mounts; G
Thermal Imaging System; G
Video Recording; G
Printers; G
Communications Interface Devices; G
Network Switch; G
Video and ESS Transmission; G
Uninterruptible Power Supply (UPS); G
Batteries; G
Component Enclosure; G
Equipment Rack; G
SD-05 Design Data
Backup Battery Capacity Calculations; G
Access Control Throughput Rates; G
CCTV Storage Calculations
SD-07 Certificates
SECTION 28 10 05 Page 4
Contractor Qualifications; G
Instructor Qualifications; G
Data Encryption; G
SD-10 Operation and Maintenance Data
Training Plan; G
Training Content; G
ESS Components and ESS Software: Data Package 4; G
ESS Software and ESS Components: Data Package 4; G
SD-11 Closeout Submittals
As-Built Drawings; G
1.3 QUALITY ASSURANCE
1.3.1 Regulatory Requirements
The advisory provisions in each of the publications referred to in this specification are mandatory. Interpret these publications as though the word "must" has been substituted for "should" wherever it appears.
Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer.
Equipment, materials, installation, and workmanship must be in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.
1.3.2 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship and:
a. Have been in satisfactory commercial or industrial use for 2 years prior to bid opening, and have been utilized in applications of equipment and materials under similar circumstances and of similar size.
b. Have been available on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.
c. Where two or more items of the same class of equipment are required, provide products of a single manufacturer.
d. Provide commercial off-the-shelf (COTS) products in which the manufacturer allows a network of qualified distributors to sell, install, integrate, maintain, and repair the hardware and software products that make up the system.
SECTION 28 10 05 Page 5
1.3.2.1 Alternative Qualifications
Products having less than a 2 year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.3.2.2 Material and Equipment Manufacturing Date
Products manufactured more than one year prior to date of delivery to the site are not acceptable.
1.3.2.3 Product Safety
System components are to conform to applicable rules and requirements of NFPA 70 . Equip system components with instruction stickers including warnings and cautions describing physical safety, and special or important procedures to be followed in operating and servicing system equipment.
1.3.3 Shop Drawings
1.3.3.1 ESS Components
Submit the ESS Components, Data Package 4 with the ESS Software submittal package.Submit drawings that clearly and completely indicate each ESS component function that includes:
a. Termination device points
b. Interconnections required for system operation
c. Interconnections between modules and devices
d. Proposed wireway or conduit systems to be used including:
(1) Locations
(2) Sizes
(3) Types
e. Drawings showing:
(1) Device locations and spacing
(2) Mounting and positioning details
(3) Riser Diagrams with cable sizes and types
(4) Bill of Materials (Device make, model and quantities)
(5) Alarm and access control zones
(6) CCTV and sensor coverage areas
(7) Spare capacity
SECTION 28 10 05 Page 6
1.3.3.2 Overall System Schematic
Indicate the relationship of integrated components on one-line diagram and show:
a. Power source
b. System controls
c. Impedance matches
d. Interconnecting wire data including:
(1) Number
(2) Size
(3) Identification
(4) Maximum lengths
1.3.4 Evidence of Experience and Qualifications
1.3.4.1 Contractor Qualifications
Submit experience and certified qualifications data prior to installation. Show that specific installers who will perform the work have a minimum of 3 years of experience successfully installing ESS of the same type and similar design as specified. Include the names, locations, and points of contact of at least two installations of similar type and design as specified in this document where the installer has installed such systems. Indicate the type of each system installed. Certify that each system has performed satisfactorily in the manner intended for a period of at least 12 months.
1.3.4.2 Instructor Qualifications
Submit the instructor's experience and certified qualifications data prior to installation. Show that the instructor has received a minimum of 24 hours of ESS training from a technical organization such as the National Burglar and Fire Alarm Association, and 2 years experience in installing the specified ESS type.
1.4 Environmental Conditions
1.4.1 Interior Conditions
Equipment installed in environmentally protected interior areas must meet performance requirements specified for the following ambient conditions:
1.4.1.1 Temperature
32 to 120 degrees F. Components installed in unheated security protected areas must meet performance requirements for temperatures as low as 0 degrees F
1.4.1.2 Pressure
Sea level to 15,000 feet above sea level
SECTION 28 10 05 Page 7
1.4.1.3 Relative Humidity
5 to 95 percent
1.4.1.4 Fungus
Components must be constructed of nonfungus nutrient materials or be treated to inhibit fungus growth
1.4.1.5 Acoustical Noise
Components must be suitable for use in high noise areas above 100 dB, without adversely affecting their performance
1.4.2 Exterior Conditions
Components in enclosures must meet performance requirements when exposed to the following ambient conditions:
1.4.2.1 Temperature
Minus 25 to 140 degrees F
1.4.2.2 Pressure
Sea level to 15,000 feet above sea level
1.4.2.3 Solar Radiation
Six hours of solar radiation per day at dry bulb temperature of 120 degrees F including 4 hours of solar radiation at 104 watts per square foot
1.4.2.4 Sand and Dust
Wind driven for up to 6 miles per hour (mph)
1.4.2.5 Rain
2 inches per hour and 5 inches per hour cyclic with wind plus one period of 12 inches per hour
1.4.2.6 Humidity
5 to 95 percent
1.4.2.7 Fungus
Warm, humid atmosphere conducive to the growth of heterotropic plants
1.4.2.8 Salt Fog
Salt atmosphere with 5 percent salinity
1.4.2.9 Wind
Continual velocity up to 50 mph with gusts to 66 mph, except that fence sensors must detect intrusions up to 35 mph
SECTION 28 10 05 Page 8
1.4.2.10 Acoustical Noise
Components must be suitable for use in high noise areas above 110 dB without adversely affecting their performance. Examples areas include flight lines, runup pads, and generator sites.
1.5 SYSTEM CALCULATIONS AND ANALYSIS
1.5.1 Backup Battery Capacity Calculations
Submit calculations showing that backup battery capacity exceeds sensor operation, communications supervision, and alarm annunciation power requirements for proposed equipment plus 25 percent spare capcity.
1.5.2 CCTV Storage Calculations
Submit calculations showing the required storage capacity for each video storage device.
1.6 ESS SOFTWARE, DATA PACKAGE 4
Submit the ESS software, Data Package 4 with the ESS Components submittal .
Describe the functions of all software in the software manual and include:
a. All information necessary to enable proper loading, testing, and operation
b. Terms and functions definitions
c. Use of system and application software
d. Procedures for system initialization, start-up and shutdown
e. Alarm reports
f. Reports generation
g. Database format and data entry requirements
h. Directory of all files
i. All communication protocol descriptions, including data formats, command characters, and a sample of each type of data transfer
j. Interface definition
k. List of software keys
1.7 AS-BUILT DRAWINGS
Maintain a separate set of drawings, elementary diagrams, and wiring diagrams of the system to be used for as-built drawings. Keep this set accurately and neatly up-to-date with all changes and additions. This set is not to be used for installation purposes.
Finish the final drawings submitted with the endurance test report.
SECTION 28 10 05 Page 9
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
Provide a complete and integrated electronic security system (ESS). ESS must be compatible with the Installation's central monitoring system and monitored within the secure/protected area and at the Installation central monitoring station. ESS consisting of the following subsystems and features:
a. Intrusion Detection System (IDS)
b. Access Control System (ACS)
c. Closed-circuit Television System (CCTV)
d. Security Command Center (SCC)
e. Communications System
f. Security Lighting Systems
Include materials not normally furnished by the manufacturer with the ESS equipment as specified in:
a. Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
b. Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM
2.2 PERFORMANCE REQUIREMENTS
Integrate the installed and operating subsystems into the overall ESS system to detect intrusion, control access, provide CCTV surveillance, provide visual verification, and perform as an entity, as specified below. Provide electronic equipment that complies with 47 CFR 15 and are suitable for the environment where they will be installed.
2.2.1 Growth Capability
Provide capability for modular ESS expansion of inputs, outputs, card readers, and remote control stations with minimal equipment modification.
Software must be able to handle design requirements plus 25 percent spare capacity. Growth capability is not to be limited by the provided products.
2.2.2 Hazardous Locations
When located in areas where fire or explosion hazards exist, provide system components rated and installed according to Chapter 5 of NFPA 70 .
2.2.3 Network Certification
Certify all Platform Information Technology (PIT) in accordance with DODI 8500.01 and the individual service implementation policy.
2.2.4 Maintainability
Provide components that can be maintained using commercially available tools and equipment. Arrange and assemble components to be readily accessible to maintenance personnel without compromising system defeat
SECTION 28 10 05 Page 10 resistance and with no degradation in tamper protection, structural integrity, EMI or RFI attenuation, or line supervision after maintenance when it is performed in accordance with manufacturer's instructions.
2.2.5 Availablity
Provide components rated for continuous operation. Provide solid-state electronic components mounted on printed circuit boards, conforming to UL 796 . Provide boards that are plug-in, quick-disconnect type. Do not impede maintenance with densely packed circuitry. Provide power-dissipating components with safety margins of not less than 25 percent with respect to dissipation ratings, maximum voltages, and current-carrying capacity. Provide solid-state type or hemetically sealed electromechanical type light duty relays and similar switching devices.
2.2.6 Fail-Safe Capability
Provide fail-safe capability in critical elements of the ESS including, but not be limited to, the capability to monitor communication link integrity and to provide self-test. Provide fault annunciation when diminished functional capabilities are detected. Annunciate fail-safe alarms to clearly distinguish from other types of alarms.
2.2.7 Line Supervision
Provide the same geographic resolution for fault isolation at the systems level as provided for intrusion detection. Provide either a static or dynanmic system with active mode for line supervision of communication links of the ESS.
a. The static system must represent "no-alarm" always by the same signal, which is different than the originally transmitted signal.
b. The dynamic system must represent "no-alarm" with a signal which continually changes with time.
2.2.8 Power Loss Detection
Detect AC and DC power loss and generate an alarm when a critical component of the system experiences temporary or permanent loss of power.
Annunciate the alarm in the Secured Area and the Security Command Center to clearly identify the component experiencing power loss.
2.2.9 Controls and Designations
Provide controls and designations as specified in NEMA ICS 1 .
2.2.10 Special Test Equipment
Provide all special test equipment, special hardware, software, tools, and programming or initialization equipment needed to start or maintain any part of the system and its components. Special test equipment is defined as any test equipment not normally used in an electronics maintenance facility.
2.2.11 Electromagnetic Interference (EMI)
Configure and provide ESS components employing electromagnetic radiation constructed to provide minimal vulnerability to electronic countermeasures.
SECTION 28 10 05 Page 11
2.2.12 Electromagnetic Radiation (EMR)
Provide only ESS communication components which are Federal Communications Commission (FCC) licensed and approved. Provide system components which are electromagnetically compatible.
2.2.13 Interchangeability
Use off-the-shelf components which are physically, electrically, and functionally interchangeable with equivalent components as complete items. Equivalent, replacement components must not require new or other component modification. Do not use custom designed or one-of-a-kind items. Interchangeable components or modules must not require trial and error matching in order to meet integrated system requirements, system accuracy, or restore complete system functionality.
2.3 INTRUSION DETECTION SYSTEM (IDS)
The IDS primary function is to detect intrusion into secured areas.
Utilize a single database for all IDS programming data that seamlessly integrates with the ESS under a single operating environment. The IDS events must be viewable as separate or as a combined list of all ESS events. Control the IDS alarm monitoring through software control from the ESS.
a. Provide both supervised and non-supervised alarm point monitoring.
b. Arm or disarm Secure or access alarm points both manually and automatically by time of day, day of week or by operator command.
2.3.1 IDS Components
Provide components:
a. Premise Control Units (PCU)
b. Detection Sensors
c. Tamper Switches
2.3.2 Detection Sensitivity
The sensitivity of the IDS must allow for the following:
a. Locating intrusions within 330 feet zones along a line or perimeter to one side of the facility or building
b. Locating intrusions at individually protected assets or at an individual portal
c. Locating intrusions within the coverage on a single volumetric sensor
d. Locating failures or tampering at individual sensors
2.3.3 Detection Alarm and Reporting Capacity
Collect, communicate, and display up to 12 sensor zone alarms and to enable control of one or more response devices in each sensor zone.
SECTION 28 10 05 Page 12
Identify individual sensors in alarm if the sensor zone is a multiple alarm source combination. Annunciate a single alarm within 2 seconds maximum, after sensor transducer or other detection device activation except that alarms transmitted by radio frequency signaling must communicate in less than 3 seconds.
2.3.4 False Alarm Rate
The false alarm rate for each interior IDS zone must not exceed one false alarm per 30-day period. The false alarm rate for each exterior IDS zone must not exceed one false alarm per 24-hour period.
2.3.5 Nuisance Alarm Rate
The nuisance alarm rate for each interior IDS zone must not exceed three nuisance alarms per 30-day period. The nuisance alarm rate for each exterior IDS zone must not exceed three nuisance alarms per 24-hour period.
2.3.6 Premise Control Unit (PCU)
Install the PCU command processor in a tamper resistant enclosure that is specified in paragraph "Component Enclosure". Package the following with the PCU:
a. Power transformer
b. Battery(s)
c. Network connection cable
d. Keypad(s)
e. Keypad connection cable(s)
f. Additional components as required for full functionality
2.3.6.1 PCU Capabilities
Provide the PCU at a minimum but not limited to, the following capabilities;
a. Expansion to a total of at least 10,000 user codes with 150 user profile definitions.
b. Support 16 keypads with alphanumeric display. Each keypad must be capable of arming and disarming securing and accessing any system area based on a pass code or access control card and or key FOB authorization. Provide keypad alphanumeric display with complete prompt messages during all stages of operation and system programming and display all relevant operating and test data.
c. Four 4 zones for each keypad.
d. Data line supervision or two separate lines of communication.
e. Two-man access code or credentials.
f. Support programming to require the same or different access code
SECTION 28 10 05 Page 13 entered within a programmed delay time of 1 to 15 minutes after disarming before activating a silent ambush alarm.
g. Support area programming that disables schedule and time-of-day changes while system is armed so that area can only be disarmed during scheduled times.
h. Provide a minimum of a 4,000 event log buffer per PCU. Record and hold alarm activity information in the log buffer until the ESS is connected and receives the information. Provide a software-configurable warning log buffer filling notification for PCU(s) configured with network switch capabilities.
i. Support a Network Interface Card (NIC) plug-in module with built in network router capable of 128 Bit AES Rijndael…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.