A.07.15 Attachment 7 - CLIN Schedule.pdf
PDF 117 KB Posted
- Solicitation number
- W91235620R2005
About this file
This document contains a price schedule for a federal construction contract solicitation. The solicitation is for the construction of a Defense Logistics Agency Aviation Operations Center in Phase II at Defense Supply Center Richmond in Virginia. The price schedule includes 15 Contract Line Item Numbers for the base bid and optional items. CLINs 0001 through 0009 cover demolition, construction, site work, geothermal wells, foundations, and options for parking, a canopy, and generator relocation, with a statutory cost limitation of $89 million. CLINs 0010 through 0015 cover optional furnished items like generators, security cameras, and IT equipment to be exercised within one year and funded non-MILCON. Responses are due under solicitation number W91235620R2005 with amendments 1, 2, 3, 5, 6, and 7. Unit pricing is required for well installation in soil and rock.
View the file
Other files
Show 40 more
Latest 50 of 127 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN # DESCRIPTION QUANTITY
UNIT
MEASURE
UNIT
PRICE AMOUNT
BASE
BID
CLIN
DEMO BLDG 33 - All costs in connection with demolition of warehouse Building 33, including removal and disposal of Hazardous Materials, all related site demolition, site improvements and site utilities complete as shown on the drawings and specified excluding the work described in CLIN 0002- 0015. Source of funds is MILCON.
1 JOB $0
CLIN
CONSTRUCT OPS CTR PH2 - All costs in connection with construction of new DLA Ops Center, building construction only, excluding all "special costs" as identified in CLIN 0006, complete as shown on the drawings and specified excluding the work described in CLIN 0001 & 0003-0015. Source of funds is MILCON.
1 JOB $0
CLIN
SITE WORK - All costs in connection with construction of new DLA Ops Center Site Work, including all related site preparation, site improvements and site utilities complete as shown on the drawings and specified excluding the work described in CLIN 0001-0002 & 0004-0015. Source of funds is MILCON.
1 JOB $0
CLIN
WELLS IN SOIL - UNIT COST for installation of geothermal wells through SOIL (installation is as described in SPEC SECTION 23 81 47); include drilling, steel encasement, grouting and associated vertical piping. The cost of the rest of the items in SPEC SECTION 23 81 47 (including permits, heat pumps, system equipment, piping pumps, electrical equipment, controls, ground heat exchanger) shall be included in CLIN 0003. Assume total bid quantity for well installation through SOIL is 16,280 LF; in accordance with FAR 52.211-18, the UNIT PRICE in this CLIN 0004 is intended to provide for field adjustment in the case where the actual field amount drilled through SOIL varies. Complete work as shown on the drawings and specified excluding the work described in CLIN 0001-0003 & 0005-0015. Source of funds is MILCON.
16,280 LF $/LF $0
ATTACHMENT 7
PART I - THE PRICE SCHEDULE - DLA OPS CENTER (PH-2)
SECTION 00010 - SUPPLIES OR SERVICES AND PRICES
SCHEDULE I - BASE BID
MEASURE
UNIT
PRICE AMOUNT
CLIN
WELLS IN ROCK - UNIT COST for installation of geothermal wells through ROCK (installation is as described in SPEC SECTION 23 81 47); include drilling, steel encasement, grouting and associated vertical piping. The cost of the rest of the items in SPEC SECTION 23 81 47 (including permits, heat pumps, system equipment, piping pumps, electrical equipment, controls, ground heat exchanger) shall be included in CLIN 0003. Assume total bid quantity for well installation through ROCK is 93,720 LF; in accordance with FAR 52.211-18, the UNIT PRICE in this CLIN 0005 is intended to provide for field adjustment in the case where the actual field amount drilled through ROCK varies. Complete work as shown on the drawings and specified excluding the work described in CLIN 0001-0004 & 0006-0015.
Source of funds is MILCON.
93,720 LF $/LF $0
CLIN
SPECIAL FOUNDATIONS (PILES AND PILE CAPS) -
All costs in connection with construction of new DLA Ops Center special foundations (piles and pile caps), complete as shown on the drawings and specified excluding the work described in CLIN 0001-0005 & 0007-0015. Source of funds is MILCON.
1 JOB $0
$0
CLIN
OPTION
PARKING LOT PAVEMENT - All costs in connection with provision of asphalt to final grade in lieu of gravel in employee parking lot (COST DIFFERENCE - Cost to provide gravel parking should remain in CLIN 0003 Site Work), as indicated on CP103 and CP104 and specified excluding the work described in CLIN 0001- 0006 & 0008 -0015. Source of funds is MILCON.
Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
1 JOB $0
CLIN
OPTION
ADDITIONAL CANOPY - All costs in connection with construction of a canopy that stretches from the entrance vestibule of the two-story portion of the building to the east and west, stopping at the five-story portion and at the finished face of Building 32 complete as shown on drawings and specified excluding the work described in CLIN 0001-0007 & 0009-0015. Source of funds is MILCON. Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
1 JOB $0
TOTAL BASE BID
SCHEDULE II - OPTIONAL BID ITEMS MILCON FUNDED COSTS
MEASURE
UNIT
PRICE AMOUNT
CLIN
OPTION
GENERATOR RELOCATION - All costs in connection with relocation of existing emergency generators, site demolition, site repair, and site preparation complete as shown on drawings and specified excluding the work described in CLIN 0001- 0008 & 0010-0015. Source of funds is MILCON.
Option to be exercised within 180 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
1 JOB $0
$0 Sum of Statutory Lines $0
CLIN
OPTION
1 JOB $0
CLIN
OPTION
1 JOB $0
CLIN
OPTION
FF&E - All costs in connection with providing Furniture, Fixtures & Equipment (FF&E) complete as shown on the drawings and specified excluding the work described in CLIN 0001-0009 & 0011-0015.
Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
NEW GENERATOR - All costs to procure and install all 150 KW Standby Diesel Generator per specifications SECTION 26 32 15.00 10 for the DLA Operations Center - PH-2, complete, including all work incidental thereto as shown on the drawings and as specified exclusive of CLIN 0001-0010 & 0012-0015. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
PROCURE & INSTALL CCTV - All costs to Procure and install all Closed Circuit Television Security Camera system equipment identified as CAM (CCTV System Interior Security Cameras, CCTV Security System Cameras Weatherproof,) in TY sheets for the DLA Operations Center - PH-2, complete, including all work incidental thereto as shown on the drawings and as specified exclusive of CLIN 0001-0011 & 0013-0015. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
1 JOB $0
TOTAL SCHEDULE II - OPTIONAL BID ITEMS MILCON FUNDED COSTS
SCHEDULE III - OPTIONAL BID ITEMS NON-MILCON FUNDED COSTS
CLIN # QUANTITY
MEASURE
UNIT
PRICE AMOUNT
CLIN
OPTION
1 JOB $0
CLIN
OPTION
1 JOB $0
CLIN
OPTION
DESCRIPTION
PROCURE & INSTALL IDS/ACS - All costs to procure and install all Intrusion Detection System (IDS) and Access Control System (ACS) (Duress Alarms, Door Contact Triple Biased Balanced Magnetic Switches, IDS Dual Technology Sensors, Card Readers), per plans and specifications for the DLA Operations Center - PH-2, complete, including all work incidental thereto as shown on the drawings and as specified exclusive of CLIN 0001-0012 & 0014
- 0015. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
PROCURE & INSTALL TVs - All costs to procure and install all Audio-Visual Equipment (Televisions) for the DLA Operations Center - PH-2, complete, including all work incidental thereto as shown on the drawings and as specified exclusive of CLIN 0001-
0013 & 0015. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
PROCURE & INSTALL UPS - All costs to procure and install all Uninterruptible Power Supply (UPS) for the DLA Operations Center - PH-2, complete, including all work incidental thereto as shown on the drawings and as specified exclusive of CLIN 0001-
0014. Source of funds is Non-MILCON. Option to be exercised within 365 days of Contract Notice To Proceed in accordance with FAR 52.217-7.
1 JOB $0
$0
$0
STATUTORY COST LIMITATION IN THIS SOLICITATION:
Per FAR 36.205 CLINS 0001 - 0009 are subject to STATUTORY
COST LIMITATION OF $89,013,000.
TOTAL SCHEDULE III - OPTIONAL BID ITEMS NON-MILCON FUNDED COSTS
TOTAL SCHEDULE I, II, & III- BASE BID, OPTIONAL NON-MILCON AND OPTIONAL ITEMS