Section 00010 - Solicitation Contract Form
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
ARRA - GENERAL REQUIREMENTS
FFP
This Line Item is for information only and should not be priced. Pricing information should be inserted in SubCLINs (0001AA - 0001AJ) only.
FOB: Destination
NET AMT
0001AA 1 Lump Sum AARA-Reimbursement for Actual
FFP
Performance and Payment Bonds Premiums
0001AB 1 Lump Sum ARRA-Mobilization and Demobilization
FFP
0001AC 22 Months ARRA-Digital Progress Images
0001AD 1 Lump Sum ARRA - Construction Project Schedule
0001AE 9 Months ARRA-Maintain Concrete Testing Lab
0001AF 9 Months ARRA-Maintain Government Field Offices
0001AG 1 Lump Sum ARRA-Demolition of Building
FFP
at Downstream Laydown and Storage Area
0001AH 1 Lump Sum ARRA - Concrete Testing Lab
FFP
Repairs and Equipment
0001AJ 9 Months $1,500.00 $13,500.00 EST ARRA- Reimbursement for Utility Services
FFP
Government Field Offices and Laboratory. A unit price and total amount have been included for bidding purposes. Measurement and Payment for this item will be made in accordance with Section 01 22 00.00 10, 1.3.21.
NET AMT $13,500.00 EST
ARRA - UPPER GUARD WALL
FFP
This Line Item is for information only and should not be priced. Pricing information should be inserted in SubCLINs (0002AA - 0002BB) only.
0002AA 1 Lump Sum ARRA-Randum IN-SITU Sampling
FFP
Upper Guard Wall
0002AB 3,860 Cubic
Yard
ARRA-Pre-Excavation
0002AC 112 Linear
Foot
ARRA-Exploratory Drilling
Soil Drilling without Sampling, Upper Guard Wall
0002AD 112 Linear
Soild Drilling with Sampling, Upper Guard Wall
0002AE 152 Linear
Rock Drilling with Coring, Upper Guard Wall
0002AF 152 Linear
Sealing of Exploratory Holes with Cement Grout, Upper Guard Wall
0002AG 1 Lump Sum ARRA-Exploratory Pile Driving
FFP
0002AH 1 Lump Sum ARRA-Nose Cell
FFP
0002AJ 1 Lump Sum ARRA-Field Demonstrations
FFP
Upper Guard Wall Drilled Shafts
0002AK 670 Linear
ARRA-Permanent Casing
72-Inch Dia. Upper Guard Wall Drilled Shafts
0002AL 340 Linear
ARRA-Soil Excavation
72-Ince Dia. Upper Guard Wall Drilled Shafts
0002AM 230 Linear
ARRA-Rock Excavation
72-Inch Dia. Upper Guard Wall Drilled Shafts
0002AN 12 Each ARRA-Crosshole Sonic Logging (CSL)
FFP
0002AP 5,290 Linear
ARRA-Access Tubes, Crosshole Sonic
Logging, Upper Guard Wall Drilled Shafts
0002AQ 840 Cubic
ARRA-Transport and Place Tremie
Concrete, Mix 1, Upper Guard Wall Drilled Shafts
0002AR 3,400 Cubic
ARRA-Transport and Place Tremie
Concrete, Mix 2, Upper Guard Wall Nose Cell
0002AS 750 Cubic
ARRA-Transport and Place Mass
Concrete, Mix 7, Upper Guard Wall Nose Cell
0002AT 270 Cubic
ARRA-Transport and Place
Mass Concrete, Mix 8, Upper Guard Wall Thrust Blocks
0002AU 350 Linear
ARRA-Coring of Upper Guard Wall Drilled
Shafts
0002AV 230,880 Pound ARRA-Reinforcing Steel
FFP
0002AW 62,500 Pound ARRA-Reinforcing Steel
FFP
Upper Guard Wall Thrust Blocks
0002AX 19,342 Square
ARRA-Sheet Pile Cut-Off Wall
0002AY 1 Lump Sum ARRA-Cap Beams
FFP
0002AZ 1 Lump Sum ARRA-Precast Box Beams
FFP
0002BA 1 Lump Sum ARRA-Precast Concrete Skirts
FFP
0002BB 1 Lump Sum ARRA-Electrical Work
FFP
ARRA - LOWER GUARD WALL
FFP
This Line Item is for information only and should not be priced. Pricing information should be inserted in SubCLINs (0003AA - 0003BD) only.
0003AA 1 Lump Sum ARRA-Randum IN-SITU Sampling
FFP
Lower Guard Wall
0003AB 3,740 Cubic
ARRA-Pre-Excavation
0003AC 95 Linear
Soild Drilling without Sampling, Lower Guard Wall
0003AD 117 Linear
Soil Drilling with sampling, Lower Guard Wall
0003AE 325 Linear
Rock Drilling, with Coring, Lower Guard Wall
0003AF 325 Linear
Sealing of Exploratory Holes with Cement Grout, Lower Guard Wall
0003AG 1 Lump Sum ARRA-Exploratory Pile Driving
FFP
0003AH 1 Lump Sum ARRA-Sheet Pile Cells
FFP
0003AJ 1 Lump Sum ARRA-Field Demonstrations
FFP
Lower Guard Wall Drilled Shafts
0003AK 948 Linear
ARRA-Permanent Casing 102-Inch Dia.
0003AL 200 Linear
ARRA-Soil Excavation, 102-Inch Dia.
0003AM 325 Linear
ARRA-Rock Excavation, 102-Inch Dia.
0003AN 13 Each ARRA-Crosshole Sonic Logging (CSL)
FFP
0003AP 9,410 Linear
ARRA-Access Tubes
Crosshole Sonic Logging, Lower Guard Wall Drilled Shafts
0003AQ 280 Cubic
ARRA-Transport and Place Tremie Concrete
Mix 1, Lower Guard Wall Shaft Enclosures and Nose Pier
0003AR 850 Cubic
ARRA-Transport and Place Tremie Concrete
Mix 2, Lower Guard Wall Drilled Shafts
0003AS 240 Cubic
ARRA-Transport and Place Mass Concrete
Mix 7, Lower Guard Wall Cap Beam Infill
0003AT 1,200 Cubic
ARRA-Transport and Place Flowable
Concrete, Mix 12, Lower Guard Wall Drilled Shafts
0003AU 670 Cubic
ARRA-Transport and Place Flowable
Concrete, Mix 13, Lower Guard Wall Shaft Enclosure and Nose Pier Infill
0003AV 380 Linear
ARRA-Coring of Lower Guard Wall Drilled
Shafts
0003AW 429,000 Pound ARRA-Reinforcing Steel
FFP
0003AX 4,960 Pound ARRA-Reinforcing Steel
FFP
Lower Guard Wall Shaft Enclosures and Nose Pier
0003AY 1 Lump Sum ARRA-Shaft Superstructures
FFP
0003AZ 1 Lump Sum ARRA-Precast Concrete Panels
FFP
0003BA 1 Lump Sum ARRA-Nose Pier Superstructure
FFP
0003BB 1 Lump Sum ARRA-Cap Beams
FFP
0003BC 11,638 Square
ARRA-Sheet Pile Wall
0003BD 1 Lump Sum ARRA-Electrical Work
FFP
ARRA -GOVERNMENT FURNISHED DISPOSAL AREA
FFP
This Line Item is for information only and should not be priced. Pricing information should be inserted in SubCLINs (0004AA - 0004AK) only.
0004AA 460 Days ARRA-Environmental Control
FFP
Representative, Government Furnished Disposal Site
0004AB 18 Months ARRA-Environmental Compliance
FFP
Measurements, Sampling, Testing and Reporting Government Furnished Disposal Site
0004AC 3 Acre ARRA-Clearing
FFP
Government Furnished Disposal Site
0004AD 2,000 Linear
ARRA-Silt Fence
0004AE 1 Lump Sum ARRA-Traffic Control Devices
FFP
Permanent, Government Furnished Disposal Site
0004AF 4 Each ARRA-Cleaning of Sediment Basin No. 1
FFP
0004AG 4 Each ARRA-Cleaning of Sediment Basin No. 2
FFP
0004AH 6 Acre ARRA-Temporary Seeding
FFP
0004AJ 32,500 Cubic
ARRA-Disposal of Material in Temporary
Stockpile, Government Disposal Site
0004AK 2,150 Cubic
ARRA-Disposal of Excavated Material at Permitted Facility
TOTALS
TOTAL, GENERAL REQUIREMENTS, ITEMS 0001AA – 0001AJ $ ____________________
TOTAL, UPPER GUARD WALL, ITEMS 0002AA – 0002BB $ _________________________
TOTAL, LOWER GUARD WALL, ITEMS 0003AA – 0003BD $ _________________________
TOTAL, GOVERNMENT FURNISHED DISPOSAL AREA
ITEMS 0004AA – 0004AK $__________________________
TOTAL, ITEMS 0001AA THROUGH 0004AK, INCLUSIVE $ __________________________
Do not round off totals, in case of a variation between the unit price and the extension, the unit price will be considered to be the bid. If a modification to a bid based on unit prices is submitted, which provides for a lump sum adjustment to the total estimated cost, the application of the lump sum adjustment to each unit price in the bid schedule must be stated. If it is not stated, the bidder agrees that the lump sum adjustment shall be applied on a prorata basis to every unit price in the bid schedule.