REVISED SECTION 03 23 00 STEEL STRESSING TENDONS AND ACCESSORIES FOR PRESTRESSED CONCRETE
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Charleroi Locks and Dam - Upper and Lower Guard Walls
SECTION TABLE OF CONTENTS
DIVISION 03 - CONCRETE
SECTION 03 23 00
STEEL STRESSING TENDONS AND ACCESSORIES FOR PRESTRESSED CONCRETE
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CERTIFICATION OF PRESTRESSING TECHNICIANS
1.4 DELIVERY, STORAGE AND HANDLING OF MATERIALS
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Stressing Tendons
2.1.1.1 Seven-Wire Stress-Relieved Strand and Strand Assemblies
2.1.1.2 High-Strength Steel Bars
2.1.2 Accessories
2.1.2.1 Ducts
2.1.2.2 Anchorages and Couplers
2.1.2.3 Grout
2.1.3 Corrosion Preventive Coating
2.2 TESTS, INSPECTIONS, AND VERIFICATIONS
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Prestressing Method and Equipment
3.1.2 Installation Drawings
3.1.3 Anchorages
3.1.4 Stressing Tendons and Ducts
3.1.5 Tensioning Tendons
3.1.5.1 Pretensioning
3.1.5.2 Detensioning
3.1.5.3 Post-Tensioning
3.1.6 Grouting Post-Tensioned Tendons
3.1.7 Accuracy of Stress and Elongation Measurement
3.1.7.1 Stress Measurement
3.1.7.2 Elongation Measurement
3.1.8 Prestressing Operations Records
3.1.9 Application of Corrosion Inhibitor
3.2 INSPECTION
3.3 MATERIALS DISPOSITION RECORDS
-- End of Section Table of Contents --
SECTION 03 23 00 Page 1 W911WN-09-B-0004 Revised by Amendment No. 0002
SECTION 03 23 00
STEEL STRESSING TENDONS AND ACCESSORIES FOR PRESTRESSED CONCRETE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ACI INTERNATIONAL (ACI)
ACI 318 (2008; Errata 2008) Building Code Requirements for Structural Concrete and Commentary
ACI SP-66 (2004) ACI Detailing Manual
ASTM INTERNATIONAL (ASTM)
ASTM A 416/A 416M (2006) Standard Specification for Steel Strand, Uncoated Seven-Wire for Prestressed Concrete
ASTM A 722/A 722M (2007) Standard Specification for Uncoated High-Strength Steel Bar for Prestressing Concrete
ASTM B 117 (2007a) Standing Practice for Operating Salt Spray (Fog) Apparatus
ASTM C 109/C 109M (2008) Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or (50-mm) Cube Specimens)
ASTM C 150 (2007) Standard Specification for Portland Cement
ASTM C 939 (2002) Flow of Grout for Preplaced-Aggregate Concrete (Flow Cone Method)
ASTM C 940 (1998a; R 2003) Expansion and Bleeding of Freshly Mixed Grouts for Preplaced-Aggregate Concrete in the Laboratory
ASTM D 2265 (2006) Dropping Point of Lubricating Grease Over Wide Temperature Range
ASTM D 512 (2004) Chloride Ion in Water
SECTION 03 23 00 Page 2
ASTM D 566 (2002) Dropping Point of Lubricating Grease
ASTM D 610 (2008) Evaluating Degree of Rusting on Painted Steel Surfaces
ASTM D 92 (2005a) Standard Test Method for Flash and Fire Points by Cleveland Open Cup Tester
ASTM D 95 (2005) Water in Petroleum Products and Bituminous Materials by Distillation1
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FTMS 791 (Rev C) Lubricants, Liquid Fuels, and Related Products; Methods of Testing
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Installation Drawings; G, ED
Installation drawings for tendons and accessories shall be submitted and approved prior to commencing the work.
SD-03 Product Data
Prestressing Method and Equipment; G, ED
Descriptions of proposed prestressing method and equipment shall be submitted and approved prior to the start of prestressing operations.
Materials Disposition Records
Records which identify the incorporation of approved materials into the work shall be submitted before completion of the contract.
Prestressing Operations Records
Complete records of the prestressing operations shall be submitted before completion of the contract.
SD-06 Test Reports
Stressing Tendons; G, ED Accessories; G, ED
Certified materials test reports shall be submitted for all required materials tests, note the specific standards followed in the performance of tests, show that materials comply with the applicable specifications, be submitted for each material shipment and be identified with specific lots prior to use of materials in
SECTION 03 23 00 Page 3 the work.
SD-07 Certificates
Certification of Prestressing Technicians
Certificates for prestressing technicians shall be submitted prior to start of prestressing operations.
Corrosion Preventive Coating; G, RE
Certification shall be submitted for corrosion preventive coating.
1.3 CERTIFICATION OF PRESTRESSING TECHNICIANS
Submitted certificates for prestressing technicians who will use the proposed system in the work shall certify by name that these technicians are thoroughly trained and skilled in the use of the system.
1.4 DELIVERY, STORAGE AND HANDLING OF MATERIALS
Materials shall be suitably wrapped, packaged or covered at the factory to prevent being affected by dirt, water and rust. Materials shall be protected against abrasion or damage during shipment and handling.
Materials stored at the site shall be placed above ground on elevated, covered platforms.
PART 2 PRODUCTS
2.1 MATERIALS
Stressing tendons and accessories shall conform to the requirements of ACI 318 except as specified.
2.1.1 Stressing Tendons
Stressing tendons shall be clean and free of loose rust, scale and pitting. Unbonded tendons shall be permanently protected from corrosion with an approved applied coating.
2.1.1.1 Seven-Wire Stress-Relieved Strand and Strand Assemblies
Seven-wire stress-relieved strand and strand assemblies shall conform to ASTM A 416/A 416M, Grade 270, strand diameter as shown. Strand assemblies may be either shop or field assembled with anchor fittings positively attached to strands.
2.1.1.2 High-Strength Steel Bars
High-strength steel bars shall conform to ASTM A 722/A 722M, Type I or II, meeting all supplementary requirements.
2.1.2 Accessories
2.1.2.1 Ducts
Tendon ducts shall be of ferrous metal, capable of transmitting forces from grout to the surrounding concrete, flexible enough to conform to the tendon
SECTION 03 23 00 Page 4 profile and strong enough to maintain their shape without deforming, sagging, or collapsing during concrete placement and vibration. The inside diameter of the ducts shall be large enough to provide an internal area at least twice the gross area of multiple wire, bar or strand assemblies and shall be at least 1/4-inch larger than the diameter of a single wire, bar or strand placed in the ducts. Tendon ducts may be standard steel pipe for straight prestressing bars or galvanized corrugated metal ducts for curved prestressing tendons. Ducts shall be designed for watertight connections with all fittings. Galvanized ducts will not be permitted.
2.1.2.2 Anchorages and Couplers
Anchorages and couplers shall be metal of proven corrosion resistance and compatible with the stressing tendons, capable of fully developing the minimum guaranteed ultimate strength of tendons without excessive slip and approved. Epoxy coated carbon steel will be acceptable. Stainless steel of other special steel that may cause galvanic corrosion due to contact between different metals will not be acceptable.Anchorages shall be the button-head, wedge, nut and thread, grip nut, thread-bar, threaded plate or other approved type and shall be provided with bearing plates bars, rings, bells or other positive-attaching anchor fittings. Couplers shall be provided with housings long enough to permit the necessary movements and fittings which allow complete grouting of all components.
2.1.2.3 Grout
Grout for grouting post-tensioned tendons shall consist of a mixture of Portland cement, shrinkage compensating admixture and potable water of which final proportions shall be based on test results of sample mixtures.
Cement shall conform to ASTM C 150, Type I or II. The shrinkage compensating admixture shall produce a 2 percent minimum and a 10 percent maximum unconfined expansion when tested in accordance with ASTM C 940, shall not contain aluminum powder, chlorides, fluorides or nitrates, may be dispensed in solid or liquid form and must be approved by the Contracting Officer prior to its use. The water content shall be the minimum necessary for proper placement but the water-cement ratio shall not exceed 0.50 by weight. The pumpability of grout shall be determined in accordance with ASTM C 939. The efflux time of a grout sample immediately after mixing shall not be less than 11 seconds. The minimum 7-day compressive strength of 2-inch grout cubes, molded, cured and tested in accordance with ASTM C 109/C 109M shall be 2500 psi.
2.1.3 Corrosion Preventive Coating
A corrosion inhibitor shall be used around the upstream stressing head assembly of the trunnion girder pier anchorage bars. The material shall be a mastic corrosion inhibitor, waterproof, non-corrosive, non-hardening sealing compound with a viscosity to suit the intended application and shall possess properties in accordance with the following table:
Test Test Method Acceptance Criteria
Dropping Point, ASTM D 566 or Minimum 300 (Degrees F) ASTM D 2265
Oil Separation @ FTMS 791 Maximum 0.5 160 Degrees F, Method 321.2 % by Weight Water, % Maximum ASTM D 95 0.1
SECTION 03 23 00 Page 5
Test Test Method Acceptance Criteria
Flash Point, Degrees F ASTM D 92 Minimum 300 (Refers to Oil Component)
Corrosion Test, ASTM B 117 For corrosive 5% Salt Fog @ 100 environments: Rust Degrees F, 5 mils, Grade 7 or better minimum hours, after 1000 hours (Q Panel Type S) of exposure according to ASTM D 610.
Water Soluble Ions,
a. Chlorides,ppm (max) ASTM D 512 10
b. Nitrates, ppm (max) ASTM D 992 10
c. Sulfides, ppm (max) APHA 427D (15th Ed.) 10
Soak Test, ASTM B 117 No emulsification of 5% Salt Fog @ 100 (Modified) the coating after 720 Degrees F, 5 mils hours of exposure.
coating, Q panels, Type S. Immerse Panels 50% in a 5% salt solution and expose to salt fog
2.2 TESTS, INSPECTIONS, AND VERIFICATIONS
The Contractor shall have required material tests performed on stressing tendons and accessories by an approved laboratory to demonstrate that the materials are in conformance with the specifications. These tests shall be at the Contractor's expense.
PART 3 EXECUTION
3.1 INSTALLATION
Stressing tendons and accessories shall be installed or placed as specified and as shown on contract and approved installation drawings. Installation details of stressing tendons and accessories not specified or shown shall be in accordance with ACI SP-66 or ACI 318. Welding shall not be performed near or adjacent to stressing tendons. Stressing tendons shall not be installed until all welding has been completed on supports or any part which might be in contact with the tendons.
3.1.1 Prestressing Method and Equipment
Descriptions of the proposed prestressing methods and equipment indicating the manufacturer of all prestressing equipment, including tensioning jacks, stress measurement gages, dynamometers and load cells or other devices for measuring stressing loads, shall be provided by the Contractor.
Descriptions shall include certified calibration records for each set of jacking equipment and testing curves for stress measurement gages which show that the gages have been calibrated within the last 60 days for the jacks for which they are to be used.
SECTION 03 23 00 Page 6
3.1.2 Installation Drawings
Detailed installation drawings for stressing tendons and accessories showing the type and size of stressing tendons and anchorages, erection methods, sequence of stressing and stressing calculations shall be provided by the Contractor.
3.1.3 Anchorages
Anchorages must be set in a plane normal to the axis of the tendons such that uniform bearing on the concrete is assured. Positive connecting anchorages rather than gripping types shall be used for anchoring embedded ends of tendons. Anchorages and anchor fittings shall be permanently protected against corrosion. Parallel wire anchorage wedges or cores shall be recessed within the members.
3.1.4 Stressing Tendons and Ducts
Protective coverings and wrappings shall be removed and each stressing tendon shall be closely inspected to see that nicks, scoring, pits or other damage does not exist and high strength steel bars shall be closely inspected to assure that they are not bent and that threaded ends are in satisfactory condition immediately prior to installation. Strand, wire and bar tendons shall be shop or field assembled as required and positively attached to anchorages. Type WA wire assemblies shall be anchored only with wedge type anchorages. Stressing tendons and ducts shall be assembled to required shapes and dimensions and placed where indicated on drawings within specified tolerances and adequately supported. Ducts shall be securely fastened at close intervals and grout openings and vents must be securely anchored to ducts and to either the forms or reinforcing steel to prevent displacement during concrete placing. The ends of ducts shall be effectively protected to prevent entry of water, concrete, grout or debris. Wires of parallel-wire assemblies shall not be spliced. Steel bar tendons may be joined by couplers where shown or approved, provided they are capable of developing the guaranteed minimum ultimate strength of the bars. Strands to be spliced shall have the same lay or direction of twist and the ends shall be cut by shears or abrasive grinders. No more than one strand shall be spliced in any one member where single strand tensioning is employed. Strand splices shall be capable of developing the full ultimate strength of the strand. Slippage of the splice shall be checked and correction made for differential slippage. Where multiple strand tensioning is used, not more than 10 percent of the strands in any member shall be spliced.
3.1.5 Tensioning Tendons
Tensioning of stressing tendons shall be as specified and shown. The stress induced in the tendons by any method of tensioning shall be determined independently by both (1) measurement of tendon elongation and
(2) direct measurement of force using a pressure gauge or load cell. If the results of these two measurements do not check each other and the theoretical values within 5 percent, the operation shall be carefully checked and the source of error determined and corrected before proceeding further. Concrete shall be allowed to attain the minimum required compressive strength before transfer of stress to ensure that the concrete strength is adequate for the requirements of the anchorages or for transfer through bond as well as meet camber or deflection requirements. The final prestress load in each unit after seating shall be as shown. Safety measures shall be taken by the Contractor to prevent accidental injury
SECTION 03 23 00 Page 7 caused by failure of a stressing tendon or tendon component. The exposed ends of stressing tendons and anchorages shall be protected from damage during stressing operations to prevent failure.
3.1.5.1 Pretensioning
Strand tendons may be tensioned by jacking of groups of strands or may be tensioned individually by means of a single-strand jack. Before final tensioning, all tendons shall be brought to a uniform initial tension of approximately 1,000 pounds per strand per 200 feet of bed, with a minimum of 1,000 pounds and a maximum of 3,000 pounds per strand. The force corresponding to the initial tension shall be measured by a dynamometer or other approved method to aid in determining the final elongation. After this initial tensioning, the tendons shall be stressed to the total tension indicated on the drawings using hydraulic or mechanical equipment with gauges or dynamometers graduated and calibrated to accurately determine the load applied. Draped pretensioned strands shall be tensioned partially by jacking at the end of the bed and partially by uplifting or depressing strands, or they shall be held in their draped positions by means of rollers, pins or other approved methods and tensioned entirely by jacking.
Approved low-friction devices shall be used at all points of change in slope of draped strands while tensioning draped strands, regardless of the tensioning method used. Cable stress shall be maintained between anchorages until the concrete has reached the specified compressive strength.
3.1.5.2 Detensioning
Forces from pretensioned strands shall be transferred to the concrete by either the multiple-strand release or the single-strand release method.
The stress transfer shall not be performed until concrete strength, as indicated by test cylinders, has reached the specified transfer strength.
If concrete has been heat-cured, the detensioning shall be done immediately following the curing period while the concrete is still warm and moist.
During detensioning, the prestressing forces shall be kept nearly symmetrical about the vertical axis of the member and shall be applied in a manner that will minimize sudden loading. Eccentricity about the vertical axis shall be limited to one strand.
a. Multiple-Strand Release: In this method, all strands shall be detensioned simultaneously and the load transferred gradually to the concrete by hydraulic jacking.
b. Single-Strand Release: In this method, all strands shall be detensioned by slow heat-cutting the strands in accordance with a pattern and schedule as approved. The strands shall be heated using a low-oxygen flame until the metal gradually loses its strength, causing release of the strands to occur gradually. The low-oxygen flame shall be played along the strand for a minimum of five inches. Strands shall be so heated that the failure of the first wire in each strand shall occur after the torch has been applied for a minimum of five seconds.
3.1.5.3 Post-Tensioning
Tensioning shall not be performed until the concrete has reached the required strength at transfer of stress. Before final tensioning of tendons, all tendons shall be brought to a uniform initial tension of approximately 10 percent of the full load. The force corresponding to the initial tension shall be measured by a dynamometer or other approved method
SECTION 03 23 00 Page 8 as a starting point in determining final elongation. A temporary overstress above the final prestress force as approved by the Contracting Officer shall be used to overcome stress losses. The units shall be tensioned until the proper elongations and jacking pressures are attained and reconciled within the limits stated above. Straight tendons may be tensioned from one end. Curved or draped tendons shall be stressed by simultaneous jacking from both ends using a common pump with identical hoses and jacks, unless otherwise shown.
3.1.6 Grouting Post-Tensioned Tendons
Grouting between each tendon and its enclosing duct shall be performed within 5 days after completion of the tensioning operation. Grouting shall not be performed if air temperature below 45 degrees F is anticipated within 48 hours after grouting unless an approved method of temperature control is used. The grout shall be mixed in a mechanical mixer of a type that will produce uniformly and thoroughly mixed grout. First water shall be placed in the mixer followed by cement and admixture. Grout shall be continuously agitated until it is pumped. Grout that has begun to set shall be discarded. Just before grouting, the ducts shall be flushed with clean water and then blown clear by compressed air to removed excess water. With the grout vent open at one end of duct, grout shall be applied continuously under moderate pressure at the other end until all entrapped air is forced out as indicated by a uniform flow of grout from the discharge vent. The discharge vent shall then be closed and the pressure raised to 50 psi minimum and held for at least 1 minute. The injection point shall then be closed by an approved means to prevent any loss of grout. For a period of at least 3 days after grouting the tendons, the prestressed members shall not have equipment or other loads placed on them. A longer period may be required, depending upon the method of curing and magnitude of imposed stresses.
3.1.7 Accuracy of Stress and Elongation Measurement
3.1.7.1 Stress Measurement
Hydraulic gauges, dynamometers, load cells or other devices for measuring stressing load shall have an accuracy of reading within two percent for stress measurement. Gauges are required to have been calibrated for the jacks for which they are used within a period not exceeding 12 months.
Recalibration shall be performed at any time that a gaging system shows indication of erratic results in the opinion of the Contracting Officer.
Gauges shall indicate loads directly in pounds or be accompanied by a chart which converts dial readings into pounds.
3.1.7.2 Elongation Measurement
After the initial force has been applied to a tendon, reference points for measuring elongation due to additional tensioning forces shall be established. They shall be located according to the method of tensioning and type of equipment. The system used shall be capable of measuring the true elongation plus or minus 1/16-inch.
3.1.8 Prestressing Operations Records
The Contractor shall compile and submit complete prestressing operations records to the Contracting Officer. These records shall show the manufacturer, identification and description of materials and equipment including prestressing tendons and jacking and load measuring equipment;
SECTION 03 23 00 Page 9 location of prestressing tendons; initial design tensioning loads, final design tensioning loads and actual tensioning loads for tendons; dates tensioning loads applied; and theoretical and actual elongations for tendons.
3.1.9 Application of Corrosion Inhibitor
Corrosion inhibitor shall be applied to the pipe/keeper channel which surrounds the upstream anchor nut assembly located on the embedded end of the pier anchorage bars. The inhibitor shall be applied in accordance with the manufacturer's instructions.
3.2 INSPECTION
The Contractor's facilities shall be open for inspection by the Contracting Officer at any time.
3.3 MATERIALS DISPOSITION RECORDS
Accurate materials disposition records identifying all materials incorporated into the work and showing the disposition of specific lots of approved tested materials shall be compiled by the Contractor.
-- End of Section --
SECTION 03 23 00 Page 10
| 03 23 00 - STEEL STRESSING TENDONS AND ACCESSORIES FOR PRESTRESSED CONCRETE |
| 03 23 00 - STEEL STRESSING TENDONS AND ACCESSORIES FOR PRESTRESSED CONCRETE |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 CERTIFICATION OF PRESTRESSING TECHNICIANS |
| 1.4 DELIVERY, STORAGE AND HANDLING OF MATERIALS |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| 2.1.1 Stressing Tendons |
| 2.1.1.1 Seven-Wire Stress-Relieved Strand and Strand Assemblies |
| 2.1.1.2 High-Strength Steel Bars |
| 2.1.2 Accessories |
| 2.1.2.1 Ducts |
| 2.1.2.2 Anchorages and Couplers |
| 2.1.2.3 Grout |
2.1.3 Corrosion Preventive Coating
2.2 TESTS, INSPECTIONS, AND VERIFICATIONS
| PART 3 EXECUTION |
| 3.1 INSTALLATION |
| 3.1.1 Prestressing Method and Equipment |
| 3.1.2 Installation Drawings |
| 3.1.3 Anchorages |
| 3.1.4 Stressing Tendons and Ducts |
| 3.1.5 Tensioning Tendons |
| 3.1.5.1 Pretensioning |
| 3.1.5.2 Detensioning |
| 3.1.5.3 Post-Tensioning |
| 3.1.6 Grouting Post-Tensioned Tendons |
| 3.1.7 Accuracy of Stress and Elongation Measurement |
| 3.1.7.1 Stress Measurement |
| 3.1.7.2 Elongation Measurement |
| 3.1.8 Prestressing Operations Records |
| 3.1.9 Application of Corrosion Inhibitor |
| 3.2 INSPECTION |
| 3.3 MATERIALS DISPOSITION RECORDS |