Charleroi Locks and Dam - Upper and Lower Guard Walls
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00.10
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
1.2 DEFINITIONS
1.3 REFERENCES
1.4 SUBMITTALS
1.5 DRAWINGS
1.5.1 Contract Drawings
1.5.2 Reference Drawings
1.6 WORK UNDER OTHER CONTRACTS
1.6.1 Charleroi Contract One (River Wall Construction)
1.6.2 Painting Tainter Gates and Bulkhead
1.6.3 Electrical System Upgrade
1.7 FEATURES OF WORK AND SEQUENCING
1.7.1 General
1.8 ACCESS AND WORK AREAS
1.8.1 General Access to Project Site
1.8.2 Access Plan
1.8.3 General Work Area Restrictions
1.8.3.1 Laydown and Storage Areas
1.8.4 Utilization of Active Lock Chamber and Approaches
1.8.4.1 General
1.8.4.2 Requests for Lockages Through Land Chamber
1.8.4.3 Work Areas
1.8.5 Protection of Existing Roads and Property
1.8.5.1 General
1.8.5.2 Hauling Permits
1.8.6 Utilities
1.8.7 Offloading Facilities at Left Bank Batch Plant
1.9 EXISTING SURVEY CONTROLS
1.9.1 Project Alignment
1.10 MAINTENANCE AND PROTECTION OF VEHICULAR TRAFFIC
1.10.1 Barricades
1.11 PROJECT SITE CONDITIONS
1.11.1 Inspection of Geologic Samples
1.11.2 Interpretation of Geologic Information, Data and Samples
1.12 DAMAGE TO WORK
1.13 PROTECTION OF UTILITIES
1.14 CONTRACTOR'S FLOATING PLANT
1.14.1 General
1.14.2 Floating Plant
1.14.3 Signal Lights
1.14.4 Maintenance of Floating Plant
1.14.5 Mooring of Floating Plant
1.14.6 Withdrawal of Equipment and Floating Plant
1.14.6.1 Plan of Action, Withdrawal of Equipment and Floating Plant
SECTION 01 30 00.10 Page 1 W911WN-09-B-0004 Revised by Amendment No. 0004
1.14.6.2 Compensation and Extension of Contract Period, Withdrawal of Equipment and Floating Plant
1.14.7 Operation of Small Water Craft
1.15 OPERATION OF PROJECT FACILITIES
1.16 CONDITIONS OF WORK
1.16.1 Charleroi Locks and Dam, Hours of Operation
1.16.2 Contractor's Work Hours
1.16.3 Coordination with Lock and Dam Operations
1.16.4 Government Access to the Site
1.16.5 Contractor Coordination and Scheduling
1.16.6 Coordination with Dam Gate Operations
1.16.6.1 Control of Flow Over Fixed Crest Weir
1.16.6.2 Operation of Dam Gates During Contract Work
1.16.6.3 Unanticipated (Emergency) Operations
1.17 POOL LEVELS
1.17.1 Hydrographs
1.17.2 Stage-Discharge
1.17.3 Stage-Duration
1.17.4 Velocities
1.18 SAFETY AND HEALTH REQUIREMENTS
1.19 INSPECTIONS AND ACCEPTANCE OF WORK
1.19.1 General
1.19.2 Access to Work
1.20 CONVEYOR OPTION
PART 2 PRODUCTS
2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE
2.2 GOVERNMENT-FURNISHED PROPERTY
2.2.1 Steel Sheet Piling
2.2.2 Concrete
2.2.3 Check Posts
PART 3 EXECUTION
3.1 SEQUENCE OF WORK AND RESTRICTIONS
3.1.1 Restrictions Due To Other Contracts
3.1.1.1 River Wall Construction
3.1.1.2 Concrete Production
3.2 OPERATION OF GOVERNMENT-FURNISHED DISPOSAL AREA
3.2.1 Contractor Operation of the Government-Furnished Disposal Area
3.3 AS-BUILT DRAWINGS
3.4 TESTING
3.5 RECORDS AND REPORTS
-- End of Section Table of Contents --
SECTION 01 30 00.10 Page 2
SECTION 01 30 00.10
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
This section contains information of a general nature, and covers general requirements applicable to the performance of the work under this contract. The information provided, and the requirements specified are in addition to those specified in other sections of the contract.
1.2 DEFINITIONS
The following definitions apply to the terms used within this section and in other sections of these specifications as applicable:
a. Charleroi Contract One - Contract No. W911WN-04-C-0003, Charleroi Locks, Contract One (River Wall Construction).
b. Completion of Construction of Charleroi River Wall - The date on which the Government accepts the construction of the River Wall as shown on the plans for New River Wall Construction to be physically complete.
c. Charleroi Upper and Lower Guard Walls Contract - This contract for construction of the Upper and Lower Guard Walls.
d. Points of Delivery - The locations at the ends of the new River Wall at which the concrete produced by others and furnished by the Government is to be conveyed to the Contractor. See also Section 03 30 00.50 CONCRETE: PRODUCTION AND TRANSPORT, paragraph POINTS OF
DELIVERY.
1.3 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
PENNSYLVANIA DEPARTMENT OF TRANSPORTATION (PDT)
PDT 408 (2007) Specifications
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2008) Safety -- Safety and Health Requirements
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in
SECTION 01 30 00.10 Page 3 accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Plan of Action, Withdrawal of Equipment and Floating Plant; G, RE
The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant in accordance with paragraph "PLAN OF ACTION, WITHDRAWAL OF EQUIPMENT AND FLOATING PLANT". The plan shall be submitted for the Government's review prior to the start of work. The Contractor is advised that the plan must be submitted and accepted or no work at the site will be allowed.
Propelling Unit Agreement; G, RE
The written agreement between the Contractor and the lessor that documents the requirement for required propelling units to be on site at all times shall be provided to the Contracting Officer prior to beginning work.
Small Water Craft Operations Plan; G, RE
The Contractor shall develop and submit a plan for operation of small water craft within the "restricted area" of the Charleroi Locks and Dam project.
Proposed Methods And Locations For Attaching Equipment For Approval;
G, RE
The Contractor shall develop and submit a plan for attaching equipment to existing structures and for repairing surfaces upon removal in accordance with paragraph General Work Area Restrictions.
SD-02 Shop Drawings
Access Plan; G, RE.
Contractor's proposed plan for accessing the site and performing the work.
Maintenance and Protection of Vehicular Traffic; G, RE.
Contractor's proposed plan(s) for maintaining and protecting traffic, including any measures required by any permits, for all construction sites covered under this contract.
1.5 DRAWINGS
1.5.1 Contract Drawings
The contract drawings reflect the work to be performed under this contract. The Contractor shall check all drawings immediately upon receipt, and verify the figures, dimensions, and representation of the work. The Contractor shall compare all drawings and verify the figures before laying out the work. Dimensions marked on drawings shall, in general, be followed in preference to scale measurements. The Contractor shall promptly notify the Contracting Officer of any discrepancies, and
SECTION 01 30 00.10 Page 4 shall be responsible for an errors which might have been avoided by complying with this paragraph. Any omissions from the contract drawings and Specifications or incorrect description of details of the work which are manifestly necessary to carry out the intent of the contract drawings and Specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or incorrectly described details of work, but shall be performed as if fully and correctly set forth and described in the Contract drawings and Specifications. Unless otherwise noted, dimensions and elevations, and other features shown on contract drawings are generally based on site surveys and measurements, and As-Built drawings. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the contract drawings which are based on the reference drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government.
1.5.2 Reference Drawings
The reference drawings show existing conditions of the site, including the original lock and dam, the existing facilities and structures at the site, and features of the new lock that have already been constructed or for which construction is currently in progress, to the best knowledge of the Government. Unless otherwise noted, dimensions and elevations, and other features shown are generally based on As-Built conditions. The Government cannot guarantee the accuracy of the dimensions, elevations, and features shown on the drawings, and it shall be the responsibility of the Contractor to verify all elevations and the dimensions shown by measurements in the field, at no additional cost to the Government. The Contracting Officer shall be notified of any discrepancies prior to commencing work.
1.6 WORK UNDER OTHER CONTRACTS
Attention is directed to the fact that other Contractors may be employed by the Government at or in the vicinity of the work covered by these specifications. It is noted that the information provided is for the Contractor's information, and no attempt has been made to list all the work activities required under those contracts. In addition, the Contractor is advised that there are various contract requirements listed herein which are requirements of this contract. Unless specified otherwise, all Contractors shall have equal rights to the use of all roads and grounds so far as practicable, and the Contractor employed under this contract shall cooperate with other Contractors so that the work may be performed with maximum efficiency. Should a disagreement occur between Contractors as to the use of facilities or in other matters, the decision of the Contracting Officer shall govern. See also Section 00700 CONTRACT CLAUSES, paragraph "Other Contracts". See also paragraph "Protection of Existing Roads and Property".
1.6.1 Charleroi Contract One (River Wall Construction)
Contract One for construction of the River Wall was awarded in September 2004 and completion is anticipated in December 2010. The contract includes construction of new River Wall monoliths adjacent to the existing stub wall at the dam, site development and previous construction of a concrete batch plant and testing laboratory on the left descending bank downstream of the dam, construction of a Government field office, and development at the Government-furnished Victory Hollow Disposal Area. The contract also includes furnishing the emptying valves and bulkheads for both the River Chamber and Land Chamber filling and emptying systems.
SECTION 01 30 00.10 Page 5
1.6.2 Painting Tainter Gates and Bulkhead
A contract for painting the tainter gates and maintenance bulkhead units on Braddock and Charleroi Dams is anticipated to commence in the Summer of 2009. Actual work at Charleroi is anticipated to begin in the Summer of 2010 with completion in the Summer of 2011. This contract includes constructing containment systems around the tainter gates in the dam gate bays, sandblasting the gates, performing some repair work, and painting the gates and bulkheads. It is anticipated that this work will be performed from floating plant located upstream of the dam.
1.6.3 Electrical System Upgrade
A contract for upgrading the dam electrical system is anticipated to commence in late Summer 2009 with completion in the Summer of 2010. The work under this contract consists of updating the electrical distribution system, lighting and controls on the dam.
1.7 FEATURES OF WORK AND SEQUENCING
1.7.1 General
The Upper and Lower Guard Wall work under this contract is located upstream and downstream of the dam at Charleroi Locks and Dam along the Monongahela River approximately 41.5 miles upstream from the confluence of the Monongahela and Allegheny Rivers at Pittsburgh Pennsylvania. The locks are located in Westmoreland County, Pennsylvania, on the right descending bank of the Monongahela River, approximately 1 mile upstream from the city of Monessen, Pennsylvania, and directly across the river from the borough of Charleroi, Pennsylvania. The dam abutment, concrete laboratory, left bank Government facilities, and Government-furnished disposal area are in Washington County, Pennsylvania.
The work under this contract primarily involves the construction of the new Upper Guard Wall and new Lower Guard Wall. The Contractor will also be responsible for taking over management and disposal operations at the Victory Hollow Disposal Area on or about February 1, 2010, including disposal of material previously placed in the temporary stockpile area at the Victory Hollow Disposal Area. Victory Hollow Disposal Area is located on the left bank approximately 7 miles downstream of the project. The work reflected in the plans and specifications relies on the sequencing requirements given in the drawings and as specified below.
1.8 ACCESS AND WORK AREAS
1.8.1 General Access to Project Site
Areas permitted to be used for access to the river and for on-loading and off-loading operations shall be as shown on the drawings. Areas proposed by the Contractor for access to the river and for on-loading and off-loading operations shall be existing permitted commercial marine facilities.
1.8.2 Access Plan
The Contractor shall prepare a plan to address maintaining access to existing facilities and temporary access as required for construction of the various features of work. The plan shall and shall address all
SECTION 01 30 00.10 Page 6 requirements or conditions given in paragraphs "WORK UNDER OTHER
CONTRACTS", "ACCESS AND WORK AREAS", "CONTRACTOR'S FLOATING PLANT",
"OPERATION OF PROJECT FACILITIES", "CONDITIONS OF WORK", "POOL LEVELS", and "VELOCITIES", herein.
1.8.3 General Work Area Restrictions
As required by Section 00700 CONTRACT CLAUSES, paragraph "OPERATIONS AND STORAGE AREAS," all operations of the Contractor shall be confined to areas shown on the drawings and as authorized and approved by the Contracting Officer. The limits of the Contractor's work areas are shown on the contract drawings. In accordance with Section 00700 CONTRACT CLAUSES, paragraph "LAYOUT OF WORK", the Contractor shall maintain and preserve all existing survey control points established by the Government. Under no circumstances will the Contractor's floating plant or construction operations be permitted to interfere with the flow of commercial river traffic through the Land Chamber, the approaches to the Land Chamber or the navigation channel. No off-loading of materials or equipment will be allowed along the Land Wall or in the approaches to the Land Chamber. See also paragraph "Mooring of Floating Plant", herein. The Contractor will only be permitted to attach equipment to the Points of Delivery for Government-furnished concrete (Monoliths R-8 and R-35). Attachment to other temporary or permanent structures of Government property will not be permitted. The Contractor shall submit his proposed methods and locations for attaching equipment for approval. All items used for attaching to the existing structure shall be removed and holes shall be repaired to the satisfaction of the Contracting Officer.
1.8.3.1 Laydown and Storage Areas
a. Laydown and Storage Areas at Charleroi Locks and Dam. Laydown and storage areas will be made available to the Conctractor as shown on the drawings. The laydown and storage area at the Lower Guide Wall area downstream of the esplanade will be made available to the Contractor on or about November 1, 2009. The existing building located in this area shall be removed by the Contractor as specified in Section 31 60 00 DEMOLITION. The laydown and storage area at the Upper Guide Wall area upstream of the esplanade will be made available upon Completion of Construction of Charleroi River Wall.
b. Laydown and storage area at Victory Hollow Disposal Area. The laydown area at the Victory Hollow Disposal Area will be made available on or about February 1, 2010. There is a 50' X 50' modified barge at the dock that has been modified to accept offloading equipment. The design of this area was based on using a 125,000 pound excavator on 24' x 32' crane mats. The design will be made available upon requested.
No separate payment will be made for any revisions to the dock area, and all costs for such work shall be borne by the Contractor.
1.8.4 Utilization of Active Lock Chamber and Approaches
1.8.4.1 General
The Contractors attention is directed to the fact that Land Chamber at Charleroi Locks and Dam will not be allowed to be taken out of operation during the performance of this contract, and the Land Chamber cannot be subject to interruptions of commercial river traffic. Unless specifically authorized or directed, no interruption of commercial traffic through the Land Chamber or its approaches will be permitted.
SECTION 01 30 00.10 Page 7
1.8.4.2 Requests for Lockages Through Land Chamber
The Government recognizes that the Contractor may need to lock through the the Land Chamber, however, these lockages must be fully coordinated with the Lockmaster and kept to an absolute minimum to ensure there are no delays to commercial river traffic. All lockages shall be subject to the following:
a. The Government retains the right to determine the order and priority of lockages at the sole discretion of the Lockmaster. The Government reserves the right to supercede and delay any requested lockage for any reason (such as increased commercial river traffic, maintenance, equipment failure, emergencies etc.) at the sole discretion of the Government. The Contractor is advised that these delays will not be subject to Section 00700 CONTRACT CLAUSES, paragraph "DISPUTES", and shall not be considered as direction from the Contracting Officer. These delays will not result in any additional time extensions or payment of any delay costs, nor shall they be the basis of any claim against the Government.
b. The Contractor is not permitted to use the Land Chamber for long term staging of equipment.
c. All requests for lockages shall be coordinated with the Lockmaster in accordance with the following provisions:
1) Upon approval of an estimated date and estimated time for a proposed lockage, the Contractor shall be ready to perform the requested lockage. The Contractor is advised that the Government will not be liable in the event the Land Chamber is not available at the requested date and time, and that any resulting delay will not be subject to Section 00700 CONTRACT CLAUSES, paragraph "DISPUTES", and will not result in any additional time extensions or payment of any delay costs, nor shall they be the basis of any claim against the Government.
2) The Contractor shall configure his floating plant, work operations and all equipment to allow safe, uninterrupted lockage through the Land Chamber in such a manner that no delays to the normal lockage time period will be incurred.
3) The Contractor is advised that the request for lockage may be delayed or postponed indefinitely due to unexpected conditions such as high water, lock breakdowns, or unanticipated maintenance demands, etc.
4) Requests for lockages that do not meet these criteria will not be approved. Requests for unscheduled lockages due to anticipated flooding or other emergency will considered on a case by case basis. Lockages or other interference with river traffic due to any situation which endangers human life will be permitted as the circumstances warrant. Movement of floating plant in the approaches to the locks shall at all times be fully coordinated with the Lockmaster and Contracting Officer, but shall not delay river traffic through the active chamber.
SECTION 01 30 00.10 Page 8
1.8.4.3 Work Areas
In accordance with the paragraph "General Work Area Restrictions" herein, under no circumstances during construction will the Contractor's floating plant or construction operations be permitted to interfere with the flow of commercial river traffic through the Land Chamber, the approaches to the Land Chamber or the navigation channel.
1.8.5 Protection of Existing Roads and Property
1.8.5.1 General
The Contractor's traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic. The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for all damage to existing roads and property occasioned by any of his operations. When intending to transport any heavy loads on roadways, the Contractor shall investigate all weight limits for the roads he intends to use and shall secure any required bond(s) from the respective owner(s).
For the Contractor's information, the access bridge on the right bank has a 40-ton weight limit, and any specially permitted loads shall be approved by the Contracting Officer prior to such loads crossing the access bridge.
The Contractor shall document the existing condition of the roadways that he will be using, with the owners thereof. In the past, video recordings of the original roadway conditions have provided satisfactory documentation. Prior to beginning any construction, the Contractor shall videotape on VHS format all existing structures including, but not limited to, local roads, public and private property, and any other areas as directed by the Contracting Officer. The owners of such roadways and other property should be present at the time of the documentation. An unedited copy of all video recordings shall be given to the owners and the Contracting officer with 5 days after documented. All damage to transportation facilities, public or private property, or utilities caused by the Contractor's operations shall be repaired to the satisfaction of the owner and the Contracting Officer at no additional cost to the Government.
Any damage to the roadways, caused by the Contractor's operations, shall be repaired in kind by the Contractor and at his own expense. Roads shall be kept clear of all debris generated by the Contractor's operations. Roads shall be cleaned of any spillage. Upon completion of all work requiring use of the local roads, the roadways shall be restored to their preconstruction condition by cleaning and or reconstruction of damaged drainage facilities, base courses, and pavements as necessary. Repairs shall be made in the same manner as the original construction. No separate payment will be made for maintaining and restoring the condition of the roads, and all costs in connection therewith shall be considered as incidental to performance of the work.
1.8.5.2 Hauling Permits
The Contractor shall be responsible for acquiring all necessary oversized hauling permits and general hauling permits for any equipment or debris transported via roadways, as required. No heavy hauling on public roads will be permitted until all permits and bonds have been obtained as required. All costs associated with securing these permits shall be borne by the Contractor.
SECTION 01 30 00.10 Page 9
1.8.6 Utilities
The Contractor shall be responsible for coordination of all existing utilities with the work and for providing utilities for construction purposes. Utilities shall be coordinated in accordance with Section
01 51 13 UTILITY COORDINATION.
1.8.7 Offloading Facilities at Left Bank Batch Plant
The bulkhead facility at the Left Bank Batch Plant may be used for delivery of materials, however, no laydown or staging areas will be made available at the batch plant area. The bulkhead structure is not designed for mooring of vessels. Use of this area for deliveries shall be coordinated with the Contracting Officer.
1.9 EXISTING SURVEY CONTROLS
The locations of Corps of Engineer survey controls are shown on the drawings. Survey and alignment control requirements are specified in Section 01 32 23 SURVEY AND ALIGNMENT CONTROL.
1.9.1 Project Alignment
All new work to be constructed under this contract shall be constructed level, plumb, and accurately from measurements made from the survey controls indicated. Additional survey control points shall be established by the Contractor as necessary to construct all work within the proper alignment. The Contractor shall verify the elevations and positions of the Corps of Engineers survey controls before using them to layout the work under this contract, and shall notify the Contracting Officer of any discrepancies prior to commencing work.
1.10 MAINTENANCE AND PROTECTION OF VEHICULAR TRAFFIC
During construction the Contractor shall maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, shall be as required by any permits or whenever the Contractor's operations interfere with the movement or safety of traffic along the public roads. Such measures shall be in accordance with the applicable provisions of PDT 408, Section 900, and local authorities having jurisdiction. The traveling public shall be protected from damage to person and property. The Contractor shall submit his proposed traffic control plan for approval and shall include documentation that his proposed plan has been coordinated and approved by the local authority having jurisdiction. Where such measures are on Government property, the Contractor shall coordinate such measures with the Contracting Officer and the Lockmaster.
1.10.1 Barricades
The Contractor shall erect and maintain temporary barricades to limit public access to hazardous areas. Such barricades shall be required whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. Barricades
SECTION 01 30 00.10 Page 10 shall be securely placed, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.
1.11 PROJECT SITE CONDITIONS
1.11.1 Inspection of Geologic Samples
Samples taken during geologic investigations by the Government are available to Contractor's and bidders for examination. Contractors and bidders may inspect these cores and samples as follows:
Pittsburgh Engineering Warehouse and Repair Shops 3510 Grand Avenue Pittsburgh, Pa 15225
Point of Contact: Mr. Stephen Stoltz, CELRP-TS-DS Tele. (412) 395-7297
A minimum of 14 calendar days notice is required. Bidders must indicate the cores which they would like to inspect.
1.11.2 Interpretation of Geologic Information, Data and Samples
Subsurface records are included with the contract drawings. Logs of borings and test data are made available for the Contractor's information and for his interpretation. Logs and test data are not represented as a complete description of the site soil, rock, and water information, but only display what was found in borings at the indicated locations on the date holes were drilled. The soil and groundwater conditions may be different from those interpreted by the subsurface investigation. It is the Contractor's responsibility to obtain additional information, if necessary in his judgment. See also Section 00100 INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS, paragraph "SITE INVESTIGATION BY THE CONTRACTOR".
1.12 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work shall be as set forth in Section 00700 CONTRACT CLAUSES, paragraph "PERMITS AND RESPONSIBILITIES". However, if the construction of Government designed cofferdams has been done in accordance with plans and progress schedules approved by the Contracting Officer, but overtopped by flood and such flood causes damage to the Government designed cofferdam or if any part of the permanent work is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precaution or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such damaged work, an equitable adjustment pursuant to Section 00700 CONTRACT CLAUSES, paragraph "CHANGES", will be made as full compensation therefore. The Contractor may, subject to approval of the Contracting Officer, flood or breach the Government designed cofferdam during a rise prior to, and in anticipation of natural flooding due to overtopping. The Contracting Officer may order the Contractor to flood or breach the cofferdam during such an anticipated rise. Such flooding or breach will be considered the same as though the cofferdam, if constructed in accordance with plans and progress schedules approved by the Contracting Officer, had been
SECTION 01 30 00.10 Page 11 overtopped, in which event an equitable adjustment will be made for damages to the cofferdam and/or any part of the permanent work, as provided for above.
1.13 PROTECTION OF UTILITIES
Utilities shall be protected as specified in Section 01 50 00.10 UTILITY COORDINATION, paragraph "Protection of Utilities".
1.14 CONTRACTOR'S FLOATING PLANT
1.14.1 General
Floating plant, and the operation of such plant, shall comply with the requirements of EM 385-1-1, Section 19. Floating plant which is not being used in the performance of the work shall be secured in a manner that does not interfere with navigation on the river. Emergency plans for removing or securing floating plant and evacuating personnel in the event of severe weather shall be prepared in accordance with EM 385-1-1, Section 19.A.03.
The Contractor shall provide personnel as necessary to adjust moorings to provide for fluctuations of pool level. Propelling units capable of moving the floating plant must be on site at all times. The written Propelling Unit Agreement between the Contractor and the lessor that documents this requirement shall be provided to the Contracting Officer prior to beginning work. The agreement shall also include documentation that the propelling unit operator currently possesses a U.S. Coast Guard First Class Pilot's license. The Contractor shall be fully responsible for selection of floating plant which is suitable for the performance of the work under this contract. Contractor's floating plant shall operate only within the areas of work shown on the drawings, unless such areas are modified with the approval of the Contracting Officer and Lockmaster. The Contractor will only be allowed to lock through the open Land Chamber with the approval of the Contracting Officer. Except as otherwise indicated, Contractor shall utilize existing permitted commercial marine facilities for access to the river and for on-loading and off-loading operations. The loading area at the left bank batch plant will not be available under this contract. The off-loading site at the Government furnished disposal site shall be used for the off-loading of excavated river sediments, and concrete debris. The off-loading site at the Government furnished disposal site may also be used for the temporary storage of non-erodable materials, e.g. pipe, steel, etc. See also paragraph "OPERATION OF GOVERNMENT-FURNISHED DISPOSAL AREA.
1.14.2 Floating Plant
The Contractor shall select floating plant and towboats of a size and capacity suitable for performance of the work under this contract.
Towboats shall have sufficient horsepower capacity to control the floating plant used, considering the size and draft of the plant, for the expected river velocities and wind conditions. The minimum size of towboats shall be 1,200 horsepower. The Contractor shall refer to Tables A and C at the end of this section for various significant river stage-discharge relationships and Tables B, D and E for various velocity excedence durations for various conditions and the applicable sections of these Specifications, as well as the charts of "Velocities and Current Directions" when planning the size and capacity of the floating plant and towboats. The Contractor shall submit a plan of all floating plant, floating plant based equipment (i.e. cranes, derricks), temporary operating systems (i.e. generators, compressors, welding machines, etc.), and other appurtenant features which he will have present during the contract period
SECTION 01 30 00.10 Page 12 for any fleet. The Contractor shall use sketches, diagrams, and narratives to indicate location of all floating plant-equipment. The Contractor shall use manufacturer's catalog information or other suitable data to describe the specific equipment to be used. The Contractor shall also indicate the methods and procedures that will be used to deliver materials, supplies and equipment via floating plant. Floating plant shall be suitably sized and arranged so that it may be efficiently withdrawn under the conditions described in paragraph "Suspension of Construction."
1.14.3 Signal Lights
The Contractor shall display signal lights and conduct his operations in accordance with the General Regulations of the Coast Guard, as set forth in Commandant, U.S. Coast Guard Instruction M16672.2 or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 809 (inland) as applicable.
1.14.4 Maintenance of Floating Plant
The Contractor shall maintain all floating plant equipment in good working condition throughout the contract period.
1.14.5 Mooring of Floating Plant
The Contractor shall be responsible for all mooring of floating plant.
When not in use, the Contractor's floating plant shall be securely moored.
The Contractor shall also be solely responsible for providing personnel in order to adjust mooring lines as required by the prevailing river conditions. Under no circumstances will the Contractor's floating plant be permitted to interfere with the flow of commercial river traffic through through the Land Chamber, approaches to the Land Chamber or the navigation channel or performance of work by the existing River Wall contractor.
Floating plant and barges will not be allowed to nose-into the bank or tie-off to trees on the shoreline.
1.14.6 Withdrawal of Equipment and Floating Plant
Charleroi Locks and Dam begins high-flow operations when the downstream river level (Pool 3) reaches El. 735.4. (Project Lower Gage = 17.5 feet).
All marine work at the project site shall cease when the river level is at this stage, but work from areas not affected by this river stage may continue. The Contractor's floating plant shall be moored by the time the river level reaches El. 735.4. It shall also be the Contractor's responsibility to withdraw any land-based equipment that would be subject to damage by river stages at this level from such affected areas, before they are subject to damage. The Contractor shall monitor the prevailing river conditions at the project site, referring to the upstream project river gage, river forecasts issued by the National Weather Services, and the Corps of Engineers River Forecast System, and shall determine when to withdraw equipment and floating plant. The withdrawal of equipment and floating plant shall ultimately be the Contractor's decision and will not be directed by the Government. It shall be the Contractor's responsibility to determine the time necessary to make a complete and safe withdrawal of equipment and floating plant with due consideration given to the location of mooring areas; amount of equipment; size of the floating plant, and capacity of towboats to operated safely and efficiently at the expected river velocities (See Tables A through E at the end of this Section). All floating plant and equipment shall remain securely moored during the period when river levels are at or above El. 735.4. The Contractor shall also be responsible for providing personnel to adjust mooring lines as required by
SECTION 01 30 00.10 Page 13 the prevailing river conditions. The Contractor shall resume all work, and remobilize equipment and floating plant from its moored location when the river level reaches El. 737 with a falling condition forecasted. The Contractor shall submit a Plan of Action for withdrawal of equipment and floating plant. The plan shall be submitted for the Government's review prior to the start of work. The Contractor is advised that the plan must be submitted and accepted or no work at the site will be allowed.
1.14.6.1 Plan of Action, Withdrawal of Equipment and Floating Plant
The Contractor shall prepare and submit a Plan of Action for withdrawal of equipment and floating plant. The plan shall detail the procedures for withdrawal of equipment and floating plant in the event that the river level reaches EL. 735.4. The Plan of Action shall include but is not limited to the following information:
Withdrawal procedures for fleet, both upstream and downstream of the dam Procedure(s) For Monitoring River Conditions Including River Levels, discharges, And Velocities Mooring Location(s) Monument River Condition Which Affect Notification Actions Monument River Conditions Which Affect Withdraw Sequence and Duration of Withdraw Procedures for Care of Moored Floating Plant and Equipment Monument River Conditions Affecting Remobilization Sequence and Duration of Remobilization
The Plan of Action shall include a listing of key Contractor's Points of Contact and telephone numbers. The Plan of Action shall include the withdrawal of any subcontractor's equipment and floating plant. The Contractor's Plan of Action shall be consistent with the applicable requirements for Emergency Planning as described in EM 385-1-1. All key Contractor personnel including superintendents, foremen, safety officers, and QC personnel shall be given a copy of the Plan of Action and shall be thoroughly familiar with their duties under this plan. Subcontractors shall also be thoroughly familiar with their responsibilities and duties under the plan.
1.14.6.2 Compensation and Extension of Contract Period, Withdrawal of Equipment and Floating Plant
The withdrawal of floating plant and equipment is considered an incidental condition of work dictated by the nature of the work site. The Contractor's withdrawal of equipment and floating plant shall not be construed as a direction on the part of the Government or Contracting Officer, under the provisions of Section 00700 CONTRACT CLAUSES, paragraph "SUSPENSION OF WORK," which shall not apply to this work condition. No compensation will be made to the Contractor for withdrawal of this equipment nor will any delay costs be made for the period during which the equipment or floating plant are withdrawn. In accordance with Section 00700 CONTRACT CLAUSES, paragraph "DEFAULT (FIXED PRICE CONSTRUCTION)," the contract period will be extended equitably for the withdrawal of floating plant and equipment.
1.14.7 Operation of Small Water Craft
The Contractor shall develop, prepare and submit a Small Water Craft Operations Plan addressing the operation of small water craft within the "restricted area" of Charleroi Locks and Dam. The "restricted area"
SECTION 01 30 00.10 Page 14 includes all areas riverward of the river wall and extends from the upstream end of the Upper Guard Wall to the downstream end of the Lower Guard Wall. The plan shall address safe operations of small water craft and shall include; maximum river stages, maximum river flows, horsepower requirements, training, and any other items necessary to address all the hazards associated with navigating in the "restricted area" of the dam.
1.15 OPERATION OF PROJECT FACILITIES
The locks and dam shall remain in operation at all times during the contract. The Contractor shall perform his work in a manner which will not interfere with the operation of the project facilities and the duties of Government personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall take all necessary precautions to ensure the safety of the workers in accordance with the applicable provisions of EM 385-1-1. Contractor operations shall be performed in such a manner to ensure that project personnel, navigation industry personnel and the public are protected at all times.
1.16 CONDITIONS OF WORK
1.16.1 Charleroi Locks and Dam, Hours of Operation
Charleroi Locks and Dam operates 24 hours per day, seven days per week.
Lockage data is provided below:
LOCKAGE DATA, CHARLEROI LOCKS AND DAM
LOCKAGES AVERAGE TOTAL
YEAR SINGLES DOUBLES TRIPLES QUADS
FIVE
CUT
SIX
CUT
(TOTAL
LOCKAGES)
EQUIVALENT
SINGLE
LOCKAGE
April
TO
SEPT
REMAINDER
OF YEAR
2001 5,593 470 49 0 0 0 6,680 3,256 3,424
2000 5,900 414 0 0 0 0 6,728 3,163 3,565
1999 6,069 526 17 0 0 0 7,172 3,562 3,610
1998 6,753 398 40 0 0 0 7,669 4,602 3,067
1997 7,049 672 0 0 0 0 8,393 5,136 3,257
1996 5,995 569 136 0 0 0 7,541 4,318 3,223
1995 7,732 813 0 0 0 0 9,358 6,093 3,265
1994 8,696 843 0 0 0 0 10,382 6,421 3,961
SECTION 01 30 00.10 Page 15
LOCKAGE DATA, CHARLEROI LOCKS AND DAM
LOCKAGES AVERAGE TOTAL
YEAR SINGLES DOUBLES TRIPLES QUADS
FIVE
CUT
SIX
CUT
(TOTAL
LOCKAGES)
EQUIVALENT
SINGLE
LOCKAGE
April
TO
SEPT
REMAINDER
OF YEAR
1993 8,009 840 0 0 0 0 9,689 6,348 3,341
1992 8,224 1,076 0 0 0 0 10,376 6,286 4,090
1991 8,166 843 0 0 0 0 9,852 6,182 3,670
1990 7,457 873 4 0 0 0 9,219 5,351 3,868
1989 7,361 840 10 0 0 0 9,071 5,268 3,803
1.16.2 Contractor's Work Hours
There will be no restrictions imposed on Contractor's work hours for this project.
1.16.3 Coordination with Lock and Dam Operations
The Contractor shall perform all work in a manner that will not interfere with the duties of the project personnel. Particular care shall be taken during all operations under this contract to prevent damage to any operating equipment or facilities at the project. The Contractor shall continuously maintain safe access to all areas of the lock and dam project for project operating personnel, during every phase of the work, unless otherwise directed by the Contracting Officer.
1.16.4 Government Access to the Site
Government access to the site shall be maintained at all times.
1.16.5 Contractor Coordination and Scheduling
In accordance with Section 01 32 01.00 10 PROJECT SCHEDULE, the Contractor shall submit a detailed project schedule for his work to the Contracting Officer. All necessary adjustments in the Contractor's work schedule shall be coordinated and approved by the Contracting Officer.
1.16.6 Coordination with Dam Gate Operations
1.16.6.1 Control of Flow Over Fixed Crest Weir
It is noted that the Government has installed flash boards on top of the fixed crest weir to minimize flow over the fixed crest weir. The Government will be responsible for maintaining the flash boards, and the
SECTION 01 30 00.10 Page 16 removal of accumulated debris.
1.16.6.2 Operation of Dam Gates During Contract Work
At the end of this Section of the Specifications is a table showing schedule of existing gate operations, and a table showing schedule of gate operations during various phases of construction. The Contractor is alerted that gate operations may vary from the schedules shown as a result of the proposed painting work which will require that individual gates will be out of operation during cleaning and painting.
1.16.6.3 Unanticipated (Emergency) Operations
The Government may open restricted (closed) gates upon short notice to the contractor in order to prevent upstream flooding. Once the unrestricted (opened) gates have been open full, the lockmaster will begin opening the restricted (closed) gates if required to maintain the upper pool at or near the normal level. If any work in progress is damaged as a result of these operations, the contractor will be fairly compensated in accordance with Section 00700 CONTRACT CLAUSES, paragraph "CHANGES".
1.17 POOL LEVELS
The Government will not attempt to vary the pool levels for the convenience of the Contractor during the progress of the work. The minimum upper pool level, termed "normal pool", is El. 743.5 (Project Lower Gage = 17.5 feet) as shown on the drawings. The actual upper pool elevation will usually be within one foot above this level, except during high flow. The minimum lower (normal) pool level is elevation 726.9, and the pool will usually be within a few feet of this level, except during high flow. It is noted that Charleroi Locks and Dam is closed to traffic at an upper gage reading of
13.0 feet and/or a lower gage reading of 29.0 feet. The Contractor should refer to the hydrographs, Stage-Discharge relationships, and the Stage-Duration curves when planning the various work activities for this project. This information is shown on the drawings and Tables A through E at the end of this Section.
1.17.1 Hydrographs
The stage hydrographs represent water surface elevations, and should be used by the Contractor to have knowledge of historical trends. For Charleroi L/D, the hydrographs were developed from actual Lockmaster stage records.
1.17.2 Stage-Discharge
The Contractor shall refer to the stage-discharge curves on the drawings to determine river discharge (cubic feet per second) for various river stages. Tables A and C at the end of this section also tabulate discharges corresponding to key river stages at Charleroi L/D that are significant in relationship to this project. Table A applies to the upper pool and Table C to the lower pool.
1.17.3 Stage-Duration
The Contractor shall refer to the Stage-Duration curves on the drawings to determine the percentage of time for which various water surface elevations were equaled or exceeded during the hydrograph's period of record. Tables A and C at end of this section also tabulate monthly stage-duration
SECTION 01 30 00.10 Page 17 relationships at Charleroi L/D upper and lower pool, respectively. To assist in determining discharge-duration relationships, obtain the relevant stage for a particular discharge from the appropriate stage-discharge relationship, and relate it to the stage-duration curve.
1.17.4 Velocities
Tables B (upper pool), D (lower pool) and E (lower pool, after pool changed) at the end of this section provide river velocities corresponding to various discharges and the percentage of time each month that these velocities are equaled or exceeded. Tables B, D and E should be referred to when planning the various work activities for this project. Table E shows excedence durations after the level of Pool 3 is changed. This condition may occur, at the Government's discretion, sometime during this contract.
1.18 SAFETY AND HEALTH REQUIREMENTS
Safety and Health Requirements shall conform to Section 01 35 26 GOVERNMENT SAFETY, EM 385-1-1, and the requirements of the Occupational Safety and Health Administration. Where provisions of EM 385-1-1 vary with OSHA requirements, the more stringent requirements shall be applied.
1.19 INSPECTIONS AND ACCEPTANCE OF WORK
1.19.1 General
Not withstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer or his authorized representative(s). Inspections and acceptance will be performed on phases of the work, before the next definable sequential phase of work commences, OR may be performed at the completion of all of the work, as determined appropriate by the Contracting Officer. The Contracting Officer or representatives of the Contracting Officer so authorized shall be the individual(s) solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.
1.19.2 Access to Work
The Contractor shall provide safe access to all areas of work for inspection by the Government and shall provide boats for transporting Government inspectors to the various areas of work.
1.20 CONVEYOR OPTION
During performance of this contract the Government may require the services of the contractor to install, operate, and maintain a Government-Furnished concrete conveyor system. Specific details regarding this requirement will be furnished at a later date. If and when required, the Government will issue a formal Request for Proposal and a price will be mutually agreed upon by the parties before the work is performed.
PART 2 PRODUCTS
2.1 PRODUCTS AND PARTS OF STANDARD MANUFACTURE
All materials, supplies and articles furnished so as to be incorporated
SECTION 01 30 00.10 Page 18 into the work under this contract shall, whenever so specified and otherwise practicable, be standard products of recognized reputable manufacturers. Standard products of manufacturers other than those specified will be accepted when it is proven to the satisfaction of the Contracting Officer, in accordance with the Section 00700 CONTRACT CLAUSES, paragraph "MATERIAL AND WORKMANSHIP," that they are equal in performance, strength, durability, usefulness and convenience for the purpose intended.
Any changes required in the details and dimensions shown on the drawings as a result of the substitution of standard products, other than those provided for, shall be properly made as approved by the Contracting Officer, and at the expense of the Contractor. All products specified by "similar or equal to" a particular brand name are for descriptive purposes only and are not to imply that the product is available from only that source. Each major piece of equipment furnished under the contract shall be provided with a substantial nameplate securely fastened or cast in place and clearly inscribed with the manufacturer's name, year of manufacture, principal rating data and other pertinent data.
2.2 GOVERNMENT-FURNISHED PROPERTY
The Government has awarded advance supply contracts under way for…