32_12_21-BITUMINOUS_ROAD-MIX_SURFACE_COURSE.pdf

PDF 67 KB Posted

Attached to
Joint Base Lewis-McChord PAVEMENT IDIQ
Solicitation number
W911S8-17-R-0001
Issued by

About this file

32 12 21-BITUMINOUS ROAD-MIX SURFACE COURSE

View the file

Other files

File Type Posted
SF1442_W911S8-17-R-0001_0002.pdf PDF
4. Technical Exbhibit C Statement of Work 19 Dec 2016.pdf PDF
JBLM Paving W911S8-17-R-0001 Contractor QUESTIONS 22 Dec16.pdf PDF
Pre-Proposal Conference Contractor Attendees.pdf PDF
33 71 02UNDERGROUND ELECTRICAL DISTRIBUTION.pdf PDF
SF30 W911S8-17-R-0001 0002.pdf PDF
Attachment 1- Sample Project 19 December 2016.pdf PDF
32 12 21-BITUMINOUS ROAD-MIX SURFACE COURSE.pdf PDF
01_45_00_10_Quality_Control_19_Dec.pdf PDF
33 71 02 JBLM DESIGN STANDARDS-UNDERGROUND ELECTRICAL DISTRIBUTION.pdf PDF
Site Visit Briefing W911S8-17-R-0001 JBLM Paving -29 Nov 2016.pdf PDF
SF30 W911S8-17-R-0001 0001.pdf PDF
W911S8-17-R-0001_Amendment_0001.pdf PDF
01 57 19-TEMPORARY ENVIRONMENTAL CONTROLS.pdf PDF
01 42 00-SOURCES FOR REFERENCE PUBLICATIONS.pdf PDF
13. Attachment 5 - Past Performance Questionaire.docx DOCX document
32_84_24_(Irrigation_Sprinkles).pdf PDF
26_56_13.00_40_Lighting_Poles_and_Standards.pdf PDF
14. Attachment 6 Insurance Certificate of Compliance.docx DOCX document
01 78 23-OPERATION AND MAINTENANCE DATA.pdf PDF
32_17_24.00_10_(Pavement_Markings).pdf PDF
1. RFP W911S8-17-R-0001 Paving IDC.pdf PDF
01 50 00-TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
01 32 01 00 10 Project Schedule.pdf PDF
7. TE F General Decision Number WA160001 Dtd 19 Aug 16.pdf PDF
31_11_00_Clearing_ _Grubbing.pdf PDF
5. TE D-Table of Contents.pdf PDF
3. TE B Proposal Item Descriptions(09-27-16).pdf PDF
10. Attachment 2-Experience Document.docx DOCX document
6. TE E Standards Plans Drawings 25Aug16.pdf PDF
31_23_00.00_20_Excavation_ _Fill.pdf PDF
01 35 29.13 Contaminated Site.pdf PDF
32_11_24_CSBC_for_Flexible_Pavement.pdf PDF
32_31_26_(Wire_Fence_ _Gate).pdf PDF
32_31_13.53_(High_Security_Fence).pdf PDF
26_56_19.00_40_Roadway_Lighting.pdf PDF
32_93_00_(Exterior_Plants).pdf PDF
31_00_00_Earthwork.pdf PDF
2. TE A ELIN Proposal Schedule 11 Oct 16.xlsx XLSX spreadsheet
33_11_00-WATER_DISTRIBUTION.pdf PDF
01 45 00 10 Quality Control.pdf PDF
01 30 00 Administrative Requirements.pdf PDF
33_30_00-SANITARY_SEWERS.pdf PDF
01 78 00- CLOSEOUT SUBMITTALS.pdf PDF
32_01_13_BITUMINOUS_SEAL_AND_FOG_COATS.pdf PDF
16. Attachment 8-JBLM Installation Access Information.docx DOCX document
32_92_19_(Seeding).pdf PDF
32_12_10_(Tack_Coat).pdf PDF
12. Attachment 4 - Relevant Contract Reference Sheet.docx DOCX document
00 10 01 - Supplementary Requirements.pdf PDF
Show 40 more

Latest 50 of 75 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 32 12 21 Page 1

SECTION 32 12 21

BITUMINOUS ROAD-MIX SURFACE COURSE

08/08

PART 1 GENERAL

1.1 UNIT PRICES

1.2 REFERENCES

1.3 SUBMITTALS

1.4 ENVIRONMENTAL REQUIREMENTS

PART 2 PRODUCTS

2.1 AGGREGATES

2.2 BITUMINOUS MATERIALS

2.3 COMPOSITION OF MIXTURE

PART 3 EXECUTION

3.1 SYSTEM EQUIPMENT

3.2 PLACING AND WINDROWING AGGREGATE

3.3 RECONDITIONING OF BASE COURSE

3.4 PREPARATION OF BASE COURSE AND AGGREGATE

3.5 MIXING WINDROWED AGGREGATE AND BITUMINOUS MATERIAL

3.6 PROCEDURE WITH THICKENED EDGE

3.7 SPREADING AND SHAPING

3.8 ROLLING FINISHED SURFACE

3.9 SHAPING OF EDGES

3.10 GRADE CONTROL

3.11 SURFACE SMOOTHNESS AND THICKNESS TESTING

3.12 SAMPLING AND TESTING

PART 1 GENERAL

1.1 UNIT PRICES

1.1.1 Measurement

1.1.1.1 Surface Course

The square yards of surface course shall be the number of square yards of completed and accepted surface course.

1.1.1.2 Bituminous Material

Bituminous material to be paid for shall be the number of 2000 pound tons.

1.1.2 Payment

SECTION 32 12 21 Page 2

The amount of pavements and quantities of bituminous material, determined as specified in paragraph Measurement, will be paid for at the respective contract unit prices in the bid schedule on which the contract is based, which payment will constitute full compensation for preparing or reconditioning subgrade or base course; furnishing all plant, materials, equipment, and tools; correcting unsatisfactory areas; and the labor and incidentals necessary to complete the work required by this section of the specifications.

1.1.3 Waybills and Delivery Tickets

Before the final statement is allowed, file with the Contracting Officer certified waybills and delivery tickets for all the bituminous and paving materials used in the construction covered by this section of specifications.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C131/C131M (2014) Standard Test Method for Resistance to Degradation of Small-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine

ASTM C183/C183M (2015) Standard Practice for Sampling and the Amount of

Testing of Hydraulic Cement

ASTM C 29/C 29M (2009) Standard Test Method for Bulk Density ("Unit Weight") and Voids in Aggregate

ASTM D 1073 (2011) Fine Aggregate for Bituminous Paving Mixtures

ASTM D140/D140M (2015) Sampling Bituminous Materials

ASTM D2026/D2026M (2015) Cutback Asphalt (Slow-Curing Type)

ASTM D2027/D2027M (2013) Cutback Asphalt (Medium-Curing Type)

ASTM D2028/D2028M (2015) Cutback Asphalt (Rapid-Curing Type)

ASTM D2397/D2397M (2013) Standard Specification for Cationic Emulsified

Asphalt

ASTM D242/D242M (2009; R 2014) Mineral Filler for Bituminous Paving Mixtures

ASTM D 4318 (2010; E 2014) Liquid Limit, Plastic Limit, and Plasticity

Index of Soils

ASTM D 490 (1992; R 2011) Road Tar

SECTION 32 12 21 Page 3

ASTM D75/D75M (2014) Standard Practice for Sampling Aggregates

ASTM D 977 (2013; E 2014) Emulsified Asphalt

1.3 SYSTEM DESCRIPTION

Maintain equipment, plant, and tools used in the performance of the work in a satisfactory working condition at all times. Provide access to the Contracting Officer, at all times, to the equipment and plant to insure proper operation and compliance with specifications.

1.3.1 Traveling-Plant Mixer

Provide a self-propelled or tractor-drawn traveling-plant mixer capable of maintaining a uniform rate of travel. The plant shall be mounted on wheels or tread equipment of such type as will not overload or damage the subgrade or base course when the mixer is loaded to capacity. The device for picking up aggregates from windrows shall be such as to pick up only the windrowed aggregate, leaving the base clean. The pick-up and elevator shall be entirely enclosed to prevent the wind from removing the fine and filler aggregate. The equipment for proportioning the aggregate and bituminous material shall accurately measure the specified amounts of material for the mix while the machine is in operation, and shall be equipped with devices for accurately proportioning the filler added to the mixture. The plant shall be capable of thoroughly combining the aggregates and bituminous material into a uniform mixture, completely coating all particles of aggregate, and shall be capable of depositing the processed mixture on the base course.

1.3.2 Bituminous Distributor

Provide a bituminous distributor with pneumatic tires of such width and number that the load produced on the base course will not exceed 650 pounds per inch of tire width. The distributor shall be so designed and equipped as to distribute the bituminous material uniformly at even heat on variable widths of surface at readily determined and controlled rates from 0.05 to 2.0 gallons/square yard, with a specified rate not exceeding 5 percent. Include with the distributor equipment a separate power unit for the bitumen pump, fully circulating spray bars, a tachometer, pressure gauges, volume-measuring devices, a thermometer for reading the temperature of the tank contents, and a hose attachment suitable for applying bituminous material to spots missed by the distributor. The distributor shall be equipped for circulation and agitation of the bituminous material during the heating process. Provide heating equipment capable of maintaining the bituminous material at the specified temperature.

1.3.3 Heating Equipment for Storage Tanks

Maintain specified temperature with heating equipment for storage tanks, but direct flame shall not be applied to walls of storage tank or transfer lines. Fix an armored thermometer with a range from 150 to 400 degrees F to the tank so that the temperature of the bituminous material can be determined at all times.

1.3.4 Blade Graders

Provide self-powered blade graders for windrowing aggregate, for mixing, and for spreading processed material. Each grader shall have a wheelbase not less than 17 feet, a blade not less than 12 feet long, and be equipped with pneumatic tires. Blade graders, weighing at least 8 tons, shall be adequately powered in order to perform the work properly.

SECTION 32 12 21 Page 4

1.3.5 Power Rollers

Provide power rollers which are steel-wheel or pneumatic-tired types conforming to the following requirements:

1.3.5.1 Steel-Wheel

Steel-wheel rollers shall be either tandem or three-wheel type weighing not less than 5 tons, and equipped with adjustable scrapers. The rollers, which may be static or vibratory, shall be equipped with watertanks and sprinkling apparatus, to be used when necessary, to keep the wheels wet preventing adherence of the bituminous material to the wheels.

1.3.5.2 Pneumatic-Tired

Provide self-propelled pneumatic-tired rollers equipped with not less than 9 wheels mounted on 2 axles in such manner that the rear tires will not follow in the tracks of the forward group. The pneumatic-tired rollers shall also be equipped with suitable beams or platforms for ballast loading and loaded to provide required compaction. Inflate the tires uniformly to not less than 45 psi.

1.3.6 Mechanical Spreaders

Provide equipment for spreading, shaping, and finishing consisting of approved, self-contained, power machines capable of taking the bituminous mixture directly from the discharge end of traveling plant and spreading the mixture at the required application rate.

1.3.7 Tractors

Tractors shall be of the crawler type equipped with street plates or flat treads.

1.3.8 Miscellaneous Equipment

Disk, spike-tooth, or spring-tooth harrows, multiple-blade or retread mixers, small tools, and other equipment shall be the required types.

1.3.9 Safety Precautions

Do not permit smoking, or open flames within 25 feet of heating, distributing, or transferring operations of cutback bituminous materials. When tar is used, a full-face, organic, vapor-type respirator and protective creams shall be used by personnel exposed to fumes.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Waybills and Delivery Tickets

SECTION 32 12 21 Page 5

Copies of waybills or delivery tickets, during the progress of the work.

SD-06 Test Reports

Tests

Copies of test results, within 24 hours after completion of tests.

1.5 ENVIRONMENTAL REQUIREMENTS

Construct bituminous courses only when the surface is dry. Do not construct the bituminous course when the atmospheric or aggregate temperature is below 40 degrees F.

PART 2 PRODUCTS

2.1 AGGREGATES

Provide aggregates consisting of a mixture of coarse aggregate, fine aggregate, and mineral filler complying with the requirements specified hereinafter.

2.1.1 Coarse Aggregate

Coarse aggregate shall consist of the following:

2.1.1.1 Crushed Stone

Crushed stone consisting of hard durable fragments which are free from soft or disintegrated pieces, vegetable matter, lumps or balls of clay, adherent coatings of clay, and other objectionable matter, and having a percentage of wear not exceeding 50 after 500 revolutions, as determined by ASTM C 131.

2.1.1.2 Crushed Gravel

Crushed gravel consisting of clean, tough, durable fragments, free from an excess of flat, elongated, soft, or disintegrated pieces, and free from fragments coated with dirt or other objectionable matter. At least 50 percent by weight of the particles retained on No. 4 sieve shall have two or more fractured faces. The crushed gravel shall have a percentage of wear not exceeding 50 after 500 revolutions, as determined by ASTM C 131.

2.1.1.3 Crushed Slag

Crushed slag shall be an air-cooled, blast furnace product having a dry weight of not less than 70 pcf consisting of angular fragments which are reasonably uniform in density, free from dust, and without an excess of thin, elongated pieces, and other objectionable matter. The weight per cubic foot of slag aggregate shall be determined by ASTM C 29/C 29M. The slag aggregate shall have a percentage of wear not exceeding 50 after 500 revolutions, as determined by ASTM C 131.

2.1.2 Fine Aggregate

Provide fine aggregate conforming to ASTM D 1073. Quantity of natural sand shall not exceed 25 percent of the total aggregate. The gradations specified in ASTM D 1073 may be adjusted to meet local materials as directed. That portion of the fine aggregate, including any blended filler, passing a

SECTION 32 12 21 Page 6

No. 40 sieve shall have a plasticity index not exceeding 6 as determined by ASTM D 4318, a liquid limit not exceeding 25 as determined by ASTM D 4318, and a clay content not to exceed 5 percent after washing and straining.

2.1.3 Mineral Filler

Provide mineral filler conforming to ASTM D 242.

2.2 BITUMINOUS MATERIALS

Bituminous materials shall conform to ASTM D 490, ASTM D 977, ASTM D 2026, ASTM D 2027, ASTM D 2028, and ASTM D 2397.

2.3 COMPOSITION OF MIXTURE

Provide aggregate for the surface course so graded that the percentage composition by weight, as determined by laboratory tests, will conform to the grading shown in TABLE I. The percentage of bituminous material by weight of the total mixture to be used for preparing the bituminous mixtures shall be as determined by the Contractor and approved by the Contracting Officer.

2.3.1 Job-Mix Formula

Do not produce any bituminous mixture until a job-mix formula has been prepared and approved by the Contracting Officer. The formula shall indicate the percentage of each sieve-fraction of aggregate and the percentage of bitumen. For the job-mix formula allow tolerances given in TABLE II. No deviation from the approved job-mix formula will be permitted without prior approval.

2.3.2 Gradation Limits for Aggregates

Gradation limits for aggregates in TABLE I are master ranges to govern mixes and represent the maximum and minimum for all cases. The approved formula will provide for a gradation of job aggregates within these master ranges. Deviation from the gradation of the approved formula will be allowed, provided that variations from the formula in any one run do not exceed the tolerances as given in TABLE II.

TABLE I. GRADATION (PERCENT BY WEIGHT PASSING)

AND RANGE OF BITUMINOUS CONTENT

Sieve Bituminous Designation Mixture Square-Mesh Sieves No. 1 No. 2 No. 3

Aggregate 1 in. 100 --- --- 3/4 in. 85-100 100 --- 1/2 in. --- 82-100 100 3/8 in. 61-90 68-93 82-100 No. 4 43-79 48-82 57-88 No. 8 32-68 36-70 42-76 No. 16 26-56 27-60 32-64 No. 30 18-44 20-48 22-52

SECTION 32 12 21 Page 7

No. 50 13-33 15-38 16-40 No. 100 9-22 10-25 10-27 No. 200 5-12 5-12 5-12

Bituminous (Percent by Weight of total mixture) --- 5.0-8.0 5.0-8.5 5.0-9.0

NOTE: The range of bituminous material shown represents the normal range of bituminous material contained in the design mix composed of nonabsorptive aggregates after evaporation of the lighter constituents. The upper limit may be raised, when approved, when absorptive aggregates are used.

TABLE II. JOB MIX FORMULA TOLERANCES (PERCENT)

Tolerances Mineral Plus or Minus

Aggregate passing No. 4 or larger sieve 7 Aggregate passing No. 8, 16, 30, and 50 sieves 5 Aggregate passing No. 100 and 200 sieves 2 Bitumen 0.4

a. Take samples from the prepared aggregate as windrowed after blending and test them for conformity with the requirements herein. Take a sufficient number of samples from the windrowed aggregate so that each sample will represent not more than 1000 square yards of finished surface course, but in no case take fewer than five samples for any day of production.

Samples shall represent equal amounts of material.

b. Bituminous materials shall not be applied on a run until a sieve analysis of the samples is made and the run is approved. A run is defined as that length of aggregate windrowed along the road and considered a convenient unit based on total job requirements or on daily capacity of the mixing unit or units, as determined by the Contracting Officer. The gradation of aggregate in the formula may be changed to meet specific field conditions without adjustment to contract unit prices.

2.3.3 Quantity of Bituminous Material

The percentage, by weight, of bituminous materials required for each run shall be approved by the Contracting Officer. The percentage of bituminous material will be computed on the basis of laboratory tests of samples of the approved aggregate and bituminous material, and on the field sieve analysis of samples taken from the windrowed blended aggregate for each run. The job-mix formula may be changed to meet specific field conditions without adjustments to contract unit prices.

PART 3 EXECUTION

3.1 PLACING AND WINDROWING AGGREGATE

SECTION 32 12 21 Page 8

Haul aggregate to the paving site in approved trucks. Deposit the aggregate on the prepared base course or subgrade from trucks equipped or supplemented with suitable measuring and spreading devices. Proportion the amount of aggregate and mineral filler by weighing with suitable equipment, or by the use of other methods or devices, as approved. Thoroughly mix the aggregate, and mineral filler by windrowing and turning with a blade grader, as directed. The aggregate shall then be bladed into uniform windrows in such quantity and proportions as to provide sufficient aggregate to produce a finished course of the specified compacted thickness. Mixing of the aggregate with shoulder material, segregation in pockets or otherwise, and mixing with the base course or subgrade shall be prevented.

3.2 RECONDITIONING OF BASE COURSE

Scarify lightly and blade the existing base course to a uniform grade and to the cross section shown, and then roll or water and roll, as directed. Depressions shall be filled and weak portions of the base course shall be strengthened with new aggregate.

3.3 PREPARATION OF BASE COURSE AND AGGREGATE

The surface of the roadway shall first be scarified lightly, and then bladed to a uniform grade and to the cross section as indicated in the delivery order or task order. The reshaped surface shall then be scarified to the depth necessary to provide the amount of aggregate required for the bituminous mixtures, and in such manner as to leave a foundation stratum of undisturbed material, and parallel, both in profile and cross section, to the proposed finished surface. Blade the loosened material into a windrow at the side of the road. The undisturbed understratum shall be rolled, or watered and rolled until a satisfactory foundation for the surface course is provided. The windrow and aggregate shall be broken up and thoroughly mixed by turning with a blade grader, and then bladed into uniform windrows of such size as to provide a finished surface course of the specified compacted thickness.

The surface of the roadway shall first be scarified lightly and bladed to a uniform grade and to the cross section shown on the drawings. The reshaped surface shall then be scarified again to such depth as indicated and in such manner as to leave a foundation stratum of undisturbed material, parallel, both in profile and cross section, to the surface course. New aggregate of the quality and gradation conforming with paragraph AGGREGATES shall be spread over the loosened existing aggregate in the required quantities. New aggregate shall be hauled to the paving site in approved trucks. The new and old aggregate shall then be thoroughly blended by harrowing and blading, after which all the thoroughly mixed aggregate shall be bladed into a uniform windrow at the side of the road.

The undisturbed understratum shall be graded, rolled, or watered and rolled until a satisfactory foundation for the surface course is provided.

3.4 MIXING WINDROWED AGGREGATE AND BITUMINOUS MATERIAL

3.4.1 Travel-Plant Method

The windrowed aggregate shall be mixed with bituminous material, by means of a traveling mixing plant, and the mixture shall be deposited in a windrow ready for spreading. The bituminous material shall be heated to the specified temperature within the range of 180 degrees F and 225 degrees F prior to application. When approved, the mixture shall be deposited in a mechanical spreader and spread in accordance with paragraph SPREADING AND SHAPING. The quantity of bituminous material will be determined in accordance with the procedure in paragraph COMPOSITION OF MIXTURE, and then introduced into the mixer. Regulate the machine's rate of travel and the amount of mixing so that the mixing operation will completely and uniformly coat all the particles of aggregate, and will produce

SECTION 32 12 21 Page 9 a homogeneous mixture. The mixture shall not be spread until the mixing is complete and satisfactory.

Should the mixture show an excess or a deficiency of any materials, correct the unsatisfactory condition by the addition of the required aggregate or bituminous material, followed by remixing.

Should the mixture show uneven distribution of bituminous material, correct the unsatisfactory condition by remixing. If directed, the material shall be harrowed or disked, and all compressed masses of material shall be broken up.

3.4.2 Blade Method

Prior to the application of bituminous material, spread the windrowed aggregates for the wearing surface in a uniform layer over the existing surface. Add bituminous material of the type, grade, or designation specified in paragraph BITUMINOUS MATERIALS to the aggregate at the temperature specified, and at the rate or rates determined by the Contracting Officer in accordance with paragraph COMPOSITION OF MIXTURE. Apply the bituminous material by means of bituminous distributors.

Immediately following the application of the bituminous material, the treated aggregate shall be mixed by an approved method. Mixing shall be continued until the bituminous material is uniformly distributed throughout the mass and the aggregate particles are uniformly and completely coated.

During the mixing, take care to avoid cutting into the underlying base or contaminating the bituminous mixture with earth or other objectionable matter. When operations are interrupted, the mixed or partially mixed material shall be bladed into a uniformly sized windrow or windrows in such manner that this material will not interfere with subsequent operations, will not be mixed with any untreated aggregate, and will not become contaminated with unsatisfactory material. Upon completion of the final mixing operations, the mixed material will be examined by the Contracting Officer. Should the mixture show an excess or deficiency of bituminous material, correct the unsatisfactory condition by the addition of required aggregate or bituminous material, followed by remixing. Should the mixture show uneven distribution of bituminous material, correct the unsatisfactory condition by remixing.

Continue the mixing until the mixture is complete and satisfactory.

3.5 PROCEDURE WITH THICKENED EDGE

Make a triangular cut conforming to the dimensions indicated at each edge of the surfacing. Place the excavated material on the shoulder in a small windrow against which the mixture will be spread. The trench area shall be primed in accordance with Section 32 12 10 BITUMINOUS TACK AND PRIME COATS prior to spreading of the bituminous mixture. Fill the trench with bituminous mixture and thoroughly roll it by means of the grader wheels, prior to the spreading of the surface course.

3.6 SPREADING AND SHAPING

After being satisfactorily mixed and aerated as directed, spread the bituminous material and mineral aggregate from the windrow upon the base course or primed surface in a layer of uniform thickness conforming to the lines and grades and typical sections indicated. Do no start spreading until an inspection of the subgrade or base course has been made, and any necessary reconditioning has been completed, as directed. The bituminous mixture shall not be spread when the surface is damp or when the mixture contains visible free moisture. The mixture shall be aerated until the volatile content is reduced to the point where the mixture can be spread on the roadway, and compacted to a stable pavement course that will withstand normal traffic without rutting, scuffing, raveling, or other detrimental effects. The mixture on sections of pavement showing any of these defects shall be loosened, further aerated, and recompacted to a stable pavement course. Spread the mixed material to the required width in layers, by a self-powered blade grader, as directed. In spreading from a windrow, take care to prevent cutting into the underlying subgrade or base course. If necessary, a layer of mixture approximately 1/2 inch thick shall be left at the bottom of the windrow to prevent damage to

SECTION 32 12 21 Page 10 the base course. After approximately one-half of the material has been spread, the remaining shall be windrowed. The material spread shall be rolled once, and then planed with a blade grader to remove high spots. The remaining material shall then be spread and rolled to the depth and width indicated.

During the spreading and compacting, the surface shall be dragged or bladed, as necessary, to fill any ruts and to remove corrugations, waves, or other irregularities.

3.7 ROLLING FINISHED SURFACE

Roll the surface after all layers have been satisfactorily spread. Final rolling shall be done by means of power-driven rollers. Begin rolling at the outside edge of the surface and proceed to the center, overlapping on successive trips at least one-half the width of the rear wheel of the roller. Alternate trips of the roller shall be of slightly different lengths. Control the speed of the roller so that lateral displacement of the mixture does not occur. Light blading or floating of the surface with a blade grader during the rolling period may be required. Continue rolling until all roller marks are eliminated, the surface is of uniform texture, and the mixture is compacted to at least 92 percent of maximum density. To prevent adhesion of the mixture to the roller, keep the wheels properly moistened, but an excess of water will not be permitted. The rollers shall be in good condition, suitable for rolling asphalt, and shall be operated by experienced rollermen. At all places not accessible to the roller, the mixture shall be thoroughly tamped with hand tampers. Should the surface of the surface course for any reason become rough, corrugated, uneven in texture, or traffic marked prior to completion, such unsatisfactory portions shall be torn up, reworked, relaid, or replaced at no additional cost to the Government. Should any portion of the surface, when laid, become water soaked for any reason, the portion shall be torn up at once, and the mix placed in a windrow and aerated until the moisture content is within the limits specified. The mixture shall then be spread, shaped, and rolled as specified.

3.8 SHAPING OF EDGES

While the surface is being compacted and finished, trim the outside edges neatly to line.

3.9 GRADE CONTROL

The finished and completed surface course shall conform to the lines, grades, cross section, and dimensions indicated. Maintain the lines and grades, as indicated, by means of line and grade stakes placed in accordance with the SPECIAL CONTRACT REQUIREMENTS.

3.10 SURFACE SMOOTHNESS AND THICKNESS TESTING

Follow tolerances for surface smoothness and thickness as specified in paragraph SAMPLING AND

TESTING.

3.11 SAMPLING AND TESTING

Sampling and testing are the responsibility of the Contractor. Perform sampling and testing by an approved commercial testing laboratory, or by the Contractor, subject to approval.

3.11.1 Sources of Materials

Select in advance of the time required for use in the work, the source of materials for the wearing course. The Contractor shall be responsible for performing tests to determine the suitability of the proposed materials and submitting the test results not less than 30 days before materials are required for the work.

SECTION 32 12 21 Page 11

3.11.2 Field Testing

3.11.2.1 Aggregate and Bitumen Sampling

Perform sampling of the aggregate and bitumen in accordance with ASTM D 75 for coarse and fine aggregates, ASTM C 183 for mineral filler, and ASTM D 140 for bituminous material. Test the materials for compliance with paragraph AGGREGATES, paragraph BITUMINOUS MATERIALS, and paragraph COMPOSITION OF MIXTURE.

3.11.2.2 Asphalt Sampling

Obtain samples of the asphalt mixture for each 400 tons of pavement produced and tested for compliance with paragraph COMPOSITION OF MIXTURE.

3.11.2.3 Testing

Perform tests for surface smoothness in accordance with paragraph Tolerances at intervals of not more than 100 feet along the surface of the finished pavement.

3.11.3 Testing of Windrowed Aggregate

Measure the windrowed aggregate, and any adjustments of quantities necessary to produce the specified thickness of the course shall be made as directed. Samples of the windrowed aggregate shall then be taken to be tested for conformance with gradation requirements of this section of the specifications, and any necessary adjustments in gradation shall be made, as directed.

3.11.4 Moisture Content of Windrowed Aggregate

Immediately prior to distributing bituminous material, sample and test for moisture content the windrowed aggregate. If the moisture content is in excess of 2 percent, the aggregate shall be aerated without degradation of the aggregate, until the moisture content is within the limits specified.

3.11.5 Tolerance

Take suitably sized core samples to determine the thickness of the completed pavement at intervals of not more than 100 feet along the surface. Replace the area where samples were removed from the pavement, at no additional expense to the Government.

3.11.5.1 Surface-Smoothness Requirements

Test the surface course longitudinally and transversely with a 12 foot straightedge. Place the straightedge parallel to and perpendicular to the centerline at 50 intervals along the surface. The finished surface of the surface course shall show no deviation greater than 1/4 inch from the 12 foot straightedge. Correct surface irregularities in excess of those specified above as directed, without additional cost to the Government.

3.11.5.2 Thickness Requirements

The thickness of the pavement shall not vary from that shown by more than 1/4 inch. Correct a variation in thickness in excess of 1/4 inch as directed, without additional cost to the Government.

SECTION 32 12 21 Page 12

-- End of Section --

SECTION 32 12 21 Page 13

PART 1 GENERAL
1.1 UNIT PRICES
1.1.1 Measurement
1.1.1.1 Surface Course
1.1.1.2 Bituminous Material
1.1.2 Payment
1.1.3 Waybills and Delivery Tickets
1.2 REFERENCES
1.3 SYSTEM DESCRIPTION
1.3.1 Traveling-Plant Mixer
1.3.2 Bituminous Distributor
1.3.3 Heating Equipment for Storage Tanks
1.3.4 Blade Graders
1.3.5 Power Rollers
1.3.5.1 Steel-Wheel
1.3.5.2 Pneumatic-Tired
1.3.6 Mechanical Spreaders
1.3.7 Tractors
1.3.8 Miscellaneous Equipment
1.3.9 Safety Precautions
1.4 SUBMITTALS
1.5 ENVIRONMENTAL REQUIREMENTS
PART 2 PRODUCTS
2.1 AGGREGATES
2.1.1 Coarse Aggregate
2.1.1.1 Crushed Stone
2.1.1.2 Crushed Gravel
2.1.1.3 Crushed Slag
2.1.2 Fine Aggregate
2.1.3 Mineral Filler
2.2 BITUMINOUS MATERIALS
2.3 COMPOSITION OF MIXTURE
2.3.1 Job-Mix Formula
2.3.2 Gradation Limits for Aggregates
2.3.3 Quantity of Bituminous Material
PART 3 EXECUTION
3.1 PLACING AND WINDROWING AGGREGATE
3.2 RECONDITIONING OF BASE COURSE
3.3 PREPARATION OF BASE COURSE AND AGGREGATE
3.4 MIXING WINDROWED AGGREGATE AND BITUMINOUS MATERIAL
3.4.1 Travel-Plant Method
3.4.2 Blade Method
3.5 PROCEDURE WITH THICKENED EDGE
3.6 SPREADING AND SHAPING
3.7 ROLLING FINISHED SURFACE
3.8 SHAPING OF EDGES
3.9 GRADE CONTROL
3.10 SURFACE SMOOTHNESS AND THICKNESS TESTING
3.11 SAMPLING AND TESTING
3.11.1 Sources of Materials
3.11.2 Field Testing
3.11.2.1 Aggregate and Bitumen Sampling
3.11.2.2 Asphalt Sampling
3.11.2.3 Testing
3.11.3 Testing of Windrowed Aggregate
3.11.4 Moisture Content of Windrowed Aggregate
3.11.5 Tolerance
3.11.5.1 Surface-Smoothness Requirements
3.11.5.2 Thickness Requirements