01 57 19-TEMPORARY ENVIRONMENTAL CONTROLS.pdf
PDF 49 KB Posted
- Attached to
- Joint Base Lewis-McChord PAVEMENT IDIQ
- Solicitation number
- W911S8-17-R-0001
About this file
01 57 19-TEMPORARY ENVIRONMENTAL CONTROLS
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JBLM DESIGN STANDARDS
SECTION 01 57 19 - TEMPORARY ENVIRONMENTAL CONTROLS
11/15
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 EROSION AND SEDIMENT CONTROL
1.4 SUBMITTALS
1.5 DELIVERY, STORAGE AND HANDLING
PART 2 PRODUCTS
PART 3 EXECUTION
3.1 INSPECTIONS
PART 1 GENERAL
1. Storm Water Management Manual for Western Washington.
2. EPA NPDES Construction General Permit. Applies to all projects having a total ground disturbance of an acre or greater and will or have a potential to discharge to US Waters.
3. Low Impact Development Technical Guidance Manual for Puget Sound
4. Erosion and Sediment Control. Provide appropriate erosion and sediment controls on all construction sites that will have ground disturbance. Proper implementation and maintenance of appropriate best management practices (BMPs) is critical to control any adverse water quality impacts from construction activities adequately. Discharges must not violate the state’s surface water quality standards (WAC Chapter 173-201A) and groundwater quality standards (WAC Chapter 173-200).
SECTION 01 57 23
TEMPORARY STORMWATER POLLUTION CONTROL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 832-R-92-005 (most current) Storm water Management for Construction Activities Developing Pollution Preventions and Plans and Best Management Practices http://www.ecy.wa.gov/programs/wq/stormwater/manual.html#How_to_Find_the_Stormwater_Manual_on_the http://www.psp.wa.gov/downloads/LID/LID_manual2005.pdf
Construction General Permit (most current) Construction General Permit, Environmental
Protection Agency NPDES General Permit for Storm water Discharges From Construction Activities
Storm water Management Manual (Most Current) Storm water Management Manual for
Western Washington State Department of Ecology Publication
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 122.26 Storm water Discharges (Applicable to State NPDES
Programs, see Section 123.25)
1.2 SYSTEM DESCRIPTION
The work consists of implementing the storm water pollution prevention measures to prevent sediments from entering United States bodies of water or municipal separate storm sewer systems leading to a United State body of water as specified in this Section in conformance with the requirements of Section 01 57
20.00 10 ENVIRONMENTAL PROTECTION, and the National Pollution Discharge Elimination System (NPDES) permit attached to that Section.
1.3 E R O S I O N AND SEDIMENT CONTROLS
If applicable contractors will comply with the EPA NPDES Construction General Permit specific control measures. In addition, the control measures described in the Western Washington Storm water Management Manual are authorized. Any deviation from the manual stated above must have approval from the DPW.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Storm water Pollution Prevention Plan; G
JBLM has a NDPES Construction General Permit for the installation and a general Storm water Pollution Prevention Plan (SWPPP). If applicable, the Contractor shall obtain individual permit coverage under the EPA's NDPES Construction General Permit by submitting a Notice of Intent to the EPA. A requirement of the permit is to prepare a SWPPP. The SWPPP must meet the requirements of the EPA's NPDES General Permit for Storm water from Construction Activities, and must be approved by JBLM Environmental Division prior to submitting the NOI.
The site specific SWPPP must be prepared in accordance with good engineering practices and must include the detailed areas required by the Construction General Permit. The SWPPP shall be submitted to the Water Program Office, Environmental Division, Public Works as early as possible for approval, in case changes or corrections must be made, but no later than 10 days prior to beginning work. The EPA SWPPP template must be used.
Approval of the Contractor's SWPPP will not relieve the Contractor of responsibility for adequate management of storm water. The SWPPP is a dynamic document. The Contractor must implement the SWPPP in accordance with the Construction General Permit requirements.
SD-06 Test Reports
Storm water Inspection Reports for General Permit Erosion and Sediment Controls
SD-07 Certificates
Mill Certificate or Affidavit
Certificate attesting that the Contractor has met all specified requirements.
SD-08 Closeout Submittals
Permit Termination
The permit must be terminated in accordance with the Construction General Permit. The notice of termination must be submitted to the Environmental Protection Agency (EPA).
The permit holder must request an inspection by a qualified member of Public Works Water Program before termination request is submitted to EPA. At the discretion of the Water Program, an inspection may or may not be conducted prior to permit termination.
SD-09 Closeout Submittals
A copy of the Notice of Termination and EPA confirmation letter must be submitted to Public Works Water Program.
SD-11 Closeout Submittals
The SWPPP must be terminated in accordance with the Construction General Permit.
The site will be inspected by a qualified member of the Public Works Water Program before termination request is submitted. Contractors shall request inspection prior to termination.
1.5 DELIVERY, STORAGE, AND HANDLING
All identification, storage and handling will be in accordance with the most current version of the Storm water Management Manual for Western Washington.
PART 2 PRODUCTS
Provide products that comply with the Storm water Management Manual for Western Washington.
PART 3 EXECUTION
Execute in accordance with the Storm water Management Manual for Western Washington.
3.1 INSPECTIONS
3.1.1 General
Inspections shall be in accordance with the Construction General Permit.
-- END OF SECTION --