31_11_00_Clearing_ _Grubbing.pdf

PDF 23 KB Posted

Attached to
Joint Base Lewis-McChord PAVEMENT IDIQ
Solicitation number
W911S8-17-R-0001
Issued by

About this file

31 11 00 Clearing Grubbing

View the file

Other files

File Type Posted
SF1442_W911S8-17-R-0001_0002.pdf PDF
4. Technical Exbhibit C Statement of Work 19 Dec 2016.pdf PDF
JBLM Paving W911S8-17-R-0001 Contractor QUESTIONS 22 Dec16.pdf PDF
Pre-Proposal Conference Contractor Attendees.pdf PDF
33 71 02UNDERGROUND ELECTRICAL DISTRIBUTION.pdf PDF
SF30 W911S8-17-R-0001 0002.pdf PDF
Attachment 1- Sample Project 19 December 2016.pdf PDF
32 12 21-BITUMINOUS ROAD-MIX SURFACE COURSE.pdf PDF
01_45_00_10_Quality_Control_19_Dec.pdf PDF
33 71 02 JBLM DESIGN STANDARDS-UNDERGROUND ELECTRICAL DISTRIBUTION.pdf PDF
Site Visit Briefing W911S8-17-R-0001 JBLM Paving -29 Nov 2016.pdf PDF
SF30 W911S8-17-R-0001 0001.pdf PDF
W911S8-17-R-0001_Amendment_0001.pdf PDF
01 57 19-TEMPORARY ENVIRONMENTAL CONTROLS.pdf PDF
01 42 00-SOURCES FOR REFERENCE PUBLICATIONS.pdf PDF
13. Attachment 5 - Past Performance Questionaire.docx DOCX document
32_84_24_(Irrigation_Sprinkles).pdf PDF
26_56_13.00_40_Lighting_Poles_and_Standards.pdf PDF
14. Attachment 6 Insurance Certificate of Compliance.docx DOCX document
01 78 23-OPERATION AND MAINTENANCE DATA.pdf PDF
32_17_24.00_10_(Pavement_Markings).pdf PDF
1. RFP W911S8-17-R-0001 Paving IDC.pdf PDF
01 50 00-TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS.pdf PDF
01 32 01 00 10 Project Schedule.pdf PDF
7. TE F General Decision Number WA160001 Dtd 19 Aug 16.pdf PDF
5. TE D-Table of Contents.pdf PDF
3. TE B Proposal Item Descriptions(09-27-16).pdf PDF
10. Attachment 2-Experience Document.docx DOCX document
6. TE E Standards Plans Drawings 25Aug16.pdf PDF
31_23_00.00_20_Excavation_ _Fill.pdf PDF
01 35 29.13 Contaminated Site.pdf PDF
32_11_24_CSBC_for_Flexible_Pavement.pdf PDF
32_31_26_(Wire_Fence_ _Gate).pdf PDF
32_31_13.53_(High_Security_Fence).pdf PDF
26_56_19.00_40_Roadway_Lighting.pdf PDF
32_93_00_(Exterior_Plants).pdf PDF
31_00_00_Earthwork.pdf PDF
2. TE A ELIN Proposal Schedule 11 Oct 16.xlsx XLSX spreadsheet
33_11_00-WATER_DISTRIBUTION.pdf PDF
01 45 00 10 Quality Control.pdf PDF
01 30 00 Administrative Requirements.pdf PDF
33_30_00-SANITARY_SEWERS.pdf PDF
01 78 00- CLOSEOUT SUBMITTALS.pdf PDF
32_01_13_BITUMINOUS_SEAL_AND_FOG_COATS.pdf PDF
16. Attachment 8-JBLM Installation Access Information.docx DOCX document
32_92_19_(Seeding).pdf PDF
32_12_10_(Tack_Coat).pdf PDF
12. Attachment 4 - Relevant Contract Reference Sheet.docx DOCX document
00 10 01 - Supplementary Requirements.pdf PDF
32_12_15.13_HMA_for_Airfields.pdf PDF
Show 40 more

Latest 50 of 74 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 31 11 00 Page 1

SECTION 31 11 00

CLEARING AND GRUBBING

08/08

PART 1 GENERAL

1.1 SUBMITTALS

1.2 DELIVERY, STORAGE, AND HANDLING

1.3 MATERIAL SAFETY DATA SHEETS

PART 2 PRODUCTS

2.1 TREE WOUND PAINT

2.2 HERBICIDE

PART 3 EXECUTION

3.1 PROTECTION

3.2 CLEARING

3.3 TREE REMOVAL

3.4 PRUNING

3.5 GRUBBING

3.6 DISPOSAL OF MATERIALS

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Nonsaleable Materials; G

Written permission to dispose of such products on private property shall be filed with the Contracting Officer.

SD-04 Samples

Tree wound paint Herbicide

Samples in cans with manufacturer's label.

1.2 DELIVERY, STORAGE, AND HANDLING

SECTION 31 11 00 Page 2

Deliver materials to store at the site, and handle in a manner which will maintain the materials in their original manufactured or fabricated condition until ready for use.

1.3 MATERIAL SAFETY DATA SHEETS

Copies of the Material Safety Data Sheets (MSDS) and other HM documentation for all hazardous materials shall be submitted per Paragraph 3.6.11 of Section 01 57 20.00 10 ENVIRONMENTAL PROTECTION as shown in the Joint Base Lewis-McChord (JBLM) Design Standards

PART 2 PRODUCTS

2.1 TREE WOUND PAINT

Bituminous based paint of standard manufacture specially formulated for tree wounds.

2.2 HERBICIDE

Comply with Federal Insecticide, Fungicide, and Rodenticide Act (Title 7 U.S.C. Section 136) for requirements on Contractor's licensing, certification and record keeping. Contact the command Pest Control Coordinator prior to starting work.

PART 3 EXECUTION

3.1 PROTECTION

3.1.1 Roads and Walks

Keep roads and walks free of dirt and debris at all times.

3.1.2 Trees, Shrubs, and Existing Facilities

Trees and vegetation to be left standing shall be protected from damage incident to clearing, grubbing, and construction operations by the erection of barriers or by such other means as the circumstances require.

3.1.3 Utility Lines

Protect existing utility lines that are indicated to remain from damage. Notify the Contracting Officer immediately of damage to or an encounter with an unknown existing utility line. The Contractor shall be responsible for the repairs of damage to existing utility lines that are indicated or made known to the Contractor prior to start of clearing and grubbing operations. When utility lines which are to be removed are encountered within the area of operations, notify the Contracting Officer at least ten (10) working days prior to proposed outages to minimize interruption of the service.

3.2 CLEARING

Clearing shall consist of the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared. Clearing shall also include the removal and disposal of structures that obtrude, encroach upon, or otherwise obstruct the work. Trees, stumps, roots, brush, and other vegetation in areas to be cleared shall be cut off flush with or below the original ground surface, except such trees and vegetation as may be indicated or directed to be left standing.

Trees designated to be left standing within the cleared areas shall be trimmed of dead branches 1-1/2

SECTION 31 11 00 Page 3 inches or more in diameter and shall be trimmed of all branches the heights indicated or directed.

Limbs and branches to be trimmed shall be neatly cut close to the bole of the tree or main branches.

Cuts more than 1-1/2 inches in diameter shall be painted with an approved tree-wound paint. Apply herbicide in accordance with the manufacturer's label to the top surface of stumps designated not to be removed.

3.3 TREE REMOVAL

Where indicated or directed, trees and stumps that are designated as trees shall be removed from areas outside those areas designated for clearing and grubbing. This work shall include the felling of such trees and the removal of their stumps and roots as specified in paragraph GRUBBING. Trees shall be disposed of as specified in paragraph DISPOSAL OF MATERIALS.

3.4 PRUNING

Prune trees designated to be left standing within the cleared areas of dead branches 1 1/2 inches or more in diameter; and trim branches to heights and in a manner as indicated. Neatly cut limbs and branches to be trimmed close to the bole of the tree or main branches. Paint cuts more than 1 1/4 inches in diameter with an approved tree wound paint.

3.5 GRUBBING

Grubbing shall consist of the removal and disposal of stumps, roots larger than 3 inches in diameter, and matted roots from the designated grubbing areas. Material to be grubbed, together with logs and other organic or metallic debris not suitable for foundation purposes, shall be removed to a depth of not less than 18 inches below the original surface level of the ground in areas indicated to be grubbed and in areas indicated as construction areas under this contract, such as areas for buildings, and areas to be paved. Depressions made by grubbing shall be filled with suitable material and compacted to make the surface conform to the original adjacent surface of the ground.

3.6 DISPOSAL OF MATERIALS

3.6.1 Saleable Timber

1. The Government shall, by separate contract, harvest all saleable timber from the project site. All remaining timber, limbs, tops, stumps, and debris shall be cleared and disposed of by the Contractor as specified.

2. All timber on the project site noted for clearing and grubbing shall become the property of the Contractor, and shall be removed from the project site and disposed of off stations.

3.6.2 Nonsaleable Materials

Logs, stumps, roots, brush, limbs and other organic based debris from the clearing and grubbing of land, except for salable timber, shall be taken to the Joint Base Lewis-McChord Earthworks or be disposed of off-site at contractor expense. POC at the Earthworks: Resource Conservation and Recovery Act (RCRA) Program Manager 253-967-3803, Solid Waste and Recycling Program Manager 253-966-6452.

-- End of Section

PART 1 GENERAL
1.1 SUBMITTALS
1.2 DELIVERY, STORAGE, AND HANDLING
1.3 MATERIAL SAFETY DATA SHEETS
PART 2 PRODUCTS
2.1 TREE WOUND PAINT
2.2 HERBICIDE
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Roads and Walks
3.1.2 Trees, Shrubs, and Existing Facilities
3.1.3 Utility Lines
3.2 CLEARING
3.3 TREE REMOVAL
3.4 PRUNING
3.5 GRUBBING
3.6 DISPOSAL OF MATERIALS
3.6.1 Saleable Timber
3.6.2 Nonsaleable Materials

File details come from the government source that posted it. Updated .