32 12 10 (Tack Coat)
View the file
Other files
Show 40 more
Latest 50 of 74 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 32 12 10 Page 1
SECTION 32 12 10
BITUMINOUS TACK AND PRIME COATS
08/08
PART 1 GENERAL
1.1 UNIT PRICES
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 DELIVERY, STORAGE, AND HANDLING
1.6 ENVIRONMENTAL REQUIREMENTS
PART 2 PRODUCTS
2.1 PLANT, EQUIPMENT, MACHINES AND TOOLS
2.2 PRIME COAT
2.3 TACK COAT
PART 3 EXECUTION
3.1 PREPARATION OF SURFACE
3.2 APPLICATION RATE
3.3 APPLICATION TEMPERATURE
3.4 APPLICATION
3.5 CURING PERIOD
3.6 FIELD QUALITY CONTROL
3.7 SAMPLING AND TESTING
3.8 TRAFFIC CONTROLS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION
OFFICIALS (AASHTO)
AASHTO M 81 (1992; R 2012) Standard Specification for Cutback Asphalt
(Rapid-Curing Type)
AASHTO T 102 (2009; R 2013) Standard Method of Test for Spot Test of
Asphaltic Materials
AASHTO T 40 (2002; R 2006) Sampling Bituminous Materials
ASTM INTERNATIONAL (ASTM)
SECTION 32 12 10 Page 2
ASTM D 140/D140M (2015) Sampling Bituminous Materials
ASTM D 2026/D2026M (2015) Cutback Asphalt (Slow-Curing Type)
ASTM D 2027/D 2027M (2013) Cutback Asphalt (Medium-Curing Type)
ASTM D 2028/D 2028M (2015) Cutback Asphalt (Rapid-Curing Type)
ASTM D 2397/D 2397M (2013) Standard Specification for Cationic Emulsified Asphalt
ASTM D 2995 (1999; R 2009) Determining Application Rate of Bituminous
Distributors
ASTM D 977 (2013; E 2014) Emulsified Asphalt
1.2 SYSTEM DESCRIPTION
1.2.1 General Requirements
Plant, equipment, machines and tools used in the work are subject to approval and shall be maintained in a satisfactory working condition at all times. Calibrated equipment such as asphalt distributors, scales, batching equipment, spreaders and similar equipment, should have been recalibrated by a calibration laboratory within 12 months prior to commencing work.
1.2.2 Bituminous Distributor
Provide a distributor with pneumatic tires of such size and number that the load produced on the base surface does not exceed 650 psi of tire width to prevent rutting, shoving or otherwise damaging the base surface or other layers in the pavement structure. Design and equip the distributor to spray the bituminous material in a uniform coverage at the specified temperature, at readily determined and controlled rates from 0.05 to 2.0 gallons per square yard, with a pressure range of 25 to 75 psi and with an allowable variation from the specified rate of not more than plus or minus 5 percent, and at variable widths. Include with the distributor equipment a separate power unit for the bitumen pump, full-circulation spray bars, tachometer, pressure gauges, volume-measuring devices, adequate heaters for heating of materials to the proper application temperature, a thermometer for reading the temperature of tank contents, and a hand hose attachment suitable for applying bituminous material manually to areas inaccessible to the distributor. Equip the distributor to circulate and agitate the bituminous material during the heating process.
1.2.3 Heating Equipment for Storage Tanks
The equipment for heating the bituminous material shall be steam, electric, or hot oil heaters. Provide steam heaters consisting of steam coils and equipment for producing steam, so designed that the steam cannot get into the material. Fix an armored thermometer to the tank with a temperature range from 40 to 400 degrees F so that the temperature of the bituminous material may be determined at all times.
1.2.4 Power Brooms and Power Blowers
Use power brooms and power blowers suitable for cleaning the surfaces to which the bituminous coat is to be applied.
SECTION 32 12 10 Page 3
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-06 Test Reports
Sampling and Testing
Copies of all test results for emulsified asphalt, and bituminous materials, within 24 hours of completion of tests. Certified copies of the manufacturer's test reports indicating temperature viscosity relationship for cutback asphalt, compliance with applicable specified requirements, not less than 30 days before the material is required in the work.
1.4 QUALITY ASSURANCE
See Section 01 33 29 LEED(tm) DOCUMENTATION for cumulative total local material requirements. Tack and prime coat materials may be locally available.
1.5 DELIVERY, STORAGE, AND HANDLING
Inspect the materials delivered to the site for contamination and damage. Unload and store the materials with a minimum of handling.
1.6 ENVIRONMENTAL REQUIREMENTS
Apply bituminous coat only when the surface to receive the bituminous coat is dry. Apply bituminous coat only when the atmospheric temperature in the shade is 50 degrees F or above and when the temperature has not been below 35 degrees F for the 12 hours prior to application, unless otherwise directed.
PART 2 PRODUCTS
2.1 PRIME COAT
Provide asphalt conforming to AASHTO M 81 and specified in the following two subparagraphs.
2.1.1 Cutback Asphalt
Provide cutback asphalt conforming to ASTM D 2026, Grade SC-70 or to ASTM D 2027, Grade MC- 70 or to ASTM D 2028, Grade RC-70.
2.1.2 Emulsified Asphalt
Provide emulsified asphalt conforming to ASTM D 977, Type SS-1 or SS1h or to ASTM D 2397, Type CSS-1 or CSS-1h.
SECTION 32 12 10 Page 4
2.2 TACK COAT
Provide asphalt conforming to ASTM D 2028 or AASHTO M 81.
2.2.1 Cutback Asphalt
Provide cutback asphalt conforming to ASTM D 2026, Grade SC-70 or to ASTM D 2027, Grade MC- 70 or to ASTM D 2028, Grade RC-70.
2.2.2 Emulsified Asphalt
Provide emulsified asphalt conforming to ASTM D 977, Type SS-1 or to SS1h or to ASTM D 2397, Type CSS-1 or CSS-1h. Dilute the emulsified asphalt with equal parts of water. The base asphalt used to manufacture the emulsion shall show a negative spot when tested in accordance with AASHTO T 102 using standard naphtha.
PART 3 EXECUTION
3.1 PREPARATION OF SURFACE
Immediately before applying the bituminous coat, remove all loose material, dirt, clay, or other objectionable material from the surface to be treated by means of a power broom or blower supplemented with hand brooms. The surface shall be dry and clean at the time of treatment.
3.2 APPLICATION RATE
The exact quantities within the range specified, which may be varied to suit field conditions, will be determined by the Contracting Officer.
3.2.1 Tack Coat
Apply bituminous material for the tack coat in quantities of not less than 0.05 gallon nor more than
0.15 gallon per square yard of pavement surface.
3.2.2 Prime Coat
Apply bituminous material for the prime coat in quantities of not less than 0.15 gallon nor more than
0.40 gallon per square yard of pavement surface.
3.3 APPLICATION TEMPERATURE
3.3.1 Viscosity Relationship
Asphalt application temperature shall provide an application viscosity between 10 and 60 seconds, Saybolt Furol, or between 20 and 120 centistokes, kinematic. Furnish the temperature viscosity relation to the Contracting Officer.
3.3.2 Temperature Ranges
The viscosity requirements determine the application temperature to be used. The following is a normal range of application temperatures:
SECTION 32 12 10 Page 5
Liquid Asphalts
SC-70 120-225 degrees F SC-250 165-270 degrees F MC-30 85-190 degrees F MC-70 120-225 degrees F MC-250 165-270 degrees F
Paving Grade Asphalts
Penetration Grades
200-300 plus 265 degrees F 120-150 plus 270 degrees F 85-100 plus 280 degrees F
Viscosity Grades
AC 2.5 plus 270 degrees F AC 5 plus 280 degrees F AC 10 plus 280 degrees F
AR 1000 plus 275 degrees F AR 2000 plus 285 degrees F AR 4000 plus 290 degrees F
Emulsions RS-1 70-140 degrees F MS-1 70-160 degrees F HFMS-1 70-160 degrees F SS-1 70-160 degrees F SS-1h 70-160 degrees F CRS-1 125-185 degrees F CSS-1 70-160 degrees F CSS-1h 70-160 degrees F
These temperature ranges exceed the flash point of the material and care should be taken in their heating.
3.4 APPLICATION
3.4.1 General
Following preparation and subsequent inspection of the surface, apply the bituminous prime or tack coat with the Bituminous Distributor at the specified rate with uniform distribution over the surface to
SECTION 32 12 10 Page 6 be treated. Properly treat all areas and spots missed by the distributor with the hand spray. Until the succeeding layer of pavement is placed, maintain the surface by protecting the surface against damage and by repairing deficient areas at no additional cost to the Government. If required, spread clean dry sand to effectively blot up any excess bituminous material. No smoking, fires, or flames other than those from the heaters that are a part of the equipment are permitted within 25 feet of heating, distributing, and transferring operations of bituminous material other than bituminous emulsions.
Prevent all traffic, except for paving equipment used in constructing the surfacing, from using the underlying material, whether primed or not, until the surfacing is completed. The bituminous coat shall conform to all requirements as described herein.
3.4.2 Prime Coat
The prime coat is required if it will be at least 7 days before the surfacing (Asphalt cement hot mix concrete) layer is constructed on the underlying (base course, etc.) compacted material. The type of liquid asphalt and application rate will be as specified herein. Protect the underlying from any damage (water, traffic, etc.) until the surfacing is placed. If the Contractor places the surfacing within seven days, the choice of protection measures or actions to be taken is at the Contractor's option. Repair (recompact or replace) damage to the underlying material caused by lack of, or inadequate, protection by approved methods at no additional cost to the Government. If the Contractor opts to use the prime coat, apply as soon as possible after consolidation of the underlying material. Apply the bituminous material uniformly over the surface to be treated at a pressure range of 25 to 75 psi and at the rate of not less than 0.20 gallon not more than 0.30 gallon per square yard. To obtain uniform application of the prime coat on the surface treated at the junction of previous and subsequent applications, spread building paper on the surface for a sufficient distance back from the ends of each application to start and stop the prime coat on the paper and to ensure that all sprayers will operate at full force on the surface to be treated. Immediately after application remove and destroy the building paper.
3.4.3 Tack Coat
Apply tack coat at the locations indictaed in the task order or delivery order. Apply the tack coat when the surface to be treated is dry. Immediately following the preparation of the surface for treatment, apply the bituminous material by means of the bituminous distributor, within the limits of temperature specified herein and at a rate of not less than 0.05 gallon nor more than 0.15 gallon of diluted emulsion per square yard. Apply the bituminous material so that uniform distribution is obtained over the entire surface to be treated. Treat lightly coated areas and spots missed by the distributor with the bituminous material. Following the application of bituminous material, allow the surface to cure without being disturbed for period of time necessary to permit setting of the tack coat. Apply the bituminous tack coat only as far in advance of the placing of the overlying layer as required for that day's operation.
Maintain and protect the treated surface from damage until the succeeding course of pavement is placed.
3.5 CURING PERIOD
Following application of the bituminous material and prior to application of the succeeding layer of pavement, allow the bituminous coat to cure and to obtain evaporation of any volatiles or moisture.
Maintain the coated surface until the succeeding layer of pavement is placed, by protecting the surface against damage and by repairing and recoating deficient areas. Allow the prime coat to cure without being disturbed for a period of at least 48 hours or longer, as may be necessary to attain penetration into the treated course. Furnish and spread enough sand to effectively blot up and cure excess bituminous material.
SECTION 32 12 10 Page 7
3.6 FIELD QUALITY CONTROL
Samples of the bituminous material used shall be obtained by the Contractor as directed, under the supervision of the Contracting Officer. The sample may be retained and tested by the Government at no cost to the Contractor.
3.7 SAMPLING AND TESTING
Perform sampling and testing by an approved commercial testing laboratory or by facilities furnished by the Contractor. No work requiring testing will be permitted until the facilities have been inspected and approved.
3.7.1 Sampling
The samples of bituminous material, unless otherwise specified, shall be in accordance with ASTM D 140 or AASHTO T 40. Sources from which bituminous materials are to be obtained shall be selected and notification furnished the Contracting Officer within 15 days after the award of the contract.
3.7.2 Calibration Test
Furnish all equipment, materials, and labor necessary to calibrate the bituminous distributor.
Calibration shall be made with the approved job material and prior to applying the bituminous coat material to the prepared surface. Calibrate the bituminous distributor in accordance with ASTM D 2995.
3.7.3 Trial Applications
Before providing the complete bituminous coat, apply three lengths of at least 100 feet for the full width of the distributor bar to evaluate the amount of bituminous material that can be satisfactorily applied.
3.7.3.1 Tack Coat Trial Application Rate
Unless otherwise authorized, apply the trial application rate of bituminous tack coat materials in the amount of 0.05 gallons per square yard. Other trial applications shall be made using various amounts of material as may be deemed necessary.
3.7.3.2 Prime Coat Trial Application Rate
Unless otherwise authorized, apply the trial application rate of bituminous materials in the amount of
0.25 gallon per square yard. Other trial applications shall be made using various amounts of material as may be deemed necessary.
3.7.4 Sampling and Testing During Construction
Perform quality control sampling and testing as required in paragraph FIELD QUALITY CONTROL.
3.8 TRAFFIC CONTROLS
Keep traffic off surfaces freshly treated with bituminous material. Provide sufficient warning signs and barricades so that traffic will not travel over freshly treated surfaces.
SECTION 32 12 10 Page 8
-- End of Section --
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SYSTEM DESCRIPTION |
| 1.2.1 General Requirements |
| 1.2.2 Bituminous Distributor |
| 1.2.3 Heating Equipment for Storage Tanks |
| 1.2.4 Power Brooms and Power Blowers |
| 1.3 SUBMITTALS |
| 1.4 QUALITY ASSURANCE |
| 1.5 DELIVERY, STORAGE, AND HANDLING |
| 1.6 ENVIRONMENTAL REQUIREMENTS |
| PART 2 PRODUCTS |
| 2.1 PRIME COAT |
| 2.1.1 Cutback Asphalt |
| 2.1.2 Emulsified Asphalt |
| 2.2 TACK COAT |
| 2.2.1 Cutback Asphalt |
| 2.2.2 Emulsified Asphalt |
| PART 3 EXECUTION |
| 3.1 PREPARATION OF SURFACE |
| 3.2 APPLICATION RATE |
| 3.2.1 Tack Coat |
| 3.2.2 Prime Coat |
| 3.3 APPLICATION TEMPERATURE |
| 3.3.1 Viscosity Relationship |
| 3.3.2 Temperature Ranges |
| 3.4 APPLICATION |
| 3.4.1 General |
| 3.4.2 Prime Coat |
| 3.4.3 Tack Coat |
| 3.5 CURING PERIOD |
| 3.6 FIELD QUALITY CONTROL |
| 3.7 SAMPLING AND TESTING |
| 3.7.1 Sampling |
| 3.7.2 Calibration Test |
| 3.7.3 Trial Applications |
| 3.7.3.1 Tack Coat Trial Application Rate |
| 3.7.3.2 Prime Coat Trial Application Rate |
3.7.4 Sampling and Testing During Construction
3.8 TRAFFIC CONTROLS