Text version
SECTION 01 74 19 Page 1
SECTION 01 74 19
CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01/07
PART 1 GENERAL
1.1 REFERENCES
1.2 GOVERNMENT POLICY
1.3 MANAGEMENT
1.4 SUBMITTALS
1.5 MEETINGS
1.6 WASTE MANAGEMENT PLAN
1.7 RECORDS
1.8 REPORTS
1.9 COLLECTION
PARTS 2 & 3: NOT USED
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E 1609 (2001) Development and Implementation of a Pollution
Prevention Program
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED (2009 Version 3) Leadership in Energy and Environmental Design(tm) Green Building Rating System for New Construction (LEED-NC)
1.2 GOVERNMENT POLICY
Government policy is to apply sound environmental principles in the design, construction and use of facilities. As part of the implementation of that policy the Contractor shall: (1) practice efficient waste management when sizing, cutting, and installing products and materials and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. A minimum of 50 percent by weight of total project solid waste shall be diverted from the landfill.
SECTION 01 74 19 Page 1
1.3 MANAGEMENT
Develop and implement a waste management program in accordance with ASTM E 1609 and as specified. Take a pro-active, responsible role in the management of construction and demolition waste and require all subcontractors, vendors, and suppliers to participate in the effort. Construction and demolition waste includes products of demolition or removal, excess or unusable construction materials, packaging materials for construction products, and other materials generated during the construction process but not incorporated into the work. In the management of waste, consideration shall be given to the availability of viable markets, the condition of the material, the ability to provide the material in suitable condition and in a quantity acceptable to available markets, and time constraints imposed by internal project completion mandates. The Contractor shall be responsible for implementation of any special programs involving rebates or similar incentives related to recycling of waste. Revenues or other savings obtained for salvage, or recycling may be credited to the JBLM Qualified Recycling Program or in certain cases accrue to the Contractor. Appropriately permit firms and facilities used for recycling, reuse, and disposal for the intended use to the extent required by Federal, State, and local regulations. Also, provide on-site instruction of appropriate separation, handling, recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the project.
SECTION 01 74 19 Page 2
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Waste Management Plan; G; (LEED) Quarterly Reports; G
SD-11 Closeout Submittals
Records; (LEED)
1.5 MEETINGS
Conduct Construction Waste Management meetings. After award of the Contract and prior to commencement of work, schedule and conduct a meeting with the Contracting Officer or their representative to discuss the proposed Waste Management Plan and to develop a mutual understanding relative to the details of waste management. The requirements for this meeting may be fulfilled during the coordination and mutual understanding meeting outlined in Section 01 45 01 USACE QUALITY CONTROL. At a minimum, environmental and waste management goals and issues shall be discussed at the following additional meetings:
a. Preconstruction meeting.
b. Regular site or QC meetings.
c. Work safety meetings.
1.6 W A S T E MANAGEMENT PLAN
A waste management plan shall be submitted within 15 days after notice to proceed. The plan shall demonstrate how the project waste diversion goal shall be met and shall include the following:
a. Name of individuals on the Contractor's staff responsible for waste prevention and management.
b. Actions that will be taken to reduce solid waste generation, including coordination with subcontractors to ensure awareness and participation.
c. Description of the regular meetings to be held to address waste management.
d. Description of the specific approaches to be used in recycling/reuse of the various materials generated, including the areas on site and equipment to be used for processing, sorting, and temporary storage of wastes.
e. Characterization, including estimated types and quantities, of the waste to be generated.
f. Name of landfill and/or incinerator to be used and the estimated costs for use, assuming that there would be no salvage or recycling on the project.
SECTION 01 74 19 Page 3
g. Identification of local and regional reuse programs, including non-profit organizations such as schools, local housing agencies, and organizations that accept used materials such as materials exchange networks and Habitat for Humanity. Include the name, location, and phone number for each reuse facility to be used, and provide a copy of the permit or license for each facility.
h. List of specific waste materials that will be salvaged for resale, salvaged and reused on the current project, salvaged and stored for reuse on a future project, or recycled. Recycling facilities that will be used shall be identified by name, location, and phone number, including a copy of the permit or license for each facility.
i. Identification of materials that cannot be recycled/reused with an explanation or justification, to be approved by the Contracting Officer.
j. Description of the means by which any waste materials identified in item (h) above will be protected from contamination.
k. Description of the means of transportation of the recyclable materials (whether materials will be site-separated and self-hauled to designated centers, or whether mixed materials will be collected by a waste hauler and removed from the site).
l. Anticipated net cost savings determined by subtracting Contractor program management costs and the cost of disposal from the revenue generated by sale of the materials and the incineration and/or landfill cost avoidance.
m. The waste management plan shall reflect a goal of not less than a 50 percent level of diversion. Demolition shall be in accordance with the requirements outlined in UFGS 02 41 00
DEMOLITION.
Revise and resubmit plan as required by the Contracting Officer. Approval of Contractor's Plan will not relieve the Contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. Distribute copies of the Waste Management Plan to each subcontractor, the Quality Control Manager, and the Contracting Officer.
1.7 R E C O R D S
Records shall be maintained to document the quantity of waste generated; the quantity of waste Diverted through sale, reuse, or recycling; and the quantity of waste disposed by landfill or incineration.
Records shall be kept in accordance with the LEED Reference Guide and using the LEED Letter Template. The records shall be made available to the Contracting Officer during construction, and a copy of the records shall be included in the LEED Documentation Notebook and delivered to the Contracting Officer upon completion of construction.
Reporting requirements will be in accordance with Section 01 57 20.00 10, ENVIRONMENTAL PROTECTION, Paragraph 3.8 using this form: Transaction Reporting form.xls.
Copies of the completed form will be sent directly to: JBLM Public Works, Attn: IMNW-LEW-PWE MS17, Box 339500, Joint Base Lewis-McChord, WA 98433-9500 Attention: Environmental and Natural Resources Division, Solid Waste Manager.
1.8 REPORTS
An additional copy of quarterly reports will be provided to Public Works Environmental Division Resource Conservation and Recovery Act or Solid Waste and Recycling Program Manager, at fax:
253-966-4985 and mail: JBLM Public Works, IMWE-LEW-PWE, Box 339500, Joint Base Lewis- McChord, WA 98433-9500. Quarterly and final reports shall include project name, information for Waste generated this quarter, and cumulative totals for the project. Each report shall include supporting documentation to include manifests, weight tickets, receipts, and invoices specifically identifying the project and waste material. Include timber harvest and demolition information, if any.
1.9 COLLECTION
Separate, store, protect, and handle at the site identified recyclable and salvageable waste products in a manner that maximizes recyclability and salvagability of identified materials. Provide the necessary containers, bins and storage areas to facilitate effective waste management and clearly and appropriately identify them. Provide materials for barriers and enclosures around recyclable material storage areas which are nonhazardous and recyclable or reusable. Locate out of the way of construction traffic. Provide adequate space for pick-up and delivery and convenience to subcontractors. Recycling and waste bin areas are to be kept neat and clean, and recyclable materials shall be handled to prevent contamination of materials from incompatible products and materials.
Clean contaminated materials prior to placing in collection containers. Use cleaning materials that are nonhazardous and biodegradable. Handle hazardous waste and hazardous materials in accordance with applicable regulations and coordinate with Section 01 57 20.00 10 ENVIRONMENTAL PROTECTION. Separate materials by one of the following methods:
1.9.1 Source Separated Method.
Waste products and materials that are recyclable shall be separated from trash and sorted as described below into appropriately marked separate containers and then transported to the respective recycling facility for further processing. Deliver materials in accordance with recycling or reuse facility requirements (e.g., free of dirt, adhesives, solvents, petroleum contamination, and other substances deleterious to the recycling process). Separate materials into the following category types as appropriate to the project waste and to the available recycling and reuse programs in the project area:
a. Land clearing debris.
b. Asphalt.
c. Concrete and masonry.
d. Metal (e.g., banding, stud trim, ductwork, piping, rebar, roofing, other trim, steel, iron, galvanized, stainless steel, aluminum, copper, zinc, lead brass, bronze).
(1) Ferrous.
(2) Non-ferrous.
e. Wood (nails and staples allowed).
f. Debris.
g. Glass (colored glass allowed).
h. Paper.
(1) Bond.
(2) Newsprint.
(3) Cardboard and paper packaging materials.
i. Plastic.
(1) Type 1: Polyethylene Terephthalate (PET, PETE).
(2) Type 2: High Density Polyethylene (HDPE).
(3) Type 3: Vinyl (Polyvinyl Chloride or PVC).
(4) Type 4: Low Density Polyethylene (LDPE).
(5) Type 5: Polypropylene (PP).
(6) Type 6: Polystyrene (PS).
(7) Type 7: Other. Use of this code indicates that the package in question is made with a resin other than the six listed above, or is made of more than one resin listed above, and used in a multi-layer combination.
j. Gypsum.
k. Non-hazardous paint and paint cans.
l. Carpet.
m. Ceiling tiles.
n. Insulation.
o. Beverage containers.
1.9.2 Co-Mingled Method
Waste products and recyclable materials shall be placed into a single container and then transported to a recycling facility where the recyclable materials are sorted and processed.
1.9.3 Other Methods
Other methods proposed by the Contractor may be used when approved by the Contracting Officer.
1.9.4 Compost
Compostable materials such as; land clearing debris, vegetation, and food scraps can be collected and composted at the JBLM composting facility. For information about composting contact the RCRA or Solid Waste and Recycling Program Manager at 253-966-3275 or 253-966-6452