About this file

AM#2

View the file

Other files for this federal contract opportunity

Other files attached to CLR039b Long Range Discrimination Radar Construction Package #2 ECF, Clear AFS, AK, newest first.
File Type Posted
01_50_00_02_00_Attachment_a.pdf PDF
01_19_30_02_29_Attachment_a.pdf PDF
01_19_30_02_29_Attachment_f.pdf PDF
01_19_30_02_29_Attachment_g.pdf PDF
05_40_00.02_00.pdf PDF
08_44_23.02_00.pdf PDF
G-100003E_Location_and_Vicinity_Map.pdf PDF
01_19_30.02_29.pdf PDF
01_11_00.02_00.pdf PDF
28_23_23.02_10.pdf PDF
09_29_00.02_00.pdf PDF
01_50_00.02_00.pdf PDF
Final_Presentation--Pre-Proposal_Site_Visit--20180515_Slide_5_Date_Corrections.pdf PDF
01_33_29.02_00.pdf PDF
Revised_E-1_Drawings.pdf PDF
T-100701E_TELECOM_CABLE_SCHEDULE_MISSION_SUPPORT_-_RACEWAYS.pdf PDF
34_71_13.02_16.pdf PDF
26_21_00.02_00.pdf PDF
Revised_E-9_Drawings.pdf PDF
Revised_M_Drawings.pdf PDF
Revised_TY_Drawings.pdf PDF
EG100101E_SITE_PLAN_-_GROUNDING.pdf PDF
Schedule_of_Drawings_AM__3_Sheet_2.pdf PDF
23_05_93.02_00.pdf PDF
01_45_35.02_00.pdf PDF
W911KB18R0006_AM_3.pdf PDF
Revised_T_Drawings.pdf PDF
Revised_Security_Drawings.pdf PDF
08_88_36.02_00.pdf PDF
G-100005E_Contractor_Laydown_Areas.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
Final_Presentation--Pre-Proposal_Site_Visit--20180515.pdf PDF
C_Drawing_revisions.pdf PDF
Revised_E_Drawings.pdf PDF
A_Drawing_Revisions.pdf PDF
28_20_00.02_00.pdf PDF
Revised_E-9_Drawings.pdf PDF
33_71_02.02_00.pdf PDF
EG100101E_-_SITE_PLAN_-_GROUNDING.pdf PDF
01_91_10.02_29.pdf PDF
28_23_23.02_10.pdf PDF
28_20_01.02_10.pdf PDF
Revised_Site_Plan_Drawings.pdf PDF
W911KB18R0006_AM_1.pdf PDF
JA_for_Vindictor_LRDR_ECF_Redacted.pdf PDF
JA_Edwards_EST3_fire_Panel_CP_2_ECF_Redacted.pdf PDF
CLR_LRDR_CP2_Rev2_RTA_Drawings_22x34.pdf PDF
CP2_RTA_SPECS_V4_CLR039_18-0410.pdf PDF
W911KB18R0006.pdf PDF
CP2_RTA_SPECS_V3_CLR039_18-0410.pdf PDF
Show all 50

CLR039b Long Range Discrimination Radar Construction Package #2 ECF, Clear AFS, AK has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W911KB-18-R-0006

CLR039 CP#2

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

PROJECT TITLE/LOCATION:CLR039b LRDR Entry Control Facility, Clear AFS, Alaska

PROPOSAL DUE DATE remains 22 June 2018, 2:00 PM Alaska Time. Proposals shall be submitted in accordance w ith Section 00 21 00 Paragraph 1.10 Proposal Submittals.

This Amendment provides changes to the solicitation as indicated on page 2 of this document.

YOU ARE REQUIRED TO ACKNOWLEDGE RECEIPT OF THIS AMENDMENT ON THE REVERSE SIDE OF THE STANDARD FORM 1442.

1. CONTRACT ID CODE PAGE OF PAGES

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Jun-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W911KB-18-R-0006

X 9B. DATED (SEE ITEM 11)

24-Apr-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Jun-2018

CODE

U.S. ARMY ENGINEER DISTRICT, AK

CEPOA-CT (W911KB)

PO BOX 6898

JBER AK 99506-0898

W911KB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

CLR039b

SUMMARY OF CHANGES

Amendment #2

The following revised documents are substituted for the superseded documents. The identifier “AM#02” appears before and after new and/or revised material and replacement pages are provided, except as noted:

Section 00 22 11 paragraph 6.1.2 (replacement page provided)

Specification Sections:

Specification Section 01 91 10.02 29. Electronic Security Systems have been removed risk management framework process (documentation and testing) which overlapped processes covered by Specification Sections 28 20 00.02 00, 28 20 01.02 10 and 28 23 23.02 10. See included replacement Specification Section 01 91 10.02 29.

Specification Section 08 88 36.02 00. Added controller and accessory requirement for dynamic glass control.

Specification Section 26 21 00.02 00. Provide exterior protective enclosure for near field antenna.

Specification Section 28 20 00.02 00. References to Section 01 91 10.02 29 for additional testing and documentation have been removed. See included replacement Specification Section 28 20 00.02 00.

Specification Section 28 20 01.02 10. References to Section 01 91 10.02 29 for other than network product listing have been removed. See included replacement Specification Section 28 20 01.02 10.

Specification Section 28 23 23.02 10. References to Section 01 91 10.02 29 for other than network product listing have been removed. See included replacement Specification Section 28 23 23.02 10.

Specification Section 33 71 02.02 00. Add shop drawing submittal requirement for pre-cast underground structures.

The following drawings are substituted for the superseded drawings:

Drawing G-100005E. Modify LRDR joint occupancy and schedules. See included replacement drawing.

Drawing C-100103E and C-100201E. Modify site plan to remove sidewalk connecting ECF with MCF.

See included replacement drawings.

New Drawing C-100105E. Modify site plan to show antenna bore sight pads and access roads plan north of site. Include communication and electrical handholes, manholes, and conduit routing from MCF to sheds located on each antenna pad. See new drawing.

Drawing C-100508E. Add details for electrical and communications handholes and manholes. See replacement drawing.

Drawing C-100702E. Remove control points for sidewalk between ECF and MCF. Add control points for antenna and access road grading, electrical and communications routing and structures. See replacement drawing.

Drawing E-100001E. Site legend corrected. See included replacement drawing.

Drawing E-100111E. Modify site lighting branch circuit sizes as noted and perimeter fence configuration. See included replacement drawing.

Drawing E-100113E. Modify site lighting branch circuit sizes as noted. See included replacement drawing.

Drawing E-100114E. Modify site lighting branch circuit sizes as noted and perimeter fence configuration. See included replacement drawing.

Drawing E-100121E. Added Near Field Antenna support. See included replacement drawing.

Drawing E-100122E. Added Near Field Antenna support. See included replacement drawing.

Drawing E-100123E. Revise heat trace requirements. See included replacement drawing.

Drawing E-100124E. Site plan drawing backgrounds updated to reflect correct perimeter fence configurations to avoid differing information from civil and security drawings. See included replacement drawing.

Drawing E-100401E. Revise Drawing Title to “ECF/MCF SERVICE INTERFACES AND HEAT TRACE” and add/revise heat trace installation details. See included replacement drawing.

Drawing E-100403E. Revised heat trace termination to future MF. See included replacement drawing.

Drawing E-100501E. Revised titles of details and collected related handholes and added electrical manholes and lighting junction boxes. See included replacement drawing.

Drawing E-100503E. Detail for handholes relocated to Sheet E-100501E. See included replacement drawing.

Drawing E-903111E. Added power for dynamic glass power. See included replacement drawing.

Drawing E-903501E. Detail 1, revised 2-pole circuit breaker designation. See included replacement drawing.

Drawing E-903502E, Detail 1. Revise Sprinkler Service heat trace circuit breaker designation on Control Diagram. See included replacement drawing.

Drawing E-903601E. Added Near Field Antenna power supply from MCF. See included replacement drawing.

Drawing E-903701E. Revised panel schedule to reflect other changes of this amendment. See included replacement drawing.

Drawing EG100101E. Added reference for Near Field Antenna and perimeter fence background correction.

Drawing T-100001E. Site legend corrected. See included replacement drawing.

Drawing T-100102E. Site plan drawing backgrounds updated to reflect correct perimeter fence configurations to avoid differing information from civil and security drawings. See included replacement drawing.

Drawing TY100001E. Modify Special Security Sequencing and Site legend corrected. See included replacement drawing.

Drawing TY100405E. Adjust the sheet match and continuation reference and perimeter fence configurations. See included replacement drawing.

The following documents/drawings are deleted:

NONE

The following documents are added:

NONE

Other:

Site Visit Brief and Sign-In Sheet provided.

Wage Rates have been updated from General Decision Number: AK180001 04/20/2018 AK1 to General Decision Number: AK160001 06/01/2018 AK1

5.2.1 Execution Concept Narrative -Proposed Contract Duration: The offeror’s proposed contract duration will become the contractually binding completion period and will replace the duration stated in FAR 52.211-10 upon contract award. The Government will evaluate the contract duration, as proposed by the Offeror under this Tab and in the Contract Line Item Schedule, not to exceed the maximum allowed duration stated in FAR 52.211-10. In assessing the reasonableness of the proposed contract duration, the Government may take into account how well the summary schedule and other technical submittals supports the proposed duration, as well as use other information, such as but not limited to independent judgment concerning logic, constraints and typical construction durations. Inconsistencies between documents will be considered a weakness. A proposed contract duration matching the maximum allowed contract duration is “acceptable”. Proposed contract duration shorter than the maximum allowed duration will receive additional rating consideration, provided it is realistic and deemed to be achievable. The Government will consider an unreasonably condensed contract duration, which places additional cost or schedule risk on the Government or which may create a risk of contract or performance failure, as a significant weakness. Synchronized Proposals (consistency amongst all documents) which incorporate innovative and realistic methods to mitigate schedule risk will be given additional consideration.

5.2.2 Summary Schedule: The length of the schedule must match the Offeror’s proposed contract duration. If it is shorter than the proposed contract duration, it offers no advantage to the Government because it is non-binding, only representing a preliminary planned schedule. The Government will evaluate the schedule to assess the strength of understanding of the project scope, restrictions which must be considered in the schedule e.g., permitting, long lead items, etc. The Government will evaluate the Offeror's capability to schedule the complete project within the proposed contract duration and the realism of the schedule. A schedule that offers advantage(s) to the Government over one that merely indicates an adequate understanding of the scope, restrictions, major milestones and general understanding of the various events that can affect start and completion of construction will receive additional consideration.

6.0 VOLUME 1, TAB D – FACTOR 4 - ORGANIZATION

6.1 SUBMISSION REQUIREMENTS:

6.1.1 Provide a project-specific narrative that describes the offeror’s organization and the items below. Limit the information to three (3) pages or less and individually address each paragraph below. Provide an organizational chart for key personal and key subcontractors including lines of authority. The page limit does not include organizational chart or resumes submitted for key personnel.

6.1.1 Organization: Describe the prime contractor proposed to participate in this project, their resources and how their resources will be utilized, their roles and responsibilities and any contractual arrangements that have been established.

Include an organizational chart with position title, lines of authority, and job location for the following key personnel as a minimum: project manager, superintendent, quality control system manager, electrical/IESS quality control, mechanical quality control, civil quality control, control specialist security specialist, and commissioning manager.

6.1.2 Key Personnel Capabilities and Experience: Provide a brief resume (not included in the two page count limit above) using the Key Personnel Resume form (Attachment 4) at the end of this section for project manager, superintendent, quality control system manager, electrical/IESS quality control, and commissioning manager. Key personnel shall at a minimum five years’ experience AM#2… in addition to the requirements list in technical specification 01 45 04.02 29 similar to the solicitation in scope, complexity and magnitude...AM#2

General Decision Number: AK180001 06/01/2018 AK1

Superseded General Decision Number: AK20170001

State: Alaska

Construction Types: Building and Heavy

Counties: Alaska Statewide.

BUILDING AND HEAVY CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018 1 01/12/2018 2 02/09/2018 3 03/30/2018 4 04/06/2018 5 04/20/2018 6 04/27/2018 7 06/01/2018

ASBE0097-001 01/01/2018

Rates Fringes

Asbestos Workers/Insulator (includes application of all insulating materials protective coverings, coatings and finishings to all types of mechanical systems).........................$ 38.68 21.57

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal scrapping, vacuming, bagging, and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 37.38 19.55

BOIL0502-002 08/01/2016

Rates Fringes

BOILERMAKER......................$ 44.26 28.41

BRAK0001-002 07/01/2017

Rates Fringes

Bricklayer, Blocklayer, Stonemason, Marble Mason, Tile Setter, Terrazzo Worker.....$ 40.81 19.19 Tile & Terrazzo Finisher.........$ 34.79 19.19

CARP1501-001 09/01/2016

Rates Fringes

MILLWRIGHT.......................$ 36.74 22.99

CARP2520-003 09/01/2017

Rates Fringes

Diver Stand-by....................$ 42.65 25.16 Tender......................$ 41.65 25.16 Working.....................$ 82.45 25.16 Piledriver Piledriver; Skiff Operator and Rigger..................$ 38.34 25.16 Sheet Stabber...............$ 38.34 25.16

Welder......................$ 43.90 25.16

DEPTH PAY PREMIUM FOR DIVERS BELOW WATER SURFACE:

50-100 feet $1.00 per foot 101 feet and deeper $2.00 per foot

ENCLOSURE PAY PREMIUM WITH NO VERTICAL ASCENT:

5-50 FEET $1.00 PER FOOT/DAY

51-100 FEET $2.00 PER FOOT/DAY

101 FEET AND ABOVE $3.00 PER FOOT/DAY

SATURATION DIVING:

The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

CARP4059-001 09/01/2016

Rates Fringes

CARPENTER

Including Lather and Drywall Hanging.............$ 38.34 25.04

ELEC1547-004 04/01/2018

Rates Fringes

CABLE SPLICER....................$ 39.82 3%+$26.44

ELECTRICIAN......................$ 39.49 3%+$26.69

ELEC1547-005 04/01/2018

Line Construction

Rates Fringes

CABLE SPLICER....................$ 52.57 3%+30.81

Linemen (Including Equipment Operators, Technician)...........$ 50.52 3%+30.81 Powderman........................$ 48.52 3%+30.81

TREE TRIMMER.....................$ 36.21 3%+24.19

ELEV0019-002 01/01/2018

Rates Fringes

ELEVATOR MECHANIC................$ 55.45 32.645+a+b

FOOTNOTE: a. Employer contributes 8% of the basic hourly rate for over 5 year's service and 6% of the basic hourly rate for 6 months to 5 years' of service as vacation paid credit. b. Eight paid holidays:

New Year's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day; Friday after Thanksgiving, and Christmas Day

ENGI0302-002 04/01/2018

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 40.28 23.05

GROUP 1A....................$ 42.04 23.05

GROUP 2.....................$ 39.51 23.05

GROUP 3.....................$ 38.79 23.05

GROUP 4.....................$ 32.58 23.05

TUNNEL WORK

GROUP 1....................$ 44.31 23.05

GROUP 1A...................$ 46.24 23.05

GROUP 2....................$ 43.46 23.05

GROUP 3....................$ 42.67 23.05

GROUP 4....................$ 35.84 23.05

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Roller: Breakdown, Intermediate, and Finish; Back Filler; Barrier Machine (Zipper); Beltcrete with power pack and similar conveyors; Bending Machine;

Boat Coxwains; Bulldozers; Cableways, Highlines and Cablecars; Cleaning Machine; Coating Machine; Concrete Hydro Blaster; Cranes-45 tons and under or 150 foot boom and under (including jib and attachments): (a) Hydralifts or Transporters, all track or truck type,(b) Derricks;

Crushers; Deck Winches-Double Drum; Ditching or Trenching Machine (16 inch or over); Drilling Machines, core, cable, rotary and exploration; Finishing Machine Operator, Concrete Paving, Laser Screed, Sidewalk, Curb and Gutter Machine; Helicopters; Hover Craft, Flex Craft, Loadmaster, Air Cushion, All Terrain Vehicle, Rollagon, Bargecable, Nodwell, and Snow Cat; Hydro Ax: Feller Buncher and similar; Loaders (2 1/2 yards through 5 yards, including all attachments): Forklifts with telescopic boom and swing attachment, Overhead and front end, 2 1/2 yards through 5 yards, Loaders with forks or pipe clamps; Loaders, elevating belt type, Euclid and similar types; Mechanics, Bodyman; Micro Tunneling Machine; Mixers: Mobile type w/hoist combination; Motor Patrol Grader; Mucking Machines:

Mole, Tunnel Drill, Horizontal/Directional Drill Operator, and/or Shield; Operator on Dredges; Piledriver Engineers, L. B. Foster, Puller or similar Paving Breaker; Power Plant, Turbine Operator, 200 k.w. and over (power plants or combination of power units over 300 k.w.); Scrapers-through 40 yards; Service Oiler/Service Engineer; Sidebooms-under 45 tons; Shot Blast Machine; Shovels, Backhoes, Excavators with all attachments, and Gradealls (3 yards and under), Spreaders, Blaw Knox, Cedarapids, Barber Greene, Slurry Machine; Sub-grader (Gurries, Reclaimer, and similar types); Tack tractor; Truck mounted Concrete Pumps, Conveyor, Creter; Water Kote Machine; Unlicensed off road hauler

GROUP 1A: Camera/Tool/Video Operator (Slipline), Cranes-over 45 tons or 150 foot (including jib and attachments): (a) Clamshells and Draglines (over 3 yards),

(b) Tower cranes; Licensed Water/Waste Water Treatment Operator; Loaders over 5 yds.; Certified Welder, Electrical Mechanic, Camp Maintenance Engineer, Mechanic (over 10,000 hours); Motor Patrol Grader, Dozer, Grade Tractor, Roto-mill/Profiler (finish: when finishing to final grade and/or to hubs, or for asphalt); Power Plants: 1000 k.w.

and over; Quad; Screed; Shovels, Backhoes, Excavators with all attachments (over 3 yards), Sidebooms over 45 tons;

Slip Form Paver, C.M.I. and similar types; Scrapers over 40 yards;

GROUP 2: Boiler-fireman; Cement Hog and Concrete Pump Operator; Conveyors (except as listed in group 1); Hoist on steel erection; Towermobiles and Air Tuggers;

Horizontal/Directional Drill Locator;Licensed Grade Technician; Loaders, (i.e., Elevating Grader and Material Transfer Vehicle); Locomotives: rod and geared engines;

Mixers; Screening, Washing Plant; Sideboom (cradling rock drill regardless of size); Skidder; Trencing Machine under 16 inches; Waste/ Waste Water Treatment Operator.

GROUP 3: "A" Frame Trucks, Deck Winches: single power drum;

Bombardier (tack or tow rig); Boring Machine; Brooms-power;

Bump Cutter; Compressor; Farm tractor; Forklift, industrial type; Gin Truck or Winch Truck with poles when used for hoisting; Grade Checker and Stake Hopper; Hoist, Air Tuggers, Elevators; Loaders: (a) Elevating-Athey, Barber Green and similar types (b) Forklifts or Lumber Carrier (on construction job site) (c) Forklifts with Tower (d) Overhead and Front-end, under 2 1/2 yds. Locomotives:Dinkey (air, steam, gas and electric) Speeders; Mechanics (light duty); Oil, Blower Distribution; Post Hole Diggers, mechanical; Pot Fireman (power agitated); Power Plant, Turbine Operator, under 200 k.w.; Pumps-water; Roller-other than Plantmix; Saws, concrete; Skid Steer with all attachments; Straightening Machine; Tow Tractor

GROUP 4: Rig Oiler/Crane Assistant Engineer;Parts and Equipment Coordinator; Swamper (on trenching machines or shovel type equipment); Spotter; Steam Cleaner; Drill Helper.

FOOTNOTE: Groups 1-4 receive 10% premium while performing tunnel or underground work. Rig Oiler/Crane Assistant Engineer shall be required on cranes over 85 tons or over 100 feet of boom.

IRON0751-003 07/01/2017

Rates Fringes

Ironworkers:

BRIDGE, STRUCTURAL,

ORNAMENTAL, REINFORCING

MACHINERY MOVER, RIGGER,

SHEETER, STAGE RIGGER,

BENDER OPERATOR.............$ 37.25 30.43

FENCE, BARRIER INSTALLER....$ 33.75 30.08

GUARDRAIL INSTALLERS........$ 34.75 30.08

GUARDRAIL LAYOUT MAN........$ 34.49 30.08

HELICOPTER, TOWER...........$ 38.25 30.43

* LABO0341-005 04/01/2018

Rates Fringes

Laborers: South of the 63rd Parallel & West of Longitude 138 Degrees

GROUP 1.....................$ 30.26 27.01

GROUP 2.....................$ 31.26 27.01

GROUP 3.....................$ 32.16 27.01

GROUP 3A....................$ 35.44 27.01

GROUP 3B....................$ 39.98 24.30

GROUP 4.....................$ 19.83 27.01

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 33.29 27.01

GROUP 2....................$ 34.39 27.01

GROUP 3....................$ 35.38 27.01

GROUP 3A...................$ 38.98 27.01

GROUP 3B...................$ 42.88 24.30

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber

Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

LABO0942-001 04/01/2018

Rates Fringes

Laborers: North of the 63rd Parallel & East of Longitude 138 Degrees

GROUP 1.....................$ 30.26 27.21

GROUP 2.....................$ 31.26 27.21

GROUP 3.....................$ 32.16 27.21

GROUP 3A....................$ 35.44 27.21

GROUP 3B....................$ 38.98 24.50

GROUP 4.....................$ 19.83 27.21

TUNNELS, SHAFTS, AND RAISES

GROUP 1....................$ 33.29 27.21

GROUP 2....................$ 34.39 27.21

GROUP 3....................$ 35.38 27.21

GROUP 3A...................$ 38.98 27.21

GROUP 3B...................$ 42.88 24.50

LABORERS CLASSIFICATIONS

GROUP 1: Asphalt Workers (shovelman, plant crew); Brush Cutters; Camp Maintenance Laborer; Carpenter Tenders; Choke Setters, Hook Tender, Rigger, Signalman; Concrete Laborer(curb and gutter, chute handler, grouting, curing, screeding); Crusher Plant Laborer; Demolition Laborer;

Ditch Diggers; Dump Man; Environmental Laborer (asbestos (limited to nonmechanical systems), hazardous and toxic waste, oil spill); Fence Installer; Fire Watch Laborer;

Flagman; Form Strippers; General Laborer; Guardrail Laborer, Bridge Rail Installers; Hydro-Seeder Nozzleman;

Laborers (building); Landscape or Planter; Laying of Decorative Block (retaining walls, flowered decorative block 4 feet and below); Material Handlers; Pneumatic or Power Tools; Portable or Chemical Toilet Serviceman; Pump Man or Mixer Man; Railroad Track Laborer; Sandblast, Pot Tender; Saw Tenders; Scaffold Building and Erecting; Slurry Work; Stake Hopper; Steam Point or Water Jet Operator;

Steam Cleaner Operator; Tank Cleaning; Utiliwalk, Utilidor Laborer and Conduit Installer; Watchman (construction projects); Window Cleaner

GROUP 2: Burning and Cutting Torch; Cement or Lime Dumper or Handler (sack or bulk); Choker Splicer; Chucktender (wagon, airtrack and hydraulic drills); Concrete Laborers (power buggy, concrete saws, pumpcrete nozzleman, vibratorman);

Culvert Pipe Laborer; Cured in place Pipelayer;

Environmental Laborer (marine work, oil spill skimmer operator, small boat operator); Foam Gun or Foam Machine Operator; Green Cutter (dam work); Gunnite Operator; Hod Carriers; Jackhammer or Pavement Breakers (more than 45 pounds);Laying of Decorative Block (retaining walls, flowered decorative block above 4 feet); Mason Tender and Mud Mixer (sewer work); Pilot Car; Plasterer, Bricklayer and Cement Finisher Tenders; Power Saw Operator; Railroad Switch Layout Laborer; Sandblaster; Sewer Caulkers; Sewer Plant Maintenance Man; Thermal Plastic Applicator; Timber Faller, chain saw operator, filer; Timberman

GROUP 3: Alarm Installer; Bit Grinder; Guardrail Machine Operator; High Rigger and tree topper; High Scaler;

Multiplate; Slurry Seal Squeegee Man

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

GROUP 4: Final Building Cleanup

TUNNELS, SHAFTS, AND RAISES CLASSIFICATIONS

GROUP 1: Brakeman; Muckers; Nippers; Topman and Bull Gang;

Tunnel Track Laborer

GROUP 2: Burning and Cutting Torch; Concrete Laborers;

Jackhammers; Nozzleman, Pumpcrete or Shotcrete.

GROUP 3: Miner; Retimberman

GROUP 3A: Asphalt Raker, Asphalt Belly dump lay down; Drill Doctor (in the field); Drillers (including, but not limited to, wagon drills, air track drills; hydraulic drills);

Powderman; Pioneer Drilling and Drilling Off Tugger (all type drills); Pipelayers.

GROUP 3B: Grade checker (setting or transfering of grade marks, line and grade)

Tunnel shaft and raise rates only apply to workers regularly employed inside a tunnel portal or shaft collar.

* PAIN1959-001 12/01/2017

NORTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

BRUSH/ROLLER PAINT OR WALL

COVERER.....................$ 32.19 21.09

TAPING, TEXTURING,

STRUCTURAL PAINTING,

SANDBLASTING, POT TENDER,

FINISH METAL, SPRAY,

BUFFER OPERATOR, RADON

MITIGATION, LEAD BASED

PAINT ABATEMENT, HAZARDOUS

MATERIAL HANDLER............$ 32.71 21.09

* PAIN1959-002 12/01/2017

SOUTH OF THE 63RD PARALLEL

Rates Fringes

PAINTER

Brush, Roller, Sign, Paper and Vinyl, Swing Stage, Hand Taper/Drywall, Structural Steel, and Commercial Spray............$ 32.19 21.09 Machine Taper/Drywall.......$ 32.71 21.09 Spray-Sand/Blast, Epoxy and Tar Applicator..........$ 32.71 20.09

PAIN1959-003 01/01/2018

NORTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 39.38 23.39

PAIN1959-004 07/01/2017

Rates Fringes

FLOOR LAYER: Carpet.............$ 29.23 13.96

PAIN1959-006 01/01/2018

SOUTH OF THE 63RD PARALLEL

Rates Fringes

GLAZIER..........................$ 39.63 22.42

PLAS0867-001 02/01/2016

Rates Fringes

PLASTERER

North of the 63rd parallel..$ 37.25 20.41 South of the 63rd parallel..$ 37.00 20.41

PLAS0867-004 02/01/2016

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

North of the 63rd parallel..$ 37.25 20.41 South of the 63rd parallel..$ 37.00 20.41

PLUM0262-002 01/01/2017

East of the 141st Meridian

Rates Fringes

Plumber; Steamfitter.............$ 38.02 26.72

PLUM0367-002 07/01/2017

South of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 39.00 23.80

PLUM0375-002 07/01/2017

North of the 63rd Parallel

Rates Fringes

Plumber; Steamfitter.............$ 40.91 25.40

PLUM0669-002 04/01/2017

Rates Fringes

SPRINKLER FITTER.................$ 46.00 23.29

ROOF0189-006 04/01/2018

Rates Fringes

ROOFER...........................$ 44.62 15.50

SHEE0023-003 07/01/2017

South of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 42.00 24.82

SHEE0023-004 07/01/2017

North of the 63rd Parallel

Rates Fringes

SHEET METAL WORKER...............$ 47.74 23.48

TEAM0959-003 03/01/2018

Rates Fringes

TRUCK DRIVER

GROUP 1.....................$ 39.59 23.62

GROUP 1A....................$ 40.86 23.62

GROUP 2.....................$ 38.33 23.62

GROUP 3.....................$ 37.51 23.62

GROUP 4.....................$ 36.93 23.62

GROUP 5.....................$ 36.17 23.62

GROUP 1: Semi with Double Box Mixer; Dump Trucks (including rockbuggy and trucks with pups) over 40 yards up to and including 60 yards; Deltas, Commanders, Rollogans and similar equipment when pulling sleds, trailers or similar equipment; Boat Coxswain; Lowboys including attached trailers and jeeps, up to and including 12 axles; Ready-mix over 12 yards up to and including 15 yards); Water Wagon (250 Bbls and above); Tireman, Heavy Duty/Fueler

GROUP 1A: Dump Trucks (including Rockbuggy and Trucks with pups) over 60 yards up to and including 100 yards; Jeeps

(driver under load)

GROUP 2: Turn-O-Wagon or DW-10 not self-loading; All Deltas, Commanders, Rollogans, and similar equipment; Mechanics;

Dump Trucks (including Rockbuggy and Trucks with pups) over 20 yards up to and including 40 yards; Lowboys including attached trailers and jeeps up to and including 8 axles;

Super vac truck/cacasco truck/heat stress truck; Ready-mix over 7 yards up to and including 12 yards; Partsman;

Stringing Truck

GROUP 3: Dump Trucks (including Rockbuggy and Trucks with pups) over 10 yards up to and including 20 yards; batch trucks 8 yards and up; Oil distributor drivers; Oil Distributor Drivers; Trucks/Jeeps (push or pull); Traffic Control Technician

GROUP 4: Buggymobile; Semi or Truck and trailer; Dumpster;

Tireman (light duty); Dump Trucks (including Rockbuggy and Truck with pups) up to and including 10 yards; Track Truck Equipment; Grease Truck; Flat Beds, dual rear axle; Hyster Operators (handling bulk aggregate); Lumber Carrier; Water Wagon, semi; Water Truck, dual axle; Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame manufactured rating over 5 tons; Bull Lifts and Fork Lifts with Power Boom and Swing attachments, over 5 tons; Front End Loader with Forks; Bus Operator over 30 passengers; All Terrain Vehicles; Boom Truck/Knuckle Truck over 5 tons; Foam Distributor Truck/dual axle; Hydro-seeders, dual axle;

Vacuum Trucks, Truck Vacuum Sweepers; Loadmaster (air and water); Air Cushion or similar type vehicle; Fire Truck/Ambulance Driver; Combination Truck-fuel and grease;

Compactor (when pulled by rubber tired equipment); Rigger (air/water/oilfield); Ready Mix, up to and including 7 yards;

GROUP 5: Gravel Spreader Box Operator on Truck; Flat Beds, single rear axle; Boom Truck/Knuckle Truck up to and including 5 tons; Pickups (Pilot Cars and all light duty vehicles); Water Wagon (Below 250 Bbls); Gin Pole Truck, Winch Truck, Wrecker, Truck Mounted "A" Frame, manufactured rating 5 tons and under; Bull Lifts and Fork Lifts (fork lifts with power broom and swing attachments up to and including 5 tons); Buffer Truck; Tack Truck; Farm type Rubber Tired Tractor (when material handling or pulling wagons on a construction project); Foam Distributor, single axle; Hydro-Seeders, single axle; Team Drivers (horses, mules and similar equipment); Fuel Handler (station/bulk attendant); Batch Truck, up to and including 7 yards;

Gear/Supply Truck; Bus Operator, Up to 30 Passengers;

Rigger/Swamper

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION