01_45_35.02_00.pdf
PDF 34 KB Posted
- Attached to
- CLR039b Long Range Discrimination Radar Construction Package #2 ECF, Clear AFS, AK Federal contract opportunity
- Solicitation number
- W911KB18R0006
About this file
01 45 35.02 00
View the file
Other files for this federal contract opportunity
Show all 50
CLR039b Long Range Discrimination Radar Construction Package #2 ECF, Clear AFS, AK has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CP#2 Long Range Discrimination Radar (LRDR) CLR039b LRDR Complex Security - Clear AFS, Alaska AM#3
SECTION 01 45 35.02 00
SPECIAL INSPECTIONS
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 7 (2010; Errata 2011; Supp 1 2013) Minimum Design Loads for Buildings and Other Structures
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2012) International Building Code
1.2 GENERAL REQUIREMENTS
Perform Special Inspections in accordance with the Statement of Special Inspections, Schedule of Special Inspections and Chapter 17 of ICC IBC .
The Statement of Special Inspections and Schedule of Special Inspections are included as indicated on the drawings and in the technical specifications. Special Inspections are to be performed by an independent third party and are intended to ensure that the work of the prime contractor is in accordance with the Contract Documents and applicable building codes. Special inspections do not take the place of the three phases of control inspections performed by the Contractor's QC Manager or any testing and inspections required by other sections of the specifications.
The Government may perform structural observation for general conformance to the approved construction documents at any time during construction.
Structural observation does not include or waive the responsibility for the special inspection required by Chapter 17 of the ICC IBC .
1.3 DEFINITIONS
1.3.1 Continuous Special Inspections
Continuous Special Inspections is the constant monitoring of specific tasks by a special inspector. These inspections must be carried out continuously over the duration of the particular tasks.
1.3.2 Periodic Special Inspections
Periodic Special Inspections is Special Inspections by the special inspector who is intermittently present where the work to be inspected has been or is being performed.
SECTION 01 45 35.02 00 Page 1
1.3.3 Perform
Perform these Special Inspections tasks for each welded joint or member.
1.3.4 Observe
Observe these Special Inspections items on a random daily basis.
Operations need not be delayed pending these inspections.
1.3.5 Special Inspector (SI)
A qualified person retained by the contractor and approved by the Contracting Officer as having the competence necessary to inspect a particular type of construction requiring Special Inspections. The SI must be an independent third party hired directly by the Prime Contractor.
1.3.6 Associate Special Inspector (ASI)
A qualified person who assists the SI in performing Special Inspections but must perform inspection under the direct supervision of the SI and cannot perform inspections without the SI on site.
1.3.7 Third Party
A third party inspector must not be company employee of the Contractor or any Sub-Contractor performing the work to be inspected.
1.3.8 Special Inspector of Record (SIOR)
A licensed engineer in responsible charge of supervision all special inspectors for the project and approved by the Contracting officer. The SIOR must be an independent third party hired directly by the Prime Contractor.
1.3.9 Contracting Officer
The Government official having overall authority for administrative contracting actions. Certain contracting actions may be delegated to the Contracting Officer's Representative (COR).
1.3.10 Contractor's Quality Control (QC) Manager
An individual retained by the prime contractor and qualified in accordance with the Section 01 45 04.02 29 CONTRACTOR QUALITY CONTROL having the overall responsibility for the contractor's QC organization.
1.3.11 Designer of Record (DOR)
A registered design professional contracted by the Government as an A/E responsible for the overall design and review of submittal documents prepared by others. The DOR is registered or licensed to practice their respective design profession as defined by the statutory requirements of the professional registration laws in state in which the design professional works. The DOR is also referred to as the Engineer of Record (EOR) in design code documents.
1.3.12 Statement of Special Inspections (SSI)
A document developed by the DOR identifying the material, systems, SECTION 01 45 35.02 00 Page 2 components and work required to have Special Inspections.
1.3.13 Schedule of Special Inspections
A schedule which lists each of the required Special Inspections, the extent to which each Special Inspections is to be performed, and the required frequency for each in accordance with ICC IBC Chapter 17.
1.3.14 Designated Seismic System
Those nonstructural components that require design in accordance with ASCE 7 Chapter 13 and for which the component importance factor, Ip, is greater than 1.0. This designation applies to systems that are required to be operational following the Design Earthquake for RC I - IV structures. AM#3...deleted text... ...AM#3
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, the "LD" designation following the "G" identifies that a Government-provided LEED Coordinator will review the submittal. Other designations following the "G" designation identify the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29.02 00 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00.02 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
SIOR Letter of Acceptance; G Special Inspections Project Manual; G Special Inspections Agency's Written Practices NDT Procedures and Equipment Calibration Records
SD-06 Test Reports
Special Inspections Daily Reports Special Inspections Biweekly Reports
SD-07 Certificates
Fabrication Plant AC472 Accreditation Steel Joist Institute Membership Precast Concrete Institute (PCI) Certified Plant Certificate of Compliance Special Inspector of Record Qualifications; G Special Inspector Qualifications; G Qualification Records for NDT technicians
SD-11 Closeout Submittals
Comprehensive Final Report of Special Inspections; G
1.5 SPECIAL INSPECTOR QUALIFICATIONS
Submit qualifications for each special inspector and the special inspector of record.
SECTION 01 45 35.02 00 Page 3
Certifying Associations
AABC Associated Air Balance Council
ACI American Concrete Institute
AWCI Association of the Wall and Ceiling Industry
AWS American Welding Society
FM Factory Mutual
ICC International Code Council
NDT Nondestructive Testing
NICET National Institute for Certification in Engineering Technologies
PCI Precast/Prestressed Concrete Institute
UL Underwriters Laboratories
1.5.1 Steel Construction and High Strength Bolting
1.5.1.1 Special Inspector
a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or
b. Registered Professional Engineer with related experience
1.5.1.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.2 Welding Structural Steel
1.5.2.1 Special Inspector
a. ICC Structural Welding Special Inspector certificate with one year of related experience, or
b. AWS Certified Welding Inspector
1.5.2.2 Associate Special Inspector
AWS Certified Associate Welding Inspector
1.5.3 Nondestructive Testing of Welds
1.5.3.1 Special Inspector
NDT Level III Certificate
SECTION 01 45 35.02 00 Page 4
1.5.3.2 Associate Special Inspector
NDT Level II Certificate plus one year of related experience
1.5.4 Cold Formed Steel Framing
1.5.4.1 Special Inspector
a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or
b. ICC Commercial Building Inspector with one year of experience, or
c. ICC Residential Building Inspector with one year of experience, or
d. Registered Professional Engineer with related experience
1.5.4.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.5 Concrete Construction
1.5.5.1 Special Inspector
a. ICC Reinforced Concrete Special Inspector Certificate with one year of related experience, or
b. ACI Concrete Construction Special Inspector, or
c. NICET Concrete Technician Level III Certificate in Construction Materials Testing, or
d. Registered Professional Engineer with related experience
1.5.5.2 Associate Special Inspector
a. ACI Concrete Construction Special Inspector in Training, or
b. Engineer-In-Training with one year of related experience
1.5.6 Prestressed Concrete Construction
1.5.6.1 Special Inspector
a. ICC Pre-stressed Special Inspector Certificate with one year of related experience, or
b. PCI Quality Control Technician/ Inspector Level II Certificate with one year of related experience, or
c. Registered Professional Engineer with related experience
1.5.6.2 Associate Special Inspector
a. PCI Quality Control Technician/ Inspector Level I Certificate with one year of related experience, or
b. Engineer-In-Training with one year of related experience
SECTION 01 45 35.02 00 Page 5
1.5.7 Masonry Construction
1.5.7.1 Special Inspector
a. ICC Structural Masonry Special Inspector Certificate with one year of related experience, or
b. Registered Professional Engineer with related experience
1.5.7.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.8 Verification of Site Soil Condition, Fill Placement and Load-Bearing Requirements
1.5.8.1 Special Inspector
a. ICC Soils Special Inspector Certificate with one year of related experience, or
b. NICET Soils Technician Level II Certificate in Construction Material Testing, or
c. NICET Geotechnical Engineering Technician Level II Construction or Generalist Certificate, or
d. Geologist-In-Training with one year of related experience, or
e. Registered Professional Engineer with related experience
1.5.8.2 Associate Special Inspector
a. NICET Soils Technician Level I Certificate in Construction Material Testing with one year of related experience, or
b. NICET Geotechnical Engineering Technician Level I Construction or Generalist Certificate with one year of related experience, or
c. Engineer-In-Training with one year of related experience
1.5.9 Deep Foundations
1.5.9.1 Special Inspector
a. NICET Soils Technician Level II Certificate in Construction Material Testing, or
b. NICET Geotechnical Engineering Technician Level II Construction or Generalist Certificate, or
c. Geologist-In-Training with one year of related experience, or
d. Registered Professional Engineer with related experience
1.5.9.2 Associate Special Inspector
a. NICET Soils Technician Level I Certificate in Construction Material
SECTION 01 45 35.02 00 Page 6
Testing with one year of related experience, or
b. NICET Geotechnical Engineering Technician Level I Construction or Generalist Certificate with one year of related experience, or
c. Engineer-In-Training with one year of related experience
1.5.10 Exterior Insulation and Finish System (EIFS)
1.5.10.1 Special Inspector
a. AWCI EIFS Inspector Certificate, or
b. Exterior Design Institute Certificate, or
c. Registered Professional Engineer with related experience
1.5.10.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.11 Fire-Resistant Penetrations and Joints
1.5.11.1 Special Inspector
a. Passed the UL Firestop Exam with one year of related experience, or
b. Passed the FM Firestop Exam with one year of related experience, or
c. Registered Professional Engineer with related experience
1.5.11.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.12 Smoke Control
1.5.12.1 Special Inspector
a. AABC Technician Certification with one year of related experience, or
b. Registered Professional Engineer with related experience
1.5.12.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.13 Special Inspector of Record (SIOR)
Registered Professional Engineer
PART 2 PRODUCTS
2.1 FABRICATOR SPECIAL INSPECTIONS
Special Inspections of fabricator's work performed in the fabricator's shop is required to be inspected in accordance with the Statement of Special Inspections and the Schedule of Special Inspections unless the fabricator is certified by the approved agency to perform such work
SECTION 01 45 35.02 00 Page 7 without Special Inspections. Submit the following certifications to the Contracting Officer for information to allow work performed in the fabricator's shop to not be subjected to Special Inspections.
American Institute of Steel Construction (AISC) Certified Fabrication Plant, Category STD.
International Accreditation Service, AC472 Accreditation Steel Joist Institute Membership Precast Concrete Institute (PCI) Certified Plant, Group C
At the completion of fabrication, submit a certificate of compliance, to be included with the comprehensive final report of Special Inspections, stating that the materials supplied and work performed by the fabricator are in accordance the construction documents.
PART 3 EXECUTION
3.1 RESPONSIBILITIES
3.1.1 Special Inspector of Record
a. Supervise all Special Inspectors required by the contract documents and the IBC.
b. Submit a SIOR Letter of Acceptance to the Contracting Officer attesting to acceptance of the duties of SIOR, signed and sealed by the SIOR.
c. Verify the qualifications of all of the Special Inspectors.
d. Verify the qualifications of fabricators.
e. Submit Special Inspections agency's written practices for the monitoring and control of the agency's operations to include the following:
(1) The agency's procedures for the selection and administration of inspection personnel, describing the training, experience and examination requirements for qualifications and certification of inspection personnel.
(2) The agency's inspection procedures, including general inspection, material controls, and visual welding inspection.
f. Submit qualification records for nondestructive testing (NDT) technicians designated for the project.
g. Submit NDT procedures and equipment calibration records for NDT to be performed and equipment to be used for the project.
h. Prepare a Special Inspections Project Manual, which will cover the following:
(1) Roles and responsibilities of the following individuals during Special Inspections: SIOR, SI, General Contractor, Subcontractors, QC Manager, and DOR.
(2) Organizational chart and/or communication plan, indicating lines of communication.
SECTION 01 45 35.02 00 Page 8
(3) Contractor's internal plan for scheduling inspections. Address items such as timeliness of inspection requests, who to contact for inspection requests, and availability of alternate inspectors.
(4) Indicate the government reporting procedures.
(5) Propose forms or templates to be used by SI and SIOR to document inspections.
(6) Indicate procedures for tracking nonconforming work and verification that corrective work is complete.
(7) Indicate how the SIOR and/or SI will participate in weekly QC meetings.
(8) Indicate how Special Inspections of shop fabricated items will be handled when the fabricator's shop is not certified per paragraph
FABRICATOR SPECIAL INSPECTIONS.
(9) Include a section in the manual that covers each specific item requiring Special Inspections that is indicated on the Schedule of Special Inspections. Provide names and qualifications of each special inspector who will be performing the Special Inspections for each specific item. Provide detail on how the Special Inspections are to be carried out for each item so that the expectations are clear for the General Contractor and the Subcontractor performing the work.
Make a copy of the Special Inspections Project Manual available on the job site during construction. Submit a copy of the Special Inspections Project Manual for approval.
i. Attend coordination and mutual understanding meeting where the information in the Special Inspections Project Manual will be reviewed to verify that all parties have a clear understanding of the Special Inspections provisions and the individual duties and responsibilities of each party.
j. Maintain a 3- ring binder for the Special Inspector's daily and biweekly reports and the Special Inspections Project Manual. This file must be located in a conspicuous place in the project trailer/office to allow review by the Contracting Officer and the DOR.
k. Submit a copy of the Special Inspector's daily reports to the QC Manager.
l. Discrepancies that are observed during Special Inspections must be reported to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.
m. Submit a biweekly Special Inspections report until all work requiring Special Inspections is complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:
(1) A brief summary of the work performed during the reporting time frame.
SECTION 01 45 35.02 00 Page 9
(2) Changes and/or discrepancies with the drawings, specifications and mechanical or electrical component certification, that were observed during the reporting period.
(3) Discrepancies which were resolved or corrected.
(4) A list of nonconforming items requiring resolution.
(5) All applicable test results including nondestructive testing reports.
n. On the first day of each month, furnish to the Government five copies of the combined progress reports of the special inspector's observations, listing all special inspections of construction or reviews of testing performed during that month, noting all uncorrected deficiencies, and describing the corrections made both to these deficiencies and to previously reported deficiencies. The report must be signed and dated and bear the seal of the SIOR.
o. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project and corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and bear the seal of the SIOR.
3.1.2 Quality Control Manager
a. Supervise all Special Inspectors required by the contract documents and the IBC.
b. Verify the qualifications of all of the Special Inspectors.
c. Verify the qualifications of fabricators.
d. Maintain a 3-ring binder for the Special Inspector's daily and biweekly reports. This file must be located in a conspicuous place in the project trailer/office to allow review by the Contracting Officer and the DOR.
e. Maintain a rework items list that includes discrepancies noted on the Special Inspectors daily report.
3.1.3 Special Inspectors
a. Inspect all elements of the project for which the special inspector is qualified to inspect and are identified in the Schedule of Special Inspections.
b. Attend preparatory phase meetings related to the Definable Feature of Work (DFOW) for which the special inspector is qualified to inspect.
c. Submit Special Inspections agency's written practices for the monitoring and control of the agency's operations to include the following:
(1) The agency's procedures for the selection and administration of inspection personnel, describing the training, experience and examination requirements for qualifications and certification of
SECTION 01 45 35.02 00 Page 10 inspection personnel.
(2) The agency's inspection procedures, including general inspection, material controls, and visual welding inspection.
d. Submit qualification records for nondestructive testing (NDT) technicians designated for the project.
e. Submit NDT procedures and equipment calibration records for NDT to be performed and equipment to be used for the project.
f. Submit a copy of the daily reports to the QC Manager.
g. Discrepancies that are observed during Special Inspections must be reported to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site, the observed discrepancies must be documented in the daily report.
h. Submit a biweekly Special Inspection Report until all inspections are complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:
(1) A brief summary of the work performed during the reporting time frame.
(2) Changes and/or discrepancies with the drawings, specifications and mechanical or electrical component certification, that were observed during the reporting period.
(3) Discrepancies which were resolved or corrected.
(4) A list of nonconforming items requiring resolution.
(5) All applicable test results, including nondestructive testing reports.
i. On the first day of each month, furnish to the Government five copies of the combined progress reports of the special inspector's observations, listing all special inspections of construction or reviews of testing performed during that month, noting all uncorrected deficiencies, and describing the corrections made both to these deficiencies and to previously reported deficiencies. Each monthly report shall be signed by all special inspectors who performed special inspections of construction or reviewed testing during that month, regardless of whether they reported any deficiencies. Each monthly report shall be signed by the Contractor.
j. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project and corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and indicate the certification of the special inspector qualifying them to conduct the inspection.
k. Submit daily reports to the SIOR.
3.2 DEFECTIVE WORK
Check work as it progresses, but failure to detect any defective work or
SECTION 01 45 35.02 00 Page 11 materials must in no way prevent later rejection if defective work or materials are discovered, nor obligate the Contracting Officer to accept such work.
-- End of Section --