Final_Presentation--Pre-Proposal_Site_Visit--20180515.pdf
PDF 9 MB Posted
- Attached to
- CLR039b Long Range Discrimination Radar Construction Package #2 ECF, Clear AFS, AK Federal contract opportunity
- Solicitation number
- W911KB18R0006
About this file
Site Visit Presentation
View the file
Other files for this federal contract opportunity
Show all 50
CLR039b Long Range Discrimination Radar Construction Package #2 ECF, Clear AFS, AK has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUILDING STRONG®
Solicitation: W911KB-18-R-0006 Pre-Proposal Conference & Site Visit
Long Range Discrimination Radar (LRDR), Construction Package #2 Entry Control Facility and IESS
Clear Air Force Station, Alaska 15 May 2018
Agenda Introductions/Opening Remarks (10:00AM – 10:15AM) Presentation (10:15AM – 12:30PM)
LRDR Program Orientation CP#2 Requirement Highlights
Lunch (12:30PM – 1:15PM)
TWC
Tour/Site Visit (1:30PM – 3:30PM) LRDR Project Site South Borrow Pit Lake Sansing Identify Haul Route Building 800 SSPARS “windshield” tour
Admin Information and Sign-in Introductions Purpose Ground Rules Technical Questions-Submitted via bidder inquiry system.
On site - Stay together
Introductions & Opening
CP#2 Project Milestone Schedule
Proposals Due – 22 June 2018 Award – 31 August 2018 ECF Beneficial Occupancy BOD – 1 June 2020 (AM#02) IESS Beneficial Occupancy (BOD) – 30 Sept 2020
(AM#02)
Government IESS acceptance testing Commences– 30
Sept 2020 (AM#02) Contract Completion Date – 30 April 2021 (AM#02)
Construction Overview
CP#2 is one of several LRDR projects under construction during late 2018 and most of 2019.
Other LRDR project under construction at the same time as CP#2.
CP#1 Mission Control Facility, LRDR Substation, Site
Infrastructure.
CP#5 Radar Foundation (LES).
CP#3 LPP, Fuel Storage and Supply.
CP#4 Maintenance Facility.
CP#6 Near Field Antenna.
LRDR Radar.
Construction Detail
Civil Architectural Structural Mechanical/Fire Protection Electrical Instrumentation and Control Communications Electronic Security
Technical
Technical Requirements Civil Engineering
Civil Engineering – Security Overview
• Perimeter Vehicle Barrier
• Boulders or Blocks sized to stop 50 mph, 5,000 lb vehicle
• Set 150' from critical facilities
• Fences
• SSL A- FE 7
•7-foot tall •3 strands of barbed wire on double extension arms •30-foot clear zone
• Animal Control (similar to SSL A) •No top and bottom rail •Lighter gauge fabric •Posts driven rather than cast in concrete
• Security Detection
• Buried Sensor Cable
• Cameras
• Infra-red detection at Entry Control
• Microwave on west side of Building
Civil Engineering – Parking and ECF
• Parking Lot
• 25 spaces
• Lighting
• Headbolt Heaters
• Entry Control Facility (ECF)
• Building
• Vehicle Entrapment
• Monitoring for overall Security
Location and Vicinity –
• Temporary Work Camp
• Job Trailer Location
• Batch Plant Options
• Construction Water
• Parking
• Haul Routes
• Borrow Pit
General Overview- Architectural
Architectural Design
• The LRDR facilities become a new
“Campus” within Clear AFS
Build on the standards established in the Facilities Excellence Plan
Create a new “district” with a unique, but compatible campus identity
Provide a platform on which several A/E designers can have pieces of the complex belong to a harmonic whole.
CP-2
Building= ECF
Multiple Buildings; Multiple Construction Packaging
Long R a n g e D iscr imi na t i o n R a d a r (LRDR) Construction Package 1 FY 17
Construction Package 2 FY 17
Construction Package 3 FY 19
Construction Package 4 FY 19
ECF
Primary point of personnel access via secured perimeter surrounding the LRDR facilities.
Normally unmanned IAW USSTRATCOM Strategic Instruction 538- 2; access control will be provided with a Level II Access Control System for ingress and Level I for egress at the ECF turnstiles for those with proper credentials
Not required to be HEMP protected.
Required to be hardened with resistance to small arms fire (UL 752
Ballistic Level V) at the interior walls which surround the Entry Control Room.
Perimeter exterior walls to meet Low Level Forced Entry for Intrusion Protection delay of 60 seconds min. per UFC 4-020-01 | 4- 9.2.1.
ECF - Entry Lobby
Unsecured side of the ECF Entry Lobby required to meet UFC 4-020-01, 4-9.2 Low Level Protection; provide intrusion protection delay of 1 minute minimum.
Aluminum curtainwall window framing system has been provided for its ‘beefier’ structural capabilities combined with triple glazed insulated glass with heat strengthened out face and polycarbonate inner units to provide sustained intrusion protection for minimum 1-minute interval while maximizing the thermal properties of the window-envelope system.
Access to secure side maintained with stainless steel revolving door and ADA gate-door access via Entry Control Room personnel.
ECF - Entry Control Room Windows, doors and walls surrounding the Entry Control Room are required to be small arms resistant with UL 752 Ballistic Level 5 assemblies at a minimum per UFC 4-022-01, subsection 6-9.6.2.
Glass clad polycarbonate and fiberglass clad wall panels at interior walls will be provided for the required ballistic level. Access control provided for stainless steel revolving door and ADA gate-door between unsecured Entry Lobby and Secured Exit Lobby.
Gun ports shall be installed between the Entry Control Office and the public access lobbies (3-gun ports).
ECF
EPDM Roof Exterior Walls:
► 6” Insulated Metal Panels ► 8” Stem walls at Aluminum Storefront Windows w/ Ground face CMU Wainscot
Interior Walls:
► Painted GWB ► Porcelain Tile
Floors:
► Ceramic Tile ► Walk-Off Matts ► Static Dissipative Tile ► Sealed Concrete
Ceilings
► ACT
► Painted GWB, Exposed
Raven-Resistant Roofing
Structural Engineering
Structural
Structural Design
ECF – Structural Summary Single Story metal stud-framed building.
Roof Framing: 5/8” plywood sheathing supported by
10-inch deep cold-formed metal joists spaced 16-inches on center. Joists will be supported on 8-inch cold formed metal stud bearing walls on the back side of the building and on steel posts and beams at the front of the building.
Plywood roof diaphragm transfers loads to ½-inch plywood sheathed shear walls attached to the exterior face of the 8-inch cold formed metal studs.
Foundation: Conventional cast-in-place concrete wall and footing system w/ 4-inch slab-on-grade.
Perimeter wall columns supported on concrete pilasters and concrete spread footings.
Mechanical (HVAC) Engineering
Mechanical (HVAC) Engineering
ECF – HVAC Summary
• (1) AHU, 1,067 CF
• (2) Local Exhaust Fans, 75 cfm ea
• (2) Condensing Units, 3.5 and 1 tons cooling
• All electric heating
• (2) 34 MBH Air Curtains at doors
• Unit heaters, duct reheat coils and electric baseboard throughout building
BUILDING HVAC – AHU Diagram
BUILDING – HVAC PLANS
Plumbing Engineering – SITE PLAN
Plumbing Engineering
Plumbing Engineering –
WATER ENTRANCES
Fire Protection Engineering – Sprinkler System
Sprinkler Summary
• OH-1, LH Building
• Dedicated, circulated fire water line
• Domestic water fill connection
• N2 Generator connection
Fire Protection Engineering – FA/MNS System
Electrical Engineering
• Significant Design Criteria
• NEC 2017
• NFPA 72
• UFC 3-520-01 Interior Electrical Systems
• UFC 3-550-01 Exterior Electrical Power
Distribution Systems
• MIL-STD-188-125-1 HEMP protection…
• Entry Control Facility E-9031xxE
• LED Lighting
• Electrical/Mechanical/Telecom Room
• Exterior Temporary Power ED100103E
• Shared Temporary Power with CP1 and
CP5
• Coordination of CP1’s Temporary Power structures on Site (Note during site visit)
• Exterior– Support of Perimeter Security
• Exterior – Non-Security
• Exterior– Support of Perimeter Security
• Lighting
• Plan North (E-100111E)
• Plan South (E-100113E/114E)
• Power Distribution (E-100121E-124E)
• Exterior – Non-Security
• Service to ECF
• Parking/Roadway Lighting
• HBH
Telecommunications
Telecommunications Engineering
• Significant Design Criteria
• UFC 3-580-01 Telecommunications Building Cabling System Planning and Design,
• BICSI OSPDRM, 5th Edition
• BICSI TDMM, 12th Edition
• Entry Control Facility T-903101E
• Site Distribution T-100102E
Security
Security Engineering
• Significant Design Criteria
• UFC 3-580-01 Telecommunications Building Cabling System Planning and Design,
• BICSI OSPDRM, 5th Edition
• BICSI TDMM, 12th Edition
• Entry Control Facility TY903101E
• Main Level
• Roof
Security Engineering
• Site Detection Features
• Buried Line Sensors
• IPIDS
• Microwave Detection
• Access Control
RMF Cyber Security
RMF Cyber Security
Cybersecurity Component Selection Systems
►Building Monitoring System (BMS) ►Fire Alarm and Mass Notification
System (FA/MNS) ►Electronic Security Systems (ESS)
RMF Specialist
See also Interface Slides
Joint Occupancy Requirements
G-100005 (As Advertised)
Updates:
• Schedule
• Job Trailers
• Access for CP-3
Construction
Tentative Construction Package Schedule:
CP-1 May 2017- Aug 2019 CP-2 Aug 1, 2018- Jan 2021 CP-3 Mar 1, 2019- Aug 2021 CP-4 Jan 2020- Sep 2021 CP-5 Mar 2018- Aug 30, 2018
CP-6 TBD
Radar Prime - Summer 2018 - Summer of 2021
CP-2
Delay Installation of Fence and Buried Sensor Cable across Alt Access for LPP and Fire Protection Line to after June 1, 2020 Fence and Buried Sensor Cable complete by Sep 30, 2020 Security Testing Complete by Jan 2021
CP- 3
Contractor access to secure site only through ECF after June 1, 2020
Joint Occupancy Requirements March 1 2018- February 28, 2019 To Be Issued by Amendment
Requirements March 1 2019- August 31, 2019
Requirements September 1, 2019 – January 1, 2021
Requirements February –September 2021
Interfaces with Other Work
Interfaces with CP1 - Power
• Raceway Connections
• Power Supply Connections
Interfaces with CP1 - Telecom
• Raceway Connections (T-100401E)
• Equipment Room Connections (T-900401E)
Interfaces with CP1/CLR027 - Security
• CP1
• Cable Connections covered
• Network connections
• Site Work
• CLR027
• Building 804
• Head End Modifications to Vindicator and
VICADS (Prometheus)
Interfaces with CP1 - Civil
• Fire Protection
• Domestic Water
• Sewer Service
• Building Foundation/Grading
Interfaces with CP1 -HVAC
• Heating
• Building Monitoring System (BMS)
Close Out
Commissioning
Systems to be Commissioned
►HVAC
• Cooling Generation
• Air Distribution
• Terminal Units
• Vibration and Sound Systems
• Controls and Instrumentation (BMS)
• Balancing and Testing
►Electrical
• Service entrance equipment
• Distribution and Branch Panelboards
• Grounding Systems
• Support of HVAC
Primary Specification Sections
• 01 91 00.02 15 General
Commissioning
• 23 08 00.02 00 HVAC
• 26 08 00.02 00 Apparatus
Inspection and Testing
• 26 08 01.02 00 Electrical
Systems
Commissioning Team (01 91 00.02 15)
• Government Members
• Contractor Members
• Designers of Record
Commissioning
Systems to be Fully Tested w/o Commissioning ►Telecommunications
• 27 10 00.02 00 Inside Cable Plants
• 34 82 00.00 00 Outside Cable Plants
►Security
• 28 20 00.02 00 Certification of
Electronic Security Systems 28 20 01.02 00 Intrusion
28 20 23.02 10 CCTV
• 28 51 23.02 00 Security Intercom ►Fire Alarm/Mass Notification System
• 28 31 76.02 00
Primary Specification Sections
• 01 91 00.02 15 General
Commissioning
• 23 08 00.02 00 HVAC
• 26 08 00.02 00 Apparatus
Inspection and Testing
• 26 08 01.02 00 Electrical
Systems
Commissioning Team (01 91 00.02 15)
• Government Members
• Contractor Members
• Designers of Record
RMF/Government Testing
Building Maintenance System
(BMS)
• Networking devices, new and modified
• Workstations, new and modified
Bldgs. 903, 900 and 800
Fire Alarm/Mass Notifications
• Networking devices, new and modified
Bldgs. 903, 900 and 251
Electronic Security Systems
• Networking devices, new and modified
• Bldgs. 903, 900 and 804.
Section 01 91 10.02 29 Cybersecurity/Risk Management Framework
RMF/Government Testing
Independent devices may be tested under individual sections while not connected to existing or new network equipment.
Networked device testing may begin after Authority to Test has been received (3.1.3.4) Step 4 Government Testing includes Contractor participation Step 5 Plan of Action and
Milestones (POAM)
Section 01 91 10.02 29 Cybersecurity/Risk Management Framework
Contract Type
Best Value Trade-Off RFP Contract will be Firm Fixed Price
Typical Proposal Shortfalls Proposal Instructions Not Followed
Check list Proposal Submission Requirements are not clearly and/or completely addressed Check List
Statements in the Proposal are Not Well Supported Proposals are Not Well Organized & the Evaluator Must
Hunt for the Information Proposal Contains Deficiencies Which Preclude Award Proposals are not signed, Amendments not acknowledged Proposals are received after the due date/time
Schedule
ProjNet – 24 April – 12 June 2018 at 4:30 pm Pre-Proposal Site Visit – 15 May 2018 Proposal Due Date – 22 June 2018 at 2:00 pm Projected Award Date – 31 August 2018
Tour/Site Visit
Site Visit
Site visit Photos
• Photography of or in the vicinity of Bldg 800 (existing operational radar) is prohibited.
Groups
• Personal Protective Equipment?
Hard Hat, Safety Glasses, and Safety Boots required to exit bus in construction area.
Stay within eye sight of your Group Lead
Summary
Closing and follow-up Safety
| Solicitation: W911KB-18-R-0006�Pre-Proposal Conference & Site Visit �Long Range Discrimination Radar (LRDR), Construction Package #2 �Entry Control Facility and IESS |
| Agenda |
| Introductions & Opening |
| CP#2 Project Milestone Schedule |
| Construction Overview |
| Construction Detail |
| Technical |
| Technical Requirements�Civil Engineering |
| Civil Engineering – �Security Overview |
| Civil Engineering – �Parking and ECF |
| Location and Vicinity – � |
| General Overview-�Architectural |
| Architectural Design |
| Architectural Design |
| Architectural Design |
| Architectural Design |
| Architectural Design |
| Architectural Design |
| Architectural Design |
| Architectural Design |
| Technical Requirements�Architectural |
| Architectural |
| Technical Requirements�Architectural |
| Architectural |
| Architectural |
| Architectural |
| Architectural |
| Technical Requirements�Architectural |
| Technical Requirements�Structural Engineering |
| Structural� |
| Structural Design |
| Technical Requirements�Mechanical (HVAC) Engineering |
| Technical Requirements�Mechanical (HVAC) Engineering |
| BUILDING HVAC – AHU Diagram |
| BUILDING – HVAC PLANS |
| Technical Requirements�Plumbing Engineering – SITE PLAN |
| Plumbing Engineering |
| Plumbing Engineering – �WATER ENTRANCES |
| Fire Protection Engineering – Sprinkler System |
| Fire Protection Engineering – FA/MNS System |
| Technical Requirements�Electrical Engineering |
| Electrical Engineering |
| Electrical Engineering |
| Electrical Engineering |
| Technical Requirements�Telecommunications |
| Telecommunications Engineering |
| Technical Requirements�Security |
| Security Engineering |
| Security Engineering |
| Technical Requirements�RMF Cyber Security |
| RMF Cyber Security |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Joint Occupancy Requirements |
| Interfaces with Other Work |
| Interfaces with CP1 - Power |
| Interfaces with CP1 - Telecom |
| Interfaces with CP1/CLR027 - Security |
| Interfaces with CP1 - Civil |
| Interfaces with CP1 -HVAC |
| Close Out |
| Commissioning |
| Commissioning |
| RMF/Government Testing |
| RMF/Government Testing |
| Contract Type |
| Typical Proposal Shortfalls |
| Schedule |
| Tour/Site Visit |
| Site Visit |
| Summary |