Technical_Exhibit_B2_-_Specifications_REVISED.pdf
PDF 1 MB Posted
- Attached to
- Open End Electrical Requirements Contract Federal contract opportunity
- Solicitation number
- W91151-16-B-0021
About this file
Revised Tech Exhibit B2 - Specifications
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AD001636P Electrical Requirements Contract August 18, 2016 Technical Exhibit C For Bidding Purposes Only
PROJECT TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 20 00.00 10 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 FIRESTOPPING
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 73.00 40 OVERCURRENT PROTECTIVE DEVICES
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 12 00 TRANSFORMERS
26 23 00 SWITCHBOARDS AND SWITCHGEAR
26 24 16.00 40 PANELBOARDS
26 24 19.00 40 MOTORS AND MOTOR-CONTROL CENTERS
26 26 00.00 40 POWER DISTRIBUTION UNITS
26 27 13.10 30 ELECTRIC METERS
26 27 26.00 40 WIRING DEVICES
26 28 16.00 40 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 51 00 INTERIOR LIGHTING
DIVISION 31 - EARTHWORK
31 23 00.00 20 EXCAVATION AND FILL
31 32 11 SOIL SURFACE EROSION CONTROL
DIVISION 33 - UTILITIES
33 71 01.00 40 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 02 41 00
SECTION 03 20 00.00 10
CONCRETE REINFORCING
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 318 (2014; Errata 1-2 2014; Errata 3 2015) Building Code Requirements for Structural Concrete and Commentary
ACI 318M (2014) Building Code Requirements for Structural Concrete & Commentary
ACI SP-66 (2004) ACI Detailing Manual
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
ASTM INTERNATIONAL (ASTM)
ASTM A1035/A1035M (2014) Standard Specification for Deformed and Plain, Low-carbon, Chromium, Steel Bars for Concrete Reinforcement
ASTM A1064/A1064M (2015) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM A184/A184M (2006; E2011) Standard Specification for Fabricated Deformed Steel Bar Mats for Concrete Reinforcement
ASTM A36/A36M (2014) Standard Specification for Carbon Structural Steel
ASTM A370 (2014) Standard Test Methods and Definitions for Mechanical Testing of Steel Products
ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, SECTION 03 20 00.00 10
Welded and Seamless
ASTM A615/A615M (2015) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A675/A675M (2014) Standard Specification for Steel Bars, Carbon, Hot-Wrought, Special Quality, Mechanical Properties
ASTM A706/A706M (2014) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement
ASTM A767/A767M (2009) Standard Specification for Zinc-Coated (Galvanized) Steel Bars for Concrete Reinforcement
ASTM A884/A884M (2014) Standard Specification for Epoxy-Coated Steel Wire and Welded Wire Reinforcement
ASTM A934/A934M (2013) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
CRSI 10MSP (2009; 28th Ed) Manual of Standard Practice
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control approval.] [information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Butt-Splices; G[, [_____]]
SD-02 Shop Drawings
Reinforcement; G[, [_____]]
SD-03 Product Data
[ SD-04 Samples
Epoxy-Coated Bars
SD-07 Certificates
Reinforcing Steel Qualified Welders Qualification of Steel Bar Butt-Splicers
1.3 QUALITY ASSURANCE
1.3.1 Welding Qualifications
Welders are required to be qualified in accordance with AWS D1.4/D1.4M.
Perform qualification test at the worksite and notify the Contracting Officer 24 hours prior to conducting tests. Special welding procedures and welders qualified by others may be accepted as permitted by AWS D1.4/D1.4M.
Submit a list of qualified welders names.
1.3.2 Qualification of Steel Bar Butt-Splicers
Qualification of steel bar butt-splicers are required to be certified to have satisfactorily completed a course of instruction in the proposed method of butt-splicing or have satisfactorily performed such work within the preceding year. Submit certificates on the Qualifications of Steel Bar Butt-Splicers prior to commencing butt-splicing.
1.3.3 Qualification of Butt-Splicing Procedure
As a condition of approval of the butt-splicing procedure, make three test butt-splices of steel bars of each size to be spliced using the proposed butt-splicing method, in the presence of the Contracting Officer. Tension tested to destruction these test butt-splices and unspliced bars of the same size, with stress-strain curves plotted for each test. Test results must show that the butt-splices meet the specified strength and deformation requirements in order for the splicing procedure to be approved.
1.4 DELIVERY, STORAGE, AND HANDLING
Store reinforcement and accessories off the ground on platforms, skids, or other supports.
PART 2 PRODUCTS
2.1 DOWELS
Provide dowels conforming to ASTM A675/A675M, Grade 80[ or ASTM A1035/A1035M ]. Steel pipe conforming to ASTM A53/A53M, Schedule 80, may be used as dowels provided the ends are closed with metal or plastic inserts or with mortar.[
Provide plate dowels conforming to ASTM A36/A36M, of size and spacing indicated. Plate dowel system must minimize shrinkage restraint by [using a tapered shape] [or] [formed void] [or] [by having compressible material on the vertical faces with a thin bond breaker on the top and bottom dowel surfaces.]]
2.2 FABRICATED BAR MATS
Fabricated bar mats conforming to ASTM A184/A184M.
2.3 REINFORCING STEEL
Reinforcing steel of deformed bars conforming to ASTM A615/A615M, ASTM A706/A706M, or ASTM A1035/A1035M grades and sizes as indicated. Cold drawn wire used for spiral reinforcement must conform to ASTM A1064/A1064M.
Submit certified copies of mill reports attesting that the reinforcing steel furnished contains no less than 25 percent recycled scrap steel and meets the requirements specified herein, prior to the installation of reinforcing steel.
[2.3.1 Zinc-Coated (Galvanized) Bars
Zinc-coated (galvanized) bars complying with the requirements of ASTM A767/A767M, Class II coating, galvanized after fabrication.
][2.3.2 Epoxy-Coated Bars
Epoxy-coated steel bars complying with the requirements of ASTM A934/A934M, including written certifications for coating material and coated bars, sample of coating material, and 1.5 pounds of patching material.
][2.3.3 Mechanical Butt-Splices
Mechanical butt splices must be an approved exothermic, threaded coupling, swaged sleeve or other positive connecting type, and develop 125 percent of the specified minimum yield tensile strength of the spliced bars or of the smaller bar in transition splices. In addition to this strength requirement, the additional deformation of number 14 and smaller bars due to slippage or other movement within the splice sleeve cannot exceed (unit strain)( 0.015 inches unit strain 0.0015 inches/inch) beyond the elongation of an unspliced bar based upon a 10 inch gage length spanning the extremities of the sleeve at a stress of 30,000 psi. The additional deformation of number 18 bars must not exceed(unit strain) 0.03 inches (unit strain 0.003 inches/inch) beyond the elongation of an unspliced bar based upon a 10 inch gage length spanning the extremities of the sleeve at a stress of 30,000 psi. Determine the amount of the additional deformation from the stress-strain curves of the unspliced and spliced bars tested as required in paragraph QUALIFICATION OF BUTT-SPLICING PROCEDURE for qualification of the butt-splicing procedure.
]2.4 WELDED WIRE REINFORCING
Welded wire reinforcing conforming to ASTM A1064/A1064M. When directed by the Contracting Officer for special applications, use welded wire reinforcing conforming to ASTM A884/A884M.
2.5 WIRE TIES
Use wire ties that are 16 gauge or heavier black annealed steel wire.[ Ties for epoxy-coated bars mustl be vinyl-coated or epoxy-coated.][ Use zinc-coated ties for zinc-coated bars.]
2.6 SUPPORTS
Design bar supports for formed surfaces in accordance with CRSI 10MSP and fabricate of steel or precast concrete blocks. Provide precast concrete blocks with wire ties and not less than 4 inches square when supporting reinforcement on ground. Precast concrete block must have compressive strength equal to that of the surrounding concrete. Coat steel supports for coated or galvanized bars with electrically compatible material for a distance of at least 2 inches beyond the point of contact with the bar.
Where concrete formed surfaces will be exposed to weather or where surfaces are to be painted, use galvanized, plastic protected or stainless steelsteel supports within 1/2 inch of concrete surface. Concrete supports used in concrete exposed to view must have the same color and texture as the finish surface. For slabs on grade and topping slabs on steel deck, supports use precast concrete blocks, plastic coated steel fabricated with bearing plates, or specifically designed wire-fabric supports fabricated of plastic.[]
PART 3 EXECUTION
3.1 REINFORCEMENT
Fabricate and place reinforcement steel and accessories as specified, as indicated, and as shown on approved shop drawings. Fabrication and placement details of steel and accessories not specified or shown mustl be in accordance with ACI SP-66 and ACI 318. Cold bend reinforcement unless otherwise authorized. Bending may be accomplished in the field or at the mill.[ Mill bend zinc-coated and epoxy-coated bars prior to coating.
Bend all steel cold unless authorized.] Do not bend bars after embedment in concrete. Place safety caps on all exposed ends of vertical concrete reinforcement bars that pose a danger to life safety. Face wire tie ends away from the forms. Submit detail drawings showing reinforcing steel placement, schedules, sizes, grades, and splicing and bending details.
Show support details including types, sizes and spacing.
3.1.1 Placement
Reinforcement must be free from loose rust and scale, dirt, oil, or other deleterious coating that could reduce bond with the concrete. Place reinforcement in accordance with ACI 318 at locations indicated plus or minus one bar diameter. Do not continue reinforcement through expansion joints and place as indicated through construction or contraction joints.
Cover with concrete coverage as indicated or as required by ACI 318. If bars are moved more than one bar diameter to avoid interference with other reinforcement, conduits or embedded items, the resulting arrangement of bars, including additional bars required to meet structural requirements, requires approval before concrete is placed.
3.2 WELDED-WIRE REINFORCEMENT PLACEMENT
Place welded-wire reinforcement in slabs as indicated. Reinforcement placed in slabs on grade must be continuous between expansion, construction, and contraction joints. Reinforcement placement at joints must be as indicated.
May lap splices in such a way that the overlapped area equals the distance between the outermost crosswires plus 2 inches. Stagger laps to avoid continuous laps in either direction. Wire or clip together reinforcement at laps at intervals not to exceed 4 feet. Position reinforcement by the use of supports.
3.3 DOWEL INSTALLATION
Install dowels in slabs on grade at locations indicated and at right angles to joint being doweled. Accurately position and align dowels parallel to the finished concrete surface before concrete placement. Rigidly support dowels during concrete placement. Coat one end of dowels with a bond breaker.[
Install plate dowels according to the manufacturer's recommendations.]
-- End of Section --
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 121R (2008) Guide for Concrete Construction Quality Systems in Conformance with ISO
ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete
ACI 211.2 (1998; R 2004) Standard Practice for Selecting Proportions for Structural Lightweight Concrete
ACI 213R (2003) Guide for Structural Lightweight-Aggregate Concrete
ACI 301 (2010; Errata 2011) Specifications for Structural Concrete
ACI 302.1R (2004; Errata 2006; Errata 2007) Guide for Concrete Floor and Slab Construction
ACI 304.2R (1996; R 2008) Placing Concrete by Pumping Methods
ACI 304R (2000; R 2009) Guide for Measuring, Mixing, Transporting, and Placing Concrete
ACI 305R (2010) Guide to Hot Weather Concreting
ACI 306.1 (1990; R 2002) Standard Specification for Cold Weather Concreting
ACI 306R (2010) Guide to Cold Weather Concreting
ACI 308.1 (2011) Specification for Curing Concrete
ACI 318 (2011; Errata 1 2011; Errata 2 2012;
Errata 3-4 2013) Building Code Requirements for Structural Concrete and
SECTION 03 30 00
Commentary
ACI 347 (2004; Errata 2008; Errata 2012) Guide to Formwork for Concrete
ACI SP-15 (2011) Field Reference Manual: Standard Specifications for Structural Concrete ACI 301-05 with Selected ACI References
ACI SP-2 (2007; Abstract: 10th Edition) ACI Manual of Concrete Inspection
ACI SP-66 (2004) ACI Detailing Manual
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
ASTM INTERNATIONAL (ASTM)
ASTM A1064/A1064M (2013) Standard Specification for Carbon-Steel Wire and Welded Wire Reinforcement, Plain and Deformed, for Concrete
ASTM A36/A36M (2012) Standard Specification for Carbon Structural Steel
ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A615/A615M (2013) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A706/A706M (2013) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement
ASTM A767/A767M (2009) Standard Specification for Zinc-Coated (Galvanized) Steel Bars for Concrete Reinforcement
ASTM A780/A780M (2009) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM A934/A934M (2013) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars
ASTM A955/A955M (2012; E 2012) Standard Specification for Deformed and Plain Stainless-Steel Bars for Concrete Reinforcement
ASTM A996/A996M (2009b) Standard Specification for Rail-Steel and Axle-Steel Deformed Bars for Concrete Reinforcement
ASTM C1017/C1017M (2007) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete
ASTM C1077 (2014) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation
ASTM C1107/C1107M (2013) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
ASTM C1116/C1116M (2010a) Standard Specification for Fiber-Reinforced Concrete
ASTM C1157/C1157M (2011) Standard Specification for Hydraulic Cement
ASTM C1218/C1218M (1999; R 2008) Standard Specification for Water-Soluble Chloride in Mortar and Concrete
ASTM C1240 (2012) Standard Specification for Silica Fume Used in Cementitious Mixtures
ASTM C1260 (2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C138/C138M (2013a) Standard Test Method for Density ("Unit Weight"), Yield, and Air Content (Gravimetric) of Concrete
ASTM C143/C143M (2012) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C150/C150M (2012) Standard Specification for Portland Cement
ASTM C1567 (2013) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)
ASTM C1602/C1602M (2012) Standard Specification for Mixing Water Used in Production of Hydraulic Cement Concrete
ASTM C172/C172M (2010) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C173/C173M (2012) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C192/C192M (2013a) Standard Practice for Making and Curing Concrete Test Specimens in the
Laboratory
ASTM C231/C231M (2010) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C295/C295M (2012) Petrographic Examination of Aggregates for Concrete
ASTM C31/C31M (2012) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C311/C311M (2013) Sampling and Testing Fly Ash or Natural Pozzolans for Use as a Mineral Admixture in Portland-Cement Concrete
ASTM C33/C33M (2013) Standard Specification for Concrete Aggregates
ASTM C330/C330M (2013) Standard Specification for Lightweight Aggregates for Structural Concrete
ASTM C39/C39M (2014) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C42/C42M (2013) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C494/C494M (2013) Standard Specification for Chemical Admixtures for Concrete
ASTM C552 (2013) Standard Specification for Cellular Glass Thermal Insulation
ASTM C567/C567M (2011) Determining Density of Structural Lightweight Concrete
ASTM C578 (2013) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
ASTM C591 (2013) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation
ASTM C595/C595M (2013) Standard Specification for Blended Hydraulic Cements
ASTM C618 (2012a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C78/C78M (2012; E 2013) Standard Test Method for Flexural Strength of Concrete (Using
Simple Beam with Third-Point Loading)
ASTM C920 (2011) Standard Specification for Elastomeric Joint Sealants
ASTM C94/C94M (2014) Standard Specification for Ready-Mixed Concrete
ASTM C989/C989M (2013) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)
ASTM D1752 (2004a; R 2013) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion
ASTM D2628 (1991; R 2011) Standard Specification for Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements
ASTM D2835 (1989; R 2012) Lubricant for Installation of Preformed Compression Seals in Concrete Pavements
ASTM D412 (2006a; R 2013) Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers - Tension
ASTM D471 (2012a) Standard Test Method for Rubber Property - Effect of Liquids
ASTM D5759 (2012) Characterization of Coal Fly Ash and Clean Coal Combustion Fly Ash for Potential Uses
ASTM D6690 (2012) Standard Specification for Joint and Crack Sealants, Hot Applied, for Concrete and Asphalt Pavements
ASTM E1155 (1996; R 2008) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers
ASTM E1643 (2011) Standard Practice for Selection, Design, Installation, and Inspection of Water Vapor Retarders Used in Contact with Earth or Granular Fill Under Concrete Slabs
ASTM E1745 (2011) Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs
ASTM E1993/E1993M (1998; R 2013; E 2013) Standard Specification for Bituminous Water Vapor
Retarders Used in Contact with Soil or Granular Fill Under Concrete Slabs
ASTM E329 (2013b) Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
ASTM E96/E96M (2013) Standard Test Methods for Water Vapor Transmission of Materials
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
CRSI 10MSP (2009; 28th Ed) Manual of Standard Practice
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY (NIST)
NIST PS 1 (2009) DOC Voluntary Product Standard PS 1-07, Structural Plywood
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 513 (1974) Corps of Engineers Specifications for Rubber Waterstops
COE CRD-C 572 (1974) Corps of Engineers Specifications for Polyvinylchloride Waterstops
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS SS-S-200 (Rev E; Am 1; Notice 1) Sealant, Joint, Two-Component, Jet-Blast-Resistant, Cold-Applied, for Portland Cement Concrete Pavement
U.S. GREEN BUILDING COUNCIL (USGBC)
LEED NC (2009) Leadership in Energy and Environmental Design(tm) New Construction Rating System
1.2 DEFINITIONS
a. "Cementitious material" as used herein must include all portland cement, pozzolan, fly ash, ground granulated blast-furnace slag, and [silica fume].
b. "Exposed to public view" means situated so that it can be seen from eye level from a public location after completion of the building. A public location is accessible to persons not responsible for operation or maintenance of the building.
c. "Chemical admixtures" are materials in the form of powder or fluids that are added to the concrete to give it certain characteristics not obtainable with plain concrete mixes.
d. "Complementary cementing materials" (CCM) include coal fly ash, [silica fume, ]granulated blast-furnace slag, natural or calcined pozzolans, and ultra-fine coal ash when used in such proportions to replace the portland cement that result in improvement to sustainability and durability and reduced cost.
e. "Design strength" (f'c) is the specified compressive strength of concrete at time(s) specified in this section to meet structural design criteria.
f. "Mass Concrete" is any concrete system that approaches a maximum temperature of 158 degrees F within the first 72 hours of placement. In addition, it includes all concrete elements with a section thickness of 3 feet or more regardless of temperature.
g. "Mixture proportioning" is the process of designing concrete mixture proportions to enable it to meet the strength, service life and constructability requirements of the project while minimizing the initial and life-cycle cost.
h. "Mixture proportions" are the masses or volumes of individual ingredients used to make a unit measure (cubic meter or cubic yard) of concrete.
i. "Pozzolan" is a siliceous or siliceous and aluminous material, which in itself possesses little or no cementitious value but will, in finely divided form and in the presence of moisture, chemically react with calcium hydroxide at ordinary temperatures to form compounds possessing cementitious properties.
j. "Workability (or consistence)" is the ability of a fresh (plastic) concrete mix to fill the form/mould properly with the desired work (vibration) and without reducing the concrete's quality. Workability depends on water content, chemical admixtures, aggregate (shape and size distribution), cementitious content and age (level of hydration).
1.3 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Reinforcing steel; G
SD-05 Design Data
Concrete mix design; G]
SD-06 Test Reports
Compressive strength tests; FIO
Slump Tests; FIO
SD-07 Certificates
Reinforcing Bars; FIO
1.4 QUALITY ASSURANCE
1.4.1 Design Data
1.4.1.1 Concrete Mix Design
15 days minimum prior to concrete placement, submit a mix design for each strength and type of concrete.
1.4.2 Shop Drawings
1.4.2.1 Reinforcing Steel
ACI SP-66. Indicate bending diagrams, assembly diagrams, splicing and laps of bars, shapes, dimensions, and details of bar reinforcing, accessories, and concrete cover. Do not scale dimensions from structural drawings to determine lengths of reinforcing bars. Reproductions of contract drawings are unacceptable.
1.4.3 Quality Control Personnel Certifications
1.4.3.1 Field Testing Technician and Testing Agency
Work on concrete under this contract must be performed by an ACI Concrete Field Testing Technician Grade 1 qualified in accordance with ACI SP-2 or equivalent.
1.4.4 Laboratory Qualifications for Concrete Qualification Testing
The concrete testing laboratory must have the necessary equipment and experience to accomplish required testing. The laboratory must meet the requirements of ASTM C1077 and be Cement and Concrete Reference Laboratory (CCRL) inspected.
1.4.5 Laboratory Accreditation
Laboratory and testing facilities must be provided by and at the expense of the Contractor.
PART 2 PRODUCTS
2.1 MATERIALS FOR FORMS
2.1.1 Wood Forms
Use lumber as specified in Section 06 10 00 ROUGH CARPENTRY and as follows.
2.1.1.1 Concrete Form Plywood (Standard Rough)
Provide plywood that conforms to NIST PS 1, B-B, concrete form, not less than 5/8-inch thick.
2.2 FORM TIES AND ACCESSORIES
Provide a form tie system that does not leave mild steel after break-off or removal any closer than 2 inches from the exposed surface. Do not use wire alone. Form ties and accessories must not reduce the effective cover of the reinforcement.
2.3 CONCRETE MIX DESIGN
[2.3.1 Mix Design
ACI 211.1, ACI 301, and ACI 318 [and ACI 211.2] ACI 304.2R [and] [ACI 213R] except as otherwise specified. Indicate the compressive strength (f'c) of the concrete for each portion of the structure(s) as specified below.
Where faster set time is required, use Type III cement before using calcium chloride with approval from the contracting officer.
2.3.1.1 Foundations, Slabs on Grade and Building Elements
Proportion normal-weight concrete mixture as follows:
a. Minimum Compressive Strength: 3000 psi (at 28 days) for foundations and slabs on grade and 4000 psi (at 28 days) for all other building elements.
b. Maximum Water-Cementitious Materials Ratio: [0.50]].
c. Slump Limit: Not less than 2 inches nor more than 5 inches.
d. Air Content: 4 to 6 percent at point of delivery for 1-1/2 inch nominal maximum aggregate size.
e. Air Content: 5 to 7percent at point of delivery for[ 1 inch] [ 3/4-inch] nominal maximum aggregate size.
f. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.
2.3.1.2 Lightweight Concrete Proportion
Lightweight concrete shall only be used when idicated and for relevant applications. ACI 211.2, using weight method. Provide ASTM C330/C330M aggregates for concrete. Compressive strength should be a minimum of 3000 psi.
]2.3.2 Ready-Mix Concrete
Provide concrete that meets the requirements of ASTM C94/C94M.
Ready-mixed concrete manufacturer must provide duplicate delivery tickets with each load of concrete delivered. Provide delivery tickets with the following information in addition to that required by ASTM C94/C94M:
Type and brand cement
Cement and complementary cementitious materials content in 94-pound bags per cubic yard of concrete
Maximum size of aggregate
Amount and brand name of admixtures
Total water content expressed by water cementitious material ratio
2.4 MATERIALS
2.4.1 Cementitious Materials
For exposed concrete, use one manufacturer and one source for each type of cement, ground slag, fly ash, and pozzolan.
2.4.1.1 Fly Ash
ASTM C618, Class F, except that the maximum allowable loss on ignition must not exceed 3 percent.
Add with cement. Fly ash content must be a minimum of 20percent by weight of cementitious material, provided the fly ash does not reduce the amount of cement in the concrete mix below the minimum requirements of local building codes. Where the use of fly ash cannot meet the minimum level, provide the maximum amount of fly ash permittable that meets the code requirements for cement content. Report the chemical analysis of the fly ash in accordance with ASTM C311/C311M. Evaluate and classify fly ash in accordance with ASTM D5759.
2.4.1.2 Raw or Calcined Natural Pozzolan
Natural pozzolan must be raw or calcined and conform to ASTM C618, Class N, including the optional requirements for uniformity and effectiveness in controlling Alkali-Silica reaction and must have an ignition loss not exceeding 3 percent. Class N pozzolan for use in mitigating Alkali-Silica Reactivity must have a Calcium Oxide (CaO) content of less than 13 percent and total equivalent alkali content less than 3 percent.
2.4.1.3 Portland Cement
Provide cement that conforms to ASTM C150/C150M, Type I,II, or III, with tri-calcium aluminates (C3A) content less than 10 percent and a maximum cement-alkali content of 0.80 percent Na2Oe (sodium oxide) equivalent..
Use one brand and type of cement for formed concrete having exposed-to-view finished surfaces.
]2.4.2 Water
Water must comply with the requirements of ASTM C1602/C1602M. Minimize the amount of water in the mix. Improve workability by adjusting the grading rather than by adding water. Water must be [potable]; free from injurious amounts of oils, acids, alkalis, salts, organic materials, or other substances deleterious to concrete.
2.4.3 Aggregates
ASTM C33/C33M, except as modified herein. Furnish aggregates for exposed concrete surfaces from one source.
2.4.3.1 Aggregates/Combined Aggregate Gradation (Floor Slabs Only)
ASTM C33/C33M, uniformly graded and as follows: Nominal maximum aggregate size of 1 inch. A combined sieve analysis must indicate a well graded aggregate from coarsest to finest with not more than 18 percent and not less than 8 percent retained on an individual sieve, except that less than 8 percent may be retained on coarsest sieve and on No. 50 (0.3mm) sieve, and less than 8 percent may be retained on sieves finer than No. 50
(0.3mm). Provide sand that is at least 50 percent natural sand.
][2.4.3.2 Aggregates for Lightweight Concrete
ASTM C330/C330M.
2.4.4 Nonshrink Grout
ASTM C1107/C1107M.
2.4.5 Admixtures
ASTM C494/C494M: Type A, water reducing; Type B, retarding; Type C, accelerating; Type D, water-reducing and retarding; and Type E, water-reducing and accelerating admixture. Do not use calcium chloride admixtures. Submit product data for admixtures used in concrete.
[2.4.5.1 Air-Entraining
ASTM C260/C260M.
]2.4.5.2 High Range Water Reducer (HRWR) (Superplasticizers)
ASTM C494/C494M, Type F [and Type G (HRWR retarding admixture)] and ASTM C1017/C1017M.[ Silica fume and HRWR must come from the same manufacturer.]
[2.4.6 Vapor Retarder[and Vapor Barrier]
ASTM E1745 Class C [A] [B] polyethylene sheeting, minimum 10 mil[ 15 mil] thickness or other equivalent material with a maximum permeance rating of
0.04 perms per ASTM E96/E96M.
]2.4.7 Expansion/Contraction Joint Filler
ASTM D1751 or ASTM D1752 Type I or II.
2.4.8 Joint Sealants
[ Submit manufacturer's product data, indicating VOC content.
]2.4.8.1 Horizontal Surfaces, 3 Percent Slope, Maximum
ASTM D6690 or ASTM C920, Type M, Class 25, Use T.
2.4.8.2 Vertical Surfaces Greater Than 3 Percent Slope
ASTM C920, Type M, Grade NS, Class 25, Use T [NT].[ FS SS-S-200, no sag].
2.5 REINFORCEMENT
2.5.1 Reinforcing Bars
ACI 301 unless otherwise specified. [Use deformed steel.] ASTM A615/A615M with the bars marked A, Grade60; or ASTM A996/A996M with the bars marked R, Grade60, or marked A, Grade60
2.5.2 Wire
2.5.2.1 Welded Wire Reinforcement
ASTM A1064/A1064M.
2.5.3 Dowels for Load Transfer in Floors
Provide greased dowels for load transfer in floors of the type, design, weight, and dimensions indicated. Provide dowel bars that are plain-billet steel conforming to ASTM A615/A615M, Grade 40.
2.6 FLOOR FINISH MATERIALS
PART 3 EXECUTION
3.1 EXAMINATION
Do not begin installation until substrates have been properly constructed;
verify that substrates are level.
Check field dimensions before beginning installation. If dimensions vary too much from design dimensions for proper installation, notify Contracting Officer and wait for instructions before beginning installation.
3.2 PREPARATION
3.2.1 General
Surfaces against which concrete is to be placed must be free of debris, loose material, standing water, snow, ice, and other deleterious substances before start of concrete placing.
Remove standing water without washing over freshly deposited concrete.
Divert flow of water through side drains provided for such purpose.
3.2.2 Subgrade Under Foundations and Footings
When subgrade material is semiporous and dry, sprinkle subgrade surface with water as required to eliminate suction at the time concrete is deposited, or seal subgrade surface by covering surface with specified vapor retarder. When subgrade material is porous, seal subgrade surface by covering surface with specified vapor retarder.
3.2.3 Subgrade Under Slabs on Ground
Before construction of slabs on ground, have underground work on pipes and conduits completed and approved.
Finished surface of subgrade or fill under exterior slabs on ground must not be more than 0.02-foot above or 0.10-foot below elevation indicated.
3.2.4 Reinforcement and Other Embedded Items
Secure reinforcement, joint materials, and other embedded materials in position, inspected, and approved before start of concrete placing.
3.3 FORMS
Provide forms, shoring, and scaffolding for concrete placement in accordance with ACI 301 Section 2 and 5 and ACI 347. Set forms mortar-tight and true to line and grade. Chamfer above grade exposed joints, edges, and external corners of concrete 0.75 inch unless otherwise indicated. Provide formwork with clean-out openings to permit inspection and removal of debris.
3.3.1 Coating
Before concrete placement, coat the contact surfaces of forms with a form release agent.
3.3.2 Reshoring
Reshore concrete elements in accordance with ACI 301 Section 2.
3.3.3 Forms for Standard Rough Form Finish
Provide formwork in accordance with ACI 301 Section 5 with a surface finish, SF-1.0, for formed surfaces that are to be concealed by other construction.
3.3.4 Forms for Standard Smooth Form Finish
Provide formwork in accordance with ACI 301 Section 5 with a surface finish, SF-3.0, for formed surfaces that are exposed to view. [Do not provide mockup of concrete surface appearance and texture.]
3.3.5 Form Ties
Provide ties in accordance with ACI 301 section 2.
3.3.6 Tolerances for Form Construction
Construct formwork to ensure that after removal of forms and prior to patching and finishing of formed surfaces, provide concrete surfaces in accordance with tolerances specified in ACI 301 Section 5 and ACI 117.
3.3.7 Removal of Forms and Supports
After placing concrete, removal of forms must be in accordance with ACI 301 Section 2 except as modified by approved form removal schedule.
3.4 PLACING REINFORCEMENT AND MISCELLANEOUS MATERIALS
ACI 301 and ACI SP-66. Provide bars, welded wire reinforcement, wire ties, supports, and other devices necessary to install and secure reinforcement.
Reinforcement must not have rust, scale, oil, grease, clay, or foreign substances that would reduce the bond. Rusting of reinforcement is a basis of rejection if the effective cross-sectional area or the nominal weight per unit length has been reduced. Remove loose rust prior to placing steel. Tack welding is prohibited.
3.4.1 General
Provide details of reinforcement that are in accordance with ACI 301 and ACI SP-66 and as specified.
3.4.2 Reinforcement Supports
Support reinforcement in accordance with ACI 301 Section 3. Supports for coated or galvanized bars must also be coated with electrically compatible material for a distance of at least 2 inches beyond the point of contact with the bars.
[3.4.3 Epoxy Coated Reinforcing
Epoxy Coated Reinforcing must meet the requirements of [ASTM A934/A934M including Appendix X2,] "Guidelines for Job Site Practices" except as otherwise specified herein.
3.4.3.1 Epoxy Coated Reinforcing Steel Placement and Coating Repair
Carefully handle and install bars to minimize job site patching. Use the same precautions as described in paragraph EPOXY COATED REINFORCING STEEL.
Do not drag bars over other bars or over abrasive surfaces. Keep bar free of dirt and grit. When possible, assemble reinforcement as tied cages prior to final placement into the forms. Support assembled cages on padded supports. It is not expected that coated bars, when in final position ready for concrete placement, are completely free of damaged areas;
however, excessive nicks and scrapes which expose steel is cause for rejection. Criteria for defects which require repair and for those that do not require repair are as indicated. Inspect for defects and provide required repairs prior to assembly. After assembly, reinspect and provide final repairs.
a. Immediately prior to application of the patching material, manually remove any rust and debonded coating from the reinforcement by suitable techniques employing devices such as wire brushes and emery paper.
Exercise care during this surface preparation so that the damaged areas are not enlarged more than necessary to accomplish the repair. Clean damaged areas of dirt, debris, oil, and similar materials prior to application of the patching material.
b. Do repair and patching in accordance with the patching material manufacturer's recommendations. These recommendations, including cure times, must be available at the job site at all times.
c. Allow adequate time for the patching materials to cure in accordance with the manufacturer's recommendation prior to concrete placement.
d. Rinse placed reinforcing bars with fresh water to remove chloride contamination prior to placing concrete.
Splicing
As indicated. For splices not indicated ACI 301. Do not splice at points of maximum stress. Overlap welded wire reinforcement the spacing of the cross wires, plus 2 inches. [AWS D1.4/D1.4M. Approve welded splices prior to use.] [Repair the cut ends of hot-dipped galvanized reinforcement steel to completely coat exposed steel, ASTM A780/A780M.]
3.4.4 Future Bonding
Plug exposed, threaded, mechanical reinforcement bar connectors with a greased bolt. Provide bolt threads that match the connector. Countersink the connector in the concrete. Caulk the depression after the bolt is installed.
3.4.5 Setting Miscellaneous Material
Place and secure anchors and bolts, pipe sleeves, conduits, and other such items in position before concrete placement and support against displacement. Plumb anchor bolts and check location and elevation.
Temporarily fill voids in sleeves with readily removable material to prevent the entry of concrete.
3.4.6 Fabrication
Shop fabricate reinforcing bars to conform to shapes and dimensions indicated for reinforcement, and as follows:
Provide fabrication tolerances that are in accordance with ACI 318 and
ACISP-66.
Provide hooks and bends that are in accordance with ACI 318 and ACI SP-66.
Reinforcement must be bent cold to shapes as indicated. Bending must be done in the shop. Rebending of a reinforcing bar that has been bent incorrectly is not be permitted. Bending must be in accordance with standard approved practice and by approved machine methods.
Tolerance on nominally square-cut, reinforcing bar ends must be in accordance with ACI SP-66.
Deliver reinforcing bars bundled, tagged, and marked. Tags must be metal with bar size, length, mark, and other information pressed in by machine.
Marks must correspond with those used on the placing drawings.
3.4.7 Placing Reinforcement
Place reinforcement in accordance with ACI 301 and ACI SP-66.
For slabs on grade and for footing reinforcement, support bars or welded wire reinforcement on precast concrete blocks, spaced at intervals required by size of reinforcement, to keep reinforcement the minimum height specified above the underside of slab or footing.
For slabs other than on grade, supports for which any portion is less than 1 inch from concrete surfaces that are exposed to view or to be painted must be of precast concrete units, plastic-coated steel, or stainless steel protected bar supports. Precast concrete units must be wedge shaped, not larger than 3-1/2 by 3-1/2 inches, and of thickness equal to that indicated for concrete protection of reinforcement. Provide precast units that have cast-in galvanized tie wire hooked for anchorage and blend with concrete surfaces after finishing is completed.
Provide supports for reinforcing bars that are sufficient in number and have sufficient strength to carry the reinforcement they support, and in accordance with ACI 318, ACI SP-66 and CRSI 10MSP. Do not use supports to support runways for concrete conveying equipment and similar construction loads.
Equip supports on ground and similar surfaces with sand-plates.
Support welded wire reinforcement as required for reinforcing bars.
Secure reinforcements to supports by means of tie wire. Wire must be black, soft iron wire, not less than 16 gage.
Reinforcement must be accurately placed, securely tied at intersections, and held in position during placing of concrete by spacers, chairs, or other approved supports. Point wire-tie ends away from the form.
Unless otherwise indicated, numbers, type, and spacing of supports must conform to ACI SP-66.
Bending of reinforcing bars partially embedded in concrete is permitted only as specified in ACI SP-66 and ACI 318.
3.4.8 Spacing of Reinforcing Bars
Spacing must be as indicated. If not indicated, spacing must be in accordance with the ACI 318 and ACI SP-66.
Reinforcing bars may be relocated to avoid interference with other reinforcement, or with conduit, pipe, or other embedded items. If any reinforcing bar is moved a distance exceeding one bar diameter or specified placing tolerance, resulting rearrangement of reinforcement is subject to preapproval by the Contracting Officer.
3.4.9 Concrete Protection for Reinforcement
Concrete protection must be in accordance with the ACI 318 and ACI SP-66.
3.4.10 Welding
Welding must be in accordance with AWS D1.4/D1.4M.
3.5 BATCHING, MEASURING, MIXING, AND TRANSPORTING CONCRETE
ASTM C94/C94M, ACI 301, ACI 302.1R and ACI 304R, except as modified herein. Batching equipment must be such that the concrete ingredients are consistently measured within the following tolerances: 1 percent for cement and water, 2 percent for aggregate, and 3 percent for admixtures. Furnish mandatory batch ticket information for each load of ready mix concrete.
3.5.1 Measuring
Make measurements at intervals as specified in paragraphs SAMPLING and
TESTING.
3.5.2 Mixing
ASTM C94/C94M, ACI 301 and ACI 304R. Machine mix concrete. Begin mixing within 30 minutes after the cement has been added to the aggregates. Place concrete within 90 minutes of either addition of mixing water to cement and aggregates or addition of cement to aggregates if the air temperature is less than 84 degrees F. Reduce mixing time and place concrete within 60 minutes if the air temperature is greater than 84 degrees F except as follows: if set retarding admixture is used and slump requirements can be met, limit for placing concrete may remain at 90 minutes. Additional water may be added, provided that both the specified maximum slump and water-cementitious material ratio are not exceeded and the required concrete strength is still met. When additional water is added, an additional 30 revolutions of the mixer at mixing speed is required. If the entrained air content falls below the specified limit, add a sufficient quantity of admixture to bring the entrained air content within the specified limits. Dissolve admixtures in the mixing water and mix in the drum to uniformly distribute the admixture throughout the batch. Do not reconstitute concrete that has begun to solidify.
3.5.3 Transporting
Transport concrete from the mixer to the forms as rapidly as practicable.
Prevent segregation or loss of ingredients. Clean transporting equipment thoroughly before each batch. Do not use aluminum pipe or chutes. Remove concrete which has segregated in transporting and dispose of as directed.
3.6 PLACING CONCRETE
Place concrete in accordance with ACI 301 Section 5.
[3.6.1 Pumping
ACI 304R and ACI 304.2R. Pumping must not result in separation or loss of materials nor cause interruptions sufficient to permit loss of plasticity between successive increments. Loss of slump in pumping equipment must not exceed 2 inches at discharge/placement.
3.6.1.1 Pumping Lightweight Concrete
ACI 213R. Presoak or presaturate aggregates. Cement content must be minimum of 564 pounds per cubic yard] and be sufficient to accommodate a 4 to 6 inch slump. Make field trial run in accordance with ACI 213R.
]3.6.2 Cold Weather
ACI 306.1. Do not allow concrete temperature to decrease below 50 degrees F.
Obtain approval prior to placing concrete when the ambient temperature is below 40 degrees F or when concrete is likely to be subjected to freezing temperatures within 24 hours. Cover concrete and provide sufficient heat to maintain 50 degrees F minimum adjacent to both the formwork and the structure while curing. Limit the rate of cooling to 37 degrees F in any 1 hour and 50 degrees F per 24 hours after heat application.
3.6.3 Hot Weather
Maintain required concrete temperature using Figure 4.2 in ACI 305R to prevent the evaporation rate from exceeding 0.2 pound of water per square foot of exposed concrete per hour. Cool ingredients before mixing or use other suitable means to control concrete temperature and prevent rapid drying of newly placed concrete. Shade the fresh concrete as soon as possible after placing. Start curing when the surface of the fresh concrete is sufficiently hard to permit curing without damage. Provide water hoses, pipes, spraying equipment, and water hauling equipment, where job site is remote to water source, to maintain a moist concrete surface throughout the curing period. Provide burlap cover or other suitable, permeable material with fog spray or continuous wetting of the concrete when weather conditions prevent the use of either liquid membrane curing compound or impervious sheets. For vertical surfaces, protect forms from direct sunlight and add water to top of structure once concrete is set.
3.6.4 Bonding
Surfaces of set concrete at joints, must be roughened and cleaned of laitance, coatings, loose particles, and foreign matter. Roughen surfaces in a manner that exposes the aggregate uniformly and does not leave laitance, loosened particles of aggregate, nor damaged concrete at the surface.
3.7 WASTE MANAGEMENT
Provide as specified in the Waste Management Plan and as follows.
3.7.1 Reinforcing Steel
Collect reinforcing steel and place in designated area for recycling.
3.8 SURFACE FINISHES EXCEPT FLOOR, SLAB, AND PAVEMENT FINISHES
3.8.1 Defects
Repair surface defects in accordance with ACI 301 Section 5.
3.8.2 Formed Surfaces
3.8.2.1 Tolerances
ACI 117 and as indicated.
3.8.2.2 As-Cast Rough Form
Provide for surfaces not exposed to public view a surface finish SF-1.0.
Patch holes and defects in accordance with ACI 301.
3.8.2.3 Standard Smooth Finish
Provide for surfaces exposed to public view a surface finish SF-3.0. Patch holes and defects in accordance with ACI 301.
3.9 FLOOR, SLAB, AND PAVEMENT FINISHES AND MISCELLANEOUS CONSTRUCTION
3.9.1 Finish
Place, consolidate, and immediately strike off concrete to obtain proper contour, grade, and elevation before bleedwater appears. Permit concrete to attain a set sufficient for floating and supporting the weight of the finisher and equipment. If bleedwater is present prior to floating the surface, drag the excess water off or remove by absorption with porous materials. Do not use dry cement to absorb bleedwater.
3.9.1.1 Steel Troweled
Use for floors intended as walking surfaces. Finish concrete in accordance with ACI 301 Section 5 for a steel troweled finish.
3.9.1.2 Nonslip Finish
Use on surfaces of exterior platforms, steps, and landings; and on exterior and interior pedestrian ramps. Finish concrete in accordance with ACI 301 Section 5 for a dry-shake finish. After the selected material has been embedded by the two floatings, complete the operation with a broomed finish.
3.9.1.3 Broomed
Use on surfaces of exterior walks, platforms, patios, and ramps, unless otherwise indicated. Finish concrete in accordance with ACI 301 Section 5 for a broomed finish. Broomed finish shall be perpendicular to path or walkway.
3.9.1.4 Pavement
Screed the concrete with a template advanced with a combined longitudinal and crosswise motion. Maintain a slight surplus of concrete ahead of the template. After screeding, float the concrete longitudinally. Use a straightedge to check slope and flatness; correct and refloat as necessary. Produce a fine, granular, sandy textured surface without disfiguring marks. Round edges and joints with an edger having a radius of 1/8 inch.
3.9.1.5 Concrete Toppings Placement
The following requirements apply to the placement of toppings of concrete on base slabs that are either freshly placed and still plastic, or on hardened base slabs.
a. Placing on a Fresh Base: Screed and bull float the base slab. As soon as the water sheen has disappeared, lightly rake the surface of the base slab with a stiff bristle broom to produce a bonding surface for the topping. Immediately spread the topping mixture evenly over the roughened base before final set takes place. Give the topping the finish indicated on the drawings
b. Bonding to a Hardened Base: When the topping is to be bonded to a floated or troweled hardened base, roughen the base by scarifying, grit-blasting, scabbling, planing, flame cleaning, or acid-etching to lightly expose aggregate and provide a bonding surface. Remove dirt, laitance, and loose aggregate by means of a stiff wire broom. Keep the clean base wet for a period of 12 hours preceding the application of the topping. Remove excess water and apply a 1:1:1/2 cement-sand-water grout, and brush into the surface of the base slab.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .