ATT_V_-_High_Mast_Poles_and_Foundations.docx

DOCX document 12 KB Posted

Attached to
Open End Electrical Requirements Contract Federal contract opportunity
Solicitation number
W91151-16-B-0021
Issued by
Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood

About this file

Tech Exhibit ATT V - High Mast Poles and Foundations Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Open End Electrical Requirements Contract, newest first.
File Type Posted
Tech_Exhibit_A_-_Bid_Schedule_REVISED_25AUG2016.xls XLS spreadsheet
W91151-16-B-00210-00002_Bid_Sheets_Revised.pdf PDF
Technical_Exhibit_B2_-_Specifications_REVISED.pdf PDF
Technical_Exhibit_B1_-_Division_1_Specifications_REVISED.pdf PDF
W91151-16-B-00210-00001_RFI.pdf PDF
ATT_A_Bid_Schedule_REVISED.xls XLS spreadsheet
ATT_P_-_Static_Ground_Details.pdf PDF
ATT_F_-_FM_10-67-1_-_Concepts_and_Equipment_of_Petroleum_Operations.pdf PDF
ATT_R_-_FH_REG_420-9_-_Energy_Conservation_Program.pdf PDF
ATT_A_Bid_Schedule.xls XLS spreadsheet
ATT_Q_-_Transformer_Concrete_Pad_Detail.pdf PDF
ATT_S_-_LED_FIXTURE_DETAIL.pdf PDF
ATT_D_-_Section_16520e_-_Exterior_Light_Fixtures_Schedule.pdf PDF
ATT_U_-_SPECIAL_PROVISIONS.pdf PDF
Technical_Exhibit_B_-_Division_1_Specifications.pdf PDF
Technical_Exhibit_B3_-_Electric_Meter_Specifications.pdf PDF
ATT_G_-_PAM_385-64_-_Ammunition_and_Explosives_Safety_Standards.pdf PDF
ATT_K_-_Handhole_Details.pdf PDF
ATT_C_-_Section_16510e_-_Interior_Light_Fixtures_Schedule.pdf PDF
ATT_M_-_In-Line_Electrical_Primary_Riser_at_90_Degrees_to_Line_Detail.pdf PDF
ATT_J_-_Trench_and_Grounding_Details.pdf PDF
ATT_T__-_Electrical_GIS_SOP.pdf PDF
W91151-16-B-0021.pdf PDF
ATT_H_-_AR_190-11_-_Physical_Security_of_Arms _Ammunition _and_Explosives.pdf PDF
ATT_L_-_In-Line_Electrical_Primary_Riser_Detail.pdf PDF
ATT_B_-_Specifications.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

High Mast Poles and Foundations

High Mast Lighting shall be supported on 100-ft tall H6 Galvanized Steel Pole with Base Plate unless specified otherwise. Anchor Bolt Cage shall be provided by steel pole vendor. It will be the responsibility of the contractor to coordinate shipment and delivery of Steel Pole and Anchor Bolt Cage. Contractor shall coordinate mounting requirements with steel pole vendor.

High Mast foundation design will vary based on subsurface soil conditions. Contractor shall provide the proper foundation from the options below:

Drilled Shaft Constructed In Clay:

36” Diameter 4000PSI Concrete Drilled Shaft Foundation Embedded 27 Feet with 3-ft reveal (30-ft Total Length). Reinforced with 16 - #10 Grade 60 Longitudinal Bars and 10 - #4 Grade 60 Ties at 6” O.C. followed by #4 Grade 60 Ties evenly spaced at 20” Max. O.C. to bottom of shaft.

Drilled Shaft NOT Constructed In Clay:

36” Diameter 4000PSI Concrete Drilled Shaft Foundation Embedded 18 Feet with 3-ft reveal (21-ft Total Length). Reinforced with 16 - #10 Grade 60 Longitudinal Bars and 10 - #4 Grade 60 Ties at 6” O.C. followed by #4 Grade 60 Ties evenly spaced at 20” Max. O.C. to bottom of shaft.