MOTCO STS Container Crane QA Log 4-29-21.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
Ship-To-Shore Container Cranes
Solicitation number
W56HZV-20-R-0025
Issued by

About this file

This document contains a question and answer log from a solicitation for two ship-to-shore container cranes. The U.S. Army Contracting Command - Detroit Arsenal issued solicitation W56HZV-20-R-0025 seeking proposals for two STS cranes to be delivered to Military Ocean Terminal Concord, California within 36 months of award. The cranes must be able to lift single and twin 20-foot containers as well as single 40- and 45-foot containers, and service a Panamax vessel with 13 containers abeam. Offerors must acknowledge all amendments and submit any questions in writing to the identified contracting specialist. The log contains 80 questions from potential offerors seeking clarification on various technical specifications and requirements, such as crane design loads, payment terms, and communication protocols. The government provides responses to help ensure offerors have a clear understanding of its needs.

View the file

Other files

File Type Posted
Attachment 0002 - Pricing Workbook (revised 06 JUN 2021).xlsx XLSX spreadsheet
W56HZV-20-R-0025 0006.pdf PDF
Attachment 0001 - STS Crane Specification (revised 26 MAY 2021).DOCX DOCX document
MOTCO STS Container Crane QA Log 5-26-21.pdf PDF
W56HZV-20-R-0025 0005.pdf PDF
W56HZV-20-R-0025 0004.pdf PDF
MOTCO STS Container Crane QA Log 5-14-21.pdf PDF
Attachment 0013 Site Visit Information (revised 29 APR 2021).docx DOCX document
W56HZV-20-R-0025 0004.pdf PDF
Attachment 0001 - STS Crane Specification (revised 26 APR 2021).DOCX DOCX document
MOTCO Crane Site Visit Sign-in Sheet (beta.sam).pdf PDF
W56HZV-20-R-0025 0003.pdf PDF
Attachment 0013 Site Visit Information (revised 26 APR 2021).docx DOCX document
Attachment 0016 - Structural Drawings.pdf PDF
Attachment 0011 - Appendix E (Revised 09 APR 2021).pdf PDF
W56HZV-20-R-0025 0002.pdf PDF
Attachment 0001 - STS Crane Specification (revised 09 APR 2021).DOCX DOCX document
MOTCO STS Container Crane QA Log 4-8-21.pdf PDF
MOTCO STS Container Crane QA Log 3-25-21.pdf PDF
Attachment 0013 - Site Visit Information (revised 23 MAR 2021).docx DOCX document
W56HZV-20-R-0025 0001.pdf PDF
MOTCO STS Container Crane QA Log 3-18-21.pdf PDF
MOTCO STS Container Crane QA Log 3-11-21.pdf PDF
MOTCO STS Container Crane QA Log 3-4-21.pdf PDF
Attachment 0013 - Site Visit Information.docx DOCX document
Attachment 0007 - Appendix A.pdf PDF
Attachment 0011 - Appendix E.pdf PDF
Attachment 0010 - Appendix D.pdf PDF
Attachment 0001 - STS Crane Specification.DOCX DOCX document
Attachment 0014 - NCIC CONSENT FORM.pdf PDF
Attachment 0008 - Appendix B.pdf PDF
Attachment 0002 - Pricing Workbook.xlsx XLSX spreadsheet
Attachment 0005 - SBP Certification - Subcontractor.docx DOCX document
W56HZV20R0025.pdf PDF
Attachment 0006 - Use of Existing Government-Furnished Property.xlsx XLSX spreadsheet
Attachment 0015 - MOTCO SITE VISIT SPREADSHEET.xlsx XLSX spreadsheet
Attachment 0003 - SBP Workbook.xlsx XLSX spreadsheet
Attachment 0012 - Appendix F.pdf PDF
Attachment 0009 - Appendix C.pdf PDF
Attachment 0004 - SBP Workbook Instructions.docx DOCX document
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Military Ocean Terminal Concord, CA (MOTCO) Ship-to-Shore Container Cranes

W56HZV-20-R-0025

Question and Answer Log

Question NumberDocumentQuestion/CommentsAnswer/ResponseDate ReceivedDate Posted
1SolicitationDo you have any update on the pre-meeting (site visit)?Please review Attachment 0013 of the solicitation in regards to information on the site visit.1-Mar-214-Mar-21
2SolicitationWhere specifications revised from the tender documents in 2019. Will you please provide a list of the changes, if a list is available?Some of the specifications have changed from the National Crane Center’s (NCC) solicitation, however, the Government does not have a complete list of those changes to provide with the solicitation.2-Mar-214-Mar-21
3SolicitationWill a proposal with a mono-girder, instead of a twin box girder, be accepted?A twin box girder is the Government's requirement, and as a result, is the only version that will be accepted.9-Mar-2111-Mar-21
4SolicitationIs there a bond requirement?No, no bonding will be required.9-Mar-2111-Mar-21
5SolicitationThe solicitation makes various references to mechanisms of application for payment, and of issuing payment. However there does not seem to be a reference to schedule (frequency) of payments but for 52.212-4 for Items Accepted. Is the Government considering allowing Installment Payments, Progress Payments, or another means of financing throughout the 36 months project schedule?The CLIN structure established in Section B allows for payments throughout the period of performance.5-Mar-2118-Mar-21
6SpecificationTechnical Specification item 3.9.9 Certificates – CDRL A010 states, in part: “The Crane shall be certified in accordance with the regulations of the U.S. Bureau of Labor Standards under Title 29, Subtitle B Part 1919 (latest edition) and any local codes as applicable”
Is it correct to understand that even though located in a military facility, these cranes will not be subject to any particular certification program (such as the Navy’s P-307) but instead a commercial certification as above required?That is correct, the NAVFAC P-307 is a Navy requirement. This requirement is now an Army requirement.10-Mar-2118-Mar-21
7SolicitationSolicitation paragraph C.1.2 item 5) states “Scale model and souvenir models; refer to Attachment 0001 MOTCO STS Crane Specifications, Section 2.5.15”. Attachment 0001, while showing an item 2.5.15 Scale Models in its index, when searching for it, it does not exist. Instead, item 2.5.15 refers to Stairs, Ladders, Platforms, and Walkways (page 170 of 204). The Scale Models paragraph seems to have been deleted from Attachment 0001. Are the scale model and souvenir models actually a requirement in this solicitation? If so, please provide the details of scale desired and materials to be used.The scale and souvenir requirement has been removed from the solicitation and an amendment is forthcoming to remove the language in C.1.2.12-Mar-2118-Mar-21
8Site VisitAttachment 0013 does not mention any PPE. Besides sturdy shoes, are there any other protective items we need to bring with us?Attendees will need closed toe shoes and face coverings (i.e. masks) in order to gain access to MOTCO. An amendment is forthcoming to update Attachment 0013.
17-Mar-2118-Mar-21
9Site VisitWill there also be a sit-down meeting / discussion regarding any aspects of the solicitation during this visit – in addition to visiting Wharf 2?No, there will be a virtual Q&A Session where questions can be asked, that will take place a few weeks after the site visit. An amendment is forthcoming to update Attachment 0013.17-Mar-2118-Mar-21
10SolicitationPlease advise where Section B, referred to in Answer #5, is located in the Solicitation.Section B begins on page 4 and goes through page 24 of the solicitation.18-Mar-2125-Mar-21
11Site VisitDue to the change of date for the Site Visit (Amendment 0001), are the visitors passes already approved for access still valid?Yes, the visitor passes are still valid.23-Mar-2125-Mar-21
12Specification para 1.1The specification defines Contractor’s EOR as “… Contractor’s professional engineers for the design…” and refers to a Section 1.3.8 that has been RESERVED. Can you please clarifyAttachment 0001 para 1.1 (Contractor's EOR) has been updated and now references Section C.2.1.1 of the Solicitation.24-Mar-218-Apr-21
13Specification para 2.2.9Please confirm a flange bolted connection can be used at the top of the legs.Yes, a flange bolted connection can be used at the top of the legs.24-Mar-218-Apr-21
14Specification para 2.2.24.2(c)Please confirm Load Combination is “DL + TL + LS +LL + LIST + TRIM + PLL + COLL + WLO” (LL and PLL removed). Load combination defined is inconsistent with 1.13.4 where trolley is stowed, no load on lift system and trolley drive is not operational.For the boom 45 and 80 cases, the LL may be removed, but the PLL shall be included. Design should review with and without PLL included.24-Mar-218-Apr-21
15Specification para 2.2.24.2(d)Please confirm Load Combination is “DL + TL + LS +LL + LIST + TRIM + PLL + COLL + WLO” (LL and PLL removed). Load combination defined is inconsistent with 1.13.4 where trolley is stowed, no load on lift system and trolley drive is not operational.For the boom 45 and 80 cases, the LL may be removed, but the PLL shall be included. Design should review with and without PLL included.24-Mar-218-Apr-21
16Specification para 2.2.24.2(f)Please confirm Load Combination is “DL + TL + LS +PLL + EQO” (PLL removed). Load combination defined is inconsistent with 1.13.4 where trolley is stowed, and trolley drive is not operational.PLL loading shall be included. There is no control to ensure the PLL has been removed prior to a EQO event, even with boom raised. Design should review with and without PLL included.24-Mar-218-Apr-21
17Specification para 2.2.24.3(b)Please confirm Load Combination is “DL + TL + LS +PLL + EQC” (PLL removed). Load combination defined is inconsistent with 1.13.4 where trolley is stowed, and trolley drive is not operational.PLL loading shall be included. There is no control to ensure the PLL has been removed prior to a EQO event, even with boom raised. Design should review with and without PLL included.24-Mar-218-Apr-21
18Specification para 2.2.24.3(c)Please confirm Load Combination is “DL + TL + LS +PLL + EQC” (PLL removed). Load combination defined is inconsistent with 1.13.4 where trolley is stowed, and trolley drive is not operational.PLL loading shall be included. There is no control to ensure the PLL has been removed prior to a EQO event, even with boom raised. Design should review with and without PLL included.24-Mar-218-Apr-21
19Specification para 2.2.25.1Please revise number of cycles shown in the fatigue spectra. The number of cycles in the figure adds up to 4,000,000 but the number of cycles in paragraphs 1.11, 2.2.1 & 2.2.25 is specified to be 2,000,000.The Government response is forthcoming to this question.24-Mar-21-
20Specification para 2.2.28.2Please confirm the trolley is only at the stowed position, not the maximum back reach. This conflicts with 1.13.4 where trolley is stowed.The Government response is forthcoming to this question.24-Mar-21-
21Specification para 2.2.28.2(a)Please confirm Stability Combination is “DL + TL + LS +PLL + 1.5 WLO” (PLL removed). Boom at 45°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to raising the boom.24-Mar-218-Apr-21
22Specification para 2.2.28.2(b)Please confirm Stability Combination is “DL + TL + LS +PLL + 1.5 WLO” (PLL removed). Boom at 80°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to raising the boom.24-Mar-218-Apr-21
23Specification para 2.2.28.2(c)Please confirm Stability Combination is “DL + TL + LS +PLL + 1.15 COLL” (PLL removed). Boom at 45°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to a COLL event. Design shall review with and without PLL.24-Mar-218-Apr-21
24Specification para 2.2.28.2(d)Please confirm Stability Combination is “DL + TL + LS +PLL + 1.15 COLL” (PLL removed). Boom at 80°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to a COLL event. Design shall review with and without PLL.24-Mar-218-Apr-21
25Specification para 2.2.28.2(e)Please confirm Stability Combination is “DL + TL + LS +PLL + EQC” (PLL removed). Boom at 45°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to a EQC event. Design shall review with and without PLL.24-Mar-218-Apr-21
26Specification para 2.2.28.2(f)Please confirm Stability Combination is “DL + TL + LS +PLL + EQC” (PLL removed). Boom at 80°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to a EQC event. Design shall review with and without PLL.24-Mar-218-Apr-21
27Specification para 2.2.28.3(c)Please confirm Stability Combination is “DL + TL + LS +PLL + EQC” (PLL removed). Boom at 45°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to a EQC event. Design shall review with and without PLL.24-Mar-218-Apr-21
28Specification para 2.2.28.3(d)Please confirm Stability Combination is “DL + TL + LS +PLL + EQC” (PLL removed). Boom at 80°. Including PLL will increase the ballast in the WS sill beam, which will increase the wheel loads.According to Note: "The PLL shall be applied or not applied, whichever is more severe." There is no control to ensure the PLL has been removed prior to a EQC event. Design shall review with and without PLL.24-Mar-218-Apr-21
29Specification para 2.2.29.1(a)Boom at 45°. Please confirm Stability Combination is “DL + TL + LS + PLL + 0.3 LATG” (PLL removed). Conflicts with 2.2.16.2 which does not include PLL.Note 3. "For combinations including the platform live load (PLL), PLL shall be applied or not applied, whichever is more severe for each load combination." shall dictate.24-Mar-218-Apr-21
30Specification para 2.2.29.1(a)Boom at 45°. Please confirm Stability Combination is “DL + TL + LS + PLL + 0.5 WLO” (PLL removed). Conflicts with 2.2.16.2 which does not include PLL.Note 3. "For combinations including the platform live load (PLL), PLL shall be applied or not applied, whichever is more severe for each load combination." shall dictate.24-Mar-218-Apr-21
31Specification para 2.2.29.1(b)Boom at 80°. Please confirm Stability Combination is “DL + TL + LS + PLL + 0.3 LATG” (PLL removed). Conflicts with 2.2.16.2 which does not include PLL.Note 3. "For combinations including the platform live load (PLL), PLL shall be applied or not applied, whichever is more severe for each load combination." shall dictate.24-Mar-218-Apr-21
32Specification para 2.2.29.1(b)Boom at 80°. Please confirm Stability Combination is “DL + TL + LS + PLL + 0.5 WLO” (PLL removed). Conflicts with 2.2.16.2 which does not include PLL.Note 3. "For combinations including the platform live load (PLL), PLL shall be applied or not applied, whichever is more severe for each load combination." shall dictate.24-Mar-218-Apr-21
33SolicitationDoes lighting require UL1598A, to be in line with the “marine grade” language?Marine grade shall require compliance with UL1598, UL1598A, and IP66.25-Mar-218-Apr-21
34SolicitationWill the sign up sheet from the site visit and virtual Q/A be available on SAM later? We are interested in seeing who the primes will be bidding.The Government anticipates posting this information with permission from those Contractors in attendance at the site visit and/or virtual Q&A session. Please watch on betaSAM.gov for any updates.25-Mar-218-Apr-21
35SolicitationWill Buy American Act (BAA) be required for the STS crane?No. Offerors shall refer to Section A, "Trade Agreement Note" and Section L.4.4.1.1.25-Mar-218-Apr-21
36SpecificationThe Technical Specification alternates using International Electro technical Commission (IEC) and National Electrical Manufacturers Association (NEMA) standards when addressing electrical components. Are we to understand that said components -motors and transformers included, could be selected according to the corresponding IEC standards for them? Motors according to IEC standards would certainly weigh less and contribute more favorably to keeping within the allowable pier loads.Specification 1.2.4 Substitution of Codes, allows for either code to apply, except for NEMA & NFPA. If IEC standards meet the requirements of NEMA and NFPA, then IEC standards are acceptable.26-Mar-218-Apr-21
37Specification para 2.4.12Technical Specification 2.4.12 MOTORS FOR THE MAJOR MOTIONS requires that they be sized “… and in accordance with FEM1.001 for continuous operation”. However, the Boom Hoist (which duty cycle duration is estimated at 10 min) and Gantry motors (estimated at 6 min) are the type that never see continuous operation for any extended period of time. Thus, can those be sized using motor ratings: S2-30 minutes?The boom and gantry motors may be sized S2-30 minute rating.26-Mar-218-Apr-21
38Specification para 2.4.2Technical Specification 2.4.2 MAIN AND SORE POWER SUPPLY: Please, advise the short circuit current (or power) at the pit connection box.This information is not available at this time. For design purposes, use 6000 amps @ 12kV as the maximum short circuit current for main power and 10,000 amps @ 480v for the shore power maximum short circuit current.26-Mar-218-Apr-21
39Specification para 1.3.5Attachment+0001+-+STS+Crane+Specification in Para. 1.3.5 Performance Requirements, indicates: “Performance requirements for the Cranes shall be as follows:

Minimum Hoist High Speeds:

No Load under spreader 490 ft/min (150 m/min) Rated Load under spreader 250 ft/min (76 m/min)”

Specification does not provide any other point in between as to the relationship between hoisting speed and load, nor does it specify any criteria such as keeping constant-power for any speed-load combination. Please, clarify the intent of the specification in this regard.The intent of the specification is to maximize performance of the crane by utilizing the maximum allowable available speed based on torque. Thus, in keeping within the machine ratings based on the specified base speed load, and the no load maximum speed, the speed/torque curve should maximize the speed of the hoist based on utilizing concept of constant horsepower.30-Mar-218-Apr-21
40Specification para 2.4.9Attachment+0001+-+STS+Crane+Specification in Para. 2.4.9 Converters states:

“There shall be at least two fully regenerative converter sections to provide the main DC bus”; and later on “…The converters shall dump excess power to resistors. The resistor bank shall be located outdoors, exterior of the machinery house. The resistors and their enclosures shall be stainless steel. The resistors shall be mounted in substantial enclosures designed to permit the free flow of air sufficient to cool the resistors by natural convection when operating within their current rating. The resistors shall be sized based on the duty cycles and load spectra contained in this specification”.

Note that fully regenerative converters do not dump excess power to resistors because excess power is regenerated to the main power supply. Thus, please remove “The converters shall dump excess power to resistors. The resistor bank shall be located outdoors, exterior of the machinery house. The resistors and their enclosures shall be stainless steel. The resistors shall be mounted in substantial enclosures designed to permit the free flow of air sufficient to cool the resistors by natural convection when operating within their current rating. The resistors shall be sized based on the duty cycles and load spectra contained in this specification” from the paragraph.The intent of the specification is to have no regenerative power returned to the power line through regeneration. Regenerative power should be dissipated by a resistor bank connected to the drive DC bus. If this can be accomplished by using a reversing, non-regenerative drive arrangement, and the regenereative energy is dissipated by the resistor bank, then a 4 quadrant regenerative converter is not required.30-Mar-218-Apr-21
41SolicitationHas the government established a Rough Order of Magnitude price for this solicitation based on the previous, recent & directly related solicitations and can you provide us this price?No, the Government will not providing its internal Government estimate to Industry for this effort.30-Mar-218-Apr-21
42SolicitationHave 2021 funds been appropriated for this project for the full amount of the ROM (or any amount)?Assurance of funding for this anticipated contract has been received.30-Mar-218-Apr-21
43Solicitation and Q&A #5Can you check FAR 52.232-30 and include in the contract clauses? Firm Fixed Price Payments for acceptance of priced CLINs 1-6 (i.e. CLIN Structure) at destination creates a significant financial burden - as we are performing extensive work off-site and are accumulating large costs early in the project with payments at the end of the project. This financial burden may reduce the number of vendors willing to participate in this Solicitation or result in finance / interest costs that will be passed to the government. Specifically, CLIN 1 includes Solicitation Section 2.3.10 - “Field Notice of Revisions” -which cannot be completed and accepted until the very end of the project after delivery and site testing. Also, specifically, CLIN 2 states that - delivery at destination is required for acceptance - and further states that all of the technical requirements of Section 3.0 (i.e. Section 3.3) are fulfilled which also states that the crane needs to delivered at the destination. The term “Fabrication” is not defined in Section 3.0. We request that FAR 52.232-30 is checked and included for these CLIN’s in the contract clauses so that we can receive installment payments toward the costs incurred on the items and services that are continuously performed throughout the project to complete the Work.The Government has reviewed over applicable financing clauses and it does not plan to add them to the Solicitation.30-Mar-218-Apr-21
44SolicitationAre there any penalties or liquidated damages for late delivery?FAR Clause 52.211-11, Liquidated Damages - Supplies, Services, or Research and Development have been added via Amendment 0003 to the solicitation.30-Mar-2129-Apr-21
45Specification para 1.2.4Regarding - Substitution of Codes, are we correctly understanding that AISC, ASTM, AWS, NEMA, NFPA and OSHA cannot be substituted with other codes – because they are governing codes?The Contractor is required to demonstrate compliance with these standards.30-Mar-2129-Apr-21
46SolicitationAre these cranes, located on MOTCO’s Pier, used strictly for the purpose of supporting DOD missions? Are the cranes used for any commercial shipping involving commerce / trade activities?The STS Cranes are strictly for DoD missions and will not be involved in commercial shipping.30-Mar-218-Apr-21
47SpecificationIt has been noted in the provided Word document, “Attachment+0001+-+STS+Crane+Specification.docx” there are multiple areas where changes have been tracked within Word, but are not fully accepted and updated. This can be viewed when print preview or printing to any device. Will a revised specification be provided with all tracked changes accepted and fully updated cross references be supplied?The Government recognizes the tracked changes that appear when Attachment 0001 is in print preview mode; however, those tracked changes have no bearing on the technical requirements and seem to be an error within the document.30-Mar-218-Apr-21
48Attachment 0007, Appendix A, Page 9Additional clarification is needed for the design loads for the pier and trestle. Design load B.1 states that the maximum design load on the main pier structure is 600 PSF. Does this value include the trestle? This value seems unrealistically low (i.e. can’t drive a car or truck or walk on the pier). What is the intent of this design load limitation?The Pier 2 drawing sheets S-002 and SR-001 [to be included] show the design loading criteria for the Pier/West Trestle and the East Trestle (following repairs) respectively. The 600 PSF Uniform live load conforms with the UFC criteria for Ammunition Piers.30-Mar-218-Apr-21
49Attachment 0007, Appendix A, Page 9Regarding the design loads for the main pier and trestle - what are the maximum loads allowed for temporary installation equipment and staging?

a. Maximum wheel loads (live loads) for Rubber Tire Self-Propelled Modular Transporters or other closely spaced wheeled carts.

b. Maximum uniformly distributed ground loads (live loads) for support of outriggers, temporary jacking, skidding, rolling or sliding equipment and their associated mats.

c. Uniformly distributed ground loads (dead loads) for staging components in containers, pallets or on dunnage.

d. Is the main pier and trestle suitable for legal over the road truck loads (live loads)? If not please provide the load limits.See response to Question 48. Offerors should use the pier structural design drawings for any load conditions that require additional analysis. (Full structural drawing set to be added to solicitation documents).30-Mar-218-Apr-21
50Specification para 1.12.10Crane specification requires Contractor to submit a Duty Cycle Analysis (Section 1.12.10). Does this analysis require the use of 3rd party software, or can Contractor use their internal computer process / methods?The Contractor may use internal computer processes and methods provided sufficient information is submitted to allow independent verification of results. The use of specific third party software is not required by specification.30-Mar-218-Apr-21
51Specification para 1.13.7Crane specification Section 1.13.7 requires crane to operate in Limping Mode should one or more systems not work as intended. Can Government provide a better definition on conditions which would trigger the Limping Mode functionality? What specific systems which when not working would trigger this mode?The intent is to design the crane and controls such that if a single system fails, the crane can continue to function at lower speeds, powers, or capacities where possible; recognizing that in many, but not all cases, it may not be advisable or possible to continue operation depending on what fails. An example of an intended limping mode is if one of the hoist inverters fails, the crane must be designed to still operate at reduced power using the remaining hoist inverter. The intent is not to add additional redundant systems unless otherwise specified.30-Mar-218-Apr-21
52SpecificationWhat is the Main Power Supply available short circuit current at the primary side of the crane’s medium voltage transformer?This information is not available at this time. For design purposes, use 6000 amps @ 12kV as the maximum short circuit current for main power and 10,000 amps @ 480v for the shore power maximum short circuit current.30-Mar-218-Apr-21
53Specification para 2.5.13Since Arc Flash Warning Labels per NFPA 70E are required per Section 2.5.13, will Government require a formal Arc Flash Hazard Analysis be a submittal document for all control enclosures?Yes, a formal Arc Flash Hazard Analysis must be submitted and all warning labels installed as specified.30-Mar-218-Apr-21
54Specification para 2.4.11To get to the required Power Factor criteria in Section 2.4.11, is it acceptable to utilize an Active Front End (AFE) with Line Regeneration in place of using converters and dynamic braking resistors?If AFE converters are required to meet the power factor and harmonic filter functions, they may be used. However, no regenerative power can flow to the MV power supply.30-Mar-218-Apr-21
55Specification para 2.4.23Per section 2.4.23, PLC Communications to remote I/O is to be provided using “standard bus protocol approved by Government.” Can Government provide a list of these approved communication bus protocols?The Government response is forthcoming to this question.30-Mar-21-
56SolicitationSolicitation Section C.1.2 item 4) indicates that the test weights are to be part of the scope of supply as per Attachment 0001 MOTCO STS Crane Specifications, Section 2.5.14. Yet Section H.3.8 Government Work and Material states “The Government will provide the test weights, rigging gear, and power, to perform the tests at no cost to the Contractor.” Please, clarify whether those test weights are to be included in the scope of supply.Section H.3.8 will be revised in Amendment 0002 and will read, "The Contractor will perform the final acceptance tests of the crane as described in the contract. The Government will provide the power to perform the tests at no cost to the Contractor."5-Apr-218-Apr-21
57Specification para 2.4.2Attachment 0001 MOTCO STS Crane Specifications, Section 2.4.2 Main and Shore Power Supply states “The main power supply shall be provided from a 12000 V,. 3-phase plus PE 60 Hz wharf main distributor transformer.” However, Appendix A, Drawing E602 indicates that voltage at which the power is supplied to the crane power cable is 4160 V. Please, confirm that 4160 V is the voltage that will be supplied to the cranes.The power provided for the cranes will be 12kV. Drawing E602 has recently become outdated. A new drawing replacement is not available at this time.5-Apr-218-Apr-21
58Appendix EAppendix E: Essential Repair PartStockage List‐ STS Crane identifies 2 ea. UPS 120V‐2000A. We understand there is a typo and the unit should be UPS 120V-2000VA. Please, confirm.Confirm. Power supply should be 120V-2000VA. Appendix E has been updated with this change.5-Apr-218-Apr-21
59Appendix EAppendix E: Essential Repair PartStockage List‐ STS Crane identifies 10 ea. festoon cable roller wheels and side wheels. Yet, Attachment 0001 MOTCO STS Crane Specifications in 2.4.18 Trolley Cable Chain (Energy Chain) specifies a means of powering the trolley that is not consistent with the repair parts. Therefore, please remove the repair parts from the list.Confirm. "Festoon cable roller wheels and side wheels" should be removed from the spare parts list. Appendix E has been updated with this change.5-Apr-218-Apr-21
60Specification para 1.3.4Attachment 0001 MOTCO STS Crane Specifications, Para. 1.3.4 Design Requirements states “The Cranes shall, as a minimum, conform to the requirements of the Machinery Directive 2006/42/EC, the Low Voltage Directive 73/23/EC and the EMC Directive 89/336/EC”. It is our understanding that these international standards are not applicable since they are to be followed to obtain a certification with legal standing in Europe and not the U.S. where these cranes will be operating. We request that this paragraph be removed from the Specification as well as the reference to these standards in 1.2.3.Concur. Attachment 0001 has been updated in Amendment 0003.8-Apr-2129-Apr-21
61Specification para 1.2.2Attachment 0001 MOTCO STS Crane Specifications, Para 1.2.2 US Domestic Codes and Standards and Specifications addresses the OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) by referring to Title 29 CFR, Part 1910. It is our understanding that Title 29 CFR Part 1917 Marine Terminals should be the primary reference for this project since Pier 2 is for marine operations. That is, the regulations detailed in Part 1917 will have precedence over those of Part 1910 in case of inconsistency. Please confirm whether our understanding is correct; and if so, amend Attachment 0001.29 CFR Part 1917 can supersede 29 CFR Part 1910, but the requirements of 29 CFR Part 1910 shall still be met unless specifically modified by 29 CFR 1917.8-Apr-2129-Apr-21
62Virtual Q&A ConferenceIs there a limit on the amount of individuals that can attend the Virtual Q&A Conference.At this time, there is no limitation as to how many individuals may register for the virtual Q&A session. Please submit any questions you and your team may have prior to the virtual Q&A event so we can provide responses at that time.
Based on the responses to Q&As that have been posted to date, the Government has determined to cancel the Virtual Q&A Conference. Q&As will continue to be posted at the Government's discretion as time allows. All Q&As that were received within the 30 day Q&A window have been responded to and posted on betaSAM.gov.9-Apr-2129-Apr-21
63SolicitationDue to the nature of the materials handled, some of our suppliers may not want to participate in or be able to participate in suppling technology for this project. We feel that full disclosure is appropriate in order to work with our compliance department to provide proper identification of technology used on these cranes. Are any of the items handled by the crane, (e.g. in containers or break bulk), identified on the Commerce Control List?15-Apr-21
64SolicitationAre any of the items handled by the crane, (e.g. in containers or break bulk), subject to the Export Administration Regulations?15-Apr-21
65SolicitationAre any of the items handled by the crane, (e.g. in containers or break bulk), subject to the International Traffic in Arms Regulations?15-Apr-21
66Solicitation A0001 NarrativeIs there a waiver and can you provide the written waiver granted in accordance to DFARS 225.403 so we can see exactly what it states? Also, specifically, what section (i.e. exact paragraph) of DFAR 225.403 is the bases of the waiver. We do not believe a waiver is valid for this solicitation for a Domestic Purchasing Activity.ACC-DTA does not have a waiver to provide. In accordance with DFARS 225-403(c)(ii) the basis of the waiver comes from 19 U.S.C. 2512(b)(2). The Government recommends reviewing that statute to see if applies to your organization.15-Apr-2129-Apr-21
67Solicitation A0001 NarrativeThe government has stated that “pier 2 at MOTCO is responsible for 25% of the nation’s total ammunition supply”. The importance of these cranes for national security can be logically concluded. Therefore, DFAR 225.401 statement holds true that this is – “an individual acquisition of a product to be indispensable for national security or national defense purposes and appropriate for exclusion from the provisions of FAR Subpart 25.4”. Please confirm that the exclusion in DFAR 225.401 is applicable to this solicitation?The Government has not determined this procurement to be an exception to DFARS Subpart 225.4 and the end product is subject to Trade Agreements in accordance with DFARS 225.401-70, as stated within the solicitation.15-Apr-2129-Apr-21
68Solicitation A0001 NarrativeAfter reviewing the details of the Product Services Groups in the WTO agreement, these cranes are not covered in the WTO agreement. Any reference to World Trade Agreements should be deleted from the requirements. Any waivers dealing with the WTO agreements are therefore not applicable.The cranes are considered Materials Handling Equipment and therefore are covered by the trade agreements.15-Apr-2129-Apr-21
69Q&A Log #43Specific clarification is required for payment on CLIN 2 – “Fabrication”. Provide governments definition of fabrication that will fulfill this requirement. Because fabrication is performed at our fabrication facility, please confirm that the Government will pay Firm Fixed Price for CLIN 2 at the Suppliers fabrication facility when all items are fabricated? Will the government accept a schedule of values totaling the amount of CLIN 2 and allow the supplier to submit invoices for each item in the schedule of values when they are fabricated? We feel, that without payments for completed fabricated items, it will create undo burden to suppliers for complex cranes that need to comply with a 200+ page technical specification.CLIN 0002 is in accordance with Specification (Attachment 0001) Section 3.0 and can be invoiced once the Factory Testing, as described in Specification 3.2.3, has been completed.

The Government is not clear on what "schedule of values" means; however, if this question is referring to performance based payments, then no. This effort is not subject to performance based payments and CLIN 0002 will remain as is.

15-Apr-2129-Apr-21
70Q&A Log #43Will the government also consider a schedule of values for CLIN 1 and provide payment for items on the schedule when completed?Please refer to the response for Q&A #69. This effort is not subject to performance based payments and CLIN 0001 will remain as is.15-Apr-2129-Apr-21
71Q&A Log #48 & 49In Q&A #48, it was stated that the 600 PSF load is in alignment with the UFC criteria. During the walk-down it appears that the pier is a significant structure capable of much higher design loads and maybe it better aligns with UFC classification for “container” loads and is suitable for 1000 PSF loading or even higher loads. Can the government review the pier design and allow higher pier loadings for installation of the cranes?15-Apr-21
72Q&A Log #48 & 49Likewise, can a larger mobile crane be used with higher outrigger float loads?15-Apr-21
73Q&A Log #48 & 49What is the applicable year / version for the UFC and where can the document be obtained?15-Apr-21
74SolicitationSEE EMAILED QUESTION. It was too big to copy into the cell. I will revised the question, but wanted you to have the context.19-Apr-21
75SpecificationThe government requires the Platform Live Load (PLL) be included when the boom is raised to 45 or 80 degrees. This requirement will decrease the stability of the crane and may require additional ballast be added at or near the waterside rail for the crane to comply with the specified stability criteria. The additional ballast at or near the waterside rail, if required, would increase the waterside wheel loads during cargo operations, which may result in the waterside wheel loads exceeding the specified allowable wheel loads. It may be impossible to comply with the specified wheel load requirements if PLL is included in the boom raised stability combinations.

Please confirm PLL will be removed from the boom raised stability requirements.

19-Apr-21
76SolicitationPlease, provide the slab details between the beams from PD-PK, as indicated in attached file S-302.pdf19-Apr-21
77SpecificationAttachment 0001 MOTCO STS Crane Specifications, Para.3.3 Delivery stated “The Cranes may be partially disassembled to achieve transportation height restrictions and to provide options for vessel and/or barge selection.” Solicitation Section C.2.6.5 Transport Manual, item 9. states “Shipment of Cranes via a barge is prohibited”.

Please, remove this item 9 from the solicitation in order to allow offeror to choose the best arrangement for delivery of the cranes according to its project plans.

19-Apr-21
78Solicitation Section LSolicitation Section L.4.4 Volume 4 - Proposal Terms and Conditions , Para. L.4.4.1 states “Signature Actions/Offeror Fill-Ins. A scanned image of a signed copy of the SF1449 cover page and a copy of all completed fill-ins for Sections A through K, including all signed copies of Amendments to the solicitation. System for Award Management (SAM) certifications need not be separately submitted; however, all offerors must be successfully registered and valid in SAM prior to award.”
It is our understanding that the requirement is to only submit form SF1449 and corresponding forms SF30 for each of the Amendments appropriately signed; as well as only those pages that have fill-ins for Sections A through K. That is, you are not seeking for offerors to include all of the pages of the Solicitation and Amendments in the offer. Is it our understanding correct?Yes, your understanding is correct. The SF1449 signed cover (and subsequent SF30 cover pages), along with any other pages that have fill-ins for Sections A-K, need to be submitted.23-Apr-2129-Apr-21
79Solicitation Section LSolicitation Section L.4.2.3 Attachment 0002 Pricing Workbook, states: “Offerors shall submit Attachment 0002 - Pricing Workbook with its proposal. Complete the attachment in accordance with the instructions included within the attachment. Propose Firm-Fixed-Prices for all CLINs included in the Attachment. Submit the attachment in Microsoft Excel format. Do not enter any proposed prices into Section B of the RFP.”
It is our understanding that based on this paragraph, the fill-in spaces in Section B are not to be completed, disregarding what Section L.4.4, Para L4.4.1 indicates. Please confirm.Correct, Section B should not be filled out. Offerors shall complete Attachment 0002 - Pricing Workbook, in lieu of Section B.23-Apr-2129-Apr-21
80SpecificationsDoes the government have a blueprint available that has estimated fixture locations for the main floodlights, walkway lights and machine house lights? Or is this up to the prime bidder?26-Apr-21