Attachment 0002 - PWS 2 Facility Planning.docx

DOCX document 38 KB Posted

Attached to
Radford Army Ammunition Plant - DRAFT Solicitation
Solicitation number
W519TC26RA046
Issued by

About this file

This is a Performance Work Statement (PWS) for Facility Plans, Strategies, and Analyses at Radford Army Ammunition Plant (RFAAP), effective April 2026. The contractor shall provide planning, analysis, and management services to support RFAAP facility modernization and investment strategy across three project types: Provision of Industrial Facilities (new capabilities, capacity expansion, or modernization); Layaway of Industrial Facilities (transitioning equipment to long-term storage); and Maintenance of Inactive Facilities (preserving laid-away facilities for future readiness).

Key technical requirements include submission of an annual PWS 2 Execution Plan 30 calendar days prior to each year, maintenance and annual updates of a 15-Year Strategic Modernization Roadmap planned against a $3.5B to $4.5B notional budget envelope, and provision of a complete actionable response to the Government's annual Production Base Support (PBS) Call Letter by 31 May or upon receipt. The contractor must submit ten P-25 project planning documents annually with detailed justifications, risk analyses, and cost estimates aligned to AACE International Classifications. Additional obligations include hosting minimum three Program Management Reviews annually at RFAAP, maintaining a prioritized project requirements database with bi-weekly stakeholder meetings and monthly exports, providing support to Government-contracted third-party efforts, implementing robust financial tracking for funded projects, and submitting monthly PWS 2 KPI Reports measuring call letter response completeness, P-25 submission delivery, database management accuracy, and a minimum of three contractor-identified efficiency metrics. Corrective Action Plans must be submitted if any KPI trends negatively or falls below target for three consecutive months.

View the file

Other files

File Type Posted
Attachment 0007 - PWS 7 Maintenance.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Attachment 0001 - PWS 01 RFAAP Environmental.docx DOCX document
Attachment 0013 - PWS 13 Technology and Cybersecurity.docx DOCX document
Attachment 0004 - PWS 4 Property.docx DOCX document
Solicitation - W519TC26RA046.pdf PDF
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Exhibit B - PWS CDRLs.pdf PDF
RFAAP Solicitation - W519TC26RA046.pdf PDF
Attachment 0019 - Price Matrix_v2.xlsx XLSX spreadsheet
Attachment 0029 - Non-Disclosure Agreement Azimuth.docx DOCX document
Attachment 0002 - PWS 2 Facility Planning.docx DOCX document
Attachment 0030 - Non-Disclosure Agreement NEPSCO.docx DOCX document
Attachment 0012 - PWS 12 - ARMS.docx DOCX document
Attachment 0031 - Wage Determinations.pdf PDF
Attachment 0001 - PWS 01 RFAAP Environmental.docx DOCX document
Attachment 0024 - RFAAP GFP Listing.xlsx XLSX spreadsheet
Attachment 0015 - PWS 15 - ALTESS.docx DOCX document
Attachment 0009 - PWS 9 Safety-Occupational Health-Industrial Hygiene.docx DOCX document
Exhibit A - CDRLs.pdf PDF
Attachment 0018 - PWS 18 - Ground Water Monitoring - Installation Restoration Program Support.docx DOCX document
Attachment 0007 - PWS 7 Maintenance.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Attachment 0026 - Hazardous Material Classification Specification.xlsx XLSX spreadsheet
Attachment 0004 - PWS 4 Property.docx DOCX document
Attachment 0011 - PWS 11 RFAAP Facility Ops and Production Reporting.docx DOCX document
Attachment 0028 - COCO SECURITY STATEMENT OF WORK 2025.docx DOCX document
Attachment 0010 - PWS 10 RFAAP Energy and Utilities.docx DOCX document
Attachment 0022 - SAMPLE OPSEC ACQUISITIONS PLAN.pdf PDF
Attachment 0021 - OPSEC SOW.docx DOCX document
Attachment 0032 - Mission Essential Services.pdf PDF
Attachment 0020 - TDP Section C Exeptions_Redacted.pdf PDF
Attachment 0019 - Price Matrix_Indemnification v2.xlsx XLSX spreadsheet
Exhibit B - PWS CDRLs.pdf PDF
Attachment 0003 - PWS 3 Fire Protection and Emergency Services.docx DOCX document
Attachment 0013 - PWS 13 Technology and Cybersecurity.docx DOCX document
Attachment 0033 - Small Business Participation Commitment Document.docx DOCX document
Attachment 0025 - CDRL Instructions.pdf PDF
Attachment 0017 - PWS 17 Transition Out.docx DOCX document
Attachment 0023 - DD254 Contract Security Classification Specification.pdf PDF
Attachment 0027 - ARMS Tenant Use Agreements.pdf PDF
Attachment 0008 - PWS 8 - Transition In.docx DOCX document
Attachment 0034 - Past Performance Questionnaire.docx DOCX document
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RADFORD ARMY AMMUNITION PLANT

PERFORMANCE WORK STATEMENT (PWS)

PWS 2: Facility Plans, Strategies, and Analyses April 2026

1. Scope and Objectives

The Contractor shall provide the planning, analysis, and management necessary to support the RFAAP facility modernization and investment strategy. This includes capacity planning, strategic modernization planning, and investment analysis to support the Production Base Support (PBS) program. The Contractor shall support three project types:

1.1. Provision of Industrial Facilities (PIF): New capabilities, capacity expansion, or modernization for efficiency, safety, and environmental compliance.

1.2. Layaway of Industrial Facilities (LIF): Transitioning equipment to long-term storage, including decontamination and demolition of excess property.

1.3. Maintenance of Inactive Facilities (MIF): Maintaining inactive facilities in a laid-away state for future readiness.

2. Technical Requirements

2.1. Strategic Execution Plan: The Contractor shall submit an annual PWS 2 Execution Plan (CDRL A02-001) 30 calendar days prior to each calendar year. This plan acts as the operational bridge between the long-term modernization roadmap and current-year execution. This plan must include:

2.1.1. Current modernization strategy, production capacities/constraints, and strategic goals.

2.1.2. Project prioritization methodology, estimated funding requirements, and sequencing/phasing recommendations for the upcoming year.

2.1.3. A Critical Path Schedule and summary of pre-planning efforts (conceptual designs, studies).

2.1.4. Risk assessment of single-point failures, operational availability, and environmental/safety constraints.

2.2. 15-Year Long-Term Modernization Roadmap: To inform Government prioritization and secure future Production Base Support (PBS) funding, the Contractor shall maintain and annually update the comprehensive 15-Year Strategic Modernization Roadmap incorporated at contract award.

2.2.1. Budget Envelope & Dependencies: The roadmap shall plan against a notional long-term budget of $3.5B to $4.5B (assuming no single year exceeds $1B in funding). The roadmap must map critical-path project dependencies, sequencing, and utility constraints to prevent long-term disruptions to active energetics production.

2.2.2. Acquisition Strategy: The roadmap shall recommend optimal acquisition approaches (e.g., Design-Build versus Design-Bid-Build) for future major capital projects to maximize cost efficiency and schedule adherence.

2.2.3. Funding Adaptability: The roadmap must maintain logical "decision gates" allowing the Government to accelerate or defer projects based on actual annual PBS funding availability.

2.3. Annual Production Base Support (PBS) Call Letter Submission: The Contractor shall utilize the 15-Year Roadmap to provide a complete, actionable response to the Government’s annual PBS Call Letter. (CDRL A02-002) If no formal letter is received, the Contractor shall independently submit the package by 31 May. Submissions must include:

2.3.1. P-25 Log: A high-level history and status of all current, prior, and candidate projects.

2.3.2. 1-N Project List: A prioritized list of candidate projects ranked by Contractor-determined priority, including estimated costs, GFY execution recommendations, and scoring results.

2.3.3. Annual Review Briefing: A summary briefing in June (including quad charts for each project) provided 15 business days prior to the review meeting. (CDRL A02-003)

2.4. Annual P-25 Project Documentation: The Contractor shall submit ten (10) P-25 project planning documents annually. (CDRL A02-004) A submission schedule must be provided within 45 calendar days of the start of each calendar year. Each P-25 must include:

2.4.1. Detailed justification (safety, quality, environment, cost avoidance) and a Risk Management Analysis.

2.4.2. Cost Estimation Maturity: Estimates must align with AACE International Classifications (Class 3 for Near-Term 0-3 years; Class 4 for Mid-Term 4-7 years; Class 5 for Long-Term 8+ years).

2.4.3. Quarterly Planning: A Quarterly P-25 Plan summarizing the status and submission schedule for the year’s P-25s.

2.5. Program Management Reviews (PMR): The Contractor shall host PMRs at RFAAP a minimum of three times per year.

2.5.1. Deliverables: Draft agenda due 30 calendar days prior; briefing charts due five business days prior; final charts and action item log due five business days after the PMR. (CDRL A02-005)

2.5.2. Scope: Reviews must cover organizational updates, production/quality metrics, safety/environmental performance, KPI status for all PWS areas, and modernization project execution updates.

2.6. Industrial Preparedness Planning (IPP) & Database Management:

2.6.1. Capacity Inquiries: The Contractor shall review industrial base capacity (utilization, bottlenecks, critical skills/materials) and provide information to the government as requested.

2.6.2. Project Requirements Database: The Contractor shall maintain a prioritized database of all new requirements and ROM cost estimates. The Contractor shall host bi-weekly meetings with Government stakeholders and provide monthly database exports by the first business day of each month. (CDRL A02-006)

2.7. Government-Funded Support: The Contractor shall support Government-contracted third-party efforts (design, demolition, construction) by providing facility data, onsite coordination, and issuance of RFAAP-specific permits. This includes providing personnel from safety, security, and engineering to ensure successful execution of Government-funded initiatives.

2.8. Project Financial Reporting and Status: The Contractor shall implement and maintain a robust financial tracking system capable of isolating and reporting costs associated with specific funded projects, completely separate from baseline facility operations and production activities. The Contractor shall compile this data and submit an annual Project Status Report to the Government. (CDRL A11-007)

3. Key Performance Metrics (KPI)

3.1. The Contractor shall track and report performance monthly via the PWS 2 KPI Report. This report must include all mandatory KPIs and at least three Contractor-identified KPIs evaluating the efficiency of RFAAP facility planning and management. The initial report is due 30 calendar days post-operational control. (CDRL A02-008) Mandatory KPIs include:

3.1.1. Call Letter Response: Completeness, compliance, and timeliness of the annual submission.

3.1.2. P-25 Submissions: Delivery of ten (10) complete and compliant P-25s annually.

3.1.3. Project Database Management: Accuracy and timeliness of the project requirements database exports.

3.1.4. Contractor-Proposed Metrics: A minimum of three (3) additional KPIs measuring planning effectiveness.

3.2. KPI Management: The initial report shall define the calculation methods and establish performance targets (justified by industry standards or baseline data) for Government approval. If any KPI trends negatively or falls below the target for three consecutive months, the Contractor must submit a Corrective Action Plan detailing mitigation steps, timelines, and the personnel responsible for achieving the target.