Attachment 0010 - PWS 10 RFAAP Energy and Utilities.docx

DOCX document 43 KB Posted

Attached to
Radford Army Ammunition Plant - DRAFT Solicitation
Solicitation number
W519TC26RA046
Issued by

About this file

This is a Performance Work Statement (PWS) defining energy and utilities service management requirements for the Radford Army Ammunition Plant (RFAAP) Main Plant and New River Storage Unit, effective April 2026.

The Contractor shall provide comprehensive labor, materials, and subcontracts to operate, manage, measure, and distribute all energy and utility services across RFAAP, prioritizing energy conservation and resilient supply. Primary operational responsibilities include generating and distributing electricity (via cogeneration turbines), steam, heating/cooling, natural gas and fuels, water systems (withdrawal, treatment, testing, and distribution with daily pH/turbidity/chlorine testing and monthly biological assessments), wastewater treatment per NPDES permit requirements, compressed air, and laundry facilities. The Contractor must establish an Energy Management System aligned with ISO 50001 structural elements, submit an annual Energy Management Execution Plan addressing energy policy, Significant Energy Uses identification, baselines, performance indicators, measurement and verification protocols, and operational controls. Metering compliance must reach 75% within one year and 100% within two years for facilities exceeding 29,000 square feet or $35K annual utility costs per feed, with >95% meter accuracy targets. The Contractor shall complete Comprehensive Energy and Water Evaluations on all active facilities every four years, maintain GIS utility infrastructure data with annual updates, develop an annual Load-Shedding Plan, and track Significant Energy User Performance Indicators with mandatory 5% annual improvement targets. Reporting requirements include monthly KPI reports (30 days after operational control), AEWRS data submission, utility interruption notifications within one hour of discovery, and Root Cause Analyses for interruptions exceeding one hour (due within 10 business days). The Contractor must maintain trained personnel with annual training certifications, manage utility provider contracts, and support cross-functional initiatives across related PWS sections including water emergency response and environmental compliance.

View the file

Other files

File Type Posted
Attachment 0007 - PWS 7 Maintenance.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Attachment 0001 - PWS 01 RFAAP Environmental.docx DOCX document
Attachment 0013 - PWS 13 Technology and Cybersecurity.docx DOCX document
Attachment 0004 - PWS 4 Property.docx DOCX document
Solicitation - W519TC26RA046.pdf PDF
Attachment 0002 - PWS 2 Facility Planning.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Exhibit B - PWS CDRLs.pdf PDF
RFAAP Solicitation - W519TC26RA046.pdf PDF
Attachment 0019 - Price Matrix_v2.xlsx XLSX spreadsheet
Attachment 0029 - Non-Disclosure Agreement Azimuth.docx DOCX document
Attachment 0002 - PWS 2 Facility Planning.docx DOCX document
Attachment 0030 - Non-Disclosure Agreement NEPSCO.docx DOCX document
Attachment 0012 - PWS 12 - ARMS.docx DOCX document
Attachment 0031 - Wage Determinations.pdf PDF
Attachment 0001 - PWS 01 RFAAP Environmental.docx DOCX document
Attachment 0024 - RFAAP GFP Listing.xlsx XLSX spreadsheet
Attachment 0015 - PWS 15 - ALTESS.docx DOCX document
Attachment 0009 - PWS 9 Safety-Occupational Health-Industrial Hygiene.docx DOCX document
Exhibit A - CDRLs.pdf PDF
Attachment 0018 - PWS 18 - Ground Water Monitoring - Installation Restoration Program Support.docx DOCX document
Attachment 0007 - PWS 7 Maintenance.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Attachment 0026 - Hazardous Material Classification Specification.xlsx XLSX spreadsheet
Attachment 0004 - PWS 4 Property.docx DOCX document
Attachment 0011 - PWS 11 RFAAP Facility Ops and Production Reporting.docx DOCX document
Attachment 0028 - COCO SECURITY STATEMENT OF WORK 2025.docx DOCX document
Attachment 0022 - SAMPLE OPSEC ACQUISITIONS PLAN.pdf PDF
Attachment 0021 - OPSEC SOW.docx DOCX document
Attachment 0032 - Mission Essential Services.pdf PDF
Attachment 0020 - TDP Section C Exeptions_Redacted.pdf PDF
Attachment 0019 - Price Matrix_Indemnification v2.xlsx XLSX spreadsheet
Exhibit B - PWS CDRLs.pdf PDF
Attachment 0003 - PWS 3 Fire Protection and Emergency Services.docx DOCX document
Attachment 0013 - PWS 13 Technology and Cybersecurity.docx DOCX document
Attachment 0033 - Small Business Participation Commitment Document.docx DOCX document
Attachment 0025 - CDRL Instructions.pdf PDF
Attachment 0017 - PWS 17 Transition Out.docx DOCX document
Attachment 0023 - DD254 Contract Security Classification Specification.pdf PDF
Attachment 0027 - ARMS Tenant Use Agreements.pdf PDF
Attachment 0008 - PWS 8 - Transition In.docx DOCX document
Attachment 0034 - Past Performance Questionnaire.docx DOCX document
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RADFORD ARMY AMMUNITION PLANT

PERFORMANCE WORK STATEMENT (PWS)

PWS 10: Energy and Utilities Service Management April 2026

1. Scope and Program Management

1.1. Scope: The Contractor shall provide all labor, materials, and subcontracts necessary to operate, manage, measure, and distribute energy and utility services across the Radford Army Ammunition Plant (RFAAP) Main Plant and New River Storage Unit. The Contractor shall prioritize energy conservation, resilient supply, and the reduction of utility demand across the installation. All costs associated with utility operations (natural gas, fuel oil, electricity, steam, potable water, wastewater) shall be charged to this PWS. Energy and utility services-related maintenance performance requirements shall fall under the purview of the Maintenance PWS.

1.2. Personnel & Training: The Contractor shall maintain a staff of appropriately trained professionals and technicians responsible for the Energy and Water Management program. The Contractor shall provide a roster of employees charging to this PWS annually and submit annual training certificates for all utility professionals/technicians. (CDRL A10-001)

1.3. Energy Management System (EnMS) and ISO 50001 Alignment

1.3.1. EnMS Execution Plan: The Contractor shall integrate energy efficiency into daily facility operations, maintenance, and capital project planning. While formal third-party ISO 50001 certification is not explicitly mandated, the Contractor’s EnMS must contain all structural elements of the standard to ensure continuous improvement in energy performance.

To demonstrate compliance, the Contractor shall develop and submit an Energy Management Execution Plan annually for Procuring Contracting Officer (PCO) approval (CDRL A10-002). The submitted plan must explicitly define and execute the following core elements:

1.3.1.1. Energy Policy & Leadership: A site-specific policy, enforced by the Plant Director, committing to continuous energy improvement.

1.3.1.2. Significant Energy Uses (SEUs): Identification of the facility's highest-consumption assets and processes.

1.3.1.3. Energy Baselines & Performance Indicators (EnPIs): Quantitative metrics and established baselines used to track efficiency gains or losses over time.

1.3.1.4. Measurement & Verification (M&V): Strict data collection protocols utilizing operational, calibrated utility meters.

1.3.1.5. Operational Control: Documented standard operating procedures (SOPs) ensuring SEUs are operated and maintained efficiently to prevent energy waste.

1.4. Geospatial Data Standards (GIS): The Contractor shall maintain and update all spatial data, maps, and digital representations of the RFAAP utility and energy infrastructure within the installation’s centralized Geographic Information System (GIS).

1.4.1. The Contractor shall deliver consolidated GIS utility network and infrastructure updates to the Government annually or sooner upon Government request. (CDRL A10-003).

1.5. The contractor shall comply with Army Regulation (AR) 420-1, Chapters 22-24, and other Army laws, policies, regulations, and Executive Orders pertaining to energy and utility operations and management to include establishing, maintaining, and implementing energy and utilities policies, objectives, and procedures.

2. Utility Operations and Distribution

2.1. Primary Utility Operations: The Contractor shall safely and reliably generate, procure, test, and distribute utilities to support all facility and production operations, including Government tenants and ARMS lessees. The Contractor shall actively manage and operate the following systems:

2.1.1. Electricity: Receive, generate (via Powerhouse cogeneration turbines), and distribute electricity.

2.1.2. Steam & Heating/Cooling: Generate and distribute steam and maintain all plant heating and cooling systems.

2.1.3. Natural Gas & Fuels: Procure and distribute natural gas, ensuring all supply agreements grant Primary Firm reservation/priority to RFAAP. Procure and safely store required diesel and gasoline for operations and vehicle fueling.

2.1.4. Water Systems: Withdraw, treat, test, and distribute river/cooling water, filtered water, and potable water. Testing shall occur at least daily (or as required by permit) for pH, turbidity, and chlorine, with monthly biological assessments. Records must be retained for at least 48 months.

2.1.5. Wastewater & Sewage: Collect, distribute, and treat sanitary and industrial sewage IAW the RFAAP National Pollutant Discharge Elimination System (NPDES) permit. Maintain an active operation log detailing monthly inflow/discharge data.

2.1.6. Compressed Air: Generate and distribute compressed air to meet production demands.

2.1.7. Laundry: Operate the installation laundry facilities.

2.2. Electrical Load-Shedding Plan: The Contractor shall develop, maintain, and submit an annual Load-Shedding Plan (CDRL A10-004) to minimize operational impacts, ensure environmental compliance, and execute safe shutdowns during periods of external electrical supply issues or internal distribution failures.

3. Metering, Data, and Continuous Improvement

3.1. Utility Metering Requirements: Metering shall be required for any facility exceeding 29,000 square feet or where utility costs exceed $35K per year per feed (per EPAct 2005 and EISA 2007).

3.1.1. Compliance Goals: The Contractor shall ensure 75% compliance with Army metering requirements within one (1) year of award, and 100% compliance within two (2) years.

3.1.2. Accuracy: The Contractor shall ensure >95% of meters are actively reading/recording data with a 100% accuracy goal. Alternate engineering methods shall be used where physical metering is impossible.

3.2. Comprehensive Energy and Water Evaluations (CEWE): The Contractor shall complete CEWEs on all active facilities every four (4) years (assessing 25% of installation square footage annually) IAW EISA 2007 and AR 420-1. Results shall include usage summaries and energy savings ideas, be maintained in a centralized database, and input into AEWRS.

4. Incident Management and Reporting

4.1. Utility Interruption Reporting: A utility interruption is defined as any breakdown causing operational downtime of energetics, propellants, utility production, or waste disposal.

4.1.1. Immediate Notification: The Contractor shall notify the Army via email within one (1) hour of discovering any service interruption.

4.1.2. Root Cause Analysis (RCA): For any interruption lasting longer than one (1) hour, the Contractor shall complete an RCA and an Analysis of Alternatives (AoA) for mitigation, submitting the documentation to the Government within 10 business days. (CDRL A10-005)

4.1.3. Tracking: The Contractor shall maintain a master database logging all interruptions, root causes, and remedies, available to the Government upon request.

5. Key Performance Indicators (KPI)

5.1. The Contractor shall track and report performance monthly via the PWS 10 KPI Report. This report must include all mandatory KPIs and at least three Contractor-identified KPIs evaluating the efficiency of RFAAP energy and utility management. The initial report is due 30 calendar days after operational control. (CDRL A02-006) Mandatory KPIs include:

5.1.1. Baseline KPIs: Establish baseline KPIs for each main utility (electricity, water, air, gas, steam, wastewater) including estimated cost per unit.

5.1.1.1. Significant Energy User (SEU) Energy Performance Indicator (EnPI): Establish EnPIs for SEUs—facilities consuming >5% of a utility. EnPIs must compare utility usage against production output (e.g., scfm/lb NC). Improvement Mandate: The Contractor shall improve each EnPI by a minimum of 5% annually through documentable conservation efforts.

5.2. KPI Management: The initial report shall define the calculation methods and establish performance targets (justified by industry standards or baseline data) for Government approval. If any KPI trends negatively or falls below the target for three consecutive months, the Contractor must submit a Corrective Action Plan detailing mitigation steps, timelines, and the personnel responsible for achieving the target.

6. Reporting and Cross-Functional Support

6.1. AEWRS Reporting: The Contractor shall input required data into the automated Army Energy and Water Reporting System (AEWRS) monthly, providing proof of submission to the local Army staff upon request.

6.2. Administrative & Cross-Functional Support: The Contractor shall:

6.2.1. Support Army energy data calls, audits, assessments, and reporting requirements (e.g., IEWP, AEPRR, ERCIP, ISR-MC).

6.2.2. Support cross-functional initiatives defined in other PWS sections, including the Water System Emergency Response Plan (WSERP - PWS 3), Energy/Water Vulnerability Assessments (PWS 6), utility maintenance (PWS 7), and environmental compliance of treatment facilities (PWS 1).

6.2.3. The contractor shall maintain a current list of RFAAP Energy and Utilities Services providers as well as providers for critical raw materials for utility operations. The provider lists and copies of all contracts held with the local utility providers shall be made available to the government upon request. The contractor shall retain records (i.e. utility bills, receipts of components replaced, surveys, etc.) for the length of the contract.