Attachment 0001 - PWS 01 RFAAP Environmental.docx

DOCX document 59 KB Posted

Attached to
Radford Army Ammunition Plant - DRAFT Solicitation
Solicitation number
W519TC26RA046
Issued by

About this file

This is a Performance Work Statement (PWS) for Environmental Management and Compliance at Radford Army Ammunition Plant (RFAAP), effective April 2026. The Contractor shall implement and maintain a comprehensive Environmental Management System (EMS) to minimize hazardous materials use and generation while assuming full responsibility for all Contractor-generated solid and hazardous waste management and disposal. The Contractor must achieve compliance with all applicable federal environmental laws including RCRA, Clean Water Act, Clean Air Act, CERCLA, NEPA, and related Army Regulations, and shall apply for, obtain, and maintain all necessary environmental permits with the Army designated as facility owner and Contractor as facility operator. The Contractor must provide Government environmental staff unrestricted read-only access to all environmental databases and documentation, support all Government audits and regulatory inspections, and maintain a 12-month Annual Environmental Compliance Calendar.

The Contractor bears primary responsibility and financial liability for all environmental non-compliances, enforcement actions, and associated fines, and must report spills or unauthorized discharges to Government staff within one hour via text message and submit written pollution incident reports with photographic evidence within 24 hours. The Contractor shall remediate spills to residential standards in non-SWMU areas or industrial standards in active SWMUs, strictly comply with all Land Use Controls, and perform post-closure care of closed surface impoundments and permitted landfills. Additionally, the Contractor must manage hazardous waste within the 90-day RCRA accumulation limit without prior written authorization from the Contracting Officer, manage energetic and non-hazardous production materials according to manufacturer-designated shelf life or a default maximum of two years from receipt, and submit monthly Environmental Status Reports tracking accumulation areas, shelf-life expirations, and disposal activities. The Contractor shall track and report Key Performance Indicators (KPIs) monthly, including zero Class I/II permit violations, 100% on-time spill reporting, 100% high-risk audit finding closure within 30 days, and 50% non-hazardous waste diversion, with corrective action plans required if any KPI trends negatively for three consecutive months.

View the file

Other files

File Type Posted
Attachment 0007 - PWS 7 Maintenance.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Attachment 0013 - PWS 13 Technology and Cybersecurity.docx DOCX document
Attachment 0004 - PWS 4 Property.docx DOCX document
Solicitation - W519TC26RA046.pdf PDF
Attachment 0002 - PWS 2 Facility Planning.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Exhibit B - PWS CDRLs.pdf PDF
RFAAP Solicitation - W519TC26RA046.pdf PDF
Attachment 0019 - Price Matrix_v2.xlsx XLSX spreadsheet
Attachment 0029 - Non-Disclosure Agreement Azimuth.docx DOCX document
Attachment 0002 - PWS 2 Facility Planning.docx DOCX document
Attachment 0030 - Non-Disclosure Agreement NEPSCO.docx DOCX document
Attachment 0012 - PWS 12 - ARMS.docx DOCX document
Attachment 0031 - Wage Determinations.pdf PDF
Attachment 0001 - PWS 01 RFAAP Environmental.docx DOCX document
Attachment 0024 - RFAAP GFP Listing.xlsx XLSX spreadsheet
Attachment 0015 - PWS 15 - ALTESS.docx DOCX document
Attachment 0009 - PWS 9 Safety-Occupational Health-Industrial Hygiene.docx DOCX document
Exhibit A - CDRLs.pdf PDF
Attachment 0018 - PWS 18 - Ground Water Monitoring - Installation Restoration Program Support.docx DOCX document
Attachment 0007 - PWS 7 Maintenance.docx DOCX document
Attachment 0006 - PWS 6 Security and Antiterrorism.docx DOCX document
Attachment 0026 - Hazardous Material Classification Specification.xlsx XLSX spreadsheet
Attachment 0004 - PWS 4 Property.docx DOCX document
Attachment 0011 - PWS 11 RFAAP Facility Ops and Production Reporting.docx DOCX document
Attachment 0028 - COCO SECURITY STATEMENT OF WORK 2025.docx DOCX document
Attachment 0010 - PWS 10 RFAAP Energy and Utilities.docx DOCX document
Attachment 0022 - SAMPLE OPSEC ACQUISITIONS PLAN.pdf PDF
Attachment 0021 - OPSEC SOW.docx DOCX document
Attachment 0032 - Mission Essential Services.pdf PDF
Attachment 0020 - TDP Section C Exeptions_Redacted.pdf PDF
Attachment 0019 - Price Matrix_Indemnification v2.xlsx XLSX spreadsheet
Exhibit B - PWS CDRLs.pdf PDF
Attachment 0003 - PWS 3 Fire Protection and Emergency Services.docx DOCX document
Attachment 0013 - PWS 13 Technology and Cybersecurity.docx DOCX document
Attachment 0033 - Small Business Participation Commitment Document.docx DOCX document
Attachment 0025 - CDRL Instructions.pdf PDF
Attachment 0017 - PWS 17 Transition Out.docx DOCX document
Attachment 0023 - DD254 Contract Security Classification Specification.pdf PDF
Attachment 0027 - ARMS Tenant Use Agreements.pdf PDF
Attachment 0008 - PWS 8 - Transition In.docx DOCX document
Attachment 0034 - Past Performance Questionnaire.docx DOCX document
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RADFORD ARMY AMMUNITION PLANT

PERFORMANCE WORK STATEMENT (PWS)

PWS 1: Environmental April 2026

1. Environmental Management and Compliance

1.1 Environmental Management System (EMS): The Contractor shall implement and maintain an EMS to ensure operations eliminate or minimize the use and generation of hazardous materials and toxic waste. The Contractor shall identify major pollutants, implement source reduction strategies, and assume full responsibility for the management and disposal of all Contractor-generated solid and hazardous waste.

1.2 Regulatory Compliance: The Contractor shall comply with all current local, state, and U.S. federal environmental laws, Executive Orders, and Army Regulations, including but not limited to:

1.2.1 Resource Conservation and Recovery Act (RCRA) (42 USC § 6901)

1.2.2 Safe Drinking Water Act (42 USC § 300f) & Clean Water Act (33 USC 1251)

1.2.3 Clean Air Act (42 USC § 7401)

1.2.4 Toxic Substances Control Act (15 USC 2601)

1.2.5 Emergency Planning and Community Right to Know Act (42 USC § 1101)

1.2.6 CERCLA (42 USC § 9601) & Federal Facilities Compliance Act (42 USC § 9620)

1.2.7 Federal Insecticide, Fungicide, and Rodenticide Act (7 USC 6)

1.2.8 National Environmental Policy Act (NEPA) of 1969, DoD NEPA Implementing Procedures (Appendix A, 30 June 2025), and Army NEPA Guidance (8 August 2025)

1.2.9 Army Regulations 200-1, 200-2, and 420-1

2. Permits, NEPA, and HAZMAT Management

2.1 Permit Management: The Contractor shall apply for, obtain, and maintain all necessary environmental permits. Applications shall designate the Army as the "facility owner" and the Contractor as the "facility operator," with the Contractor signing all certifications required by operators. The Contractor shall provide primary facility permit applications (Title V, RCRA, VPDES) to the Government environmental staff for review 35 working days prior to regulatory submittal. All other permit applications require a 7-working-day Government review period.

2.2 NEPA Documentation: The Contractor shall initiate and complete environmental documentation required by NEPA and AR 200-1. While the Contractor is not required to write Environmental Assessments (EAs) or Environmental Impact Statements (EISs), they shall provide necessary supporting data to the Army. The Contractor shall prepare Records of Environmental Consideration (RECs), inclusive of all background data and potential impacts, for Government approval and signature. The Contractor shall be responsible for completing NEPA requirements for all Tenant Use Agreements and Facility Use Requests under the ARMS program. The costs incurred to comply with NEPA for any other requirements shall be programmed and charged to the associated project.

2.3 Hazardous Materials Management: The Contractor shall develop a Hazardous Materials Management Plan and manage materials/waste IAW Army policies. The Contractor shall obtain user access for and utilize the WEBCASS-E Hazardous Material Inventory Database (HMID) Module as the system of record for HAZMAT/HAZWASTE authorization, tracking, and reporting.

3. Government Access, Audits, and Planning:

3.1 Government Data Access: The Contractor shall provide Government environmental staff unrestricted, read-only access to all environmental databases, drives, TEAMs channels, and document repositories (including blueprints, logs, and procedures) used to store environmental records associated with the operation of RFAAP and New River Unit (NRU) operations to the extent such systems exist.

3.2 Audits and Planning: The Contractor shall support Government audits (e.g., Environmental Performance Assessment System, Command Inspection Program). The contractor shall assist U.S. Army personnel and support external audit teams and provide access to contractor areas. Additionally, the Contractor shall develop and maintain a forward-looking, 12-month Annual Environmental Compliance Calendar that tracks critical regulations, permit deadlines, training, and reporting obligations. This calendar must be continuously accessible to on-site Government staff.

3.3 The contractor shall provide information and support for all environmental taskers received from the government.

4. Regulatory Inspections and Enforcement

4.1 Inspections: The Contractor shall immediately notify Government environmental staff of any regulatory communications, visits or inspections. The Contractor shall not proceed with any communications, visits or inspections with regulators without a Government representative unless a waiver is granted or Government staff fails to arrive within 30 minutes of notification. The Contractor shall submit meeting minutes/notes (CDRL A01-001) and a list of all materials provided to visitors within 48 hours of completion.

4.2 Enforcement and Liabilities: The Contractor bears primary responsibility and financial liability for all environmental matters, non-compliances, and fines resulting from Contractor (or subcontractor/tenant) actions or inactions. The Contractor shall defend, negotiate, and resolve enforcement actions (e.g., Notices of Violation, orders, citizen suits) at their own expense and reimburse the Government for any associated fines. The Contractor shall not engage in negotiations that obligate the Government without prior written agreement.

5. Incident Reporting and Site Restoration

5.1 Spill Notification and Reporting: Upon discovery of any spill, unauthorized discharge, excursion, or NOV, the Contractor shall notify Government environmental staff via text message within one (1) hour (including time, duration, estimated quantity, location, and suspected cause). For any discharge incident that is reportable to environmental and/or federal agencies, the Contractor shall submit a written pollution incident report with photographic evidence (CDRL A01-002) within 24 hours. If required, the Contractor shall also provide a formal root cause analysis and corrective action plan.

5.2 Environmental Restoration Standards: The Contractor shall clean any spills/releases caused by their operations (including tenants/subcontractors). Cleanup standards are dictated by the location's status:

5.2.1 Non-SWMU/NFA Status: Spills occurring in non-SWMU areas or Solid Waste Management Units (SWMUs) with No Further Action (NFA) status shall be remediated to residential standards to prevent future Army liabilities.

5.2.2 Active SWMUs: Spills on active SWMUs (or HWMU, AOPC, SSA) shall be remediated to industrial standards following appropriate regulatory notification.

5.3 Land Use Controls (LUC): The Contractor shall strictly comply with all LUCs for SWMUs, HWMUs, and AOCs. Prior to issuing dig permits or beginning construction, the Contractor shall review current GIS data to ensure LUCs are maintained and groundwater monitoring wells are protected.

5.4 Perform post-closure care of closed surface impoundments, permitted landfills, and land treatment facilities.

6. Integrated Active Waste Stream Management Plan Execution

6.1 Waste Minimization and Monetization: The Contractor shall implement waste minimization processes and process optimization techniques to reduce active waste generation. The Contractor shall aggressively pursue byproduct reuse and identify commercial outlets for spent acids, solvents, and out-of-specification products. All commercial revenues and cost-savings generated from waste monetization shall be tracked, managed, and deposited into the Facility Contractor Account (FCA) in accordance with the ARMS PWS 12 program guidelines.

7. Material Storage and Accumulation Limits

7.1 Hazardous Waste (90-Day Limit Execution): The Contractor shall manage, accumulate, and dispose of all generated hazardous wastes, and residual hazardous materials in strict accordance with the Resource Conservation and Recovery Act (RCRA) (40 CFR Parts 260-270), Virginia Hazardous Waste Management Regulations (VHWMR), and the RFAAP facility's specific RCRA Part B permit limits. Under no circumstances shall hazardous waste exceed the regulatory 90-day accumulation limit on-site without prior written authorization from the Contracting Officer.

7.2 Energetic and Non-Hazardous Production Materials (2-Year/Shelf-Life Limit Execution): To prevent the indefinite accumulation of active energetics, manage industrial footprint, and prevent chemical degradation, the Contractor shall manage all energetic and non-hazardous production materials (including propellants, raw chemicals and stabilizers) according to the following:

7.2.1 Inventory and Expiration Tracking: Maintain a centralized, real-time inventory of all unused or intermediate energetic materials or propellants, including the date of manufacture. All materials must be tracked via their manufacturer-designated shelf life or a default maximum of two (2) years from receipt. For the purpose of this requirement, the two-year storage period shall commence on the date of receipt at the facility for procured materials or the date of manufacture completion for materials or intermediates produced on-site.

7.2.2 Exemption for Inert/Non-Degrading Materials: Inert hardware, spare parts, and structural materials (e.g., metals, piping, non-reactive equipment) that do not chemically or physically degrade are exempt from the two-year disposal limit. While exempt from the time limit, the Contractor must still maintain these items on inventory and store them in an orderly manner subject to standard Government property management, safety, and housekeeping standards.

7.2.3 Shelf-Life Extension Testing: The Contractor may extend the shelf life of a material (including energetic materials requiring stability verification) only if supported by documented laboratory analysis proving the material remains stable, safe, and effective. These lab results must be maintained on file and made available to the Government upon request.

7.2.4 Disposition of Expired Goods: Once a material exceeds its shelf life (without an approved extension) or exceeds the two-year limit, the Contractor must remove it from the active production inventory within sixty (60) days and initiate appropriate waste characterization and disposal procedures at the Contractor's expense.

7.3 Monthly Environmental Status Report (MESR): The Contractor shall submit a monthly report to the Procuring Contracting Officer (PCO). (CDRL A01-004) The MESR must include:

7.3.1 A log of all active 90-day central accumulation areas and their earliest accumulation start dates.

7.3.2 A list of any energetic or non-hazardous materials approaching their shelf-life expiration or the 2-year storage limit.

7.3.3 A summary of materials disposed of due to expiration or limit exceedance.

8. Environmental Key Performance Indicators (KPI)

8.1 The Contractor shall track and report performance monthly via the PWS 1 KPI Report. This report must include all mandatory KPIs and at least three Contractor-identified KPIs evaluating the efficiency of RFAAP environmental management. The initial report is due 30 days post-operational control. (CDRL A02-019) Mandatory KPIs include:

8.1.1 Environmental Permit & Spill Compliance: Zero Class I/II Permit Violations;100% on-time spill reporting.

8.1.2 Corrective Action & Audit Resolution: 100% of high-risk findings closed within 30 days.

8.1.3 Waste Diversion & Compliance Rate: 100% compliant manifest tracking;≥ 50% diversion of non-hazardous waste.

8.2 KPI Management: The initial report shall define the calculation methods and establish performance targets (justified by industry standards or baseline data) for Government approval. If any KPI trends negatively or falls below the target for three consecutive months, the Contractor must submit a Corrective Action Plan detailing mitigation steps, timelines, and the personnel responsible for achieving the target.