This document is a Tinker General Requirements Change Log for August 2022 that documents revisions to multiple specification sections and attachments.

The primary changes involve terminology updates throughout sections 01 33 00 and 01 78 00, replacing references to "Contracting Officer" with "Contracting Officers Representative" and adding "and/or Contracting Officer's Representative" language to multiple sections. Section 01 33 00 includes revisions to sections 1.2.3, 1.4.2.1, 1.5.1, 1.5.3.3.2, 1.5.3.8.1, 1.8.2, 1.8.7, and 1.14. Substantive changes in Section 1.5.5 specify that file naming conventions are defined in contract documents, authorize the Contracting Officer's Representative to modify submittal format requirements, and add DOD Safe as an approved method for transmitting submittals. Section 1.8.2 modified the timing requirement for submitting the Contractor's Submittal Register to coincide with final design submittal rather than as a standalone requirement, and Section 1.8.7 changed the updated Submittal Register submission frequency to monthly. Section 01 78 00 updates include reference updates to reflect current standards, modification of "Interim DD Form 1354" to "DD Form 1354," and addition of attachment references in Section 3.6. Attachment 1 replaces the Air Force Form 3000 with the new TAFB Form 3000. Sections 00 70 00, 00 71 00, 00 72 00, 00 80 00, 00 80 05, 01 32 16.00 20, 01 33 16.00 10, 01 42 00, 01 45 00.00 10, 01 50 00, and 01 78 23 contained no changes.

View the file

Other files

File Type Posted
240176_ATT02_STATEMENT OF WORK_Admendment 2.pdf PDF
Solicitation - FA813726R0043.pdf PDF
240176_ATT09_SOW.pdf PDF
240176_STATEMENT OF WORK-Amendment 1.pdf PDF
240176_ATT 11_Submittal Register.xlsx XLSX spreadsheet
240176_ATT 10_Design Narrative.pdf PDF
Industrial Waste Lines 1969.pdf PDF
WWYK143004_CU507.pdf PDF
WWYK143004_CU503.pdf PDF
WWYK143004_CU500.pdf PDF
WWYK143004_CU504.pdf PDF
Pages from 910139.pdf PDF
20010298.pdf PDF
710237.pdf PDF
430515.pdf PDF
2025 TAFB Electrical Standards - Signed.pdf PDF
01 78 00.pdf PDF
UMRL.pdf PDF
ERDCITL_TR12-6_r6.pdf PDF
ufc_3_260_01_2019_c1.pdf PDF
EM_385-1-1.pdf PDF
tinkerafb_INRMP_App G.pdf PDF
dafi21-101.pdf PDF
dafi13-213.pdf PDF
afman40-201.pdf PDF
dodio-2000.16v1_afi10-245-o.pdf PDF
tinkerafbi21-100.pdf PDF
007200_Attch13_AF487.pdf PDF
007200_Attch7a_AF3952.pdf PDF
SOW Att 02a_Controlled Area Training.pptx PPTX presentation
240176_ATT 11_Submittal Register.pdf PDF
240176_Final_ Plan Set.pdf PDF
WWYK143004_CU502.pdf PDF
WWYK143004_CU513.pdf PDF
WWYK143004_CU501.pdf PDF
WWYK143004_CU505.pdf PDF
20090026A.pdf PDF
B02119.txt TXT text file
690255.pdf PDF
480211.pdf PDF
Combined As-Built Record Dwgs.pdf PDF
FIRE SUPPRESSION GEODESIC SHOP DRAWINGS AS-BUILTS.pdf PDF
2025 TAFB Mechanical Standard_Signed.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
01 32 16.00 20.pdf PDF
tinkerafb_INRMP.pdf PDF
afman32-7003.pdf PDF
afman48-148.pdf PDF
dafi13-213_tinkerafbsup.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker General Requirements Change Log – Aug 2022

00 70 00 No Changes

00 71 00 No Changes

00 72 00 No Changes

00 80 00 No Changes

00 80 05 No Changes

01 32 16.00 20 No Changes

01 33 00 Throughout document, changed ‘Contracting Officer’ to ‘Contracting Officers Representative.’

Section 1.2.3. Added definition of ‘Contracting Officers Representative.’

Section 1.4.2.1. Added ‘and/or Contracting Officer’s Representative.’

Section 1.5.1. First sentence revised for clarity.

Section 1.5.3.3.2. Added ‘and/or Contracting Officer’s Representative.’

Section 1.5.3.3.2. Added ‘and/or Contracting Officer’s Representative.’

Section 1.5.3.8.1. Added ‘and/or the Contracting Officer or designated alternate.’

Section 1.5.5. Multiple Changes

- Added Language specifying that file naming convention are specified in contract documents.

- Added language specifying that the COR can change requirement for submittals in PDF format.

- Added DOD Safe as means for transmittal of submittals.

Section 1.8.2. Changed requirement that Contractor’s Submittal Register must be submitted with final design submittal.

Section 1.8.7. Changed requirement that updated Submittal Register must be submitted monthly.

Section 1.14. Added ‘and/or Contracting Officer’s Representative.’

Attachment 1. Replaced AF Form 3000 with new TAFB Form 3000.

01 33 16.00 10 No Changes.

01 42 00 No Changes.

01 45 00.00 10 No Changes.

01 50 00 No Changes

01 78 00 Throughout document, changed ‘Contracting Officer’ to ‘Contracting Officers Representative.’

Section 1.1. Updated references as required to reflect most current.

Section 1.2.1. Added ‘and/or Contracting Officer’s Representative.’

Section 1.4. Changed ‘Interim DD Form 1354’ to ‘DD Form 1354.’

Section 1.7.1. Added ‘and/or Contracting Officer’s Representative.’

Section 1.7.2. Added ‘and/or Contracting Officer’s Representative.’

Section 1.7.3. Added ‘and/or Contracting Officer’s Representative.’

Section 3.6. Added ‘attachment’ references.

01 78 23 No Changes