007000_Attch1_TAFB Outage Request Form.pdf

PDF 186 KB Posted

Attached to
Tinker AFB MAC BOA - WWYK240176 - Replace Industrial Waste Lift Stations 6N & 6S, B62501
Solicitation number
FA813726R0043
Issued by

About this file

This is a Tinker Air Force Base Outage Request Form used to request interruptions in parking or utility services at the facility.

The form classifies all outages into three categories based on advance notice and urgency. Planned (Routine) outages are foreseen well in advance and require submission to the Outage Coordinator with specific lead times: 60 calendar days for roads/parking lots/sidewalks, 21 calendar days for all utilities, and 10 calendar days for fire alarm testing. Limited Notice (Urgent) outages cannot be reasonably foreseen in advance and require 21 calendar days notice for roads/parking/sidewalks, 10 calendar days for utilities, and 7 calendar days for fire alarm testing. Emergency outages must be accomplished immediately to safeguard property or occupant health (such as mechanical failure, flooding, water line breaks, or electrical outages) and can be submitted with less than the Urgent timeline notice; emergency requests outside normal working hours (0700-1600 M-F) should call the Customer Service Desk at 734-3117.

The form itself requests project information including project number, work order number, project name, exact location, outage start/end dates and times, and a detailed description of work to be performed. It also requires identification of the type of outage (fire suppression, gas, steam, breathing air, sidewalk, fire alarm outage, fire alarm testing, domestic water, chilled water, road, electric, HVAC, compressed air, parking lot, or gate), operational support required (plumbing shop, electrical shop, HVAC, alarms/sprinkler shop, OG&E, fire department, plant maintenance, Honeywell, or other), impact assessment on occupants and surrounding areas, and contact information for both the requestor and the TAFB Contract Point of Contact (Inspector/PM/COR). All submissions should be directed to the Utility Outage Coordination Team at the Civil Engineering office.

View the file

Other files

File Type Posted
240176_ROUND 3_PRE BID RFIs_For Signature 2 - COR Signed.pdf PDF
240176_Site Visit Sign In.pdf PDF
SOW Att 02a_Controlled Area Training.pptx PPTX presentation
240176_ATT 11_Submittal Register.pdf PDF
240176_Final_ Plan Set.pdf PDF
WWYK143004_CU502.pdf PDF
WWYK143004_CU513.pdf PDF
WWYK143004_CU501.pdf PDF
WWYK143004_CU505.pdf PDF
20090026A.pdf PDF
B02119.txt TXT text file
690255.pdf PDF
480211.pdf PDF
Combined As-Built Record Dwgs.pdf PDF
FIRE SUPPRESSION GEODESIC SHOP DRAWINGS AS-BUILTS.pdf PDF
2025 TAFB Mechanical Standard_Signed.pdf PDF
01 33 00.pdf PDF
01 33 16.00 10.pdf PDF
01 32 16.00 20.pdf PDF
tinkerafb_INRMP.pdf PDF
afman32-7003.pdf PDF
afman48-148.pdf PDF
dafi13-213_tinkerafbsup.pdf PDF
017800_Attch1_DD1354.pdf PDF
007200_Attch14_Information for New Boilers.pdf PDF
017800_Attch2_DD1354 Checklist.docx DOCX document
007200_Attch9_EMS Awareness Training.pdf PDF
Site Visit Meet-up Point.png PNG image
240176_ATT 9_STATEMENT OF WORK.pdf PDF
920203.pdf PDF
1995_IndWaste.pdf PDF
WWYK143004_CU511.pdf PDF
WWYK143004_CU508.pdf PDF
WWYK143004_CU506.pdf PDF
730155.pdf PDF
710238.pdf PDF
551213.pdf PDF
531005.pdf PDF
FIRE SUPPRESSION TANK FIRE ALARM AS-BUILT SHOP DRAWINGS.pdf PDF
00 72 00.pdf PDF
00 71 00.pdf PDF
Tinker General Requirements Specifications_Nov 2022_Change Log.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
00 80 00.pdf PDF
01 78 23.pdf PDF
HAZMAT Reporting at Tinker AFB FEB 2025.pdf PDF
ufc_3_535_01_2017_c4.pdf PDF
dafi21-101_afmcsup_afmcgm2023-01.pdf PDF
afman91-203_oc-alcsup.pdf PDF
tinkerafb_INRMP_App E.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

All outages and service interruptions will be classified in one of three possible categories:

a. Planned (Routine) – An interruption in parking or utility services, which can be foreseen well in advance and/or is part of an existing schedule. Planned outages include all repair projects, with enough lead time to allow them to be accomplished on a non-emergency basis, and all capital and renovation projects which require outages during construction. Planned outages should be submitted to the Outage Coordinator prior to the requested outage using the following timelines:

• Roads/Parking Lots/Sidewalks – 60 calendar days

• Utilities (all) – 21 calendar days

• Fire Alarm Testing – 10 calendar days

b. Limited Notice (Urgent) – An interruption in parking or utility services that cannot reasonably be foreseen in advance to be considered a “routine” outage or which does not allow for extensive pre-planning or coordination prior to the interruption. A Limited Notice Outage may be required when repairs must be accomplished within a short time frame (which may not allow time for BCE to notify or meet with stakeholders) to safeguard property and occupant health.

Limited Notice or Urgent outages should be submitted to the Outage Coordinator prior to the requested outage using the following timelines:

• Roads/Parking Lots/Sidewalks – 21 calendar days

• Utilities (all) – 10 calendar days

• Fire Alarm Testing – 7 calendar days

c. Emergency Outage – An interruption in parking or utility services that must be accomplished immediately to safeguard property or occupant health. This may occur as the result of a natural or human-caused hazard. Examples of emergency outages may include, but are not limited to:

mechanical failure, flooding within buildings, water line breaks, electrical outages or “power blips”, or hazardous materials incidents. Outages requests are considered an Emergency Request if they are submitted to the Outage Coordinator in a time frame that is less than the Urgent timelines noted above. Emergency requests must still be supported with an outage request form explaining the situation and reason that the outage cannot be accomplished as a Routine or Urgent Outage. Emergency Requests outside of normal working hours (0700-1600 M-F) should call the Customer Service Desk at 734-3117 for immediate assistance.

Form - Outage Request
Vance Gate Outage Request Form.pdf
Other or Remarks:
Gates specify which:
Primary_2:
Type1: Off
Type2: Off
Type3: Off
Reason:
Work Order #:
Project #:
Description of Work to be Performed:
Other Operational Support Required:
Impact of Outage:
Check Box19: Off
Check Box20: Off
Check Box21: Off
Check Box22: Off
Road_2: Vance Gate
Project Name:
Exact Location Bldg Post intersection etc:
Outage Start Date:
Outage End Date:
Outage StartTime:
Outage End Ti me:
Primary:
Position:
Phone:
Email:
Alternate:
Position_2:
Phone_2:
Email_2:
TAFB Contract Point of Contact lnspectorPMCOR: Darren Hulsey
Position_3:
Phone_3:
Email_3:
Alternate_2:
Position_4:
Phone_4:
Email_4:
Check Box1: Off
Check Box2: Off
Check Box3: Off
Check Box4: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box9: Off
Check Box10: Off
Check Box11: Off
Check Box12: Off
Check Box13: Off
Check Box14: Off
Check Box15: Off
Check Box16: Off
Check Box17: Off
Check Box18: Off
Text19:
Text20:
Text21:
Text22: Preventive Maintenance on mechanical and electronic controls
Check Box23: Off
Check Box24: Off
Check Box25: Off
Check Box26: Yes
Check Box27: Off
Check Box28: Off
Check Box29: Off
Check Box30: Off
Check Box31: Off
Text32:
Text33: This gate is only open mornings and evenings. Mid day work will not impact traffic