240176_ROUND 3_PRE BID RFIs_For Signature 2 - COR Signed.pdf

PDF 442 KB Posted

Attached to
Tinker AFB MAC BOA - WWYK240176 - Replace Industrial Waste Lift Stations 6N & 6S, B62501
Solicitation number
FA813726R0043
Issued by

About this file

This is a Pre-Bid Request for Information (RFI) responses document for a federal construction project at Tinker Air Force Base. The document provides government responses to 68 contractor questions regarding Project WWYK240176, which involves replacing two industrial waste lift stations (6N and 6S) at Building B62501.

The project scope requires combining two existing lift stations into a single new lift station with three submersible pumps rated at 180 GPM each to handle peak flows of 310 GPM from Buildings B2122 and B2136. The contractor must construct reinforced concrete vaults (wet well, valve vault, and flow meter vault) with corrosion-resistant coatings per UFC 3-240-01 standards. Key requirements include: providing double-wall force main piping extending to the flow meter vault; installing two flow meters on outlet lines with no substitutions allowed; providing stainless steel 316 control panels with factory-applied enamel finish rated NEMA 4X for Class I, Division 1, Group C and D hazardous locations; establishing a 20-foot-wide concrete driveway extending 25 feet into the fenced area; placing 4-foot minimum concrete sidewalks around equipment; and installing 6 inches of #57 washed aggregate throughout the gated area. The contractor must conduct subsurface exploration to determine groundwater levels and soil bearing capacity, though previous boring indicated no groundwater presence. The existing lift station must remain operational throughout construction, with sequencing that does not require bypass pumping but allows contractor discretion for temporary bypass if necessary. The contractor is responsible for field verification of existing utilities, valve locations, and electrical requirements. Design plans require submission to Oklahoma City Utilities Water Trust (OCWUT) and permit approval from OKDEQ. Project contacts include Gloria Butcher (Project Manager), Mark Williams (Construction Inspector), Joshua Wheeler (CSAG Program Manager), and Randall Floyd (Contracting Officer Representative).

View the file

Other files

File Type Posted
240176_ATT03_Amendment 2_Drawings.pdf PDF
240176_ATT01_Design Narrative_Amendment 2.pdf PDF
240176_ATT02_STATEMENT OF WORK_Admendment 2.pdf PDF
240176_PRE-BID RFI RESPONSES - COR Signed.pdf PDF
240176_Site Visit Sign In.pdf PDF
WWYK143004_CU503.pdf PDF
tinkerafbi21-100.pdf PDF
EM_385-1-1.pdf PDF
dafi13-213.pdf PDF
240176_ATT 11_Submittal Register.xlsx XLSX spreadsheet
240176_STATEMENT OF WORK-Amendment 1.pdf PDF
1993_IndWaste.pdf PDF
00 70 00.pdf PDF
Industrial Waste Lines 1969.pdf PDF
afman32-7003.pdf PDF
WWYK143004_CU513.pdf PDF
ERDCITL_TR12-6_r6.pdf PDF
480211.pdf PDF
240176_ATT 3_Green Procurement Statement.pdf PDF
WWYK143004_CU514.pdf PDF
dafi13-213_tinkerafbsup.pdf PDF
017800_Attch1_DD1354.pdf PDF
WWYK143004_CU501.pdf PDF
SOW Att 01_Appointment of Security Representative Template 496.docx DOCX document
tinkerafb_INRMP_App G.pdf PDF
WWYK143004_CU504.pdf PDF
00 80 00.pdf PDF
01 78 23.pdf PDF
1995_IndWaste.pdf PDF
ufc_3_535_01_2017_c4.pdf PDF
WWYK143004_CU511.pdf PDF
017800_Attch2_DD1354 Checklist.docx DOCX document
01 33 00.pdf PDF
tinkerafb_INRMP.pdf PDF
007200_Attch14_Information for New Boilers.pdf PDF
FIRE SUPPRESSION GEODESIC SHOP DRAWINGS AS-BUILTS.pdf PDF
20010298.pdf PDF
UMRL.pdf PDF
WWYK143004_CU502.pdf PDF
20090026A.pdf PDF
B02119.txt TXT text file
SOW Att 02a_Controlled Area Training.pptx PPTX presentation
WWYK143004_CU505.pdf PDF
afman91-203_oc-alcsup.pdf PDF
007000_Attch1_TAFB Outage Request Form.pdf PDF
013300_Attch1_TAFBF3000.pdf PDF
240176_ATT 9_STATEMENT OF WORK.pdf PDF
531005.pdf PDF
dafi21-101_afmcsup_afmcgm2023-01.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
Show 40 more

Latest 50 of 120 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 72 AIR BASE WING (AFMC)

TINKER AIR FORCE BASE OKLAHOMA

27 July 26

MEMORANDUM FOR AFSC/PZIOC (ATTN: Tamara Torres)

THROUGH: 72 ABW/CENM

FROM: 72 ABW/CEED

Tepa Companies

SUBJECT: Pre-Bid RFI Responses Project: WWYK240176, Replace Industrial Waste Lift Stations 6N & 6S, B62501

Reference: Memo, 27 July 26, Pre-Bid RFIs, WWYK240176, Replace Industrial Waste Lift

Stations 6N & 6S, B62501

1. This office reviewed the referenced RFIs for the subject project and provided answers below. Please forward to the contractor(s) for their use in preparing proposals

(1) Is the intent of the project to combine the two existing lift stations into a single lift station?

Government Response: roject.

(2) Is there a flow diagram of how the existing lift stations are piped with isolation valves and bypass piped?

Government Response: Yes, please refer to As-Built files: 1994_IndWaste and 1993_IndWaste (Year 1993).

(3) It appears that there might be two flows from B2122 Paint Hanger. Please confirm that there are only two total inlet flows into the existing lift stations?

Government Response: As-Built file 1994_IndWaste (June 1993) shows one 8” PP ‘Gravity Flow’ pipe with downstream flow into 6N branching into 6S. Before each LS, there is an 8” Gate Valve with associated Valve Box (for access). This As-Built supersedes As-Built file 1993_IndWaste (Line H from Bldg 2122) showing an 8” VCP Gravity pipe with downstream flow into 6S branching into 6N. The 8” VCP pipe has been abandoned and replaced by the 8” PP pipe. As-Built file 1994_IndWaste shows the 8” VCP ‘flushed and capped’ only and not removed. Please refer to sheet 9/11 details 2/C7-P.1 and sheet 10/11 details 10/C6-P.1.

(4) Are As-Built documents available for the existing lift stations flow lines and pipe routing?

Government Response: Yes, please refer to As-Builts files 1994_IndWaste referenced in #3 and 1993_IndWaste file (sheets C-1/View-A and M-2/ View-A).

(5) Are As-builts available for B2119 electrical and emergency generator system?

Government Response: See RFI 11 below, no electrical as-builts.

(6) Is Piping type for existing inlet and force main?

Government Response: Inflows: at Invert EL 1280.3 with Strainer Basket for both the 8” PP and 8” VCP ‘Gravity Flow’ pipes going into 6S & 6N. There are 2 force mains: 6” FM coming out of 6N and 6”FM coming out of 6S. All FM are flowing north towards the Treatment Plant. All other FM are apparently abandoned. As-Builts do not indicate the FM’s material type. (Round 1 Pre-Bid answer)

(7) Are there any special cleaning requirements for removal of pumps, piping, manholes, etc.

Government Response: Under Unified Facilities Criteria (UFC 3-240-01), code requires all pumps and piping to be removed along with associated fittings, valves…etc. Prior to removal, components must be isolated (de-energized with LOTO), drained, and thoroughly flushed with approved cleaners before proper disposal to prevent environmental contamination. Flush all cleaning liquids back into the system (sewer/MH) with care not to discharge onto the ground. Any spillage into the ground must be cleaned immediately by removing the grass and all soaked soil and reinstated in kind. See SOW 2.8 for more information. (Round 1 Pre-Bid Answer)

(8) Will the Contractor be required to control and monitor the existing lift stations during construction?

Government Response: Dependent upon means and methods, If the contractor intends to demo or make inoperable a portion of the lift station or interfere with the current operational state of the lift station, then the onus will be on the contractor. If bypass pumping is required, the monitor and control of the bypass pumping will be the responsibility of the contractor. (Round 1 Pre-Bid answer)

(9) There are currently two antennas on the existing lift stations. Do the antennas serve the lift station and will they be required to remain?

Government Response: Both antennas were installed to support the Lift station. One is a monitor that communicated to the IWTP for alarms and has failed. The second is a Monaco alarm panel for the LS level alarms, which communicates with emergency service dispatch center. The inoperable radio frequency reporting system shall be demolished. The Monaco system is to remain in place during construction, disconnected from the existing pumps and connected to the new pump system upon system switch-over. Level alarms must be reconnected. The government reserves the right to retain antenna’s, controllers, and any controller accessories deemed necessary. The government requires that Fire Alarm/Controls shop supervisor and Plant Maintenance Supervisor to be contacted once the lift station is taken out of service, and the shops will respond to remove and retain necessary equipment.

Communication connection, points and frontend updates to the Honeywell EBI is NOT required. (Round 1 Pre-Bid answer)

(10) Is there any work scope on existing wooden pole with camaras?

Government Response: The intent of the design is that the existing wooden poles, cameras, and lights are not part of this project and are to remain undisturbed. If a conflict arises during design or construction that necessitates their relocation, this scope will be handled as a change order. The Contractor will then be responsible for coordinating the relocation and ensuring the items are fully operational. Bidders should not include costs for this potential work in their base bid. (This response was part of Round 1 Pre-Bid RFi’s. A follow up RFI was posted in the Round 2 Pre-Bid RFi’s #19. This will be referenced again later in this document and will be superseded by that answer. See #66 below.)

(11) Paragraph 3.5: Are electrical utility records available for the existing pumping system?

Government Response: Electrical records for the existing pumping system are not available. The Contractor shall be responsible for determining the actual operating requirements through their own field metering and investigation. Include all costs for this investigation in the bid. Coordinate with the project point of contact for site access.

(12) Paragraph 5.7.3: Indicates that a VFD with integral bypass are required. How will VFD be controlled or is VFD for system balancing? Is a VFD required for each pump.

Government Response: VFD nomenclature should be changed to Soft Start Drive and therefore does not have a control point.

(13) Paragraph 5.7.4: Will control wiring be required to be routed back to B2136?

Government Response: No, individual control wiring for pump operation (e.g., start/stop, fault) is not required to be routed back to Building 2136.

The design intent is as follows: (1) Local Control: All pumps will be operated by a local, packaged control system located at the lift station site. This system will manage pump operation based on effluent levels and includes the soft start drives. (2) Remote Communication: The existing Monaco System shall remain for monitoring purposes.

Disconnection from existing pumps and connecting to the new pump system shall be required.

(14) Paragraph 5.7.4: Where in B2136 is existing control panel located or is a new

Honeywell EBI Panel required?

Government Response: Existing panel is located in B2136, first floor ‘Lobby’, designated B2136_CPU1. See Response to items (9) & (13), above.

(15) Paragraph 6.1: Requirements indicate both Stainless Steel Panel and Factory Enamel

Finish?

Government Response: Provide stainless steel panels with an approved factory-applied enamel finish. This is based on the requirements of the lift station environment.

The project requires panels that meet the following criteria: (1) Base Material: Stainless steel 316 is required for its inherent properties, including a hygienic, non-porous surface and material strength. (2) Protective Finish: A factory-applied enamel finish is required for added durability, chemical resistance, and specified color.

(3) Environmental Rating: The complete panel assembly (stainless steel base with enamel finish) must be suitable for Class I, Division 1, Group C and D locations and meet or exceed NEMA 4X standards for corrosion and chemical resistance.

(16) How wide of a drive and how far into the fence is required?

Government Response: Since there is a double fence gate, construct a 20ft wide concrete drive to protrude 25ft into the fence area for maintenance vehicle parking.

Place 4ft minimum concrete sidewalk around the proposed IWLS, VV and Control Panels (can be staged at the end of LS construction). Concrete Driveway and sidewalk per UFC 3-250-04 (Standard Practice for Concrete Pavement Construction) and Construction Specification: UFGS 32 16 19 (Concrete Curbs, Gutters and Sidewalks).

Once the IWLS construction is complete, remove the grass/sod and replace with aggregate as per sec 2.4.3 Aggregates (maximum size of ¾” washed aggregates) and in compliance with ASTM C33/C33M. Aggregates must be placed along the entire fenced area and be 1 inch below the top of the proposed concrete sidewalk and IWLS and any other drainage structure within the fenced area.

(17) Will a concrete “Collar” be required around the Manhole and valve boxes?

Government Response: Yes. Place a minimum of 12” to maximum of 18” diameter collar with 8” thickness 3000PSI concrete reinforced with #4 rebars. Collars to be flush with the top of existing ground.

(18) Manhole detail indicates Debris Basket for 2” Spheres. Are there special expectations for how the Debris basket would be retrieved from the manhole.

Government Response: A rail system is called out in the leader note on Detail A, Sheet P-501.

(19) Flow meters on the inlet to the could be rather deep. Will a permanent ladder be required for access?

Government Response: Flow meters are only called out on the two outlet pipes. If required, provide OSHA approved access for safe travel to/from meters to grade level.

Refer to detail B sheet P-501. DOR to design Flow Meter Vault as required for meters and safe access.

(20) Sheet P-601 Item #4 indicates a Hydrostatic Pressure Level Sensor for pump operations. Are there any additional sump level controls or monitoring required?

Government Response: Pumps are to be energized/de-energized by a level control system compatible with pumps and effluent.

(21) Sheet P-601 doesn’t indicate that flow meter for outlet of the lift station. Is a single flow meter required for the lift station discharge?

Government Response: Flow meters, two (2), count are described by Note 5 on Sheet P-601. No substitutions allowed

(22) Will the Government be responsible for emptying the existing of tanks of residual waste treatment water?

Government Response: The government will manually operate the pumps to pump down the wet well as low as practical and/or install a sump pump to remove as much waste as practical. Any residual beyond that will be attempted to be pumped by governments contracted Vactor truck. Once the Vactor truck step is completed, any residual, rainwater, or ground water infiltration will be the responsibility of the contractor.

(23) The existing electrical panels and pole will need to be relocated prior to any digging taking place. Is this possible?

Government Response: The existing electrical panels and pole must remain fully operational throughout the construction period until the new lift station is commissioned and ready for final cutover.

Relocating these electrical components prior to all excavation may not be possible if it interrupts service to the existing station.

The Contractor/DOR is responsible for developing and submitting a detailed phasing, sequencing, and cutover plan for approval. This plan must clearly show the "means and methods" the Contractor will use to perform all work, including any required relocations and excavations, while ensuring continuous, uninterrupted operation of the existing lift station

(24) Due to the size of the excavation needed, the exterior fence offsets will need to be removed. Is it possible to have the site completely accessible from off the base? This would allow for an area to store the excavated dirt and easier access for trucks, cranes and offloading of equipment.

Government Response: Temporary fencing to the exterior will be allowed. Government requests that for the duration of the project, while 6N is in use contractor is to provide temporary fencing around it with a lockable gate while demo or new work is ongoing with 6S. Follow UFC code 4-022-03. When the project transitions to demolition on 6N and 6S is in working order; to relocate the temporary fencing around 6S. Permanent fencing must be reinstalled in original location when the project is complete.

(25) Will the design plans need to be submitted to Oklahoma City Utilities Water Trust

(OCWUT) for review?

Government Response: Yes, design plans need to be submitted to Oklahoma City Utilities Water Trust (OCWUT) for review.

(26) Will a permit from OKDEQ be required for the new lift-station?

Government Response: Yes, a permit from OKDEQ be required for the new lift-station

(27) Buoyancy requirements:

a. Is the government expecting a specific type of anti-floatation system for the foundation?

Government Response: Under Unified Facilities Criteria (UFC) 3-220-01 which require anti-floatation systems for foundations, in areas with high groundwater tables to prevent upward movement (buoyancy) of underground structures. Nevertheless, as indicated in # 28, there was no evidence of high ground water levels. To reiterate this critical step, contractor is required to conduct his own investigation of sub-surface exploration not only to detect ground water levels but to obtain the soil bearing capacity needed for the proposed IWLS which we believe is mandatory for the design of the structure and foundation.

(28) Is there a schedule identifying the requirements for the wet well pumps shown on

Sheet P-501?

Government Response: (Pre-Bid, Round 1 question #37 says- to refer to RFI 25 & 27 responses. These are copied below. Data Sheets mentioned in #27 were sent with Round 1 Pre-Bid RFI’s).

No schedule. Previous RFI questions and answer-

25. Design Narrative notes DOR to confirm 100 gpm, 10 HP pumps. Can existing flows be provided for the existing pump stations? Either into or out of each lift station?

Government Response: Below information from the Using Agency:

B2122: Peak flow rate of ~280 GPM DOR to determine final pump size to meet a minimum of 2 ft/s velocity. Refer to sheet P-101, General Note 4.

27. Can the chemical make-up of the industrial waste be provided to ensure compatibility with pump, valve, force main, etc. materials?

From the Using Agency (See attachments for data sheets):

Using a KC-135 full strip as a baseline, the dilution for any of B&B 9095, PS-3010, Cee-Bee E3000M, and Hybrid Strip can be approximated by the following:

Gallons Percentage of Total

Chemical 185 1.68%

Rinsing Water 10,800* 98.32%

Note: 10,800 gallons of rinsing water is estimated based on 12 personnel spraying water at 10 gallons per minute for 90 minutes.

Trace amounts of Crest Stripper 18 (Phenol) may also be used for specific paint removal applications.

Gallons Percentage of Total

Crest Stripper 18 3 0.498%

Rinsing Water 600* 99.502%

Note: 600 gallons of rinsing water is estimated based on 2 personnel spraying water at 10 gallons per minute for 30 minutes.

The dilution for Crest Stripper 18 will be approximately 1 part chemical to 200 parts water. See attachments Prebid 1-6.

(29) Can additional descriptions or specifications be provided for the Concrete Vaults?

(Waste Lift Station, IW Valve Vault, Flow Meter and Controllers Vault.)

Government Response: As-Built can be utilized at the sole responsibility of the Contractor to have an ‘distant’ example of the proposed design of the new IWLS. It is premature to give a specific configuration of the proposed IWLS structure with the absence of the aforementioned Sub-Surface exploration to aid in the foundation design and the reinforced concrete structure (refer to #36). Wet Well and Valve Vault configurations are shown from a previous project that Civil Engineering would like to standardize but has not formally defined in the Tinker AFB Standards.

(30) Are the sump pumps required to be explosion-proof rated?

Government Response: Yes. The sump pumps are required to be rated for the hazardous location in which they are installed.

The sump pump wet well is classified as a Class I, Division 1 environment. Therefore, the entire pump assembly, including the motor and all associated electrical components located within the wet well, must be suitable for this classification.

The Contractor is responsible for ensuring the furnished pumps and all related components meet the requirements for this classified area as detailed in the contract document

(31) Are the control panels required to be explosion-proof rated?

Government Response: The requirement for an explosion-proof rating depends on the final installation location of the control panel. (1) If the panel is located inside a classified hazardous area boundary, it must be explosion-proof rated for that specific environment. (2) If the panel is located outside all classified hazardous area boundaries, a standard NEMA 4X enclosure is acceptable.

The Contractor is responsible for installing the panel in a non-hazardous location. If the DOR chosen location or construction sequence necessitates placing the panel within a hazardous area, they shall be responsible for providing the required explosion-proof rated enclosure at no additional cost to the Government

(32) Are the sensors located within the vaults (such as flow sensors) required to be explosion-proof rated?

Government Response: Yes. All electrical components, including but not limited to sensors (flow, level, etc.), junction boxes, and wiring, that are installed within the sump pump wet well must be rated for the hazardous environment. The wet well is classified as a Class I, Division 1 hazardous location. Therefore, all electrical systems within this area must be either: (1) Explosion-proof in accordance with the area classification, or

(2) Intrinsically safe, with the associated intrinsic safety barriers located outside the classified area.

The Contractor is responsible for ensuring all equipment and installation methods within the wet well comply with this classification.

(33) Are the 480V panels required to be explosion-proof rated?

Government Response: The requirement for an explosion-proof rating depends on the Contractor's final installation location for the panel. The Contractor's attention is directed to the Hazardous Area Classification drawings included in the contract documents. (1) If the panel is installed inside a classified hazardous area boundary, it must be explosion-proof and rated for that specific environment. (2) If the panel is installed outside all classified hazardous area boundaries, a standard NEMA 4X enclosure is acceptable.

(34) Is the Lan Drop connection existing and in good order?

Government Response: Connection to Honeywell EBI will be under a separate contract and not a part of this project. This response supersedes previous RFI responses. Amendment forthcoming.

(35) Sheet P-601 Note #4 (under Pump Control) references SCADA. Is integration with the SCADA system included as part of this project scope?

Government Response: No. Design and install RTU as directed in the construction documents. Connection to Honeywell EBI will be under a separate contract and not a part of this project. This response supersedes previous RFI responses. Amendment forthcoming

(36) For the Valve Vault, Wet Well, and Flow Meter Vault, what material are the tanks required to be constructed from (Steel, Concrete, or Fiberglass)? Please provide the required material specifications and wall thickness/schedule?

Government Response: All surfaces coming into contact with sewage must be protected by an approved sewage-resistant coating (e.g., PVC epoxy primer, chloric rubber paint) per UFC 3-240-01. Reinforced concrete structures are recommended here with Corrosion-resistant concrete per UFC 1-200-01 and UFC 3-301-01. Concrete strength at 4000 psi at 28 days per ASTM C-478. Please refer to #36+#38 for wall thickness.

(37) P101#6 Does this require troubleshooting? (Touchscreen & control panel).

Government Response: Yes, as described for the RTU on sheet P-601. This answer supersedes previous RFI answer.

(38) Can the drain lines from the Valve Vault and Flow Meter Vault be tied together and routed to the wet well, provided the piping is sized appropriately?

Government Response: To be determined by DOR.

https://www.google.com/search?q=UFC+3-240-01&sca_esv=8b7032114d8adf20&biw=1920&bih=945&ei=1ki3aaeGAeC4wN4Pvu-vkAk&ved=2ahUKEwiB39m5kaOTAxUF6MkDHSa5CI8QgK4QegQIARAB&uact=5&oq=lift+station+wall+material+per+ufc+code&gs_lp=Egxnd3Mtd2l6LXNlcnAiJ2xpZnQgc3RhdGlvbiB3YWxsIG1hdGVyaWFsIHBlciB1ZmMgY29kZTIIECEYoAEYwwRIn1xQAFjJUnABeAGQAQCYAW-gAbETqgEEMjMuNLgBA8gBAPgBAZgCG6ACoRPCAgUQABjvBcICCBAAGIAEGKIEwgIIEAAYogQYiQXCAgoQIRigARjDBBgKwgIEECEYCpgDAJIHBDIyLjWgB51JsgcEMjEuNbgHnxPCBwY0LjIxLjLIByqACAA&sclient=gws-wiz-serp

(39) What are the existing pipe sizes for the connections to the water discharge and carwash waste systems?

Government Response: Please refer to the As-Builts referenced in previous points.

(40) Sheet P-501 indicates ductile iron piping inside the vaults and HDPE piping outside the vaults. Is this piping material transition required for all vault installations shown on the plans?

Government Response: Yes, piping material transition required for all vault installations.

(41) Do the Drain lines off the Flow Meter Vault & Valve Vault headed to the Wet Well need to have some means of back flow prevention in case the power goes down or power outage? Or else industrial waste will make its way back to the valves and flow meters?

Government Response: No, backup power is provided via an emergency generator.

(42) Will the existing system need to remain operational during construction? Please note that the installation of the new equipment will require a significant excavation area?

Government Response: Yes. Refer to SOW para. 2.3 Sequencing and response to RFI 29. (Response to RFi 29 is found in the Round 1 Pre-Bid RFI’s. See below).

29. The SOW requires that at least one industrial waste lift station remain operational throughout construction. Please confirm whether temporary bypass pumping is anticipated/required or if all sequencing is expected to occur within existing infrastructure.

Government Response: Sequencing described in para. 2.3 does not require bypass pumping but intends on using IWLS 6N pumps. Contractor means and methods does not preclude temporary bypass pumping if deemed necessary.

(43) Are there any as-built drawings available showing the location of existing piping, wiring, or other underground utilities in the project area?

Government Response: Refer to response of RFI 26. (Response to RFI 26 is found in Round 1 Pre-Bid RFI’s. See below).

26. Can routing and elevations of existing force mains to the IWTP be provided?

Including discharge elevations and any discharge head to overcome at the IWTP.

Government Response: Inflows: existing 8” PP ‘Gravity Flow’ pipe going into 6N with invert EL 1280.3 with Strainer Basket. Top EL of 6 is 1294.33. please refer to As-Built file 1993_IndWaste (Year 1993). Refer to sheets C-1/View-A and M-2/ View-A. Also, refer to the following: As-Built file 1995_IndWaste- sheet C1.218, C1.208, C1.214 and file 1994_IndWaste – sheet C-7

(44) Please see the attached drawing with notes.

Government Response: Not enough information is given. Drawing is missing.

(45) If the proposed bypass is intended to take 6S out of service and pump into 6N, we will need to verify whether the 8” line flow can be diverted to 6N. It appears there may be a branch line connecting to 6N, but confirmation is needed.

Government Response: Please refer to point #3. In brief, the 8” PP Gravity line coming into 6N but is branching via Y to 6S with a gate valve + valve box. Contractor needs to shut down the service to 6S via the valve and then perform the steps outlined in point #7. (Point #3 and #7 can be found in the Round 1 Pre-Bid RFI’s. See Below.)

3. It appears that there might be two flows from B2122 Paint Hanger. Please confirm that there are only two total inlet flows into the existing lift stations.

Government Response: As-Built file 1994_IndWaste (June 1993) shows one 8” PP ‘Gravity Flow’ pipe with downstream flow into 6N branching into 6S. Before each LS, there is an 8” Gate Valve with associated Valve Box (for access). This As-Built supersedes As-Built file 1993_IndWaste (Line H from Bldg 2122) showing an 8” VCP Gravity pipe with downstream flow into 6S branching into 6N. The 8” VCP pipe has been abandoned and replaced by the 8” PP pipe. As-Built file 1994_IndWaste shows the 8” VCP ‘flushed and capped’ only and not removed. Please refer to sheet 9/11 details 2/C7-P.1 and sheet 10/11 details 10/C6-P.1

7. Are there any special cleaning requirements for removal of pumps, piping, manholes, etc?

Government Response: Under Unified Facilities Criteria (UFC 3-240-01), code requires all pumps and piping to be removed along with associated fittings, valves…etc. Prior to removal, components must be isolated (de-energized with LOTO), drained, and thoroughly flushed with approved cleaners before proper disposal to prevent environmental contamination. Flush all cleaning liquids back into the system (sewer/MH) with care not to discharge onto the ground. Any spillage into the ground in kind. See SOW 2.8 for more information.

(46) Additionally, please verify whether there are any manholes located near the work area that could be used to pump the bypass into if required Government Response: Contractor to field verify. Please follow the requirements as mentioned in point #7. (Response that indicates to review point #7 is found in Round 1 Pre-Bid RFI’s. See below)

7. Are there any special cleaning requirements for removal of pumps, piping, manholes, etc.?

Government Response : Under Unified Facilities Criteria (UFC 3-240-01), code requires all pumps and piping to be removed along with associated fittings, valves…etc. Prior to removal, components must be isolated (de-energized with LOTO), drained, and thoroughly flushed with approved cleaners before proper disposal to prevent environmental contamination. Flush all cleaning liquids back into the system (sewer/MH) with care not to discharge onto the ground. Any spillage into the ground in kind. See SOW 2.8 for more information

(47) C-102 Keynote 5 & RFI #16. Please confirm how far West the new concrete driveway shall extend, towards Warehouse Road?

Government Response: Keynote#5/Dwg #C-102 indicates new concrete pad within the gated area of the IWLS. No concrete pads, either driveway or sidewalks outside the IWLS area.

(48) Is the entire lift station yard to receive new gravel:

a. Is #57 stone acceptable gravel material for this application?

b. If required, please confirm the entire lift station yard shall be cleared/grubbed of existing vegetation

c. Is there a minimum thickness required for the new gravel?

Government Response: There is to be concrete drive into the area and a sidewalk to the lift station. The remaining space is to receive gravel.

a. #57 aggregates are acceptable to meet Oklahoma Department of Transportation (ODOT) specifications for construction and drainage. The minimum aggregate size is ½” and maximum acceptable size is 1”. All crushed aggregate must be clean and washed without any fines.

b. All vegetation within the IWLS gated area to be removed and replaced with 6” lift of #57 aggregate.

c. 6” minimum thickness required.

(49) Will the Government require a geotextile fabric beneath the gravel? If so, is there a basis of design?

Government Response: Geotextile fabric will not be needed since this is not a drainage layer under roadway.

(50) The civil design narrative, para 3.3, states to provide drainage away from new lift station areas avoiding low spots and ponding. Please confirm the intent is to simply divert water away from the new lift station areas only & towards the culvert shown clouded below?

Government Response: Yes, the intent is to divert the surface water away from the new lift station areas and towards the culvert.

(51) There is an existing fire line that intersects the lift station yard / construction area.

Please confirm it is the design intent to reroute this line outside of the lift station yard.

Government Response: No, the design intent is to maintain the fire line in place and avoid relocation. As noted in the drawings the Contractor shall verify utilities and propose a space to minimize additional cost and/or delay to the Government.

(52) Please confirm the valves (shown below) exist per the “correct as-built” drawings from the previous documents RFI COR Response document dated 19 March 2026.

a. If the subject valves cannot be located, please confirm the contractor shall be required to install new valves to facilitate isolation of the North & South Lift stations

Government Response: This is the correct As-Built showing the feeder lines with associated gate valves. The contractor must exert all efforts to locate these valves. If these valves either cannot be located or found un-operable, the Contractor must coordinate with COR for concurrence and submit a request for replacement.

Please note that As-Built file 1994_IndWaste (June 1993) shows one 8” PP ‘Gravity Flow’ pipe with downstream flow into 6N branching into 6S. Before each LS, there is an 8” Gate Valve with associated Valve Box (for access). This As-Built supersedes As- Built file 1993_IndWaste (Line H from Bldg 2122) showing an 8” VCP Gravity pipe with downstream flow into 6S branching into 6N. The 8” VCP pipe has been abandoned and replaced by the 8” PP pipe. As-Built file 1993_IndWaste shows the 8” VCP ‘flushed and capped’ only and not removed. Please refer to sheet 9/11 details 2/C7- P.1 and sheet 10/11 details 10/C6-P.1.

As such, in your red-lined As-Built, above, there should be only 2 valves that are live, while the 3rd valve that is clouded, is part of an abandoned line: again the 8” VCP Gravity pipe.

(53) Please confirm the contractor shall provide a geotechnical report including boring logs to determine groundwater depths.

a. If high ground water depths are found, please confirm this will be considered unforeseen site conditions which will entitle the contractor to a contract modification.

Government Response: As indicated in previous RFI response # 28, there was no evidence of high ground water levels in areas of close proximity. To reiterate this critical step, contractor is required to conduct their own investigation of sub-surface exploration not only to detect ground water levels (if any) but to obtain the soil bearing capacity needed for the proposed IWLS which we believe is mandatory for the design of the IWLS structure and foundation. (Response for RFI #28 mentioned above is found in Round 1 Pre-Bid RFI’s. See below)

28. Is information available for anticipated average and high-level groundwater depths in the area? If groundwater levels encountered during construction differ from any provided information or assumptions used during design, please clarify whether resulting impacts to foundation design would be addressed by the Contractor or via contract modification.

Government Response: Boring conducted last October 2025 along RWY 18/36 to a depth of 20ft did not reveal any ground water present which is in close proximity to the lift stations. Contractor should verify by conducting a Sub-Surface exploration to bore thru the area for a depth equivalent to the depth of the proposed IWLS.

(54) Please confirm the design needs to be submitted to OCWUT for the fire line relocation.

Government Response: No, there is not an anticipated relocation of the fire line

(55) If the design is required to be submitted to OCWUT please confirm they shall only review the fire line relocation scope of work..

Government Response: No, there is not an anticipated relocation of the fire line.

(56) Sheet P-501 Valve Vault indicates connection to two industrial waste lines in the Valve Vault.

a. Is the intent to connect to both existing 6” INW lines in the valve vault?

b. If both are connected to the lift station, will they both be operational at the same time? Operating both lines changes the flow requires to provide the required minimum of 2 fps flow?

c. SOW Valve sections indicate transitioning from Ductile Iron to HDPE exterior to the valve vault. Material transition in the double wall system is less than desirable. Can HDPE piping be routed into the Valve box and flanged at the valve?

Government Response:

a. Yes, the intent is to connect to both existing 6” INW lines in the valve vault

b. No, both lines are not required to be operational at the same time.

c. Yes, HDPE piping can be routed into the Valve box and flanged at the valve.

(57) Sheet P-101 General Note 4 indicates (3) Submersible 100gpm pumps and Sheet P101 Keyed Note 1 indicates peak Flow Rates for B2122 at 280gpm and 30gpm for B2136. Full operating of the (3) Submissible pumps would not provide the required 310gpm peak flow. To get the N+1 requirement in a (3) pump arrangement each pump would be sized for 50% of the peak flow, which would be 155 gpm minimum for each pump. Additionally, If the lift station force main discharge is limited to a single 6” line, the individual pump flow would need to be increased to 180gpm to maintain 2fps required by the same general note. For bidding purpose pump flows will be based on 180gpm at required head loss.

Government Response: Concur

(58) It appears that some of the existing double wall piping is monitored. Is monitoring system operational? Are there as-builts for the monitoring system?

Government Response: The existing monitoring system is not operational and is not a part of the scope of work of this project.

(59) Which of the existing gravity and force mains piping system are double wall?

Government Response: Both force mains are double wall pipes and the gravity drains are single wall. Extend double wall piping of both force mains to the flow meter vault.

(60) Will monitoring wells be required at any of the double wall piping connections the new wet well or vaults?

Government Response: No, monitoring wells will not be required.

(61) Will the drain line between valve vault and wet well be required to be double wall?

Government Response: No, a drain line will not be required between the valve vault and wet well.

(62) Sheet P-101 Note 3: Can flow meter(s) be located in Valve Vault rather than constructing a separate vault for the flow meter(s) Government Response: No, due to the required upstream straight length of pipe for the flow meters to operate properly.

(63) Will new isolation valves be required for the existing effluent line entering the wet well from B2122 and B2136?

Government Response: Yes, new isolation valves will be required for the existing effluent line entering the wet well from B2122 and B2136.

(64) The existing Gate tracks for gates to cross Douglas Blvd are located in the entrance to the lift station area. Are there any special closures or construction requirements for the gate and the tracks?

Government Response: No, there are not any special closures or construction requirements for the gate and tracks. Existing rail tracks outside the IWLS area must remain and be protected from damage. No proposed work outside the gated area.

(65) What Government agency is responsible for the existing security cameras located on the telephone pole in the site? What are the requirements for outage of the security camera during construction to allow for installation of the new lift station?

Government Response: After further investigation, there is no agency coming forth and claiming ownership of this equipment. These cameras are no longer in use and have been abandoned in place. There will not be an outage required. This response supersedes previous Pre-Bid RFI #10 regarding the cameras

(66) Follow up to round 2 RFI question 20. (Below Picture) With the lift stations being converted to the Honeywell management system on project WWYK240146.

a) Is this Telecommunication box still required to be in the area?

b) Does this termination cabinet service any other area?

Government Response: a. Yes, this telecommunication equipment will be required for the new system. The existing cabinet shall be removed that supports the legacy wireless communication system, which will remain in service. Provide new NEMA 4X enclosure.

b. No, this termination cabinet does not service any other known area. The contractor shall demolish and remove this cabinet, its foundation, and all associated conduit and wiring as part of the obsolete system decommissioning.

(67) Please clarify If the 480/120v XFMR and 120/208v electrical panel on the rack near the lift stations are to be replaced to meet the NEMA 4x requirements. (below picture) With the lift stations being converted to the Honeywell management system on project

WWYK240146.

a. Is this Telecommunication box still required to be in the area?

Government Response: Yes, the existing 480V transformer and 120/208V electrical panel are to be replaced. These components are part of the legacy system and are not rated for the wet, corrosive environment of a lift station. The contractor shall provide and install a new transformer and panel that meet the NEMA 4X requirement for corrosion resistance and suitability for outdoor/wet locations.

(68) Please clarify if the intent to have the Monaco controller is to be placed in a NEMA 4x enclosure? (below picture)

Government Response: The existing Monaco controller and its associated antenna shall remain in service for this project as they are part of the legacy wireless monitoring system. Therefore, a new NEMA 4X enclosure for this controller is required.

2. The points of contact for this project are:

a. Gloria Butcher, Project Manager. PH: 582-4830

b. Mark Williams, Construction Inspector. PH: 582-9042

c. Joshua Wheeler, CSAG Program Manager. PH: 582-4826

d. Randall Floyd, Contracting Officer Representative (COR). PH: 730-320-6068

Gloria Butcher Randall Floyd Project Manager 72 ABWEngineer/COR 72d Civil Engineering Directorate (Tepa) 72d Civil Engineering Directorate

0 Attachment(s):

cc:

Project folder

2026-07-31T08:47:00-0500
FLOYD.RANDALL.G.1383281306
2026-07-31T08:58:33-0500
BUTCHER.GLORIA.MARIE.1269258701