TGI_38K4212359A01_c0v0.pdf
PDF 213 KB Posted
- Attached to
- USS DEWEY (DDG-105) FY26 6C1 CNO SRA(d) BUNDLE #2, Chief of Naval Operation Availability Yokosuka Japan
- Solicitation number
- N6264926RA004
About this file
This document is a Task Group Instruction (TGI) for the USS Dewey (DDG-105) detailing a comprehensive inspection, repair, and preservation work order for the aft uptake space. The work involves a detailed visual inspection of multiple ship compartments and components, including exterior surfaces, gas turbine exhaust ducts, and various structural elements across frames 247-272. Specific tasks include power tool cleaning to bare metal for 1,490 square feet, ultrasonic thickness measurements in up to 100 locations, and multiple repair activities such as base metal weld build-up (160 square inches), plate replacement (94 square feet), stiffener replacement (75 linear feet), and weld repairs (25 linear feet).
The instruction includes special requirements involving fire zone boundaries, mandating a non-flammable closure in accordance with naval regulations. The work will be performed by SRF-JRMC (Ship Repair Facility-Japan Regional Maintenance Center), with government-furnished materials including various specialized gaskets, washers, and ferrules. The document specifies precise technical requirements for inspection, measurement, and repair techniques, with an emphasis on structural integrity assessment and preservation of the ship's uptake system. The work is scheduled for August 2025, with multiple planners and a work integration manager identified to oversee the project.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: AFT UPTAKE SYS AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-105 USS DEWEY K42
CU PHASE TITLE:
F/O - INSPECT, REPAIR, AND PRESERVE AFT UPTAKE SPACE
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
TETSUYA UEMATSU 231A 315-243-9943 05-AUG-2025
APPROVED BY: CODE PHONE DATE
YUUJI NAKAMURA 231A 315-243-6041 05-AUG-2025
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
SURFMEPP
This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: AFT UPTAKE SYS AY A 0
FOUO
SHIP: DDG-105 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-6 J1-2 M1-2
1. SCOPE/PURPOSE
1.1 Title: Inspection, Repair, and Preservation of Aft Uptake Space; accomplish
1.2 Location of Work:
1.2.1 05 Level Weather, Frames between 247 and 272, Port and Starboard (Stbd)
1.2.2 Uptake Engine Room No. 2 (02-242-0-Q)
1.2.3 Uptake Engine Room No. 2 (01-248-0-Q)
1.2.4 Intake/Uptake Engine Room No. 2 (1-268-2-Q)
1.2.5 Passage (1-254-6-L)
1.3 Identification:
1.3.1 Quantity (One EA), Exterior Surface of 05 Level Deck Plating, Frames between 246 and 272, above 81 feet 3 Inches above base line, Port and Stbd
1.3.2 Quantity (One EA), 2A Propulsion Gas Turbine Exhaust Duct
1.3.3 Quantity (One EA), 2B Propulsion Gas Turbine Exhaust Duct
1.3.4 Quantity (One EA), SSGTRB Number 2 Exhaust Duct
1.3.5 Quantity (One EA), 02 Level, 2A Module Gas Turbine Engine Deck Foundation and Bolting Ring
1.3.6 Quantity (One EA), 02 Level, 2B Module Gas Turbine Engine Deck Foundation and Bolting Ring
1.4 Security Classification: None.
1.5 Initial Condition: None.
1.6 Contractor work start date: See attached POP list.
1.7 Contractor work completion date: See attached POP list.
2. REFERENCES:
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI NSI FY-
NAVSEA Standard Items 1 1 N
2 LI LI FY-26 Local Standard Items - ORG N
3 DWG 259-
7060867
FAB & INSTL OF GTRB UPTAKE
ENG RM NO.2 & ABOVE
B N
FOUO
SHIP: DDG-105 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
4 DWG 259-
7060869
FAB & INSTL OF SSGTG UPTAKE
ENG ROOM NO.2 & ABOVE
B N
5 DWG 100-
7060401
UNIT STRUCTURAL ARR DWG
ASSY UNIT 2440
C Y 3-6
6 DWG 100-
7060397
UNIT STRUCTURAL ARR DWG
ASSY UNIT 2340
D Y 3-
7 DWG 100-
7060398
UNIT STRUCTURAL ARR DWG
UNIT 2350
D Y 3-
8 DWG 100-
7060402
UNIT STRL ARR DWG ASSY UNIT
F Y SE
E N
OT
E
9 DWG 150-
7060435
UNIT STRUCTURAL ARR DWG
ASSY UNIT 4510
G Y SE
E N
OT
E
10 DWG 150-
7060436
UNIT STRUCTURAL ARR DWG
ASSY UNIT 4520
C Y SE
E N
OT
E
11 TM
SYSTEMS &
SPECIFICAT
IONS
SSPC Painting Manual Volume 2 - N
12 TM T9074-
AS-GIB-
010/271
Requirements for Nondestructive Testing Methods
1 N
13 TM S9086-
DA-STM-
010/CH-100
Hull Structures 4 N
14 MIL MIL-
STD-2035
Nondestructive Testing Acceptable Criteria
A N
3. APPENDICES:
3.1 Appendix “J” TGI Job Summary Information Sheet
3.2 Appendix "M" TGI Material List
3.3 Appendix “D” Deficiency Form
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Accomplish a visual inspection of the current ship condition, listed in 1.3.1 through 1.3.6, located in 1.2.1 through 1.2.4, using 2.3 through 2.10 for guidance, and as designated by the SUPERVISOR.
5.1.1 Ensure to inspect each exterior vertical, horizontal, deck, and foundation surface, and each interior exhaust stack, exterior uptake duct and mixing tube, anchor foundation, eductor, eductor nozzle, overhead, bulkhead, deck, restraint, steel channel, penetration, deck spool, ladder foundation, bolting ring, and pipe hanger.
5.1.2 Mark each identified and designated area requiring repair.
5.1.3 Submit one legible copy, in hard copy or approved transferrable media, of a report with a sketch listing results of the requirements of 5.1 to the SUPERVISOR.
FOUO
SHIP: DDG-105 CHG/VER: 0/0
5.2 Power tool clean to bare metal for each location reported in 5.1.3, listed in 1.3.1 through 1.3.6, located in 1.2.1 through 1.2.4, to include each exposed longitudinal, vertical, and traverse stiffener, for a total 1,490 square feet.
Accomplish each requirement of Surface Preparation Specification SSPC-SP 11 of 2.11, as designated by the
SUPERVISOR.
5.3 Accomplish a visual inspection in each location for coating removed in 5.2, listed in 1.3.1 through 1.3.6, located in 1.2.1 through 1.2.4 for structural integrity, deterioration, pitting, each crack, and area of damage or distortion, using
2.3 through 2.10 for guidance.
5.3.1 Mark each corroded, damaged and/or deteriorated area.
5.3.2 Submit one legible copy, in hard copy or approved transferable media, of a report with a sketch listing results of the requirements of 5.3 to the SUPERVISOR.
5.4 Accomplish each ultrasonic thickness measurement (UTM) in up to 100 locations in each location reported in 5.3.2, listed in 1.3.1 through 1.3.6, located in 1.2.1 through 1.2.4 in accordance with Paragraph 6.7 of 2.12 and 2.13, as designated by the SUPERVISOR, using 2.3 through 2.10 for guidance. The acceptance criteria must be in accordance with 2.14.
5.4.1 Submit one legible copy, in hard copy or approved transferable media, of a report listing results of the requirements of 5.4 to the SUPERVISOR.
5.4.2 Ensure a sketch showing each location of each UTM reading, original material thickness, existing material thickness, and percentage of material thickness reduction.
5.5 Accomplish the following repairs reported in 5.1.3, 5.3.2, and 5.4.1, listed in 1.3.1 through 1.3.6, located in 1.2.1 through 1.2.4, using 2.3 through 2.10 for guidance, as designated by the SUPERVISOR. See 5.9.4 and 5.9.5.
5.5.1 Base metal weld build-up a total of 160 square inches.
5.5.1.1 Ensure each base metal buildup area does not exceed 2 inches in diameter.
5.5.1.2 Estimate the base metal buildup repair to be one quarter inch thick for pricing purposes.
5.5.1.3 Fill each local pit and groove with weld metal prior to the application of each principle build-up layer.
5.5.1.4 Ensure each surface is ground smooth to metal.
5.5.2 Remove existing and install new a total of 94 square feet of plate for each bulkhead, overhead, and deck plate.
5.5.3 Remove existing and install new a total of 75 linear feet of longitudinal, vertical, and traverse stiffener.
5.5.4 Remove existing and install new a total of 5 square feet of anchor foundation and flange joint.
5.5.5 Remove existing and install new each deck spool, gasket and bolting ring.
5.5.6 Vee out and weld a total of 25 linear feet of cracked, split, broken or damaged weld.
5.5.7 Chip and grind each surface flush in way of each repair.
5.5.8 Template exact size, configuration, and location from each existing shipboard condition, in way of each repair.
5.5.9 Accomplish the requirements of 009-012 of 2.1, including Table 2, Columns A and D, Lines One through 7.
FOUO
SHIP: DDG-105 CHG/VER: 0/0
5.5.10 Accomplish the requirements of 009-025 of 2.1 for a local air hose test of each new weld seam. Allowable leakage: None.
5.6 Accomplish the requirements of 009-032 of 2.1, including Table 3, Line 22A for interior surface, Table 2, Line(s) 3 for exterior surface, for coating removed in 5.2, located in 1.2.1 through 1.2.4.
5.7 Confirm that all personnel have exited the space prior to closure of the space listed in 1.2.3 and1.2.4. Designate one person to account for all personnel who may have entered the space.
5.8 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
5.9 Notes:
5.9.1 Planner: Code 231A T. Uematsu, 243-9943
Planner: Code 231A H. Ishikawa, 243-6152 Planner: Code 234 K. Akase, 243-2372
5.9.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.9.3 This TGI meets the intent of DDG CSWT File No. 259-090.
5.9.4 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair in 5.5 are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.9.5 Materials for structural members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
5.9.6 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.9.7 WPC will copy the following pages in reference.
REF. 2.8: Pages 7D, 7A-12, 5-12, 5A-12, 5B-12, and 3-12.
REF. 2.9: Pages 5A-7, 5B-12, 3-12, 4-12, 7-12, and 3A-12.
REF. 2.10: Pages 3G-5, 3H-5, 3E-6, 3F-6, 3K-6, 3J-7, 3-12, 3A-12, 3B-12, 3C-12, and 3D-12.
5.9.8 JCNs EM02-ZB46, EM02-ZB48, EM02-ZB49, and EX03-ZA11 are related to this TGI.
5.10 Government Furnished Material (GFM):
5.10.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.11 SRF-JRMC will provide the following service work: (TGI No. 38K4212359S02).
5.11.1 [C740] Crane and crane rigging service.
5.11.2 [X99E] Utility service, electrical.
5.11.3 [X99M] Utilities service, including water supply, steam supply, and low pressure air supply except onboard blasting work.
FOUO
SHIP: DDG-105 CHG/VER: 0/0
5.11.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.11.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.11.6 [C133] QA Inspection for (G) symbol(s).
FOUO
J-1
SHIP: DDG-105 CHG/VER: 0/0
APPENDIX "J"
TGI JOB SUMMARY INFORMATION SHEET
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
AFT UPTAKE SYS AY A 0 0
CU PHASE TITLE:
F/O - INSPECT, REPAIR, AND PRESERVE AFT UPTAKE SPACE
PRIMARY COMPONENT:
COMPONENT UNIT LIST (FOR ASSEMBLIES):
05LVL & ABV EXTERIOR MS CMPT 01-248-0-Q MS #2A GTM UPTAKE UT #2B GTM UPTAKE
UT #2 SSGTG UPTAKE UT CMPT 1-268-2-Q MS CMPT 02-242-0-Q MS
ATTACHMENT LIST:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA ,TAKEHIDE
JO: KO: TOTAL MAN HRS: TOTAL DURATION: PLANNING ACCEPTANCE:
38K4212359 A01
TOTAL MAT’L COST
CU PHASE DESCRIPTION:
The purpose of this TGI is to inspect, repair, and preserve aft uptake space.
Location of Work:
05 Level Weather, Frames between 247 and 271, Port and Starboard (Stbd) Uptake Engine Room No. 2 (02-242-0-Q) Uptake Engine Room No. 2 (01-248-0-Q) Intake/Uptake Engine Room No. 2 (1-268-2-Q) Passage (1-254-6-L)
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
5.1 SFTR , RGRS 22 KE PC 0
5.2 PNTR 22 KE PC 0
5.3 SFTR 22 KE PC 0
5.4 SFTR 22 KE PC 0
5.5 SFTR , WELD , BLRM , PNTR , QA 22 KE PC 0
5.6 PNTR , QA , CARP , RGRS s 22 KE PC 0
5.7 SFTR 22 KE PC 0
5.8 PNTR , QA 22 KE PC 0
Structure and Preservation Work CFM: for all paints, thinner, grits, disposal cost, UT inspection cost, air compressor and fuel cost, marine chemist cost, strong back material, firewatch cost, confined space watch cost, fastener, gasket, compressor, dryer, fuel, (continues to below)
22 MQ CS 0 0 0
(continues from above) and misc such as electrode, gases, covering material, enclosing material, closure material, and other consumable.
22 MQ CS 0 0 0
FOUO
J-2
SHIP: DDG-105 CHG/VER: 0/0
TASK NAME
SHOP TSD/WC TS CREW# MHRS
HIGH RAD
HOURS
RC
GRID#
Boiler Work CFM: for covering material, anti-seize compound, and other consumable material (MISC).
22 MQ CS 0 0 0
Process Funding Document 10 CT OM 1 1 0
FOUO
M-1
SHIP: DDG-105 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
AFT UPTAKE SYS AY A 0 0
CU PHASE TITLE:
F/O - INSPECT, REPAIR, AND PRESERVE AFT UPTAKE SPACE
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
38K4212359 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
400 M GASKET , GASKET, FIBROUS
GLASS, WIRE-REINFORCED
PLAIN, CLOTH, SPEC: HH-P-31,
TYPE I, CLASS 1, SIZE: 88-
11/16” OD X 83-7/16” ID X 3/8”
THK, BOLT CIRCLE DIA: 86-
11/16”, 40 BOLT HOLES, 25/32”
DIA HOLES, HOLES EQUALLY
SPACED,
REMARKS: NON ASBESTOS
REQUIRED, BIW CAT#: 52248-
9B 5330 LL9810187 NA 4 N 2/SH
NOTES:
FOUO
M-2
SHIP: DDG-105 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
401 M GASKET, FIBER GLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, MATERIAL: FIBER GLASS,
WIRE INSERT, FIBER GLASS
SIZE: 81-11/16" OD X 76-7/16"
ID X 3/8" THK, BOLT CIRCLE
DIA: 79-11/16" , 36 BOLT
HOLES, 25/32 DIA HOLES,
HOLES EQUALLY SPACED
REMARKS: NON ASBESTOS
REQUIRED,
9B 5330 LL9810157 NA 4 N 4/EA
402 M WASHER,2, WASHER,
FIBROUS GLASS, WIRE-
REINFORCED PLAIN, CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1 SIZE: 2" OD X 21/32" ID, 3/8"
THK. BIW CAT#: 52419-026
*DARCO SOUTHERN P/N:
ZFL0HHP-000-017
ORIG: C234 K.AKASE, 243-2372
ORDERED FOR KTR
9Z 5310 LL4917124 NA 4 N 52007427
290/EA
403 M FERRULE, FERRULE, FIBROUS
GLASS, WIRE-REINFORCED
PLAIN, CLOTH, SPEC: HH-P-31,
TYPE I, CLASS 1,
SIZE: 31/32"OD X 21/32"ID X
1/2" THK, REMARKS: NON-
ASBESTOS REQUIRED,
BIW CAT NO. 54638-027,
ORIG: C234 K.AKASE, 243-237
ORDERED FOR KTR
9B 5340 LL4941032 NA 4 N
290/EA
404 M GASKET, FIBERGLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
CLOTH,
SPEC: HH-P-31, TYPE I, CLASS
1, SIZE: 53-11/16"OD X 48-7/16"ID
X 3/8"THK,
BOLT CIRCLE DIA: 51-11/16",
24 BOLT HOLES, 25/32" DIA
HOLES, HOLES EQUALLY
SPACED,
REMARKS: NON-ASBESTOS
REQUIRED,
BIW CAT NO. 52248-434
C234 K.AKASE, 243-2372
ORDER FOR KTR
9B 5330 LL9604082 NA 4 N 2/EA
405 M GASKET, FIBERGLASS,
GASKET, FIBROUS GLASS,
WIRE-REINFORCED PLAIN,
TAPE,
SPEC: HH-P-31, TYPE I, CLASS
2, SIZE: 1/2"W X 1/8"THK X 20FT
L, REMARKS: NON-ASBESTOS
REQUIRED
ORIG: C234 K.AKASE, 243-2372
ORDER FOR KTR
9B 5330 LL4924382 NA 4 N 9/RO
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-105 AFT UPTAKE SYS AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38K4212359 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-105 AFT UPTAKE SYS AY A 0
File details come from the government source that posted it. Updated .