VI_-_Q&As_Seymour_Johnson_AFB.pdf

PDF 24 KB Posted

Attached to
Bulk Storage Services- Solicitation Federal contract opportunity
Solicitation number
SPE603-18-R-0513
Issued by
Defense Logistics Agency Energy

About this file

VI - Q&As Seymour Johnson AFB

View the file

Other files for this federal contract opportunity

Other files attached to Bulk Storage Services- Solicitation, newest first.
File Type Posted
SF30_SPE603-18-R-0513_Amendment_0007.pdf PDF
Shaw_Appendix_AF_-_Apr_10,_2018.pdf PDF
III_-_Q&As_Langley_AFB.pdf PDF
XIII_-_Shaw_AFB_Appendix_AF.pdf PDF
V_-_Q&As_Pope_AFB.pdf PDF
I_-_General_Technical_Q&As.pdf PDF
II_-_Q&As_Dover_AFB.pdf PDF
X_-_McGuire_AFB_Appendix_AF.pdf PDF
XI_-_Pope_AFB_Appendix_AF.pdf PDF
VIII_-_Dover_AFB_Appendix_AF.pdf PDF
IX_-_Langley_AFB_Appendix_AF.pdf PDF
IV_-_Q&As_McGuire_AFB.pdf PDF
VII_-_Q&As_Shaw_AFB.pdf PDF
XII_-_SJ_AFB_Appendix_AF.pdf PDF
SF30_SPE603-18-R-0513_Amendment_0006.pdf PDF
Seymour_Johnson_AFB_WD_15-4379.pdf PDF
SF30_SPE60318R0513_Amendment_0005.pdf PDF
Pope_WD_15-4377.pdf PDF
AF_Consolidated_PWS_-_as_of_12_Feb_18.pdf PDF
Appendix_G_CAC_Procedures.pdf PDF
SF30_SPE603-18-R-0513_Amendment_0004_.pdf PDF
SF30_SPE603-18-R-0513_Amendment_0003.pdf PDF
Solicitation_SPE603-18-R-0513_Rev._8_Mar_2018.pdf PDF
SF30_SPE603-18-R-0513_Amendment_0002__.pdf PDF
Final_Solicitation_SPE603-18-R-0513_Amend_0001.pdf PDF
SF30-SPE603-18-R-0513-00001.pdf PDF
Pope_AFB_WD_15-4379.pdf PDF
Pope_AAF_Appendix_AF_FINAL.pdf PDF
ATTACHMENT_II_-__OFFEROR_SUBMISSION_PACKAGE_AF_GOCOs_EAST_FINAL.pdf PDF
Seymour_Johnson_WD_15-4377.pdf PDF
Seymour_Johnson_Appendix_AF_FINAL.pdf PDF
ATTACHMENT_IV_JOINT_VENTURE_CONSENT_FORM_EAST.pdf PDF
Final_Solicitation_SPE603-18-R-0508.pdf PDF
McGuire_Appendix_AF_FINAL.pdf PDF
Shaw_Appendix_AF_FINAL.pdf PDF
Langley_Appendix_AF_FINAL.pdf PDF
McGuire_WD_15-4191.pdf PDF
Final_AF_Consolidated_PWS_-_as_of_21_Nov_17.pdf PDF
Dover_Appendix_AF_FINAL.pdf PDF
Shaw_WD_15-4439.pdf PDF
Langley_WD_15-4341.pdf PDF
Dover_WD_15-4217.pdf PDF
ATTACHMENT_III_-_PAST_PERFORMANCE_QUESTIONAIRE_-_AF_GOCOs_East.pdf PDF
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPE603-18-R-0513

East Coast Region

Seymour Johnson Technical Questions & Answers

1. Please verify number of truck receipts by product per week. At the site visit the COR thought the information on the appendix was incorrect.

Answer: Refer to PWS Appendix AF, Section (1) Introduction.

2. What is the average duration of a 130,000 gallon transfer?

Answer: Refer to PWS Appendix AF, Section (1) Introduction.

3. Referring to the TS collateral duty restrictions listed in PWS Appendix D, would the

Government consider removing this restriction for AF Bulk Storage GOCO sites with fewer than 10 FTEs assigned? Administrative and management duties for small workforces will not require 8-hrs per day, 5-days per week, and segregation of duties is not a factor.

Answer: No, Refer to PWS Appendix D.

4. The Seymour Johnson Appendix AF was changed to state "None. Contractor available 24 hours" for number of times called in after hours. What is the intent of this change?

Refer to PWS Appendix AF, Section (2) Hours of Operation.

5. Does the Fuels Management Flight designate the number of fuels personnel who must be present when off-loading multiple tank trucks simultaneously in their Fuels Operating Instructions? And if so, what does it stipulate?

Answer: Refer to PWS Section C-4.0 Applicable Directives.

6. Please provide the average number of JAA receipts per month. Appendix AF states Average

JAA receipts per month is 15; however, during the site visit it was noted that receipts actually occur 5 days a week, so 20 to 21 times per month.

Answer: Refer to PWS Appendix AF, Section (3) Workload Information.

7. Please confirm if railcar is a receipt mode. Reference Introduction Section of the Appendix

AF (page 2), the base receives by rail car and tank truck. However, the Workload Information table indicates mode of delivery as tank truck and pipeline. Please clarify.

Refer to PWS Appendix AF, Section (3) Workload Information.

8. Reference Introduction Section of the Appendix AF (page 2), the base receives ground fuel once a month on average (MUR, E-85, BDI, DS2). However, the Workload Information table does not reflect any information for ground fuel receipts. Please confirm if the

Contractor is responsible for ground fuel products (receipt/fillstand) and provide workload data to include receipt mode and frequency of receipts by product.

Answer: This is not a contractor requirement. Ground fuels is not the contractor’s responsibility.

9. Please confirm if the Contractor performs return to bulk operations (i.e. R-11 or bowsers).

Answer: Refer to PWS Section C-5.2.2.1.

10. The workload information states that there have been 0 times that the Contractor has been called in outside normal duty hours. Please confirm the Contractor has also not had to have personnel stay after normal duty hours to complete receipts/transfers/issues.

Answer: Refer to PWS Section C-5.1 Staffing.

11. The workload information states that there have been 0 times that the Contractor has been called in outside normal duty hours. Would the Contractor be reimbursed if personnel have to stay after normal duty hours to complete receipts/transfers/issues?

Answer: Refer to PWS Section C-5.1 Staffing and PWS Appendix F.

12. The workload information references an emergency generator being in the Contractor's AOR.

Please confirm that a Government entity is responsible for conducting the periodic generator testing and maintenance.

13. The workload information references an emergency generator being in the Contractor's

AOR. Please confirm that the Government provides the fuel for this generator in the event that the Contractor is responsible for testing.

14. The base specific requirements provide a listing of Government-furnished facilities to be used by the Contractor. Are spill kits to be provided by the Government?

Answer: Refer to PWS Section C-5.8.2 Government Furnished Property (GFP) and Services.

15. There is no listing of furniture included for the Government furnished facilities. Does the Government provide furniture for the Contractor's use?

Answer: Refer to PWS Appendix AF, Section (5) Facilities.

16. The workload information does not include information on when the Contractor can receive product. What is the normal window that receipts occur, by conveyance, to the Installation?

17. The workload identifies 5 confined spaces. Does the Contract enter confined spaces to complete their job function?

18. The workload information states that quarterly, semi-annual, and annual maintenance on

GFP is provided by DLA Energy. Please confirm the Contractor is only responsible for operator level inspection.

Answer: Refer to PWS Section 5 Performance Requirements, Sub-Paragraph C-5.3.1 and C- 5.3.2.1.

19. The workload information states that quarterly, semi-annual and annual maintenance on GFP is provided by DLA Energy. Please confirm the Contractor is only responsible for coordination with CE for maintenance of GFP.

Answer: Refer to Appendix AF Table 2 and PWS Section C-5.3.