SOW - 637-20-103.pdf

PDF 404 KB Posted

Attached to
Y1AZ--Renovate Bldg. 15, 2nd Floor
Solicitation number
36C24625B0007
Issued by

About this file

This Statement of Work outlines interior renovation requirements for the 2nd floor of Building 15 at the VA Medical Center in Asheville, NC. The contractor must provide all materials, labor, tools, supervision, transportation and equipment for the renovation, which includes creating open areas for 66 new cubicles (to be installed by owner), two new conference rooms, four closed offices, an enlarged IDF room, and two renovated restrooms.

The work includes removal of existing flooring/doors/walls, new gypsum board installation, painting, new flooring throughout, door refinishing, HVAC modifications, electrical system upgrades (including new LED lighting and controls), plumbing updates, and installation of new communications systems with cabling and PA system with white noise. Work hours are 7:30 AM to 4:30 PM Monday-Friday, with off-hours required for noisy work. Contractors must comply with VA security procedures, complete COVID screening if required, receive annual influenza vaccinations, undergo TB screening, and adhere to the facility's nicotine-free campus policy. The VA Medical Center in Asheville manages this project under solicitation number 36C24625B0007.

View the file

Other files

File Type Posted
36C24625B0007 Amendment 0011.pdf PDF
Block 14 Cont. - VAAR 852.222-71.pdf PDF
36C24625B0007 Amendment 0010.pdf PDF
Attachment IV - Drawings Set rev w Changes Summary.pdf PDF
Attachment III - Additional Questions and Responses rev.pdf PDF
Block 14 Continuation I.pdf PDF
Block 14 Continuation II.pdf PDF
Attachment I - Questions and Responses rev.pdf PDF
36C24625B0007 0009.docx DOCX document
Attachment II - Follow-On Questions and Responses rev.pdf PDF
36C24625B0007 Amendment 0008 - Renovate Bldg 15 2nd Floor.pdf PDF
Asbestos Abatement Report 12.06.2024.pdf PDF
36C24625B0007 0007.docx DOCX document
36C24625B0007 0006.pdf PDF
36C24625B0007 0005.docx DOCX document
Follow-On Questions.docx DOCX document
01 91 00 GENERAL COMMISSIONING REQUIREMENTS - REV 1.pdf PDF
Specifications - REV 4.pdf PDF
Dwgs C-AJ-0070 - Floor Infill Details.pdf PDF
VAMC Build 15 3rd FL ASB-LBP Report.pdf PDF
Drawings - REV 3.pdf PDF
SBA DSBS Profile Instructions.pdf PDF
Drawing Changes Identified REV 3.pdf PDF
Additional Questions and Responses.pdf PDF
36C24625B0007 0004.docx DOCX document
Asbestos Bulk Sampling Report.pdf PDF
Map for Dumpster and Temp Power Hook Up.pdf PDF
Asbestos Inspection Report.pdf PDF
36C24625B0007 0003.docx DOCX document
RFI Questions and Responses - Renovate B15 2nd Floor 2.20.2025.pdf PDF
Site Visit Sign-in Sheets - B15.pdf PDF
36C24625B0007 0002.docx DOCX document
36C24625B0007 0001.docx DOCX document
Map of Hospital - Path to B15.pdf PDF
NC Wage Determination 1.03.2025.pdf PDF
Specifications - Final.pdf PDF
36C24625B0007_1.docx DOCX document
Bid Item Cost Breakdown.xlsx XLSX spreadsheet
Drawings - Final.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project # 637-20-103

RENOVATE BUILDING 15 2ND FLOOR

ASHEVILLE, NC

SCOPE

Contractor shall provide all materials, labor, tools, supervision, transportation and equipment necessary to perform work as described in the SOW, construction Drawings and Specifications to be provided with Solicitation. This project includes the interior renovation of the Building 15, 2nd Floor and modifications to the MEP systems. We have included the removal of the flooring and designated doors and walls to provide the open area for the new cubicle arrangement. There are two new conference rooms, four closed offices, and an enlarged IFD room and two completely renovated restrooms. New gypsum board is provided in rework areas and on columns. All new surfaces are painted and new flooring is provided throughout, existing doors that remain are refinished, and eleven new doors are provided.

There are sixty-six new fully fit-out cubicles that are provided and installed by the Owner. The existing HVAC equipment remains, cleaned and reinstalled flex duct, registers and grilles, and some minor changes to the ductwork for air flow is included. Two electrical panels are removed and new provide and the existing feeders remain, new LED light fixtures, new lighting controls, new wall receptacles in new rooms, power is provided to the cubicles, and new branch wiring. New water closets, urinals, and lavatories are included in the two restrooms and modifications to domestic water piping and sanitary sewer is included. A new Communications system is provided to include cabling and equipment in the new IDF room, and a new PA system with white noise is provided, and integration with the FA system in included. A cable tray is installed to cover the open areas and J-hooks are used as a minimum. Rough-ins to the cubicles are provided and wall rough-ins to access the cable tray. The Voice/Data outlets in the cubicles are provided by the contractor and the Cat 6 cabling. The Fire Alarm head end equipment is assumed to remain and is able to carry the new devices for the fit out. It is assumed that there is not a fire suppression existing and that one will not be provided in this scope of work.

SITE ACCESS

The Contractor shall obtain and monitor assigned security badges, passes, and/or identification (used by prime contractor, designer, and/or subcontractor staff) used during the duration of the Contract. All security badges or passes shall be returned to the COR upon expiration of the badge, upon completion of the project, or when possession of the badge is no longer necessary (e.g., upon removal of contracted personnel from specific projects). The Contractor shall ensure access is authorized to the appropriate construction site and routes/areas required to complete the Contract. All personnel shall comply with Medical Center security rules and procedures.

HOURS OF WORK

The normal hours of work on installations are from 7:30 a.m. to 4:30 p.m., Monday through Friday, excluding holidays. Off-hour work including evenings and weekends will be required for work which transmits noise and vibrations through the building structure. For work during other than these hours of work, the Contractor shall submit, in writing, for the Contracting Officer's approval, a notice of any period of scheduled work other than the normal hours of work specified above. This notice shall be submitted not less than two weeks prior to each period of work scheduled at times other than normal hours of work including holidays.

US Government holidays. When any of the US Government Holidays fall on a non-workday, the holiday will be observed on either the preceding or succeeding workday. The choice of any such preceding or succeeding workday shall be coordinated with the COR and the CO.

FEDERAL HOLIDAYS: The following Federal Legal Holidays are observed by Asheville VA Medical Center:

• New Year’s Day – 1 January

• Martin Luther King’s Birthday – Third Monday in January

• Presidents Day – Third Monday in February

• Memorial Day – Last Monday in May

• Juneteenth/Freedom Day – 19 June

• Independence Day – 4 July

• Labor Day – First Monday in September

• Columbus Day – Second Monday in October

• Veterans Day – 11 November

• Thanksgiving Day – Fourth Thursday in November

• Christmas Day – 25 December

• Any other Federal Holiday granted by the President of the United States

OTHER CONTRACT REQUIREMENTS

COVID SCREENING (IF REQUIRED)

Contractor shall submit to COVID screening daily in accordance with National VA policy when onsite or entering buildings when required by the VA. This will be coordinated with the COR before arrival at any

VA facility.

INFLUENZA VACCINE

All contractors shall receive annual seasonal Influenza vaccinations and the GC is responsible for maintaining the required paperwork on site and must provide when requested by VA personnel.

TUBERCULOSIS SCREENING

Contractor shall provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculosis screening within 90 days prior to assignment to the worksite and been found have negative TB screening reactions. Contractors shall be required to show documentation of negative TB screening reactions for any additional workers who are added after the 90-day requirement before they will be allowed to work on the work site.

NICOTINE FREE CAMPUS EFFECTIVE 1 OCT 2019

As part of the U.S. Department of Veterans Affairs’ (VA) commitment to provide excellent health care for Veterans, the department will implement a new policy restricting smoking by patients, visitors, volunteers, contractors and vendors at its health care facilities by October. VHA’s new smoke-free policy applies to cigarettes, cigars, pipes, any other combustion of tobacco and non-Federal Drug Administration approved electronic nicotine delivery systems (ENDS), including but not limited to electronic or e-cigarettes, vape pens or e-cigars.

COMPLIANCE

Compliance Awareness Training shall be completed by vendor prior to access at the Charles George VA

Medical Center (CGVAMC). Vendor has responsibility for “Duty to Report” any fraud, waste and abuse witnessed while on VA premises to the Compliance Officer.

RECORDS MANAGEMENT OBLIGATIONS

A. Applicability

This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined in Section B, regardless of the medium in which the record exists.

B. Definitions

“Federal record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.

The term Federal record:

1. includes CGVAMC Clinic records.

2. does not include personal materials.

3. applies to records created, received, or maintained by Contractors pursuant to their CGVAMC contract.

4. may include deliverables and documentation associated with deliverables.

C. Requirements

1. Contractor shall comply with all applicable records management laws and regulations, as well as

National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C. chs. 21, 29, 31, 33), NARA regulations at 36 CFR

Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of

44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for

Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law.

Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4. The CGVAMC and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of the CGVAMC or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting

Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to CGVAMC. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the contract. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to

CGVAMC control or the Contractor must hold it until otherwise directed. Items returned to the

Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the

Contracting Officer or address prescribed in the contract. Destruction of records is EXPRESSLY

PROHIBITED unless in accordance with Paragraph (4).

6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The

Contractor (and any sub-contractor) is required to abide by Government and CGVAMC guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with CGVAMC policy.

8. The Contractor shall not create or maintain any records containing any non-public Charles

George VAMC information that are not specifically tied to or authorized by the contract.

9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10. The CGVAMC owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S. Government for which the Charles

George VAMC shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take CGVAMC-provided records management training. The

Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

[Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor.]

D. Flow down of requirements to subcontractors

1. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this contract, and require written subcontractor acknowledgment of same.

2. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.

File details come from the government source that posted it. Updated .