Bid Item Cost Breakdown.xlsx

XLSX spreadsheet 29 KB Posted

Attached to
Y1AZ--Renovate Bldg. 15, 2nd Floor
Solicitation number
36C24625B0007
Issued by

About this file

This is a bid cost breakdown spreadsheet template provided by the VA for contractors to itemize costs for the renovation of Building 15, 2nd Floor in Asheville, NC (Project #637-20-103). The template contains two identical sections - one for the base bid and one for bid alternate I.

The spreadsheet is organized into 24 construction divisions including general requirements, existing conditions, concrete, masonry, metals, wood/plastic, thermal/moisture protection, doors/windows, finishes, specialties, equipment, furnishings, special construction, conveying equipment, fire suppression, plumbing, HVAC, electrical, communications, security, earthwork, exterior improvements, utilities, and transportation. For each division, contractors must enter labor costs and material costs, which are automatically summed. The template also includes fields for overhead percentage, profit percentage, and bond percentage, which are calculated based on the division subtotals. All fields are currently blank with $0 values.

View the file

Other files

File Type Posted
36C24625B0007 Amendment 0011.pdf PDF
Block 14 Cont. - VAAR 852.222-71.pdf PDF
36C24625B0007 Amendment 0010.pdf PDF
Attachment IV - Drawings Set rev w Changes Summary.pdf PDF
Attachment III - Additional Questions and Responses rev.pdf PDF
Block 14 Continuation I.pdf PDF
Block 14 Continuation II.pdf PDF
Attachment I - Questions and Responses rev.pdf PDF
36C24625B0007 0009.docx DOCX document
Attachment II - Follow-On Questions and Responses rev.pdf PDF
36C24625B0007 Amendment 0008 - Renovate Bldg 15 2nd Floor.pdf PDF
Asbestos Abatement Report 12.06.2024.pdf PDF
36C24625B0007 0007.docx DOCX document
36C24625B0007 0006.pdf PDF
36C24625B0007 0005.docx DOCX document
Follow-On Questions.docx DOCX document
01 91 00 GENERAL COMMISSIONING REQUIREMENTS - REV 1.pdf PDF
Specifications - REV 4.pdf PDF
Dwgs C-AJ-0070 - Floor Infill Details.pdf PDF
VAMC Build 15 3rd FL ASB-LBP Report.pdf PDF
Drawings - REV 3.pdf PDF
SBA DSBS Profile Instructions.pdf PDF
Drawing Changes Identified REV 3.pdf PDF
Additional Questions and Responses.pdf PDF
36C24625B0007 0004.docx DOCX document
Asbestos Bulk Sampling Report.pdf PDF
Map for Dumpster and Temp Power Hook Up.pdf PDF
Asbestos Inspection Report.pdf PDF
36C24625B0007 0003.docx DOCX document
RFI Questions and Responses - Renovate B15 2nd Floor 2.20.2025.pdf PDF
Site Visit Sign-in Sheets - B15.pdf PDF
36C24625B0007 0002.docx DOCX document
36C24625B0007 0001.docx DOCX document
Map of Hospital - Path to B15.pdf PDF
NC Wage Determination 1.03.2025.pdf PDF
Specifications - Final.pdf PDF
36C24625B0007_1.docx DOCX document
SOW - 637-20-103.pdf PDF
Drawings - Final.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Bid

Base Bid Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

Bid Alt I

Bid Alternate I Cost Breakdown

Project Number:

Edward L Roy: VA assigned project #

Date:
Project Title
Edward L Roy: VA assigned Project TitleProject Location
Offeror Name
Offeror Street
Offeror CityStateZip

Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division

Material Cost
Edward L Roy: Enter all Material Costs by DivisionTotal Cost

Edward L Roy: This Column is the sum of the Division's Labor and Material Costs

Division 1General Requirements$ - 0$ - 0$ - 0
Division 2Existing Conditions- 0- 0- 0
Division 3Concrete- 0- 0- 0
Division 4Masonry- 0- 0- 0
Division 5Metals- 0- 0- 0
Division 6Wood and Plastic- 0- 0- 0
Division 7Thermal & Moisture Protect- 0- 0- 0
Division 8Doors and Windows- 0- 0- 0
Division 9Finishes- 0- 0- 0
Division 10Specialties- 0- 0- 0
Division 11Equipment- 0- 0- 0
Division 12Furnishings- 0- 0- 0
Division 13Special Construction- 0- 0- 0
Division 14Conveying Equipment- 0- 0- 0
Division 21Fire Suppression- 0- 0- 0
Division 22Plumbing- 0- 0- 0
Division 23HVAC- 0- 0- 0
Division 26Electrical- 0- 0- 0
Division 27Communications- 0- 0- 0
Division 28Electronic Safety & Security- 0- 0- 0
Division 31Earthwork- 0- 0- 0
Division 32Exterior Improvements- 0- 0- 0
Division 33Utilities- 0- 0- 0
Division 34Transportation Subtotal- 0- 0- 0
Division Subtotals :$ - 0$ - 0$ - 0

Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).

Edward L Roy: Date Offer Prepared/Submitted

- 0
Profit %0.00%
Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38).- 0
Bond %0.00%

Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).

Edward L Roy: Enter all Labor Costs by Division

- 0
Overhead/Profit Subtotals :$ - 0

Edward L Roy: Sum of Overhead, Profit and Bond %.

Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0

File details come from the government source that posted it. Updated .