About this file
This is a bid cost breakdown spreadsheet template provided by the VA for contractors to itemize costs for the renovation of Building 15, 2nd Floor in Asheville, NC (Project #637-20-103). The template contains two identical sections - one for the base bid and one for bid alternate I.
The spreadsheet is organized into 24 construction divisions including general requirements, existing conditions, concrete, masonry, metals, wood/plastic, thermal/moisture protection, doors/windows, finishes, specialties, equipment, furnishings, special construction, conveying equipment, fire suppression, plumbing, HVAC, electrical, communications, security, earthwork, exterior improvements, utilities, and transportation. For each division, contractors must enter labor costs and material costs, which are automatically summed. The template also includes fields for overhead percentage, profit percentage, and bond percentage, which are calculated based on the division subtotals. All fields are currently blank with $0 values.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Bid
Base Bid Cost Breakdown
Project Number:
Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
| Edward L Roy: VA assigned Project Title | Project Location | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | - 0 | - 0 | - 0 |
| Division 3 | Concrete | - 0 | - 0 | - 0 |
| Division 4 | Masonry | - 0 | - 0 | - 0 |
| Division 5 | Metals | - 0 | - 0 | - 0 |
| Division 6 | Wood and Plastic | - 0 | - 0 | - 0 |
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | - 0 |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0
Bid Alt I
Bid Alternate I Cost Breakdown
Project Number:
Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
| Edward L Roy: VA assigned Project Title | Project Location | ||
| Offeror Name | |||
| Offeror Street | |||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | - 0 | - 0 | - 0 |
| Division 3 | Concrete | - 0 | - 0 | - 0 |
| Division 4 | Masonry | - 0 | - 0 | - 0 |
| Division 5 | Metals | - 0 | - 0 | - 0 |
| Division 6 | Wood and Plastic | - 0 | - 0 | - 0 |
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | - 0 |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.
Edward L Roy: Enter all Material Costs by Division Edward L Roy: This Column is the sum of the Division's Labor and Material Costs Total Base Offer Cost $ - 0 $ - 0 $ - 0
File details come from the government source that posted it. Updated .