SK1 R3 11-18-2024.pdf

PDF 314 KB Posted

Attached to
Oak Creek Youth Correctional Facility (OCYCF) New Parole and Probation
Solicitation number
S-DASOBO-00009472
Issued by
Lake County, Albany City, Oregon

About this file

This document is a detailed design sketch (SK#1 R3 - 11/18/2024) provided by the utility company Commonwealth Power Inc. (CPI) for a state and local contract opportunity related to upgrading the electrical infrastructure at the Oak Creek Youth Correctional Facility (OCYCF) in Albany, Oregon. The scope of work includes excavating and intercepting the existing buried primary conduit/conductors, installing a 3-phase junction cabinet, and refeedingundeground primary 3-phase conductors back to the CPI switch. The customer contractor is required to provide and install various conduits, pull strings, and a concrete transformer vault per the provided specifications and details. CPI will provide and install the new transformer.

The document also includes general notes outlining requirements for locates, conduit routing, clearances, access, and coordination with CPI during the construction process. This work is part of a larger state and local contract opportunity for the construction of a new parole and probation building at the OCYCF facility in Albany, Oregon, which is being procured by the state of Oregon and involves the jurisdictions of Lake County and the City of Albany.

View the file

Other files

File Type Posted
Specs_Project Manual_Appendix.pdf PDF
G0.01 R1 07-16-2024 and R3 11-18-2024.pdf PDF
Addendum4_S-DASOBO-00009472_OCYCF_ParoleProbation.pdf PDF
A1.61 R2 11-13-2024.pdf PDF
Addendum 2 S-DASOBO-00009472_OCYCF_ParoleProbation.pdf PDF
EP-0097-23 OYA New Building Improvements EPSC Plan-1.pdf PDF
S-DASOBO-00009472_Q&A_07192024.pdf PDF
S1.10 R2_S5.10 R2.pdf PDF
Addendum 3 S-DASOBO-00009472_OCYCF_ParoleProbation.pdf PDF
S0.10 R3 07-31-2024.pdf PDF
C3.00 R2 11-13-2024.pdf PDF
S-DASOBO-00009472_OCYCF Parole_ PreBidAttendance.pdf PDF
IntentToAward_Notice_AllBidders_12052024.pdf PDF
OCYCF Substitution Request 265100_Approved.pdf PDF
Addendum 5 S-DASOBO-00009472_OCYCF_ParoleProbation_08222024.pdf PDF
OCYCF Substitution Request 074113_Approved.pdf PDF
Addendum 008 S-DASOBO-00009472_OCYCF_ParoleProbation.pdf PDF
Addendum1_Attachment1_Geotech Report YWTP.pdf PDF
First Tier Filled Out FCC.pdf PDF
FINAL_OYA Construction Set_2024-0412.pdf PDF
A6.01 R2 11-13-2024.pdf PDF
S2.10 R1_S2.11 R1_S8.11 R1_S8.12 R1.pdf PDF
A6.01 R1 07-16-2024.pdf PDF
Addendum 1 S-DASOBO-00009472_OCYCF_ParoleProbation_Corrected.pdf PDF
Addendum 7 S-DASOBO-00009472_OCYCF_ParoleProbation_10162024.pdf PDF
FINAL_OCYCF_Specifications_2024-0614.pdf PDF
REVISED SPECIFICATIONS 11-13-2024_corrected.pdf PDF
A5.27 R1 07-16-2024.pdf PDF
Structural Calculations_Stamped.pdf PDF
Bid_Tab_S-DASOBO-00009472_OCYCF Parole and Probation.pdf PDF
SK2 R3 11-18-2024.pdf PDF
Structural Calculations _Add_MechanicalScreenWall.pdf PDF
S-DASOBO-00009472_OCYCF_Parole_Probation_06242024.pdf PDF
S-DASOBO-00009472_Q&A_11212024_Final.pdf PDF
S-DASOBO-00009472_Q&A_11182024_Final.pdf PDF
G0.03 R1 07-16-2024.pdf PDF
G1.01 R1 07-16-2024.pdf PDF
Addendum 009 S-DASOBO-00009472_OCYCF_ParoleProbation_FinalApproved_11182024.pdf PDF
9473 ITB.pdf PDF
Addendum 6 S-DASOBO-00009472_OCYCF_ParoleProbation.pdf PDF
OCYCF Substitution Request 075400_Approved.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TO EXISTING VAULT MOUNTED

150 KVA 3-PH TRANSFORMER

EXISTING CPI

SWITCH #LTL/4

CPI TO EXCAVATE AND INTERCEPT EXISTING

BURIED PRIMARY CONDUIT/CONDUCTORS AND

INSTALL 3-PHASE JUNCTION CABINET. CPI TO

REFEED UG PRIMARY 3-PHASE CONDUCTORS

BACK TO CPI SWITCH. CUSTOMER

CONTRACTOR TO PROVIDE 1-YARD ¾ MINUS

ROCK FOR CPI TO INSTALL IN BASE OF PIT.

CUSTOMER CONTRACTOR TO PROVIDE AND INSTALL (3) 3” SCHEDULE 40

PVC CONDUITS IN A 48” BELOW GRADE TRENCH. PROVIDE AND INSTALL

200-LB PULLSTRING INSTALLED THROUGH EACH CONDUIT. STUB

CONDUITS 2’ FROM LOCATE MARKS OF EXISTING BURIED POWER

CONDUITS. LEAVE (3) 3” SCHEDULE 40 PVC SWEEP CONDUITS WITH

MINIMUM 36” RADIUS NEED TO JUNCTION CABINET FOR CPI TO INSTALL.

CUSTOMER CONTRACTOR TO EXCAVATE A 6’W X 8’L X 4’-6”D PIT FOR NEW

CONCRETE TRANSFORMER VAULT. SEE ATTACHED VAULT/LID DETAIL FOR

FURTHER INSTALLATION INSTRUCTIONS. STUB THE (3) 3” CONDUITS AND

THE (2) 4” CONDUITS INTO THE CONCRETE VAULT. CONTRACTOR TO

PROVIDE AND INSTALL GROUT AROUND CONDUIT ENTRY POINTS TO RE-

SEAL THE VAULT. CPI TO PROVIDE AND INSTALL THE TRANSFORMER.

CUSTOMER CONTRACTOR TO PROVIDE AND

INSTALL (2) 4” SCHEDULE 40 PVC CONDUITS

IN A 36” BELOW GRADE TRENCH. PROVIDE

AND INSTALL 200-LB PULLSTRING INSTALLED

THROUGH EACH CONDUIT.

EXISTING BURIED 3-PHASE PRIMARY LINE

EXTENSION TO REMAIN. SEE NOTES

INCLUDED WITH THIS DESIGN SKETCH

CUSTOMER CONTRACTOR TO SWEEP THE

4” CONDUITS, WITH PULL STRING, UP INTO

BOTTOM OF CT ENCLOSURE. ALL SWEEPS

TO HAVE A MINIMUM 36” RADIUS.

CUSTOMER CONTRACTOR TO PROVIDE AND INSTALL CT ENCLOSURE, CT MOUNTING

BASES, (1) 1.5” SCHEDULE 40 PVC CONDUIT AND 20A RATED METER-BASE. SEE

ATTACHED CT/METER SPECIFICATION SAMPLE OF APPROVED EQUIPMENT.

SK#1

R3 - 11/18/2024

GENERAL NOTES:

HAVE LOCATES PERFORMED ON ENTIRE EXISTING UNDERGROUND PRIMARY POWER LINE EXTENSION PRIOR TO ANY EXCAVATION. MARK LOCATION OF EXISTING CONDUIT ROUTE TO ENSURE THAT EXISTING CONDUIT ROUTE WILL NOT BE

LOCATED UNDER THE FOUNDATION OF THE NEW BUILDING.

IF IT IS FOUND THAT THE EXISTING UNDERGROUND 3-PHASE CONDUIT SYSTEM THAT EXTENDS FROM OUR SWITCH TO 150KVA 3-PHASE TRANSFORMER IS LOCATED UNDER THE PROPOSED BUILDING, CPI WILL DEVELOP A NEW UNDERGROUND DESIGN TO REFEED THE EXISTING 150KVA TRANSFORMER. THE COST FOR THIS ADDITIONAL DESIGN, MATERIAL AND LABOR WILL BE INVOICED TO THE CUSTOMER SEPARATELY FROM THE ORIGINAL SUBMITTED INVOICE.

ALL SWEEPS TO HAVE A MINIMUM 36” RADIUS.

CUSTOMER TO INSTALL 200LB POLY-LINE (PULLSTRING) IN ALL POWER CONDUITS.

NO MORE THAN 270 DEGREES OF BENDS ARE ALLOWED IN A SINGLE CONDUIT RUN. NO HEATED BENDS ALLOWED. IF FOUND THAT CUSTOMER HAS HEATED THE CONDUIT TO CREATE A BEND, CUSTOMER WILL BE RESPONSIBLE TO RUNNING A MADREL THROUGH THE CONDUIT TO ENSURE IT WILL ACCEPT THE WIRING BEING INSTALLED IN THE CONDUIT.

WHEN THE TRANSFORMER VAULT PIT IS EXCAVATED

MAINTAIN 12” SEPARATION BETWEEN CPI POWER CONDUIT SYSTEM AND ANY OTHER UTILITY CONDUITS OR PRIVATELY OWNED CONDUITS/PIPING.

WHEN THE TRENCH IS OPEN, THE CONDUITS, SWEEPS AND PULLSTRING IS INSTALLED PLEASE CALL ME OR TEXT ME AS I WILL NEED TO INSPECT THE UNDERGROUND EQUIPMENT INSTALLATION PRIOR TO YOUR BACKFILLING THE TRENCH.

CPI SECONDARY SERVICE WIRE WILL BE TWO RUNS OF 4/0 QUAD ALUMINUM QUAD CABLE. CUSTOMER TO ENSURE UTILITY SECTION OF CT ENCLOSURE WILL BE ABLE TO ACCEPT AND HAVE AVAILABLE LUG SPACE FOR LANDING THESE CABLES.

THE TRANSFORMER VAULT MUST BE LOCATED WITHIN 20’ OF A DRIVABLE SURFACE.

SEE TRANSFORMER CLEARANCE REQUIREMENTS PROVIDED IN THE ATTACHED DETAIL.

CPI WILL ALLOW THE NEW PAVED PARKING LOT TO BE LOCATED OVER OUR EXISTING BURIED PRIMARY LINES. THE CUSTOMER WILL NEED TO BE MADE AWARE THAT SHOULD WE REQUIRE ACCESS TO THIS EQUIPMENT , CUTTING THE

PAVEMENT TO GAIN ACCESS MAY BE REQUIRED. CPI WILL AVOID THIS IF AT ALL POSSIBLE.

PLEASE ENSURE THAT THE CRITICAL ROOT ZONE OF ANY TREE IS NOT LOCATED OVER OUR EXISTING BURIED PRIMARY LINES. NO TRESS SHOULD BE PLANTED DIRECTLY OVER OUR EXISTING LINES.

LIGHT POLES, CUSTOMER EQUIPMENT OR GROUNDING EQUIPMENT SHOULD BE INSTALLED DIRECTLY OVER CPI’S EXISTING BURIED PRIMARY LINES.

CPI WILL REQUIRE 24-HOUR ACCESS TO ALL EQUIPMENT, 365 DAYS A YEAR.

File details come from the government source that posted it. Updated .