SDN1501E ES1 Building Facility Description.pdf
PDF 688 KB Posted
- Solicitation number
- BD-16-1019-DCP08-ENR01-00000008759
- Issued by
- Norfolk County, Massachusetts
About this file
The provided document is a Building Facility Description Report for the Norfolk County Correctional Center in Dedham, Massachusetts. The facility consists of a 140,000 square foot main building and a 12,000 square foot Dedham Alternative Center (DAC), along with a 2,500 square foot vehicle maintenance building. The report details the HVAC systems, domestic hot water, and lighting and lighting control systems serving the complex. Key HVAC components include air handling units, terminal units, return/exhaust fans, chilled water systems, condenser water systems, and hot water/glycol systems. The domestic hot water is provided by multiple systems serving the main building and DAC. The lighting primarily consists of metal halide and fluorescent fixtures, with manual controls.
The related state and local contract opportunity is an Energy Design Build RFP for the Norfolk Sheriff's Office in Dedham, Massachusetts, posted on COMMBUYS on June 8, 2016. The RFP is pursuant to Chapter 25A 11c, seeking a contractor to finalize design, install, and commission various energy conservation measures (ECMs), including LED lighting upgrades, water controls, HVAC control upgrades, VFD upgrades, ozone laundry system, kitchen hood controls, solar photovoltaics, combined heat and power, and other building improvements.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NORFOLK COUNTY CORRECTIONAL CENTER
DRAFT Building Facility Description Report
B1502090.000
June 19, 2015
Prepared For:
DCAMM
One Ashburton Place, 15 th
Floor
Boston, MA 02108
May 15, 2015
DRAFT Building Facility Description Report
Table of Contents
1. Baseline Facility Description
1.1 General Information
1.2 HVAC Systems
1.2.1 Air Handling Systems
1.2.2 Terminal Units
1.2.3 Return and Exhaust Fans
1.2.4 Chilled Water System
1.2.5 Condenser Water System
1.2.6 Hot Water and Glycol System:
1.3 Domestic Hot Water
1.4 Lighting and Lighting Controls System
1.4.1 Main Building
1.4.2 DAC ........................................ Error! Bookmark not defined.
B1502090.000 1 | 7
1. Baseline Facility Description
1.1 General Information
The Norfolk Country Correctional Center (NCCC) is located in Dedham, MA and opened in 1993. The campus consists of two (2) buildings – a 140,000 square foot main building with 502 beds and a 12,000 square foot Dedham Alternative Center (DAC). Additionally, there is a 2,500 square foot vehicle maintenance building adjacent to the DAC. NCCC is owned by the Commonwealth of Massachusetts and operated by the Norfolk County Sheriff’s Office. The main building consists of four (4) pods connected to the central unit. There is a control center and two levels of cells at each pod. The central unit is single story and consists of a kitchen, laundry room, administrative spaces, mechanical/back of house areas, and a gym. The gym is now being used to house additional inmates. The main building is currently over occupied and there are plans to add an additional building, potentially housing 50 inmates. There are approximately 600 inmates and 100 staff members on campus.
Figure 1.1 - Campus Layout
1.2 HVAC Systems
The main building consists of four integrated “pods” connected to the central unit. One (1) air-conditioning unit (ACU) serves each of the four pods (ACU-1 through ACU-4). There are four (4) additional ACUs (ACU-5 through ACU-8) serving administrative and office spaces in the central unit. The kitchen, laundry room, and gym are served by four (4) different Heating and Ventilation (HV) units (HV-1 through HV-4). Separate computer room air-conditioning (CRAC) systems serve the computer/IT rooms, which require cooling year round.
The DAC is served by one (1) ACU (ACU-9). The vehicle maintenance building is served by various unit heaters.
1.2.1 Air Handling Systems
ACU-1 through ACU-4 – Main Building
DAC building
Vehicle Maintenance Building
Main Building
B1502090.000 2 | 7
Heating, cooling, and ventilation at the main building pods are provided by four (4) 6,700 to 12,000 CFM constant volume (CV) ACUs. Each unit consists of an outside air intake and filter, one (1) return air fan and relief air section, hot water heating coil, chilled water cooling coil, and one (1) supply fan. The hot water heating coil provides heat for hot deck operation during the winter. The chilled water cooling coil provides cooling for cold deck operation during the summer months.
ACU-5 through ACU-8
Heating, cooling, and ventilation at the main building central unit are provided by four (4) 9,500 to 11,600 CFM variable air volume (VAV) ACUs. Each unit consists of an outside air intake and filter, one (1) return air fan and relief air section, hot water heating coil, chilled water cooling coil, and one (1) supply fan. The supply fan and return fan are equipped with variable frequency drives (VFDs) that modulate the fan speed to maintain duct static pressure.
HV-1 through HV-4 – Main Building
Heating and ventilation in the main building kitchen and laundry spaces are provided by HV-1, HV-2, and HV-3.
These three (3) units are constant volume and consist of an outside air intake and filter, hot water heating coil, and supply fan.
Heating, cooling, and ventilation in the main building gym are provided by HV-4. The gym is currently being used to house approximately 70 inmates. HV-4 is consists of an outside air intake and filter, hot water heating coil, chilled water cooling coil, and a supply fan. Note that the cooling coil was added after the original construction.
AHU-1, AHU-2 and Fan Coil Units – DAC
Ventilation at the DAC is provided by two (2) constant volume air handling units (AHUs). The units consists of an outside air intake and filter, hot water heating coil, chilled water cooling coil, and supply fan. The ventilation air is delivered downstream to the corridors and fan coil units (FCUs) serving various cells and administrative spaces.
Each fan coil unit is equipped with a hot water heating coil and chilled water cooling coil.
All air handling systems are listed in Table 1.1 below:
Table 1.1 – Air Handling Units
Mark No
AREA SERVED LOCATION
FAN DATA
MOTOR
DATA
Cooling Coil Data Heating Coil Data
WATER Water
TOTAL
CFM
MIN
OA
HP GPM PD EWT °F GPM PD EWT °F
ACU-
JAIL JAIL - MER 9,500 3,950 10 69 10 45 48 7 180
ACU-
SEG UNIT SEG - MER 6,700 2,750 8 49 10 45 34 7 180
ACU-
HOC I HOC I - MER 16,200 7,000 20 118 15 45 84 5 180
ACU-
HOC II HOC II - MER 12,000 4,350 15 82 10 45 54 5 180
ACU-
MED / BOOK-
ING
ROOF 9,500 1,200 15 72 10 45 23 5 180
ACU-
STAFF ROOF 11,600 5,100 15 94 10 45 39 7 180
ACU-
VISITING /
DINING
ROOF 11,100 2,100 15 75 10 45 26 5 180
ACU-
EDUCATIONAL ROOF 10,000 1,700 15 68 10 45 24 5 180
HV-1
KITCHEN /
MAKE-UP
ROOF 11,200 1,200 10 NA NA NA 95 5 180
HV-2
KITCHEN /
MAKE-UP
ROOF 3,250 3,250 3 NA NA NA 26 5 180
HV-3
KITCHEN /
LAUNDRY
ROOF 2,100 500 3 NA NA NA 18 5 180
HV-4 GYM ROOF 16,000 4,000 15 Unknown Unknown Unknown 57 5 180
AHU- PRERELEASE PRERELEASE TBD TBD 1.5 TBD
B1502090.000 3 | 7
1 MER
AHU-
PRERELEASE
PRERELEASE
MER
TBD TBD 1.5 TBD
1.2.2 Terminal Units
Air distribution downstream at the main building central unit is provided by forty (40) single ducts, cooling only, VAV terminal units. Additionally, there are seventeen (17) fan powered terminal units (FPTs) with hot water reheat coils.
The FPTs primarily serve the corridors in the central unit.
1.2.3 Return and Exhaust Fans
The campus is equipped with exhaust fans located on the roof of the main building, DAC, and vehicle maintenance building. The fans serve the kitchen, toilets, electrical rooms, laundry room, and various other spaces. These fans are either energized thermostatically, energized 24/7, or energized via a manual switch. Additionally, there are return fans serving the ACUs and HV-4.
The fans are listed in Table 1.2 below:
Table 1.2 – Fan Schedule
MARK NO AREA SERVED LOCATION AIR VOLUME (CFM) MAX BHP
MOTOR DATA
HP VOLT PH
RF-1 JAIL JAIL - MER 5,600 1.3 2.00 480 3
RF-2 SEG UNIT SEG - MER 4,000 1 1.50 480 3
RF-3 HOC I HOC I - MER 9,200 2 3.00 480 3
RF-4 HOC II HOC II - MER 7,700 2 3.00 480 3
RF-5 ACU-5 ROOF 740 3.5 5.00 480 3
RF-6 ACU-6 ROOF 6,500 2.5 7.50 480 3
RF-7 ACU-7 ROOF 9,000 4.5 7.50 480 3
RF-8 ACU-8 ROOF 8,300 4 5.00 480 3
RF-10 HV-4 ROOF 12,000 6.9 10.00 480 3
TX-1 JAIL WEST ROOF 1,750 - 0.75 480 3
TX-2 JAIL SOUTH ROOF 1,350 - 0.75 480 3
TX-3 SEG SOUTH ROOF 650 - 0.33 120 1
TX-4 SEG EAST ROOF 1,350 - 0.75 480 3
TX-5 HOC I WEST ROOF 2,900 - 480 3
TX-6 HOC I NORTH ROOF 3,000 - 480 3
TX-7 HOC II NORTH ROOF 1,700 - 0.75 480 3
TX-8 HOC II EAST ROOF 1,750 - 0.75 480 3
TX-9 MEDICAL ROOF 1,350 - 0.50 480 3
TX-10 QUARANTINE ROOF 400 - 0.25 120 1
TX-11 STAFF ROOF 3,400 - 1.00 480 3
TX-12 BOOKING ROOF 450 - 0.50 480 3
TX-13 KITCHEN / DINING ROOF 1,200 - 0.50 480 3
TX-14 VISITING ROOF 850 - 0.50 480 3
TX-15 MECH WING ROOF 150 - 0.25 120 1
TX-16 PRERELEASE ROOF 700 0.2 0.33 120 1
TX-17 PRERELEASE ROOF 700 0.2 0.33 120 1
TX-18 VEH MAINT ROOF 150 - 0.25 120 1
SX-1 JAIL WEST ROOF 7,500 - 2.00 480 3
SX-2 JAIL SOUTH ROOF 6,500 - 1.50 480 3
SX-3 SEG SOUTH ROOF 3,000 - 0.75 480 3
SX-4 SEG EAST ROOF 4,500 - 1.50 480 3
SX-5 HOC I WEST ROOF 12,000 - 5.00 480 3
SX-6 HOC I NORTH ROOF 12,000 - 5.00 480 3
SX-7 HOC II NORTH ROOF 9,500 - 3.00 480 3
SX-8 HOC II EAST ROOF 9,500 - 3.00 480 3
EX-1 VEH SALLYPORT ROOF 2,000 - 0.50 3
EX-2 CAN WASH ROOF 300 - 0.05 120 1
EX-3 LAUNDRY ROOF 300 - 0.07 120 1
EX-4 GYM ROOF 4,000 - 1.00 480 3
EX-5 BOILER ROOM ROOF 6,000 - 1.00 480 3
B1502090.000 4 | 7
EX-6 BOILER ROOM ROOF 6,000 - 1.00 480 3
EX-7 ELEC ROOM ROOF 500 - 0.13 120 3
EX-8 ELEC ROOM ROOF 500 - 0.13 120 3
EX-9 COMM ROOM ROOF 500 - 120 1
EX-10 VEH MAINT ROOF 2,780 0.48 0.50 480 3
EX-11 VEH MAINT GARAGE 1,600 - 1.50 480 3
EX-12 VEH MAINT ROOF 720 0.13 0.13 120 1
EX-13 CARPENTRY ROOF 400 - 0.05 120 1
EX-14 MECHANICAL SHOP ROOF 200 - 0.07 120 1
KX-1 KITCHEN HOOD ROOF 11,900 - 7.50 480 3
KX-2 SERVERY HOOD ROOF 3,450 - 2.00 480 3
KX-3 DISHWASHER ROOF 600 - 0.33 120 1
KX-4 GEN KITCHEN ROOF 800 - 0.25 120 1
KX-5 PRERELEASE CEILING 150 - 0.33 120 1
LX-1 LAUNDRY ROOF 1,800 - 0.50 480 3
EX-15 STORAGE ROOM 154 ROOF 100 0 0.02 120 1
EX-16 STORAGE ROOM 153 ROOF 100 0 0.02 120 1
EX-17 COMPRESSOR ROOM ROOF 100 0 0.02 120 1
EX-18 STORAGE ROOM 121 ROOF 100 0 0.02 120 1
EX-19 STORAGE ROOM 123 ROOF 100 0 0.02 120 1
EX-20 STORAGE ROOM ROOF 100 0 0.02 120 1
1.2.4 Chilled Water System
The main building contains two (2) 150-ton, water-cooled, hermetic centrifugal chillers (CH-1, CH-2) located in the Boiler Room. The chillers provide chilled water to the ACUs and HV-4 to maintain the discharge air temperature setpoint.
The DAC contains one (1) 35-ton, air-cooled, reciprocating chiller (CH-3) located outside. The chiller provides chilled water to AHU-1, AHU-2, and the fan coil units to maintain discharge air temperature setpoint.
All chillers are listed in Table 1.3 below.
Table 1.3 - Chiller Schedule
MARK NO SERVICE LOCATION
CAPACITY
TONS
COMPRESSOR DATA EVAPORATOR DATA CONDENSER DATA
KW
INPUT
MAX KW PER TON EWT LWT GPM EWT LWT GPM
CH 1&2 MAIN BLG
BOILER
ROOM
150 98 0.65 58 45 280 85 95 450
CH3
PRERE-
LEASE
OUTSIDE 35 40.2 1.15 58 45 70 - - -
Main building chilled water is supplied to the ACUs and HV-4 via three (3) 10 HP pumps (P-5A, P-5B, P-5C). Pump operation is lead/lag/standby with a manual rotation cycle to equalize run time.
DAC chilled water is supplied to AHU-1, AHU-2, and the fan coil units via two (2) 3 HP pumps. Pump operation is lead/lag with a manual rotation cycle to equalize run time.
All chilled water pumps are listed in Table 1.4 below.
Table 1.4 - Chilled Water Pump Schedule
MARK NO SERVICE LOCATION PUMP TYPE
PERFORMANCE DATA MOTOR DATA
GPM TDH (FT) RPM HP VOLT PHASE
P5-(A,B,C) CHILLED WATER BOILER ROOM END SUCTION 280 80 1750 10 480 3
P8-(A&B) CHILLED WATER PRERELEASE IN-LINE 70 60 1750 3 480 3
B1502090.000 5 | 7
1.2.5 Condenser Water System
Heat generated by the water-cooled chillers (CH-1, CH-2) is rejected to the atmosphere by a two (2) cell, 274-ton (total) cooling tower (CT-1, CT-2) serving the condenser water system. Each cooling tower fan is constant volume.
The cooling towers are listed in Table 1.5 below:
Table 1.5 – Cooling Tower Schedule
MARK NO SERVICE LOCATION TYPE
CONDENSER WATER DATA FAN MOTOR DATA
GPM EWT LWT AIR TEMP NO OF MOTOR HP CFM
CT 1&2 CH 1&2 ROOF FORCED DRAFT 450 95 85 76 1 20 26400
Condenser water is circulated through the chillers and cooling towers via three (3) 15 HP pumps (P-6A, P-6B, P- 6C). Pump operation is lead/lag/standby with a manual rotation cycle to equalize run time. The pumps are constant volume and are energized in conjunction with cooling tower and chiller operation.
The condenser water pumps are listed in Table 1.6 below:
Table 1.6 – Condenser Water Pump Schedule
MARK NO SERVICE LOCATION PUMP TYPE
PERFORMANCE DATA MOTOR DATA
GPM TDH (FT) RPM HP VOLT PHASE
P6-(A,B,C) CONDENSER WATER BOILER ROOM END SUCTION 450 65 1750 15 480 3
1.2.6 Hot Water and Glycol System:
The main building contains two (2) natural gas fired boilers (B-1, B-2) rated at 3,000 MBH each, located in the boiler room. The boilers provide hot water to:
1. Hot Water / Glycol Heat Exchanger (glycol loop serves the ACUs and HVs)
2. Fintube Radiation Loop (serves fintube radiators, unit heaters, and fan-powered boxes)
The DAC contains one (1) natural gas fired boiler (B-3) rated at 850 MBH. The boiler provides hot water to AHU-1, AHU-2, fan coil units, and unit heaters in the vehicle maintenance building.
All boilers are listed in Table 1.7 below:
Table 1.7 – Boiler Schedule
MARK NO LOCATION
CAP SBI
GROSS
MBH
HEATING
SURFACE
SQ FT MIN
FURNACE
VOLUME CU
FT MIN
FIRING RATES
BURNER
HP
MIN GAS
PRESS IN
WC
GPH CFH
B1&2
BOILER
ROOM
3000 500 25
- 4200 3 11
B3 PRELEASE 850 105 16 - 1490 0.5 5
Hot water is circulated through the main building boilers via three (3) 5 HP pumps (P-1A, P-1B, P-1C). Pump operation is lead/lag/standby with a manual rotation cycle to equalize run time. The pumps are constant volume and are energized in conjunction with boiler operation.
Hot water is circulated through the hot water / glycol heat exchanger via two (2) 10 HP pumps (P-2A, P-2B). Pump operation is lead/standby with a manual rotation cycle to equalize run time. The pumps are constant volume and are controlled based on the glycol supply water temperature.
Glycol is circulated through the ACUs and HVs via two (2) 15 HP pumps (P-3A, P-3B). Pump operation is lead/standby with a manual rotation cycle to equalize run time. The pumps are constant volume and are energized whenever the ACUs and HVs are calling for heat.
Hot water is circulated through the fintube radiation loop via two (2) 3 HP pumps (P-4A, P-4B). Pump operation is lead/standby with a manual rotation cycle to equalize run time. The pumps are constant volume and are energized when the outside air temperature is below the setpoint.
B1502090.000 6 | 7
Hot water at the DAC is circulated by two (2) 3 HP pumps (P-9A, P-9B). These pumps provide hot water to the fin tube radiators, air conditioning units, and fan coil units in the DAC. The pumps are constant volume and are energized 24/7 throughout the heating season. Pump operation is lead/lag with a manual rotation cycle to equalize run time.
There are two (2) 2 HP pumps (P-7A, P-7B) that provide hot water to the vehicle maintenance unit heaters. The pumps are constant volume and are energized 24/7 throughout the heating season. Pump operation is lead/lag with a manual rotation cycle to equalize run time.
All hot water pumps are listed in Table 1.8 below:
Table 1.8 - Hot Water Pumps
MARK NO SERVICE LOCATION PUMP TYPE
PERFORMANCE DATA MOTOR DATA
GPM TDH (FT) RPM HP VOLT PHASE
P1-(A,B,C) HOT WATER BOILER ROOM END SUCTION 310 30 1750 5 480 3
P2-(A&B) HW-GLYCOL BOILER ROOM END SUCTION 540 40 1750 7.5 480 3
P3-(A&B) GLYCOL BOILER ROOM END SUCTION 540 70 1750 15 480 3
P4-(A&B) RADIATION BOILER ROOM IN-LINE 90 50 1750 3 480 3
P5-(A,B,C) CHILLED WATER BOILER ROOM END SUCTION 280 80 1750 15 480 3
P6-(A,B,C) CONDR WATER BOILER ROOM END SUCTION 450 65 1750 15 480 3
P7-(A&B) CONDR WATER MAINT BLDG IN-LINE 50 20 1750 2 480 3
P8-(A&B) CHILLED WATER PRERELEASE IN-LINE 70 60 1750 3 480 3
P9-(A&B) HOT WATER PRERELEASE IN-LINE 50 60 1750 3 480 3
FR1-(A&B) DIESEL OIL EMER GEN BLDG 5 30 950 0.5 480 3
B1502090.000 7 | 7
1.3 Domestic Hot Water
There are three (3) domestic hot water systems serving the main building.
Main DHW System – serves sinks and showers
The main domestic hot water system has been recently replaced with two (2), condensing, 850 MBH THB water heaters. The 1,500 gallon storage tank is original to the building. The system supply temperature is set at 110F.
Laundry DHW System
The laundry domestic hot water system consists of two (2) 400 MBH Raypack units with a 750 gallon storage tank.
The system supply temperature is set at 170F, which tends to drop to 150F under load. The system supports five
(5) commercial grade washing machines.
Kitchen DHW System
The kitchen domestic hot water system consists of two (2) 400 MBH Raypack units with a 1,000 gallon storage tank. The system supply temperature is set at 150F.
Additionally, there is one (1) domestic hot water system serving the DAC. This system is located on the second floor and consists of two (2) 300 MBH Raypack units with a 350 gallon horizontal storage tank. There are two (2) sets of paired circulation pumps; this is, one set for circulation between the heaters and storage tank, and the second set for system circulation. The system serves lavatories, showers, and one (1) commercial washing machine.
1.4 Lighting and Lighting Controls System
1.4.1 Main Building
Lighting within the central unit corridors primarily consists of 1’ x 1’ 135W metal halide fixtures. During the walkthrough, it was noted that every alternate fixture was on. Lighting within the pod corridors consists of T8 fluorescent fixtures. Lighting within the cells primarily consists of T8 fluorescent fixtures. Directly outside each cell, is a 9W compact fluorescent lamp. There are 10 high bay 250W metal halide fixtures in each of the pods. During the walkthrough, it was noted that only four (4) of the metal halide lamps were energized. There are additional metal halide fixtures in the gym.
1.4.2 DAC
Lighting with the corridors consists of 4’ T8 fluorescent fixtures with two (2) lamps per fixture. There are four (4) high bay metal halide lamps in the lobby. Each cell consists of one (1) 4’ T8 fluorescent fixture with two (2) lamps per fixture.
All lighting on the campus is manually controlled. Exterior lighting on the campus is controlled via a timeclock.
- End of Building Description -
WSP
88 Black Falcon Avenue, Ste 210 Boston, MA 02210 617 210 1600 www.wspgroup.com/usa
P:\B13\B1310200000_BCBS_OED_TA_Study\FAC\FINAL DELIVERABLES\2. Building Facility Description\TAB 2 - Building Facility Description.docx