SDN1501E ES1 BOD body.pdf

PDF 10 MB Posted

Attached to
SDN1501E ES1 Norfolk Sheriff Office Energy Project Dedham
Solicitation number
BD-16-1019-DCP08-ENR01-00000008759
Issued by
Norfolk County, Massachusetts

About this file

This document appears to be a Request for Proposals (RFP) for an Energy Design Build contract with the Norfolk Sheriff's Office in Dedham, Massachusetts. The RFP was posted on COMMBUYS on June 8, 2016, pursuant to Chapter 25A 11c, and seeks a contractor to finalize design, install, and commission various energy conservation measures (ECMs) including LED lighting upgrades, water controls, HVAC control upgrades, VFD upgrades, ozone laundry system, kitchen hood controls, and potentially solar photovoltaics, combined heat and power, and other building improvements.

The RFP does not provide specific details on pricing terms, set asides, incumbents, funding requirements or sources, or contract amounts. However, it indicates the contract will be for the design, installation, and commissioning of the specified ECMs for the Norfolk Sheriff's Office facility in Dedham, Massachusetts.

View the file

Other files

File Type Posted
SDN1501E ES1 Forms BCD.xlsx XLSX spreadsheet
AEP Audit Template SDN1501E-ES1.xlsm XLSM spreadsheet
SDN1501E FormE.xlsx XLSX spreadsheet
N.C.S.O. CORI Security Clearance Request Form.pdf PDF
SDN1501E-ES1 RFP Final~1.pdf PDF
SDN1501E ES1 Main HOC Toilet Locations.pdf PDF
SDN1501E-ES1 3rd Site Visit Sign In 7-19-16.pdf PDF
SDN1501E ES1 Conditions Assessment.pdf PDF
SMRT Chiller EMS Study-Pg 57-61.pdf PDF
SMRT Chiller EMS Study-Pg 51-56.pdf PDF
SDN1501E ES1 Proposals Received.pdf PDF
SDN1501E-ES1 Pre-Proposal Sign-In.pdf PDF
SDN1501E ES1 BOD.pdf PDF
SDN1501E-ES1 Addnedum 1.pdf PDF
SDN1501 Preproposal AGENDA 6-22-16.pdf PDF
SDN1501E FormE - Rev 1.xlsx XLSX spreadsheet
SMRT Chiller EMS Study-Pg 48-50.pdf PDF
SDN1501E ES1_ListFinalQ-A.pdf PDF
SDN1501E ES1 BOD Plumb 0-3.pdf PDF
SDN1501E ES1 ASHRAE Level I and II Report.pdf PDF
SDN1501E ES1 Forms BCD - Rev 1.xlsx XLSX spreadsheet
SDN1501E ES1 DCAMM File Release Form.pdf PDF
SDN1501E ES1 PV Addenda to BOD.pdf PDF
SDN1501E-ES1 Addendum 3.pdf PDF
SDN1501E ES1 BOD Plumb-4-7.pdf PDF
SDN1501 Pre-Proposal Presentation 6-22-16.ppt PPT presentation
SDN1501E-ES1 2nd Site Visit Sign in 7-13-16.pdf PDF
SMRT Chiller EMS Study-Pg 43-47.pdf PDF
SMRT Chiller EMS Study-Body.pdf PDF
SMRT Chiller Draft CDs.pdf PDF
SDN1501E-EC1 - ESA for RFP Final.pdf PDF
SDN1501E ES1 Accessible Toilet Room Report.pdf PDF
SDO Certified MWBE Subcontractors.xlsx XLSX spreadsheet
SDN1501E ES1 PV Array Layout Plan.pdf PDF
SDN1501E-ES1 Addendum 2.pdf PDF
SDN1501E ES1 Prevailing Wage Rates.pdf PDF
SDN1501Pre-proposal Minutes.pdf PDF
SDN1501E ES1 BOD Mech and Elec.pdf PDF
SDN1501E ES1 BOD Plumb-8-12.pdf PDF
SDN1501E ES1 Building Facility Description.pdf PDF
SMRT Chiller EMS Study.pdf PDF
SDN1501E-ES1 Form F.docx DOCX document
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORFOLK COUNTY CORRECTIONAL CENTER (NCCC)

Basis of Design Description of Mechanical, Plumbing and Electrical Systems B1509940.000

January 22, 2016

Prepared For:

Division of Capital Asset Maintenance and Management

TABLE OF CONTENTS

I. INTRODUCTION

II. HEATING, VENTILATION, AIR CONDITIONING (HVAC)

III. PLUMBING

IV. ELECTRICAL

V. GENERAL SPECIFICATIONS REQUIREMENTS

VI. APPENDICES

VII. MEP DRAWINGS

I. INTRODUCTION

A. PURPOSE

a. The purpose of this document is to develop schematic level design documentation in the form of a basis of design and applicable drawings and specifications in order to be procured through a request for proposal (RFP) by DCAMM under Chapter 25A.

b. The design concept was derived from an ASHRAE Level-II Energy Audit from which energy conservation measures (ECM’s) required further development in a basis of design (BOD) in order to procure through Chapter 25A.

B. DELIVERABLES

a. WSP I Parsons Brinckerhoff has provided a Basis of Design (BOD) that includes design criteria, drawings, diagrams, and performance specifications that has brought the ECM’s to a 30% schematic design level; where the awarded Contractor shall complete the design and implement the ECM’s per all applicable local and state codes.

C. SCOPE

a. In general, the scope of measures included in this BOD includes installing the following selected ECM’s outlined in WSP I Parsons Brinckerhoff’s Energy Audit Report:

a. ECM-1.01: Retrofit Interior Lighting Fixtures with LED and Install Lighting Control Sensors

b. ECM-1.07: Retrofit Exterior Lighting Fixtures with LED

c. ECM-4.10: Convert ACU’s 1 through 4 to Full DDC Actuation & Control and Optimize System

d. ECM-4.13a: Integrate ACU-7 and ACCU-8 Operation with Occupancy Schedule

e. ECM-4.13b: Integrate HV-2 operation with Occupancy Schedule.

f. ECM-4.14a: Interlock Dishwasher Exhaust Fan with Dishwasher Operation

g. ECM-4.14b: Integrate Laundry Exhaust Fan LX-1 and Heating Ventilation Unit HV-3 with Occupancy Schedule

h. ECM-4.14c: Install Demand Controlled Ventilation/Exhaust Controls for Kitchen Exhaust Fan KX-1 and Heating Ventilation Unit HV-1

i. ECM-5.02a: Install Low Flow / Ultra Low Flow Fixtures for Water Closets, Faucets, Urinals, and Showerheads serving Admin/Staff Areas.

j. ECM-5.02b: Install a Computerized Water Conservation System for the Combi-Units and Showers Serving Inmates. Replace Inmate Showerheads with New Low-Flow Showerheads

k. ECM-7.01: Ozone Laundry Water Conservation System

l. ECM-9.00: Convert Multizone Units ACU-1 through ACU-4 to Variable Volume Units

m. ECM-9.01: Install VFD’s on Secondary HW Glycol Pumps P-3A & P-3B and Convert the Existing HW Boiler System to DDC and Connect to the new BMS

n. ECM-16.00: Install Cogeneration System for Domestic Hot Water

o. ECM-17.00a: Replace Unit Heater Thermostats with new DDC Thermostats

p. ECM-17.00b: Optimize Fin Tube Radiation Heating System Control

q. ECM-21.00: Install Photovoltaic System on Main Building Roof

r. ECM-23.00: Walk-In Refrigerator / Freezer Controls

II. HEATING, VENTILATION, AIR CONDITIONING (HVAC)

A. Outdoor Design Conditions:

a. Summer: 90 F dry bulb, 76 F wet bulb (ASHRAE 0.5%)

b. Winter: F dry bulb (ASHRAE 0.2%)

B. Codes and Standards

a. The following codes and standards are applicable, in addition to any other local code requirements.

a. 2009 International Building Code

b. 2009 International Mechanical Code

c. 2009 International Plumbing Code

d. Massachusetts State Building Code 8th Edition

e. 2007 National Fire Protection Association (NFPA)

f. Sheet Metal and Air Conditioning Contractors National Association

(SMACNA)

g. Underwriters Laboratories (UL)

h. American Society of Heating, Refrigeration and Air Conditioning

Engineers (ASHRAE)

i. American Association of Balancing Contractors (AABC)

j. Air Movement and Control Association (AMCA)

k. Air Conditioning and Refrigeration Institute (ARI)

l. Occupational Safety & Health Administration (OSHA)

C. ECM-4.10: Convert ACU-1 through 4 to Full DDC Actuation & Control and Optimize

System

1. Existing Conditions

a. HVAC equipment on campus is controlled via a pneumatic control system. The system consists of a compressed air supply system, main line distribution system, branch lines, sensors, controllers and actuators.

2. Recommendations

a. As part of the chiller replacement project by SMRT Architecture and Engineering the chiller plant is to be replaced and a full direct digital control (DDC) energy management system (EMS) is to be installed.

Additionally, SMRT Architecture and Engineering is installing electro-pneumatic transducers on ACU-1 through ACU-4 to allow for electro-pneumatic DDC control of the units in lieu of installing new electronic valves and actuators, which would provide electro-electro control of the units. The project is estimated to be completed by September 2016.

Any new equipment installed after this project is to be tied into the energy management system.

b. Convert ACU-1 through ACU-4 to full DDC control and actuation (electro-electro). All necessary hardware, software and labor shall be provided to obtain the sequences of operation for ACU-1 through ACU-4. A complete, fully integrated control system shall be provided. The scope of work for electro-electro control of ACU-1 through ACU-4 shall include:

1) Fan start/stop, status, fault to be picked up at EMS (Note see ECM 9.00 regarding replacement of fan motors)

2) Variable Frequency Drive (VFD) speed and status to be picked up at EMS and coordinated with manufacturer (Note see ECM

9.00 regarding installation of VFDs)

3) Temperature sensors to be picked up at EMS (Note see ECM

9.00 regarding replacement of zone temperature sensors)

4) Replacement of existing hot water and chilled water 3-way control valves/actuation with new electronic 2-way valves/actuation (valve positions to be picked up at EMS)

5) Installation of ACU pressure differential sensor across the filtration section (clean/dirty filter status to be picked up at EMS)

6) Smoke detection and unit shutdown (status to be picked up at

EMS)

7) Replacement of existing outside air, return air, and relief air electro-pneumatic actuation with electro-electro actuation (damper positions to be picked up at EMS)

8) Replacement of existing hot deck / cold deck electro-pneumatic actuation with electro-electro actuation (damper positions to be picked up at EMS).

c. Please carry (20) EMS points for each ACU. Contractor to provide unit price ($ per EMS point) for additional points, as required.

d. Refer to specifications for additional control system information.

D. ECM-4.13a: Integrate ACU-7 & ACU-8 Operation with Occupancy Schedule

a. Existing ACU-7 & ACU-8 serve the visiting/dining and educational spaces. These spaces do not require 24/7 operation. The units are equipped with hot water / glycol coil and a chilled water coil to maintain a discharge air temperature to downstream VAV boxes. The supply and return fans control at variable volume based on static pressure demand and modulate outside air, return and relief dampers as needed to maintain minimum outside air requirements

2. Recommendations:

a. Existing ACU-7 & ACU-8 are to be placed on Occupancy Schedules through the new Energy Management System.

E. ECM-4.13b: Integrate HV-2 Operation with Occupancy Schedule

a. Existing Conditions:

a. Existing HV-2 is a 100% outside air heating and ventilation units equipped with hot water heating coils serving the kitchen. HV-1 provides makeup air for the kitchen.

b. Recommendations:

a. Existing HV-2 is to be placed on Occupancy Schedules through the new Energy Management System.

F. ECM-4.14a: Interlock Dishwasher Exhaust Fan with Dishwasher Operation

a. The existing dishwasher exhaust fan KX-3 is manually controlled via a switch. Through discussions with the facility personal it was learned that the dishwasher exhaust fan does not de-energize when the switch is in the off position and remains in operation 24/7.

b. Recommendations:

a. Existing exhaust fan KX-3 is to be interlocked with the operation of the dishwasher. The fan is to be on only when the dishwasher is on.

b. Refer to electrical drawing E-001 for interlocking detail; as well as, the electrical section of this BOD.

G. ECM-4.14b: Integrate Laundry Exhaust Fan LX-1 and Heating Ventilation Unit HV-3 with Occupancy Schedule.

1. Existing Conditions:

a. The existing Laundry Exhaust Fan LX-1 and Heating Ventilation unit HV- 3 are energized 24/7.

a. Existing Laundry Exhaust fan LX-1 and HV-3 are to be placed on Occupancy Schedules through the new Energy Management System.

H. ECM-4.14c: Install Demand Controlled Ventilation/Exhaust Controls for Kitchen Exhaust

Fan KX-1 and Heating Ventilation Unit HV-1.

a. Existing HV-1 is an 11,200 CFM heating and ventilation unit equipped with a hot water heating coil that provides make-up air for the kitchen exhaust system. KX-1 exhausts 11,900 cfm from the kitchen exhaust hoods. HV-1 is energized 24/7 and KX-1 is energized via a switch.

a. The Kitchen shall have Demand Controls installed on the existing kitchen Exhaust and Make-up air systems. A complete MeLink System (or equivalent) shall be installed. All necessary Hood Controllers, Touchpads, Optic Sensors, Optic Sensor Purge Units, Temperature Sensors, VFD’s, Motors and System Controllers shall be provided to retrofit the existing system.

b. The existing kitchen hood exhaust fan (KX-1) motor is to be replaced with a high efficiency motor, equipped with a VFD.

c. The existing kitchen heating and ventilation unit (HV-1) is to be retrofitted with a high efficiency motor, equipped with a VFD.

d. Provide a MeLink System Controller (or equivalent) for the kitchen HVAC system. Provide all software programs, all hardware and all additional equipment, as required, to obtain Demand Controls on existing Kitchen Exhaust and Make-Up Air systems.

I. ECM-9.00: Convert Multizone Units AC-1 Through AC-4 to Variable Volume Units

a. Existing Conditions

a. Within the main building there are four (4) main pods that house holding cells. Each pod is served by one (1) penthouse multizone air handling unit with heating and cooling. The mechanical room that houses each ACU acts as a mixed-air chamber for return and outside air. A return fan (RF) operates in tandem with the AC supply fan to recirculate/exhaust air as dictated by the orientation of the unit dampers. The units operate 24/7 as hot deck / cold deck units with cold deck operation in the summer and hot deck operation in the winter. A hot water coil and chilled water coil within the unit operate to maintain room temperature setpoint. The supply and return fans control at constant volume and modulate outside air, return and exhaust dampers to maintain minimum outside air requirements.

a. The existing supply fan and return fan motors for Multizone Units are to be replaced with high efficiency motors equipped with VFD’s.

b. The temperature sensors for each zone of the Multizone Units are to be replaced. The Multizone Temperature sensors will report back to the energy management system, which will use the worst-case temperature of all three (3) sensors. The VFDs will modulate the AC supply fan speed to maintain space temperature setpoint. When the space temperature is satisfied, the ACU will operate at minimum speed to provide code required minimum ventilation.

J. ECM-9.01: Install VFDs on Secondary HW Glycol Pumps P-3A & P-3B and Convert the Existing HW Boiler System to DDC and Connect to the new BMS

1. Existing Conditions:

a. The existing Secondary Glycol Pumps (P-3A, P-3B) operate to maintain flow through the ACU and HV units. The pumps control to provide glycol hot water to the ACU and HV units when there is a call for heat. The current pumping configuration is lead/standby and is constant volume.

b. The hot water (HW) heating boiler system is currently local control only with internal microprocessors controlling the HW heating supply temperature to the downstream HVAC equipment.

a. Pumps P-3A & P-3B motors are to be replaced with high efficiency motors and equipped with VFDs. The VFDs are to operate to maintain system differential pressure. The existing system differential by-pass configuration is to be utilized and the differential sensor and by-pass valve is to be replaced.

b. The existing Hot Water three-way valves at the Multizone units are to be replaced with two-way control valves.

c. The site is currently installing a new BMS system under a separate project. The scope of work for this ECM (ECM-9.01) is to connect the HW boiler system to the new BMS system (convert ALL pneumatics associated with this plant to DDC and connect to the new BMS system).

Systems to be included are:

1) HW boilers (B-1, B-2)

2) Heat Exchanger (HX-1)

3) Three primary HW pumps (P-1A, P-1B, P-1C)

4) Six secondary HW pumps. (P-2A, P-2B, P-3A, P-3B, P-4A, P-

4B)

5) All corresponding devices for proper control of this plant via the new BMS.

K. ECM-16.00: Install Cogeneration System for Domestic Hot Water.

a. There are six (6) domestic hot water heaters serving three (3) domestic hot water (DHW) systems, which each operate year round.

1) Main DHW System: Two (2) 850 MBH condensing boilers and 1500-gallon storage tank that operates at 110F.

2) Laundry DHW System: Two (2) 400 MBH Raypack units and 750-gallon storage tank that operates at 170F (drops to 150F under load).

3) Kitchen DHW system: Two (2) 400 MBH Raypack units and 1000-gallon storage tank that operates at 150F.

a. Install a cogeneration system to preheat domestic water and produce electricity to the site. The preheated domestic water will reduce the load on the existing Main, Laundry and Kitchen domestic hot water systems while the electricity output will reduce purchased power consumption from the grid.

b. A cogeneration system should be selected such that the heat output from the generator can always be used and not wasted. The heating output of the six (6) domestic water heaters is 600,000 BTU/hour. The proposed cogeneration system is an Aegen ThermoPower TP75 (or equivalent) system. The system is 85% efficient, has a power output of 75KW and a thermal output of 523,000 BTU/hour.

c. Please note, the design build contractor shall review the most recent (12) months of utility bills to confirm the cogeneration system size.

L. ECM-17.00a: Replace Unit Heater Thermostats with new DDC Thermostats

a. Ceiling-mounted hot water unit heaters (UH’s) provide supplemental heat to such spaces as the boiler room, vehicle maintenance building, carpentry shop, metal shop, storage spaces and various other back-of-house spaces.

a. Replace all thermostats controlling unit heaters throughout the site.

Total quantity counted as per this BOD is 32 UH’s.

b. Note, ECM-17.00b below: Along with a new thermostat, each UH will be retrofitted with a 2-way control valve to be controlled via the new thermostat.

M. ECM-17.00b: Optimize Fin-Tube Radiation Heating System Control

a. The main building central unit has finned tube radiators throughout the perimeter of the building to provide supplemental heat. Hot water secondary pumps P-4A & P-4B operate at constant volume to provide hot water to the finned tube radiation system and unit heaters when the outside air is below set point (refer to ECM-17.00a for additional info).

The Finned Tube system operates as a single close loop with no segregated temperature control zones.

a. Modify the existing Perimeter Heating system into three control zones (refer to mechanical drawings in appendix for further information). Install control valves and thermostats for each new zone to enhance controllability of the system.

b. Install or replace control valves on each Unit Heater on site (refer to ECM-1700a for additional information.

c. Pumps P-4A & P-4B motors are to be replaced with NEMA high efficiency motors and equipped with VFDs. Refer to electrical section for additional information.

N. ECM-23.00a: Walk-in Refrigerator / Freezer Controls

a. Recommendations:

a. Install walk-in freezer and refrigerator controls to reduce the run time of the evaporator fans, compressors and electric door heaters by maintaining the cooler temperature based on dew point instead of dry bulb temperature. The system shall also provide diagnostic and trending features to aid in system maintenance and trouble shooting.

b. Install controls on (4) refrigeration walk-ins and (2) freezer walk-ins.

Provide any necessary cabinet/casing repair work and equipment replacing to the existing walk-ins.

c. The Automated Temperature Control Contractor and Mechanical

Contractor are to coordinate the Energy Management System integration of new Walk-in Box OEM controller (or equivalent) with the manufacturer, including all necessary communications protocols.

Provide all necessary refrigeration box equipment replacement, hardware, controls and labor to obtain smart controls sequence of operation.

III. PLUMBING

A. Codes and Standards

1. Massachusetts 248 CMR: Board of State Examiners of Plumbers and Gas Fitters.

2. Massachusetts State Building Code Eighth Edition.

B. ECM-5.02a: Install Low Flow / Ultra Low Flow Fixtures for Water Closets, Faucets, Urinals, and Showerheads serving Admin/Staff Areas

a. Many of the existing water closets, urinals, and faucets are vintage high-flow fixtures and shall be replaced as per the plumbing drawings. Refer to plumbing drawings for locations and quantities of existing fixtures to be upgraded.

a. Provide low-flow fixtures in areas shown on the plumbing drawings.

Note, the plumbing drawings are meant to be diagrammatical and final quantities to be determined by the awarded contractor.

b. Refer to the appendix for the cut sheets regarding the basis of design for the new fixtures as per this ECM.

C. ECM-5.02b: Install a Computerized Water Conservation System for the Combi-Units and

Showers Serving Inmates. Replace Inmate Showerheads with New Low-Flow Showerheads

a. Generally the combi-units’ fixtures are in fair shape and are intended to be reused.

b. The showerheads, however, are vintage and shall be replaced.

c. Currently, the facility does NOT have control via a computerized system to remotely control the water usage within the inmate areas regarding the combi-units and showers.

a. Provide a water conservation control system for the combi-units and showers serving the inmates. The basis of design is I-Con (or equivalent). The plumbing drawings outline the intent and potential locations for control panels to be installed, including the location of the master control head-end computer. Note, the plumbing drawings are meant to be diagrammatical and final locations for control modules and the head-end computer to be determined/coordinated by the awarded contractor.

b. Retrofit all Combi-Units (final count to be determined by the awarded contractor), add control module within chase and provide computer at guard station in order to control and monitor cell activities.

c. Replace all showerheads with new low-flow showerheads, equipped with a shower control module, and wire into the new water conservation control system for remote control of showers.

d. Provide an EMS (energy management system) connection to the new water conservation control system for all control modules regarding the comb-units and showers. Note, the EMS is being provided to the facility under a separate project and is not part of this scope of work. In conclusion, please purchase the new water conservation system with the means necessary to remotely monitor points into the EMS.

e. Please note, the site team and DCAMM are requiring the awarded contractor to integrate the water conservation control system (basis of design is ICON) into the existing security system. For further information, please see Appendix D for the Icon specifications outlining the communications protocol. Note, the basis of design is ICON; however, the awarded contractor has the option to provide an equivalent system as per the performance specifications.

D. ECM-7.01: Ozone Laundry Water Conservation System

a. The facility currently does not have a water conservation system for their laundry usage and this ECM is intended to address the issue.

a. The installation of an Ozone Laundry System will improve efficiency.

b. Plumbing Contractor shall install Ozone Laundry System on existing water system feeding washing machines. The manufacturer’s recommendations indicate there shall be one unit per four washing machines. Note, please refer to manufacturer’s installation and operations requirements upon purchasing and installation.

c. The Basis of Design is Aqua-Wing Ozone Injection System Tower: AF- Tower Series.

d. Refer to the appendix for the cut sheets. Also, refer to P-007 for a part plan of the Laundry Room.

e. Provide a BMS (building management system) connection to the new ozone laundry system. Note, the BMS is being provided to the facility under a separate project and is not part of this scope of work. In conclusion, please purchase the ozone laundry system with the means necessary to remotely monitor points into the BMS.

E. ECM-16.00: Install Cogeneration System for Domestic Hot Water Pre-Heating

a. The facility currently does not use any energy recovery to preheat air or water and this ECM is intended to address the issue.

a. The intent of this ECM is to provide preheating capabilities via a cogeneration system to be provided by the mechanical contractor. The basis of design is Aegen (or equivalent), which is shown on the MEP drawings in diagrammatic fashion.

b. The Plumbing Contractor shall provide and coordinate gas service, and if required, gas booster. The Plumbing Contractor shall provide and coordinate point of connection to the existing domestic hot water system.

c. Provide an EMS (energy management system) connection to the new cogeneration system. Note, the EMS is being provided to the facility under a separate project and is not part of this scope of work. In conclusion, please purchase the cogeneration system with the means necessary to remotely monitor points into the BMS.

IV. ELECTRICAL

A. Codes and Standards

1. Massachusetts Electrical Code: NFPA 70: (NEC) 2014 with Massachusetts Amendments.

2. Massachusetts State Building Code, 8th Edition

3. Massachusetts State Building Code 248 CMR

4. International Building Code, 2009 Edition

5. International Energy Code, 2012 Edition

6. NFPA 72

7. NFPA 101

8. Underwriters Laboratories (UL)

9. Occupational Safety & Health Administration (OSHA)

B. ECM-1.01: Retrofit Interior Lighting Fixtures with LED and Install Lighting Control Sensors

1. Design intent is mostly retrofit of T12 and T8 fixtures with LED fixtures, and replacement of metal halide fixtures with LED.

2. Occupancy sensors are to be installed in areas where life safety is not a concern, including conference rooms, private offices, classrooms and private rest rooms.

3. Where light fixture is indicated to be replaced, disconnect and remove existing fixture and maintain existing wiring and outlets.

4. Where fixtures are indicated to be relamped, existing lamp and ballast shall be replaced.

5. Where existing fluorescent lamp is being replaced with LED tube, existing ballast shall remain.

6. Reconnect all lighting outlets to the existing branch circuit wiring.

7. Refer to Lighting Matrix on Drawing E-002 for information for each lighting fixture type.

8. Refer to Existing Lighting Matrix on Drawing E-003 for information for each existing lighting fixture type.

9. Existing controls shall be maintained unless otherwise indicated in the lighting matrix.

10. Recommendations

a. Refer to Drawing E-002 for fixture quantity located in each building.

b. Confirm with owner all proposed fixture replacements in secure areas.

c. Confirm quantities of fixtures, lamps and ballasts.

d. Occupancy sensors shall be ceiling mounted, 360 o , PIR and ultrasonic duel technology type in offices and shared rooms.

e. Manual override switches shall remain in all locations where occupancy sensors are being installed.

f. In storage areas and private rest rooms, occupancy sensors shall be wall mounted, PIR type with integral manual override.

C. ECM-1.07: Retrofit Exterior Lighting Fixtures with LED

1. Design intent is mostly retrofit of high intensity discharge (HID) fixtures with LED.

2. Where light fixture is indicated to be replaced, disconnect and remove existing fixture and maintain existing wiring and outlets.

3. Where fixtures are indicated to be relamped, existing lamp and ballast shall be replaced.

4. Where existing fluorescent lamp is being replaced with LED tube, existing ballast shall remain.

5. Reconnect all lighting outlets to the existing branch circuit wiring.

6. Refer to Lighting Matrix on Drawing E-003 for information for each lighting fixture type.

7. Refer to Existing Lighting Matrix on Drawing E-003 for information for each existing lighting fixture type.

8. Existing controls shall be maintained unless otherwise indicated in the lighting matrix on E-002.

9. Recommendations

a. Refer to Drawing E-002 for fixture quantity located in each building.

b. Confirm with owner all proposed fixture replacements in secure areas.

Confirm quantities of fixtures, lamps and ballasts.

D. ECM-4.14a: Interlock Dishwasher Exhaust Fan with Dishwasher Operation

a. The existing dishwasher exhaust fan KX-3 is manually controlled via a switch. Through discussions with the facility personal it was learned that the dishwasher exhaust fan does not de-energize when the switch is in the off position and remains in operation 24/7.

a. Existing exhaust fan KX-3 is to be interlocked with the operation of the dishwasher. The fan is to be on only when the dishwasher is on.

b. Provide power relay to interconnect the dishwasher with KX-3, wired such that the fan is energized only when the dishwasher disconnect is in the “on” position.

c. Refer to drawing E-001 for wiring diagram and additional information.

E. ECM-4.14c: Install VFD for Kitchen Exhaust Fan KX-1 and Heating Ventilation Unit HV-1 and replace motors.

a. Existing HV-1 is energized 24/7 and KX-1 is energized via a switch.

b. HV-1 and KX-1 are both served via motor control center MCC-2 located in Central Unit North electrical closet.

a. Provide new VFD and fan motor replacement for existing kitchen hood exhaust fan KX-1.

b. Provide new VFD and fan motor replacement for existing Heating Ventilation unit HV-1

c. Coordinate location of VFD within building with the facilities manager. If VFD is housed outdoors, provide stainless steel NEMA 4X enclosure with internal electric heater and control thermostat within VFD enclosure.

d. Disconnect and remove existing electric and maintain existing wiring and conduit.

e. Disconnect and remove existing motor control center bucket currently serving HV-1 and replace with new Siemens 30A molded case circuit breaker retrofit kit.

f. Disconnect and remove existing motor control center bucket currently serving KX-1 and replace with new Siemens 30A molded case circuit breaker retrofit kit.

g. Refurbished or repaired units are not acceptable. Unit shall be original manufacturers replacement unit rated UL845 and listed to maintain existing UL ratings for the MCC.

h. Replace motor in kind with new NEMA premium efficiency inverter duty motor of the same HP rating.

i. Provide 3#12 & 1#12G in 3/4"C to VDF location. Intercept and extend wiring from VFD to pump location.

j. Reconnect new motor to existing circuit.

Electrical contractor shall inspect existing wiring and conduit and replace if found defective. Existing local disconnect switches and flex connections were found to be damaged by the weather and shall be replaced with new.

F. ECM-7.01: Ozone Laundry Water Conservation System

a. The facility currently does not have a water conservation system for their laundry usage and this ECM is intended to address the issue.

a. Electrical Contractor shall provide 2#12 & 1#12G in 3/4”C from panel KLP to Ozone Laundry System located in laundry room approximately 100 feet away.

b. Provide 20A-1P circuit breaker in existing panel for Ozone equipment.

Coordinate with plumbing contractor for exact location of Ozone system equipment.

G. ECM-9.00: Convert Multizone Units AC-1 Through AC-4 to Variable Volume Units

a. Existing Conditions

a. Within the main building there are four (4) main pods that house holding cells. Each pod is served by one (1) penthouse air handling unit with heating and cooling. Each air handling unit is served by a motor control center located on the floor below.

b. AC-1 is served via 20AS/20AF motor control center EMCC-3

c. AC-2 is served via 20AS/20AF in motor control center EMCC-3

d. AC-3 is served via 60AS/35AF in motor control center EMCC-2

e. AC-4 is served via 30AS/30AF in motor control center EMCC-2

a. The existing supply fan and return fan motors for Multizone Units are to be replaced with NEMA premium efficiency motors equipped with VFDs.

b. AC-1: Disconnect and remove existing motor control center bucket and replace with new 20A molded case circuit breaker retrofit kit. Intercept and extend extend existing wiring to new VFD. Provide 3#12 and 1#12 ground in 3/4” EMT to VFD locations.

c. AC-2: Disconnect and remove existing motor control center bucket and replace with new 20A molded case circuit breaker retrofit kit. Intercept and extend extend existing wiring to new VFD. Provide 3#12 and 1#12 ground in 3/4” EMT to VFD locations.

d. AC-3: Disconnect and remove existing motor control center bucket and replace with new 40A molded case circuit breaker retrofit kit. Intercept and extend extend existing wiring to new VFD. Provide 3#8 and 1#10 ground in 1” EMT to VFD locations.

e. AC-4: Disconnect and remove existing motor control center bucket and replace with new 30A molded case circuit breaker retrofit kit. Intercept and extend extend existing wiring to new VFD. Provide 3#10 and 1#10 ground in 3/4” EMT to VFD locations.

f. Provide VFD for each supply and exhaust fan located in the mechanical space each air handling unit is located.

g. Refurbished or repaired MCC retrofit units are not acceptable. Unit shall be original manufacturers replacement unit rated UL845 and listed to maintain existing UL ratings for the MCC.

ECM-9.01: Install VFDs on Secondary HW Glycol Pumps P-3A & P-3B and Convert the Existing HW Boiler System to DDC and Connect to the new BMS

a. The existing pumps P-3A and P-3B are currently being served via (2)-

30AS/30AF in existing 225A, 480V, 3ph, 3w Siemens motor control center “EMCC-1” located in the central unit boiler room.

a. Pumps P-3A & P-3B motors are to be replaced with NEMA high efficiency motors and equipped with VFDs.

b. Disconnect and remove existing motor control center bucket and replace with new 40A molded case circuit breaker retrofit kit.

c. Provide new VFD for each glycol pump. Locate VFDs within the same room as pumps.

d. Provide 3#10 & 1#10G in 3/4"C to VDF location. Intercept and extend

e. The site is currently installing a new BMS system under a separate project. The scope of work for this ECM (ECM-9.01) is to connect the HW boiler system to the new BMS system (convert ALL pneumatics associated with this plant to DDC and connect to the new BMS system).

Systems to be included are:

1) HW boilers.

2) Two primary HW pumps.

3) Four secondary HW pumps.

4) All corresponding devices for proper control of this plant via the new BMS.

H. ECM-16.00: Install Cogeneration System for Domestic Hot Water.

1. Provide 200A circuit breaker in existing 2500A main switchboard “MSB-1” located in the main electric room for new 75kW Cogen system. Circuit breaker shall match manufacturer, type and AIC rating of existing breakers in switchboard

MSB-1.

2. Provide 4#3/0 & 1#6 in 2”C from MSB-1 to Cogen system located in yard approximately 200 feet away.

c. The conduit shall be PVC schedule 40 where installed underground and shall be EMT where installed within building. All wiring shall be XHHW/XHHW-2.

3. Provide (3)-20A-1P circuit breakers in panel LP1 located in main switchboard room for peripherals for Cogen system.

4. Provide 2#12 & 1#12G – 3/4"C from each 20A-1P circuit breaker added to panel

LP1 to Cogen location for battery charger, lights and heater to be provided with Cogen system. Coordinate with manufacturer’s recommendations for exact power requirements.

I. ECM-21.00: Install Photovoltaic System on Main Building Roof

1. Recommendations

a. This measure includes installing a photovoltaic roof mounted array on the Main building roof with associated sub-metering

b. Note that the implementation of this measure is contingent upon a feasibility study, which at minimum, shall include the following:

1) Assessment of available roof area for the photovoltaic array

2) Structural assessment of the load bearing roof capacity

3) Detailed utility bill assessment of the electric load of the facility

c. An addendum to the Basis of Design, outlining the proposed photovoltaic system design, will follow upon determination of feasibility

J. ECM-17.00(b): Optimize Fin Tube Radiation Heating System Control

a. The existing hot water pumps P-4A and P-4B are currently being served via (2)-30AS/20AF in existing 225A, 480V, 3ph, 3w Siemens motor control center “EMCC-1” located in the central unit boiler room.

a. Pumps P-4A & P-4B motors are to be replaced with NEMA high efficiency motors and equipped with VFDs.

b. Disconnect and remove existing motor control center bucket and replace with new 20A molded case circuit breaker retrofit kit.

c. Provide new VFD for each hot water pump. Locate VFDs within the same room as pumps.

d. Provide 3#12 & 1#12G in 3/4"C to VDF location. Intercept and extend

V. GENERAL SPECIFICATIONS REQUIREMENTS

A. 018100 – COMMISSIONING

B. 092116 – GYPSUM BOARD ASSEMBLIES

C. 095113 – ACOUSTICAL PANEL CEILINGS

D. 099000 – PAINTING AND COATING

E. 220001 – PLUMBING

F. 230001 – HVAC

G. 260001 – ELECTRICAL

DCAMM STANDARD SPECIFICATIONS MASS. STATE PROJECT NUMBER SDN1501E E51

NCCC DEDHAM, MA

COMMISSIONING JANUARY 22, 2016

018100 - 1

SECTION 018100

COMMISSIONING

TABLE OF CONTENTS

PART 1 - GENERAL

1.01 GENERAL PROVISIONS

1.02 DESCRIPTION OF WORK

1.03 COORDINATION

1.04 COMMISSIONING PROCESS

1.05 RELATED WORK

1.06 COMMISSIONING COMPLETION

1.07 SYSTEMS TO BE COMMISSIONED

1.08 RESPONSIBILITIES

1.09 TESTING REQUIREMENTS

1.10 TESTING PREREQUISITES

1.11 MONITORING

1.12 DEFINITIONS

PART 2 - PRODUCTS

2.01 TEST EQUIPMENT

PART 3 - EXECUTION

3.01 MEETINGS

3.02 REPORTING

3.03 SUBMITTALS

3.04 START-UP, PREFUNCTIONAL CHECKLISTS AND INITIAL CHECKOUT

3.05 FUNCTIONAL PERFORMANCE TESTING

3.06 DOCUMENTATION, NON-CONFORMANCE AND APPROVAL OF TESTS

3.07 DEFERRED TESTING

3.08 OPERATION AND MAINTENANCE MANUALS

3.09 TRAINING OF OWNER PERSONNEL

PLUMBING

3.10 PLUMBING WATER SYSTEM

MECHANICAL

3.11 HOT WATER HEATING SYSTEM (BOILERS, PUMPS, DISTRIBUTION)

3.12 TERMINAL UNITS (FCU, FPT, VAV, CUH, UH)

3.13 PACKAGED DX SPLIT SYSTEM AIR CONDITIONING OR HEAT PUMP

3.14 EXHAUST FANS

3.15 BUILDING AUTOMATION SYSTEM (BAS)

3.16 TEST AND BALANCE WORK (TAB)

3.17 AIR HANDLING UNITS (RECIRCULATING AND 100% O.A.)

ELECTRICAL

3.18 SHORT CIRCUIT TRIP

3.19 LIGHTING CONTROL SYSTEM

018100 - 2

PART 1 - GENERAL

1.1 GENERAL PROVISIONS

A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS, which are hereby made a part of this Section of the Specifications.

1.2 DESCRIPTION OF WORK

A. Commissioning: Commissioning is a planned, collaborative process of witnessing and testing that confirms that a new building and its systems meet the Owner’s Project Requirements (OPR) and the project’s Basis of Design (BOD). The OPR is a written document that details the ideas, concepts and criteria that are defined by the owner to be important to the success of the project. The BOD includes design information necessary to accomplish the OPR, including system descriptions, indoor environmental quality criteria, design assumptions, and references to applicable codes, standards, regulations and guidelines. Achievement of these goals begins in the Pre-Design phase, continues through the Design, Construction and Acceptance Phases and concludes in the Post-Acceptance Phase with actual verification of performance.

Commissioning shall encompass and coordinate the traditionally separate functions of system documentation, equipment startup, control system calibration, testing and balancing, performance testing and training. The commissioning process will be directed by an independent, third-party Commissioning Authority (CA) whose services will be provided by

DCAMM.

1. In addition to collaborating in the development of the project’s BOD and OPR, during the Pre-Design Phase the Commissioning Authority shall review the size and skill levels of the Owner’s maintenance staff in relation to the requirements of the new building in order to fill any deficiencies.

2. In the Design Phase the Commissioning Authority shall complete the following tasks:

a. Write commissioning specifications that define contractor responsibilities and provide samples of required commissioning documentation (based on the most recent industry-accepted format) to the Designer for integration into the project specifications.

b. Develop the Commissioning Plan, detailing commissioning team organization, schedule, training and documentation requirements. Include all related testing, verification and quality control procedures.

c. Establish the schedule for all commissioning activities, including periodic design reviews. Insure that commissioning activities do not interfere with any phase of the project.

d. Review the design calculations and performance criteria for the project, identifying operation and maintenance problems. Provide written comments and a checklist of required actions to be completed by the Designer prior to phase approval and recommend alternatives where appropriate.

e. Check and confirm that the BOD includes all of the elements defined in the OPR at the end of the Design Phase.

3. In the Construction Phase the Commissioning Authority shall complete the following tasks:

a. Update the Commissioning Plan to reflect any changes in the BOD.

018100 - 3

b. Coordinate the commissioning process with the Project Team through project planning and scheduled meetings.

c. Review contractor submittals in collaboration with the Project Team for conformance to project specifications and operation and maintenance requirements and report findings.

d. Observe and document system verification checks.

e. Observe and document equipment and system start-ups.

f. Document testing and balancing work.

4. In the Acceptance Phase the Commissioning Authority shall complete the following tasks:

a. Monitor and document functional performance tests on all building systems in collaboration with the Project Team.

b. Review O&M documentation and develop O&M training plans and videos. Ensure that the Owner’s staff is able to operate and maintain all building systems.

c. Review all as-built documents and warranty information in collaboration with the

Project Team. Submit warranty information and preventive maintenance schedules for all building systems in a comprehensive, five-year preventive maintenance plan. The format for this submittal shall be approved jointly by DCAMM and the Owner. This submittal shall also include list(s) of recommended spare parts, bench stock and special tools/equipment required for the first year of building operation.

d. Convene and chair a comprehensive final debriefing with the entire Project Team (including the owner’s maintenance staff) to coordinate correction of any required re-testing and identification of any training deficiencies prior to building turnover.

e. In collaboration with the Designer, Contractor(s) and General Contractor populate all operational information, including equipment data, for each building system in the digital format specified by DCAMM.

5. In the Post-Acceptance Phase the Commissioning Authority shall complete the following tasks:

a. Coordinate with the project team to ensure that any required “off-season” tests are completed.

b. Ensure that any required changes are provided as written updates in the project documentation.

c. Confirm that all equipment continues to perform as designed and alert the Owner to any warranty claims by providing a review of all system warranties prior to their one-year expiration date.

d. Document the estimated savings generated by the commissioning process through specific examples of avoided costs collected during all project phases. The required format will be provided by DCAMM. Compare the actual tested performance of the building’s completed systems with established standards.

e. Implement a measurement and verification (M&V) plan consistent with Option D:

Energy Conservation Measure Isolation as specified in the International Performance Measurement & Verification Protocol (IPMVP) Volume III:

Concepts and Options for Determining Energy Savings in New Construction, April, 2003. The M&V period must cover at least one year of post-construction occupancy.

6. The commissioning process does not eliminate or reduce the responsibility of the system designers and installing contractors to provide a finished and fully functioning product.

B. Commissioning Authority: The Commissioning Authority directs and approves the commissioning work.

018100 - 4

C. Responsibility of Disciplines: The parties listed below are part of the commissioning team and will be required to participate in the commissioning process. The responsibilities relative to commissioning for each of these parties is defined in this section.

1. Designer

2. Engineer

3. Owner

4. Commissioning Authority

5. General Contractor

6. Mechanical/Electrical Coordinator

7. Test Technician

8. Mechanical Contractor

9. Plumbing Contractor

10. Fire Protection Contractor

11. Electrical Contractor

12. Controls Contractor

13. Testing, Adjusting and Balancing Contractor

14. All Subcontractors and equipment suppliers/manufacturers that are associated with the above disciplines.

D. Abbreviations:

1. The following are common abbreviations used in the Specifications and in the commissioning process. Definitions are found in Section 1.11.

A/E- Designer and Design Engineers EC- Electrical Contractor CA- Commissioning Authority FM- Facility Manager CC Controls Contractor FT- Functional Performance Test MC- Mechanical Contractor GC- General Contractor (prime) PC- Prefunctional Checklist Subs- Subcontractors Cx- Commissioning TAB- Test and Balance Contractor MEC Mechanical/Electrical Coordinator TT Test Technician

1.3 COORDINATION

A. Commissioning Team. The members of the commissioning team consist of the Commissioning authority (CA), Facility Manager (FM), the designated representative of the General Contractor (GC), the Designer and design engineers (A/E), the Mechanical Contractor (MC), the Electrical Contractor (EC), the TAB representative, the Controls Contractor (CC), Mechanical/Electrical Coordinator (MEC), Test Technician (TT) and any other installing Subcontractors or suppliers of equipment. The Owner’s building or plant operator/engineer is also a member of the commissioning team.

B. Management: The CA is hired by DCAMM, directs and coordinates all commissioning activities and reports to the Owner. All Project Team members work together to fulfill their contracted responsibilities and meet the objectives of the Contract Documents.

C. Scheduling: The CA will work with the General Contractor according to established protocols to schedule commissioning activities. The CA will provide sufficient notice to the General Contractor and/or MEC for scheduling commissioning activities. The General Contractor will

018100 - 5 integrate all commissioning activities into the master schedule. All parties will address scheduling problems and make necessary notifications in a timely manner in order to expedite the commissioning process.

1. The CA will provide the initial schedule of primary commissioning events at the commissioning scoping meeting. As construction progresses more detailed schedules are developed by the CA and are incorporated into the project schedule by the General Contractor.

1.4 COMMISSIONING PROCESS

A. Commissioning Process. The following narrative provides a brief overview of the typical commissioning tasks during construction and the general order in which they occur.

1. Commissioning during construction begins with a scoping meeting conducted by the CA wherein the commissioning process is reviewed with the commissioning team members.

2. Additional meetings scheduled by the CA will be required throughout construction, to plan, scope, coordinate, and schedule future activities and resolve problems.

3. Equipment documentation is submitted to the Engineer during normal submittals, including detailed start-up procedures. The CA will review and comment on applicable items.

4. The Subcontractors develop startup plans and startup documentation formats and provide to the CA. The CA uses this information to supplement prefunctional checklists to be completed, during the startup process.

5. The Subcontractors execute and document the prefunctional checklists and perform startup and initial checkout. The CA documents that the checklists and startup were completed according to the approved plans. This may include the CA witnessing start-up and prefunctional tests of selected equipment.

6. The CA develops specific equipment and system Functional Performance Test procedures. The Subcontractors review the procedures.

7. The procedures are executed by the Subcontractors, and witnessed and documented by the CA. The Owner’s FM is also invited to witness testing.

8. Items of non-compliance in material, installation, or setup are corrected at the Sub’s expense and the system in question is retested.

9. The CA reviews the O&M documentation for completeness.

10. The CA approves the training plan and audits training.

11. The CA assembles all project documentation into Systems Manuals

12. Deferred testing is conducted, as specified or required.

1.5 RELATED WORK

A. All of the following sections apply to the Work of this section. This list does not limit the work that may be required by the General Contractor under additional specification section for the completion of the Commissioning process.

1. Section 017700 - CONTRACT CLOSEOUT

2. Section 013100 - PROJECT MANAGEMENT AND COORDINATION

3. Section 210001 - FIRE PROTECTION

4. Section 220001 - PLUMBING

018100 - 6

5. Section 230001 - HEATING, VENTILATING AND AIR CONDITIONING

6. Section 260001 - ELECTRICAL WORK

1.6 COMMISSIONING COMPLETION

A. Prerequisites to functional completion

1. All TAB work and commissioning activities must be complete prior to Functional Completion, unless approved in writing by the CA. Exceptions to this are the planned control system training performed after occupancy and any required seasonal or approved deferred testing. This requirement covers all systems, but is not limited to:

a. Completed and signed start-up and prefunctional checklist documentation

b. Requested trend log data

c. Submission of final approved TAB report

d. Completion of all functional testing

e. Required training of Owner maintenance personnel

f. Submission of the approved O&M manuals

g. All identified deficiencies have been corrected or are approved by the DCAMM

Project Manager to be accepted from this milestone.

B. The General Contractor will determine the date of Functional Completion after reviewing the Commissioning Agent’s recommendation for Functional Completion.

C. Commissioning activities are non-compensable and cannot be a cause for delay claims.

1.7 SYSTEMS TO BE COMMISSIONED

A. The following systems will be commissioned in this project, but this list does not limit the testing that may be required to achieve LEED certification of the project by the United States Green Building Council. Testing requirements are part of this section. Each member of the commissioning team shall review all test procedures in this section to determine if his/her presence is required for each test (for example, certain tests of mechanical equipment may require the support of electrical personnel and vice versa)

Equipment and System

Functional Test Requirements Specified In:

Plumbing System

Plumbing Water System 3.10

HVAC System

Hot Water Heating System (Boilers, Pumps, Distribution

3.11

Terminal Units (FCU, FPT, VAV, CUH, UH) 3.12 Packaged DX Split System Air Conditioning or Heat Pump

3.13

Exhaust Fans 3.14

018100 - 7

Equipment and System

Functional Test Requirements Specified In:

Building Automation System (BAS) 3.15 Test and Balance Work (TAB) 3.16 Air Handling Units (Recirculating and 100% O.A.) 3.17

Electrical System

Short Circuit Trip 3.18 Lighting Control System 3.19

1.8 RESPONSIBILITIES

A. The responsibilities of all parties in the commissioning process are provided in this section.

B. All Parties:

1. Attend commissioning scoping meeting and additional meetings, as necessary.

C. Designer (of A/E):

1. Construction Phase

a. Attend the commissioning scoping meeting and selected commissioning team meetings.

b. Perform normal submittal review, construction observation, as-built drawing preparation, O&M manual preparation, etc., as contracted.

c. Provide any design narrative documentation requested by the CA.

d. Coordinate resolution of system deficiencies identified during commissioning, according to the contract documents.

e. Prepare and submit design intent documentation clarifications for inclusion in the

O&M manuals. Review and approve the O&M manuals.

2. Post Construction Phase

a. Coordinate resolution of design non-conformance and design deficiencies identified during warranty-period commissioning.

D. Design Engineer:

1. Construction Phase

a. Perform normal submittal review, construction observation, as-built drawing preparation, etc., as contracted. One site observation should be completed just prior to system startup.

b. Provide any design narrative and sequences documentation requested by the CA.

The designers shall assist (along with the contractors) in clarifying the operation and control of commissioned equipment in areas where the specifications, control drawings or equipment documentation are not sufficient for writing detailed testing procedures.

c. Participate in the resolution of system deficiencies identified during commissioning, according to the contract documents.

018100 - 8

E. Commissioning Authority (CA): The CA is not responsible…