SDN1501 Pre-Proposal Presentation 6-22-16.ppt

PPT presentation 500 KB Posted

Attached to
SDN1501E ES1 Norfolk Sheriff Office Energy Project Dedham
Solicitation number
BD-16-1019-DCP08-ENR01-00000008759
Issued by
Norfolk County, Massachusetts

About this file

This document is a pre-proposal presentation for an Energy Design Build Request for Proposals (RFP) issued by the Massachusetts Division of Capital Asset Management and Maintenance (DCAMM) Energy Efficiency & Sustainable Buildings Group for the Norfolk Sheriff's Office in Dedham, Massachusetts. The RFP seeks proposals for the design, equipment purchase, installation, commissioning, measurement and verification, warranty services, and maintenance of various energy conservation measures (ECMs) including LED lighting upgrades, water controls, HVAC control upgrades, VFD upgrades, ozone laundry system, kitchen hood controls, solar photovoltaics (alternative), and combined heat and power. The RFP was posted on June 8, 2016, and proposals are due on August 10, 2016 at 2 PM. A pre-proposal conference and site visits are scheduled for June 22, July 13, and July 19, 2016. The target selection date is September 16, 2016.

The project is funded through the Commonwealth's Clean Energy Investment Program based on energy savings. M/WBE participation is required, and the total contract value may not exceed the single or aggregate project limit outlined in the RFP. Pricing will be evaluated based on 50 points for non-price criteria and 50 points for price criteria. Payments will be made in progress payments up to 85%, with 95% upon final ECM acceptance and 100% upon completion of all installation services.

View the file

Other files

File Type Posted
SDN1501E ES1 Forms BCD.xlsx XLSX spreadsheet
AEP Audit Template SDN1501E-ES1.xlsm XLSM spreadsheet
SDN1501E FormE.xlsx XLSX spreadsheet
N.C.S.O. CORI Security Clearance Request Form.pdf PDF
SDN1501E-ES1 RFP Final~1.pdf PDF
SDN1501E ES1 Main HOC Toilet Locations.pdf PDF
SDN1501E-ES1 3rd Site Visit Sign In 7-19-16.pdf PDF
SDN1501E ES1 Conditions Assessment.pdf PDF
SMRT Chiller EMS Study-Pg 57-61.pdf PDF
SMRT Chiller EMS Study-Pg 51-56.pdf PDF
SDN1501E ES1 Proposals Received.pdf PDF
SDN1501E-ES1 Pre-Proposal Sign-In.pdf PDF
SDN1501E ES1 BOD.pdf PDF
SDN1501E-ES1 Addnedum 1.pdf PDF
SDN1501 Preproposal AGENDA 6-22-16.pdf PDF
SDN1501E FormE - Rev 1.xlsx XLSX spreadsheet
SMRT Chiller EMS Study-Pg 48-50.pdf PDF
SDN1501E ES1_ListFinalQ-A.pdf PDF
SDN1501E ES1 BOD Plumb 0-3.pdf PDF
SDN1501E ES1 ASHRAE Level I and II Report.pdf PDF
SDN1501E ES1 Forms BCD - Rev 1.xlsx XLSX spreadsheet
SDN1501E ES1 DCAMM File Release Form.pdf PDF
SDN1501E ES1 PV Addenda to BOD.pdf PDF
SDN1501E-ES1 Addendum 3.pdf PDF
SDN1501E ES1 BOD Plumb-4-7.pdf PDF
SDN1501E ES1 BOD body.pdf PDF
SDN1501E-ES1 2nd Site Visit Sign in 7-13-16.pdf PDF
SMRT Chiller EMS Study-Pg 43-47.pdf PDF
SMRT Chiller EMS Study-Body.pdf PDF
SMRT Chiller Draft CDs.pdf PDF
SDN1501E-EC1 - ESA for RFP Final.pdf PDF
SDN1501E ES1 Accessible Toilet Room Report.pdf PDF
SDO Certified MWBE Subcontractors.xlsx XLSX spreadsheet
SDN1501E ES1 PV Array Layout Plan.pdf PDF
SDN1501E-ES1 Addendum 2.pdf PDF
SDN1501E ES1 Prevailing Wage Rates.pdf PDF
SDN1501Pre-proposal Minutes.pdf PDF
SDN1501E ES1 BOD Mech and Elec.pdf PDF
SDN1501E ES1 BOD Plumb-8-12.pdf PDF
SDN1501E ES1 Building Facility Description.pdf PDF
SMRT Chiller EMS Study.pdf PDF
SDN1501E-ES1 Form F.docx DOCX document
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCAMM Energy Efficiency & Sustainable Buildings Group

Norfolk Sheriff’s Office, Dedham Energy Design Build Project

SDN1501E-ES1

Pre-proposal meeting June 22, 2016

The Facility – Norfolk Sheriff’s Office - Dedham

Overview of Facility
Protocol for Site Visits
Key Contacts: Mike Reinhardt (michael.reinhardt@state.ma.us) and
Stephen Randall (srandall@norfolksheriffma.org)

Request for Proposals (RFP)

Posted on www.commbuys.com
Communication – goes to Mike Reinhardt. Written questions must be submitted to commbuys.com
MGL Ch. 25A, 11C – Multiple ECMs, Design Build, Not low bid
DCAMM certified – prime contractor
Project Funding – CEIP based on energy savings

Procurement Schedule

RFP IssuedJune 8, 2016
Pre-Proposal ConferenceJune 22, 2016 @ 10:00
Site VisitJune 22, 2016
July 13 & July 19, 2016
@ 10:00 AM
Written Questions DueJuly 27, 2016
Final Deadline for Addenda to RFPAugust 3, 2016
Proposals DueAugust 10, 2016, 2 PM
Target InterviewsAugust 31, 2016
Target Selection DateSeptember 16, 2016

Minimum Threshold Requirements

Proposal received by Proposal Due Date and time
Current Certificate of Eligibility
2 copies of Update Statement
Forms A-F completed.
Total Contract Value may not exceed the Single or Aggregate Project Limit - as outlined in Attachment G.

RFP Attachments

Attachment A – Submission requirements
Attachment B – Scope of Services, ECM Package
Attachment C – Facility Profile
Attachment D – M/WBE participation is required
Attachment E – Energy Services Agreement (ESA)
Attachment F – Payment Terms
Attachment G – Contractor Certification
Attachment H – Evaluation Criteria
Attachment I – Security Clearance Request Form

Attachment A

Checklist – double check all parts are in your Proposal
Form A- Cover Letter / signature of Principal Person
Form B / Summary Form B- Total Contract Value
Form C – Energy Savings by Measure
Form D – Cashflow (B/C/D are the “Financials”)
Form E / multiple worksheet tabs – please double check that your revised Form E matches with responses to Attachment A, Part III.
FORM F – Questions. Answer clearly and completely. Some Proposers have not provided complete responses, making the evaluation problematic.

Attachment B - Scope of Services

Part I - Scope of Services – Energy Audit, MAAB Accessibility Report
Part II – BOD – 30% SD and Performance Specifications
Part III – Data Acquisition – CHP, PV

The Commonwealth is soliciting proposals for design, equipment purchase, installation, commissioning, Measurement & Verification (M&V), warranty services, and maintenance.

Attachment C Facility Profile

Building Facility Description
Existing Condition Assessment
Ongoing Projects (Chiller/EMS upgrades)
Site Audit Template
Plans CD

Attachment E – Energy Services Agreement

Review all schedules in the construction contract.
Table B-2 Permitted Work Hours. Review to develop schedule and costs for your proposal.
Form E Tables from proposal entered into ESA.

Program Procedures and Requirements

Attachment D – M/WBE participation is required
Attachment F – Payment Terms
85% Progress Payments
95% Final ECM Acceptance
100% Completion of all Installation Services
Attachment G – Contractor Certification
Attachment H – Evaluation Criteria
Non-Price Criteria (50 points)
Price Criteria (50 points)
Attachment I – Security Clearance Request Form

1. Facility Tour

2. Meeting Minutes, Q&A, Addenda posted to Commbuys.com. REMINDER: all written questions must be officially submitted to www.commbuys.com

Michael Reinhardt, Energy Project Manager

(857) 204-1234 michael.reinhardt@state.ma.us

Jim Freeley, Program Manager

(857) 204-1239 james.a.freeley@state.ma.us

Next Steps