About this file

This document is a comprehensive set of fire protection system design and construction specifications for the renovation of Building 3 (EHRM Admin and Training) at the VA Dorn Veterans Affairs Medical Center in Columbia, South Carolina. The project involves modifications to the existing wet-pipe fire sprinkler system, including demolition of outdated components and installation of new fire suppression infrastructure to support renovated spaces and new mechanical equipment.

The specifications establish detailed requirements for system design, installation, testing, and commissioning. The fire protection contractor must design a complete system in accordance with NFPA 13 (2022 Edition), NFPA 25, and the VA Fire Protection Design Manual, with hydraulic calculations based on current fire hydrant flow test data (dated 04/10/2024 showing static pressure of 101 PSI). The system utilizes the existing diesel fire pump (Patterson model 6X5X17, 1000 GPM at 1750 RPM) and incorporates design densities of 0.10 GPM/sq.ft. for light hazard areas and 0.15-0.20 GPM/sq.ft. for ordinary hazard areas, with maximum sprinkler head coverage of 130-225 sq.ft. depending on occupancy classification. All shop drawings and calculations must be sealed by a licensed professional engineer registered in South Carolina or a NICET Level III/IV sprinkler designer. The contractor bears responsibility for coordination with other trades, all cutting and patching, through-penetration firestop assemblies meeting UL standards, pipe support and seismic restraints per VA Seismic Design Requirements, and comprehensive testing with final certification of approval from the VA fire official and engineer of record prior to project acceptance. Interim fire protection measures including fire watches, temporary heat detectors interfaced with the fire alarm system, and fire extinguishers are required during system impairments exceeding four hours, with minimum one-week advance notice to the VA Contracting Officer's Representative.

View the file

Other files

File Type Posted
S06 - Amendment 0006-Att 2-Tech Questions-Columbia.pdf PDF
S06-Amendment 0006-Att 1-SF30-Columbia.pdf PDF
S06 - Amendment 0005-Att 1-Tech Questions-Columbia.pdf PDF
S06-Amendment 0005-Att 2-SF30-Columbia.pdf PDF
S06 -Amendment 0004-Att 4- Tech Questions-Columbia.pdf PDF
S06-Amendment 0004-Att 1- BLDG 3 EHRM - DIV 23 Specs Combined.pdf PDF
S06-Amendment 0004-Att 3-HL100.pdf PDF
S06-Amendment 0004-Att 2 - Lim. AB LBP Report - Bld3 EHRM.pdf PDF
S06-Amendment 0004-Att 5- SF30-Columbia.pdf PDF
S06-36C77626R0032-Amendment 0003.pdf PDF
S06-36C77626R0032 Amendment 0002.pdf PDF
S04- Pre Bid Conference - Columbia.pptx PPTX presentation
S06-36C77626R0032 0001.pdf PDF
S06-Site Visit Sign-In Sheet 03062026-Columbia.pdf PDF
S02-RFP Attachment 13-Specifications-Columbia_Part3.pdf PDF
S02-RFP Attachment 11-Specifications-Columbia_Part1.pdf PDF
S02-RFP Attachment 9- Mechanical Drawings-COL.pdf PDF
S02-RFP Attachment 6- Electrical Drawings-COL.pdf PDF
S02 - RFP Attachment 3 - Limitations on Subcontracting - Columbia.docx DOCX document
S02-RFP Attachment 1-Wage Rates-Col.txt TXT text file
S06-RFP Attachment 17-Spce Update for 01321615-2025-12.pdf PDF
S02-RFP Attachment 15-Specifications-Columbia_Part5.pdf PDF
S02-RFP Attachment 5- ARCH Drawings-COL.pdf PDF
S02-RFP Attachment 4-Campus Map-Columbia.pdf PDF
S02-36C77626R0032-Columbia.pdf PDF
S02-RFP Attachment 12-Specifications-Columbia_Part2.pdf PDF
S02-RFP Attachment 10- Plumbing Drawings-COL.pdf PDF
S02-RFP Attachment 16-Final SOW-Col.pdf PDF
S02-RFP Attachment 14-Specifications-Columbia_Part4.pdf PDF
S02-RFP Attachment 7- Fire Alarm Drawings-COL.pdf PDF
S02-RFP Attachment 2 Site Visit Information-Columbia.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRE PROTECTION GENERAL NOTES

1. THE ADDITIONS TO THE EXISTING NEW SPRINKLER SYSTEM SHALL BE SIZED IN ACCORDANCE WITH NFPA

13 AND SHALL BE HYDRAULICALLY CALCULATED TO MEET THE REQUIREMENTS OF NFPA 13 AND

APPROVED BY THE VA FIRE SAFETY OFFICIAL HAVING JURISDICTION, THE ENGINEER, AND THE ARCHITECT. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING FLOW TEST DATA TO PERFORM

AS A BASIS OF THEIR CALCULATIONS.

2. THE SYSTEM SHALL BE DESIGNED AND BUILT IN A WORKMANLIKE MANNER, IN ACCORDANCE WITH DETAILED DRAWINGS TO BE SUBMITTED FOR APPROVAL. THE WORK SHALL INCLUDE ALL COMPONENTS

REQUIRED TO PROVIDE A COMPLETE SYSTEM.

3. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE A SET OF SHOP DRAWINGS THAT INCLUDE ALL PIPE SIZES, ELEVATIONS, HEAD LOCATIONS, DIMENSIONS, VALVES, INSPECTOR TESTS, FLOW SWITCHES, TAMPER SWITCHES, ETC.

4. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE SPRINKLER LAYOUT INCLUDING LOCATION OF

PENDANT HEADS FOR ALL LOCATION IN THIS SCOPE OF WORK.

5. THE SHOP DRAWINGS AND CALCULATIONS IF REQUIRED, SHALL BE SUBMITTED TO VA'S FIRE OFFICIAL AND VA ’ S ENGINEER AND THESE CALCULATIONS AND DRAWINGS SHALL BE SUBMITTED TO ALL

AUTHORITIES HAVING JURISDICTIONS.

6. SPRINKLER HEADS AND ASSOCIATED MAIN/BRANCH PIPING SHALL BE PROVIDED AND LOCATED IN

ACCORDANCE WITH NFPA 13 AND THE VA FIRE PROTECTION DESIGN MANUAL.

7. THE FIRE PROTECTION CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS AT THE PROJECT SITE.

8. SPRINKLER PIPING SHOULD BE ROUTED AS HIGH AS POSSIBLE WHILE STILL COORDINATING WITH OTHER

TRADES. ELEVATION OF SPRINKLER PIPING AND HEAD MUST BE DETERMINED BY PROPOSED OR

EXISTING CEILING HEIGHTS.

9. ALL MATERIAL AND ITS INSTALLATION SHALL BE IN COMPLETE COMPLIANCE WITH ALL APPLICABLE SECTIONS OF THE LATEST EDITION OF NFPA. AND FACTORY MUTUAL GUIDELINES. THE FIRE PROTECTION CONTRACTOR SHALL BE REQUIRED TO COMPLY WITH ALL SPECIAL CONDITIONS SET FORTH BY THE VA

FIRE MARSHAL , VA FIRE PROTECTION DESIGN MANUAL AND THE PROJECT SPECIFICATIONS.

10. THE FIRE PROTECTION CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL AND EQUIPMENT; AND, PERFORM ALL OPERATIONS NECESSARY FOR THE INSTALLATION OF A COMPLETE FIRE PROTECTION SYSTEM THAT IS READY FOR USE WITHIN THE INTENT OF AND AS INDICATED ON THE DRAWINGS, SPECIFICATIONS AND AS HEREIN SPECIFIED.

11. PROVIDE CUTTING AND PATCHING OF BUILDING AS REQUIRED TO INSTALL NEW WORK.

12. SMALL ITEMS NOT SHOWN OR SPECIFIED, BUT OBVIOUSLY REQUIRED BY GOOD GENERAL PRACTICE TO

COMPLETE THE WORK SHALL BE FURNISHED AND INSTALLED THE SAME AS IF BOTH SHOWN AND

SPECIFIED.

13. BY SUBMITTING A PROPOSAL FOR THIS WORK, THE CONTRACTOR WILL BE HELD TO HAVE EXAMINED THE SITE AND SATISFIED THEMSELVES AS TO EXISTING CONDITIONS UNDER WHICH THEY WILL BE OBLIGED

TO OPERATE OR THAT WILL IN ANY MANNER AFFECT THEIR WORK UNDER THIS CONTRACT. NO

ALLOWANCES SHALL BE MADE SUBSEQUENTLY IN THIS CONTRACT IN BEHALF OF CONTRACTOR OF ANY

ERROR OR NEGLIGENCE ON THEIR PART

14. FIRE PROTECTION CONTRACTOR SHALL MAKE CONNECTION INTO THE EXISTING WET-PIPE FIRE

SPRINKLER SERVICE FOR THIS SCOPE OF WORK.

15. THE FIRE PROTECTION CONTRACTOR SHALL SCHEDULE WITH THE VA COR ALL TIE-INS TO EXISTING

SYSTEMS AND PERFORM REQUIRED SHUTDOWN AND RE-INITIALIZATION OF THE EXISTING FIRE

SPRINKLER SYSTEM; THESE SERVICES WILL INCLUDE DRAIN AND REFILL OF THE FIRE SPRINKLER

SYSTEMS IN THE AFFECTED AREAS OF THIS PROJECT WORK SCOPE.

16. ALL FIRE PROTECTION WORK SHALL BE MADE IN ACCORDANCE WITH RULES AND REGULATIONS OF VA FIRE PROTECTION DESIGN MANUAL, PROJECT SPECIFICATIONS, NFPA 13 AND NFPA 25. THE ENTIRE FIRE PROTECTION SYSTEM FOR THE WORK SCOPE SHOWN ON THESE DESIGN DRAWINGS SHALL BE MADE BY THIS CONTRACTOR IN THE PRESENCE OF AN INSPECTOR FROM THE VA FIRE OFFICIAL, VA COR AND THE VA'S ENGINEER. THE FIRE PROTECTION SYSTEM SHALL BE TESTED AS REQUIRED BY NFPA 13.

17. THROUGH PENETRATION ASSEMBLIES SHALL BE PROVIDED AT EACH OPENING WHERE EXPOSED SPRINKLER PIPING PASS THROUGH RATED WALLS, FLOORS AND PARTITIONS. ALL PIPING PENETRATIONS MUST BE SEALED IN ACCORDANCE WITH “ UL ” LISTING SEALING METHOD AND/OR AS DETAILED IN THESE

CONTRACT DRAWINGS OR SPECIFICATIONS.

18. ALL APPLIANCES AND APPURTENANCES SHALL BEAR LABEL OF UL/FM APPROVED AND LABELED FOR ITS

INTENDED USE.

19. ALL MATERIALS AND EQUIPMENT SHALL BE INSTALLED AND COMPLETED IN A FIRST-CLASS

WORKMANLIKE MANNER AND IN ACCORDANCE WITH THE BEST MODERN METHODS AND PRACTICES.

ANY MATERIALS WHICH SHALL NOT PRESENT AN ORDERLY AND REASONABLY NEAT AND/OR

WORKMANLIKE APPEARANCE SHALL BE REMOVED AND REPLACED WHEN SO DIRECTED BY THE VA COR, VA FIRE OFFICIAL, THE ARCHITECT OR ENGINEER OF RECORD. THE REMOVAL AND REPLACEMENT OF THIS WORK SHALL BE DONE WHEN DIRECTED IN WRITING BY THE VA COR, AT THE CONTRACTOR ’ S

EXPENSE.

20. SUPPLY ALL SPRINKLER EQUIPMENT ACCESSORIES AS REQUIRED.

21. ALL HANGERS SHALL BE FASTENED BY MEANS OF BEAM CLAMPS, CONCRETE INSERTS OR OTHER

APPROVED DEVICES INSTALLED BY THIS CONTRACTOR.

22. SPRINKLER HEAD RATINGS, SPRAY TYPE, AND FINISH SHALL BE AS SPECIFIED ON PROJECT PLANS.

WHERE NOT SPECIFICALLY IDENTIFIED ON PLANS, SPRINKLER HEADS SHALL QUICK RESPONSE TYPE UPRIGHT PENDANT WITH PAINTED COVER PLATE OR AS REQUIRED BY THE VA COR. REGULAR PENDANT HEADS IN FINISHED SPACES SHALL BE CHROME PLATED WITH CHROME PLATED CEILING PLATES UNLESS

OTHERWISE NOTED. NEW HEADS SHALL MATCH EXISTING.

23. THE FIRE PROTECTION CONTRACTOR WILL BE REQUIRED TO COORDINATE ACCEPTANCE FOR VARIATION OF EQUIPMENT LOCATIONS AND EQUIPMENT CONFIGURATIONS WITH THE FIRE MARSHAL, THE LOCAL

JURISDICTION, THE OWNER, AND THE GENERAL CONTRACTOR.

24. THE FIRE PROTECTION CONTRACTOR IS RESPONSIBLE FOR COORDINATING CHANGES IN ELECTRICAL

REQUIREMENTS WITH THE ELECTRICAL CONTRACTOR.

25. VARIATION FROM SPECIFIED PHYSICAL EQUIPMENT APPEARANCE WILL NEED TO BE APPROVED

THROUGH THE ARCHITECT.

26. SYSTEM PIPING WILL BE SUPPORTED AND BRACED WITH HANGERS AND LISTED EARTHQUAKE BRACE ASSEMBLIES IN ACCORDANCE WITH THE VA SEISMIC DESIGN REQUIREMENTS MANUAL AND NFPA 13.

27. ONE SET OF STAMPED, APPROVED DRAWINGS SHALL BE ON SITE AT ALL TIMES AND MADE AVAILABLE TO

THE INSPECTOR AND/OR ARCHITECT/OWNER UPON DEMAND.

28. FIRE PROTECTION SYSTEMS SHALL BE INSTALLED BY A CONTRACTOR LICENSED TO PERFORM SUCH

WORK IN THE PROJECT JURISDICTION.

29. AVOID DAMAGING EXISTING SURFACES AND EQUIPMENT AND ASSOCIATED MATERIALS FROM THE SITE.

REPAIR ANY DAMAGE CAUSED DURING WORK AT NO EXTRA COST TO THE VA.

30. REPAIR FIRE AND SMOKE RATED PARTITIONS SURROUNDING FIRE ALARM WORK AS SPECIFIED. REFER

TO ARCHITECTURE PLANS FOR LOCATIONS OF SMOKE AND FIRE PARTITIONS.

31. THREADED BUSHING SHALL NOT BE USED.

32. ANY SPRINKLER REMOVED FROM SERVICE FOR ANY REASON (E.G., REMOVED, RELOCATED, ETC.) SHALL BE REPLACED WITH A NEW SPRINKLER HEAD IN ACCORDANCE WITH NFPA 25, SECTION 5.4.1.1.

33. NEW ARMOVERS SHALL BE PROVIDED TO EITHER RELOCATED OR NEW SPRINKLERS AS REQUIRED BY

NFPA 13.

34. SPRINKLER SYSTEM SHOP DRAWINGS SHALL INCLUDE ALL MATERIALS REQUIRED BY NFPA 13 CHAPTER 27.

35. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CUTTING AND PATCHING OF WALLS AND CEILING AS

MAY BE REQUIRED FOR THE INSTALLATION OF THE NEW FIRE SUPPRESSION SYSTEM.

36. INTERRUPTIONS IN OPERATION OF THE FIRE SUPPRESSION SYSTEM MUST BE SCHEDULED WITH THE VA COR AT LEAST ONE(1) WEEK IN ADVANCE; WITH PROPER NOTICE PROVIDED TO THE EMERGENCY

RESPONSE TEAMS - BOTH INSIDE AND OUTSIDE OF THE VA DORN CAMPUS.

37. WHEN WORK IS BEING PERFORMED IN AREAS THAT MUST CONTINUE OPERATION, CONTRACTOR SHALL KEEP THE AREAS CLEAN AND CLEAR OF OBSTRUCTIONS, AS MUCH AS POSSIBLE, PROVIDE WARNING

SIGNS AS NECESSARY FOR PROTECTION OF OCCUPANTS FROM ASSOCIATED RISKS. REMOVE ALL

DEBRIS AS WORK PROGRESSES.

38. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE VA COR WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE VA COR, VA FIRE OFFICIAL AND VA'S

ENGINEER OF RECORD WILL BE REQUIRED PRIOR TO FINAL ACCEPTANCE OF THE PROJECT.

39. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE

SPRINKLER SYSTEM PER NFPA 13 AND VA FIRE PROTECTION DESIGN MANUAL REQUIREMENTS.

40. LIGHT FIXTURES AND HVAC DIFFUSERS TAKE SPACE PREFERENCE, ADD ADDITIONAL SPRINKLER HEADS AS REQUIRED TO MEET "COVERAGE REQUIREMENTS" OF NFPA 13 AND THE VA FIRE PROTECTION DESIGN

MANUAL

41. COORDINATE PLACEMENT OF SPRINKLER HEADS WITH ALL MECHANICAL DUCTS, DIFFUSERS AND

ELECTRICAL LIGHT FIXTURES.

42. THE FIRE PROTECTION CONTRACTOR SHALL INDICATE ON THEIR SHOP DRAWINGS; CEILING TILE

LOCATIONS WITH ALL CEILING MOUNTED FIRE PROTECTION DEVICES.

43. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH A NON-SHRINKING

GROUT OR CAULKING MATERIAL.

44. THE FIRE PROTECTION SYSTEM / AREA OF PROTECTION INDICATED ON THE PLANS IS FOR COORDINATION AND BIDDING PURPOSES ONLY. THE FIRE PROTECTION CONTRACTOR SHALL BE RESPONSIBLE FOR THE

COMPLETE DESIGN

45. ALL PIPING SYSTEMS THAT ARE NOT INTENDED TO BE REUSED SHALL BE REMOVED AND PIPES SHALL BE

CAPPED AS CLOSE TO MAINS AS POSSIBLE.

46. IT IS THE INTENTION OF THE SPECIFICATION AND DRAWINGS TO CALL FOR A COMPLETE AND FUNCTIONAL SYSTEM, INSTALLED AS PER THE APPLICABLE CODES WITH ALL FINISHED WORK TESTED AND READY FOR

OPERATION.

47. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE VA COR, VA FIRE OFFICIAL, VA'S ENGINEER OF RECORD, FIRE ALARM CONTRACTOR, AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN

OR INTERRUPTION OF SERVICE.

48. ALL MATERIALS, PIPING, FITTINGS, VALVES, AND APPLIANCES HEREINAFTER SPECIFIED AND THOSE WHICH ARE ESSENTIAL BUT HAVE NOT BEEN SPECIFIED SHALL BE NEW AND OF THE HIGHEST GRADE AND

QUALITY, FREE FROM DEFECTS AND SUCH AS BREAKS, FLAWS, AND IMPERFECTIONS.

49. CORE DRILL MASONRY WALLS FOR NEW PIPING. SEAL PENETRATIONS AS NECESSARY TO MAINTAIN

INTEGRITY OF EXISTING WALLS.

50. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CUTTING AND PATCHING OF WALLS AND CEILING AS MAY

BE REQUIRED FOR THE INSTALLATION OF THE NEW FIRE SUPPRESSION SYSTEM.

51. ALL APPLIANCES AND APPURTENANCES SHALL BEAR LABEL OF UL LISTED, / FM APPROVED AND LABELED

FOR ITS INTENDED USE.

52. LONG RUNS OF PIPE SHALL BE PROVIDED WITH A SUITABLE MEANS TO PERMIT FREE MOVEMENT RESULTING FROM EXPANSION AND CONTRACTION OF PIPE. REDUCTION IN PIPE SIZES SHALL BE MADE

WITH ONE-PIECE REDUCTION FITTINGS.

53. THE FIRE PROTECTION CONTRACTOR IS TO MAINTAIN A SET OF UP TO DATE CONSTRUCTION DOCUMENTS AVAILABLE AT THE PROJECT SITE AT ALL TIMES DURING CONSTRUCTION. THE FIRE PROTECTION CONTRACTOR IS TO INSTRUCT THE VA'S REPRESENTATIVE(S) IN THE OPERATION AND MAINTENANCE REQUIREMENTS OF THE COMPLETED BUILDING FIRE PROTECTION SYSTEM AT A TIME AGREED ON BY THE OWNER. THE OWNER’S REPRESENTATIVE(S) SHALL BE PROVIDED WITH AN UP TO DATE CONSTRUCTION

DOCUMENTS AND A COPY OF NFPA 25 PRIOR TO INSTRUCTION BY THIS CONTRACTOR.

54. COORDINATE WITH OTHER WORK, INCLUDING HVAC, PLUMBING PIPING, ELECTRICAL AS NECESSARY TO INTERFACE COMPONENTS OF FIRE SPRINKLER PIPING PROPERLY WITH OTHER WORK. SYSTEM PIPING WILL BE SUPPORTED AND BRACED WITH HANGERS AND LISTED EARTHQUAKE BRACE ASSEMBLIES IN ACCORDANCE WITH THE VA SEISMIC DESIGN MANUAL, VA FIRE PROTECTION DESIGN MANUAL AND NFPA 13.

55. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO REMOVE AND LEGALLY DISPOSE OF

DEMOLISHED MATERIALS UNLESS NOTED OTHERWISE IN THE DRAWINGS.

56. ALL WALL AND FLOOR PENETRATIONS SHALL BE CORE-DRILLED AND SLEEVED.

57. UNLESS INDICATED OTHERWISE IN THE DRAWINGS OR SPECIFICATIONS, FIRE SUPPRESSION CONTRACTOR IS RESPONSIBLE FOR SEALING ALL FIRE RATED WALL PARTITIONS WITH UL LISTED MATERIAL AND

METHODS.

58. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH A NON-SHRINKING

GROUT OR CAULKING MATERIAL AND APPROVED ASSEMBLY.

59. BEFORE SUBMITTING A PROPOSAL FOR THE WORK, EACH BIDDER WILL BE HELD RESPONSIBLE TO HAVE EXAMINED THE EXISTING SITE CONDITIONS FOR THE WORK INCLUDED UNDER THIS CONTRACT. NO ALLOWANCE WILL BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR

ANY ERROR OR NEGLIGENCE ON HIS PART.

60. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE COMPLETE DESIGN OF THE FIRE PROTECTION SYSTEM AND SHALL PROVIDE SEALED SHOP DRAWINGS. SPRINKLER SYSTEM PLANS AND CALCULATIONS SHALL BE SEALED BY AN PROFESSIONAL ENGINEER REGISTERED IN THE STATE WHERE THE WORK IS TO OCCUR, OR SEALED BY A NICET LEVEL III OR LEVEL IV SPRINKLER DESIGNER CERTIFIED IN "WATER BASED SYSTEMS LAYOUT". DRAWINGS SHALL BE SEALED IN ACCORDANCE WITH REQUIREMENTS

OF THE VA COR, VA FIRE OFFICIAL AND THE ENGINEER OF RECORD.

61. THE FIRE SUPPRESSION SYSTEM AREA OF PROTECTION INDICATED ON THE PLANS IS FOR COORDINATION AND BIDDING PURPOSES ONLY. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE

COMPLETE DESIGN.

62. ALL HANGERS MUST BE FM APPROVED, UL LISTED AND THE TYPE APPROVED BY NFPA 13. NO SPRINKLER PIPING IS TO BE SUPPORTED FROM ANY MECHANICAL OR ELECTRICAL DEVICES. ALL PIPE SHALL BE SUPPORTED FROM THE BUILDING STRUCTURE IN A NEAT AND WORKMANLIKE MANNER. VERTICAL RISERS SHOULD BE SUPPORTED AT EACH FLOOR LEVEL WITH STEEL PIPE CLAMPS. HANGING PIPES FROM OTHER PIPES WILL BE NOT PERMITTED. PIPING SHALL BE CAREFULLY COORDINATED BEFORE INSTALLATION WITH OTHER SYSTEMS AND EQUIPMENT IN CHASES AND OTHER CONGESTED AREAS. MAXIMUM DISTANCES BETWEEN PIPE SUPPORTS SHALL MEET THE REQUIREMENT STATED IN NFPA 13, SECTION 17.4.2.1 AND TABLE 17.4.2.1(a). TITLED "MAXIMUM DISTANCE BETWEEN HANGERS (FT-IN)."

63. MAINTAINABILITY

A. EXTERNAL AND INTERNAL PARTS SHALL BE ARRANGED SO THAT WHEN INSTALLED, ALL PARTS REQUIRING MANIPULATION, OBSERVATION, AND/OR MAINTENANCE ARE READILY ACCESSIBLE AND

SAFE FOR OPERATION AND MAINTENANCE PERSONNEL. WHEREVER PRACTICAL, VALVES AND

INSTRUMENTS SHALL BE LOCATED SUCH THAT THEY CAN BE OPERATED AND EASILY ACCESSED FROM

GRADE LEVEL.

B. MAINTAINABILITY SHALL BE INCORPORATED INTO THE DESIGN OF ALL CONTRACTOR SUPPLIED EQUIPMENT. THE PRIMARY MAINTAINABILITY OBJECT SHALL BE TO MINIMIZE THE COMPLEXITY AND TIME REQUIRED FOR MAINTENANCE. THE FOLLOWING GENERAL CRITERIA SHALL BE FOLLOWED TO

ACHIEVE THIS OBJECTIVE:

a. CONTRACTOR SUPPLIED EQUIPMENT SHALL BE LOW MAINTENANCE DESIGN AND SHALL BE EASILY

MAINTAINABLE.

b. CONTRACTOR SUPPLIED EQUIPMENT SHALL BE DESIGNED TO BE MAINTAINED IN PLACE, IF

POSSIBLE, WITH MINIMUM DISASSEMBLY OF SURROUNDING EQUIPMENT AND MINIMUM USAGE OF

TEMPORARY SCAFFOLDING AND HANDLING EQUIPMENT.

64. DEVICES SHOWN ON THIS PLAN ARE NEW, UNLESS OTHERWISE NOTED.

65. DRAWING ARE DIAGRAMMATIC AND ARE NOT INTENDED TO SHOW EACH AND EVERY SPRINKLER HEAD, BRANCH PIPING, DEVICES, FITTINGS, VALVES OR COMPLETE DETAIL OF ALL THE WORK TO BE PERFORMED, BUT ARE FOR THE PURPOSES OF ILLUSTRATING THE TYPE OF SYSTEM AND CONDITIONS NECESSARY FOR AN EXPERIENCED TRADESMAN TO LAYOUT HIS WORK. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING SUCH SITE OBSERVATIONS AND MEASUREMENTS AS NECESSARY TO PROPERLY COMPLETE THE

WORK.

66. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH NON-SHRINKING

GROUT OR CAULKING MATERIAL AND APPROVED ASSEMBLY.

67. SPRINKLER SHOP DRAWINGS SHALL INDICATE THE FOLLOWING:

A. CEILING TYPES AND GRIDS.

B. ALL CEILING MOUNTED DEVICES (LIGHTS, DIFFUSERS AND SPECIAL ELECTRICAL SYSTEMS.

68. THE FIRE SUPPRESSION CONTRACTOR SHALL LOCATE SPRINKLER HEADS IN CEILINGS AS FOLLOWS. ALL HEADS SHALL BE LOCATED IN THE CENTER OF TILES (2' X 2') OR IN THE CENTER OF ONE QUADRANT (2' X 4') IN GYP. BOARD CEILING SPRINKLER HEADS SHALL BE LOCATED IN SYMMETRICAL PATTERN RELATIVE TO

OTHER DEVICES LOCATED IN THE CEILING.

69. ADEQUATE HOUSING SHALL BE PROVIDED FOR ALL MATERIAL STORED ON THE JOB. ALL MATERIALS FURNISHED FOR THE PROJECT SHALL BE NEW WITH LISTINGS AND LABELS BY A TESTING AGENCY

APPROVED BY THE STATE OF WHERE THE WORK IS TO BE PERFORMED.

70. WHERE WORK IS BEING PERFORMED IN AREAS THAT MUST CONTINUE NORMAL OPERATION, CONTRACTOR SHALL KEEP THE AREAS CLEAN AND CLEAR OF OBSTRUCTIONS, AND AS MUCH AS POSSIBLE, PROVIDE WARNING SIGNS AS NECESSARY FOR PROTECTION OF OCCUPANTS FROM ASSOCIATED RISKS. REMOVE

ALL DEBRIS AS WORK PROGRESSES.

71. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE VA COR, VA FIRE OFFICIAL AND VA'S ENGINEER OF RECORD WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE VA FIRE OFFICIAL AND VA'S ENGINEER OF RECORD WILL BE REQUIRED PRIOR TO FINAL

ACCEPTANCE OF THE PROJECT.

72. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE SPRINKLER

SYSTEM PER NFPA 13 AND A FIRE PROTECTION DESIGN MANUAL REQUIREMENTS.

73. REFER TO ARCHITECTURAL REFLECTED CEILING PLAN FOR COORDINATION OF SPRINKLER LOCATIONS WITH CEILING HEIGHTS AND TYPES. LOCATE SPRINKLER HEADS THROUGHOUT ALL AREAS AS REQUIRED BY NFPA 13 AND VA FIRE PROTECTION DESIGN MANUAL. COORDINATE SPRINKLER HEAD LOCATIONS WITH ALL OTHER TRADES BUT NOT LIMITED TO THE FOLLOWING: LIGHTS, STRUCTURAL SUPPORTS, BOOM, SPECIAL SYSTEMS, SMOKE DETECTORS,FIRE ALARM INDICATION DEVICES, HVAC DIFFUSERS, ETC. OBTAIN

ARCHITECT'S, ENGINEER AND/OR APPROVAL OF ALL SPRINKLER HEAD LOCATIONS.

74. ALL SPRINKLER HEAD PIPE ROUTING AND ELEVATIONS SHALL BE COORDINATED WITH ALL OTHER TRADES INCLUDING BUT NOT LIMITED TO THE FOLLOWING: CEILINGS, STRUCTURAL STEEL AND SUPPORTS, HVAC

DUCTWORK, CABLE TRAYS, CONDUIT, SPECIAL SYSTEMS, CONTROLS, ETC.

75. THE AUTOMATIC SPRINKLER CONTRACTOR IS TO PROVIDE ALL NECESSARY OFFSETS, RISES OR DROPS IN THE PIPING AND AUXILIARY DRAINS AS REQUIRED TO INSTALL COMPLETELY COORDINATED SPRINKLER SYSTEM. HYDRAULIC CALCULATIONS SHALL BE ORIGINATED AT THE FIRE PUMP AS A MINIMUM FOR

FACILITIES THAT POSSES A FIRE PUMP OR AT LOCATION OF FIRE HYDRANT FLOW TEST.

76. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF TWO (2) FOOT DISTANCE FROM A SIDE WALL- MOUNTED OR CEILING MOUNTED DIFFUSER USING AN ORDINARY TEMPERATURE SPRINKLER HEAD.

SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF THREE (3) FOOT DISTANCE FROM THE FRONT OF A

WALL-MOUNTED HOT AIR DIFFUSER.

77. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF 18 INCHES FROM ANY LIGHT FIXTURE USING AN ORDINARY TEMPERATURE SPRINKLER HEAD. IT IS PREFERRED THAT THE CONTRACTOR MAINTAINS A TWO

(2) FOOT SPACING BETWEEN THE LIGHT FIXTURE AND SPRINKLER HEAD.

78. SPRINKLER PLANS AS SHOWN ARE FOR BIDDING PURPOSES ONLY. SPRINKLER CONTRACTOR IS TO OBTAIN CURRENT HYDRANT TEST DATA AND PROVIDE HYDRAULIC CALCULATIONS FOR SYSTEM PIPE SIZING IN ACCORDANCE WITH NFPA 13 AND THE VA FIRE PROTECTION DESIGN MANUAL. CONTRACTOR IS TO SUBMIT SHOP DRAWINGS INDICATION HYDRAULIC CALCULATIONS, PIPING LAYOUT & SIZING. ALL WORK IS TO BE DONE IN ACCORDANCE WITH NFPA 1, NFPA 13, NFPA 241, NFPA 291 AND THE VA FIRE PROTECTION DESIGN

MANUAL.

79. SPRINKLER CONTRACTOR SHALL MAINTAIN SUPERVISION OF EXISTING SPRINKLER SYSTEM AT ALL TIMES

AND SHALL COORDINATE TRANSFER OF SYSTEM WITH OWNER AND ENGINEER OF RECORD.

80. PIPE SUPPORTS:

A. ALL HANGERS MUST BE FM APPROVED, UL LISTED AND MEET THE REQUIREMENTS OF NFPA 13. NO

SPRINKLER PIPE IS TO BE SUPPORTED FROM ANY MECHANICAL OR ELECTRICAL DEVICE, SPECIFICALLY, DUCTWORK.

B. ALL PIPE SHALL BE SUPPORTED FROM THE BUILDING STRUCTURE IN A NEAT AND WORKMANLIKE MANNER. VERTICAL RISERS SHOULD BE SUPPORTED AT EACH FLOOR LEVEL WITH STEEL PIPE CLAMPS.

THE USE OF WORE OR STRAP METAL HANGERS TO SUPPORT PIPES WILL NOT BE PERMITTED. HANGING

PIPES FROM OTHER PIPES WILL NOT BE PERMITTED. CAREFULLY COORDINATED BEFORE

INSTALLATION WITH OTHER SYSTEMS AND EQUIPMENT IN CHASES AND OTHER CONGESTED AREAS.

C. MAXIMUM DISTANCES BETWEEN PIPE SUPPORTS SHALL MEET THE REQUIREMENTS STATED IN NFPA 13, SECTION 17.4.3.2 AND TABLE 17.4.2.1(a), TITLED, "MAXIMUM DISTANCE BETWEEN HANGERS (FT.-IN.).

81. ALL WALL AND FLOOR PENETRATIONS SHALL BE CORE-DRILLED AND SLEEVED THIS IS A VA DORN

REQUIREMENT, NO EXCEPTIONS.

82. NEW ARMOVERS SHALL BE PROVIDED TO NEW SPRINKLERS FOR COMPLIANCE WITH NFPA 13.

83. INDIVIDUAL BRANCH LINES TO A SINGLE SPRINKLER SHALL COMPLY WITH NFPA 13, SECTION 28.2.1.2 WHICH STATES, "PIPE SIZES SHALL BE NO LESS THAN 1-INCH (25 MM) NOMINAL FOR BLACK OR GALVANIZED STEEL PIPING AND 3/4-INCH (20 MM) NOMINAL FOR COPPER TUBING OR BRASS, STAINLESS STEEL OR NONMETALLIC PIPING LISTED FOR FIRE SPRINKLER SERVICE UNLESS PERMITTED BY SECTIONS 30.4 AND

30.6 OF NFPA 13."

84. ALL NEW EXPOSED PIPING MUST BE PAINTED IN COMPLIANCE WITH PROJECT SPECIFICATION 09 91 00, PAINTING.

85. THE SHOP DRAWINGS AND CALCULATIONS SHALL BE SUBMITTED TO THE ARCHITECT, ENGINEER AND VA

FIRE MARSHAL AND VA COR FOR REVIEW AND COMMENT.

86. IT IS THE INTENTION OF THE SPECIFICATION AND DRAWINGS TO CALL FOR A COMPLETE AND FUNCTIONAL SYSTEM, INSTALLED AS PER NFPA AND THE VA FIRE PROTECTION DESIGN MANUAL WITH ALL FINISHED

WORK TESTED AND READY FOR OPERATION.

87. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE VA COR, VA FIRE MARSHAL, VA'S ENGINEER OF RECORD, FIRE ALARM CONTRACTOR, AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN

OR INTERRUPTION OF SERVICE.

88. ALL MATERIALS, PIPING, FITTINGS, VALVES, AND APPLIANCES HEREINAFTER SPECIFIED AND THOSE WHICH ARE ESSENTIAL BUT HAVE NOT BEEN SPECIFIED SHALL BE NEW AND OF THE HIGHEST GRADE AND

QUALITY, FREE FROM DEFECTS AND SUCH AS BREAKS, FLAWS, AND IMPERFECTIONS.

89. THROUGH PENETRATION ASSEMBLIES SHALL BE PROVIDED AT EACH OPENING WHERE EXPOSED SPRINKLER PIPING PASS THROUGH RATED WALLS, FLOORS AND PARTITIONS. ALL PIPING PENETRATIONS MUST BE SEALED IN ACCORDANCE WITH “UL” LISTING SEALING METHOD AND/OR AS DETAILED IN THESE

CONTRACT DRAWINGS OR SPECIFICATIONS.

90. BEFORE SUBMITTING A PROPOSAL FOR THE WORK, EACH BIDDER WILL BE HELD RESPONSIBLE TO HAVE EXAMINED THE EXISTING SITE CONDITIONS FOR THE WORK INCLUDED UNDER THIS CONTRACT. NO ALLOWANCE WILL BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR

ANY ERROR OR NEGLIGENCE ON HIS PART.

91. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE COMPLETE DESIGN OF THE FIRE PROTECTION SYSTEM AND SHALL PROVIDE SEALED SHOP DRAWINGS. SPRINKLER SYSTEM PLANS AND CALCULATIONS SHALL BE SEALED BY AN PROFESSIONAL ENGINEER REGISTERED IN THE STATE OF SOUTH

CAROLINA OR A NICET LEVEL III OR LEVEL IV SPRINKLER DESIGNER.

92. DRAWING ARE DIAGRAMMATIC AND ARE NOT INTENDED TO SHOW EACH AND EVERY SPRINKLER HEAD, BRANCH PIPING, DEVICES, FITTINGS, VALVES OR COMPLETE DETAIL OF ALL THE WORK TO BE PERFORMED, BUT ARE FOR THE PURPOSES OF ILLUSTRATING THE TYPE OF SYSTEM AND CONDITIONS NECESSARY FOR AN EXPERIENCED TRADESMAN TO LAYOUT HIS WORK. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING SUCH SITE OBSERVATIONS AND MEASUREMENTS AS NECESSARY TO PROPERLY COMPLETE THE

WORK.

93. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE OWNER WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE APPROPRIATE AGENCY INSPECTION AGENT

WILL BE REQUIRED PRIOR TO FINAL ACCEPTANCE OF THE PROJECT.

94. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE SPRINKLER

SYSTEM PER NFPA 13 AND VA FIRE PROTECTION DESIGN REQUIREMENTS.

95. ALL SPRINKLER HEAD PIPE ROUTING AND ELEVATIONS SHALL BE COORDINATED WITH ALL OTHER TRADES INCLUDING BUT NOT LIMITED TO THE FOLLOWING: CEILINGS, STRUCTURAL STEEL AND SUPPORTS, HVAC

DUCTWORK, CABLE TRAYS, CONDUIT, SPECIAL SYSTEMS, CONTROLS, ETC.

96. HYDRAULIC CALCULATIONS SHALL BE ORIGINATED AT THE LOCATION OF FIRE HYDRANT FLOW TEST.

97. THE FIRE PROTECTION CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL, EQUIPMENT AND SERVICES NECESSARY FOR ANY REASONABLY INCIDENTAL TO FURNISHING A FIRE PROTECTION SYSTEM, AS INDICATED ON THE CONTRACT DRAWINGS AND / OR SPECIFIED IN THE PROJECT SPECIFICATIONS.

98. THE FIRE PROTECTION CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION WITH OTHER TRADES TO ELIMINATE CONFLICT WITH OTHER TRADES. ANY WORK INSTALLED BY THIS CONTRACTOR THAT RESULTS IN CONFLICT, DUE TO LACK OF COORDINATION BETWEEN TRADES, SHALL BE CHANGED AS DIRECTED BY THE ARCHITECT /ENGINEER WITHOUT ADDITIONAL COMPENSATION TO THE CONTRACTOR.

99. THE FIRE PROTECTION CONTRACTOR SHALL COORDINATE ROUTING OF SPRINKLER LINES TO ENSURE

PIPING DOES NOT PASS OVER ELECTRICAL PANELS.

100. ANY NEW PIPE OR DUCTWORK INSULATION THAT IS DAMAGED DURING CONSTRUCTION SHALL BE REMOVED AND REPLACED WITH NEW INSULATION TO MATCH ADJACENT INSULATION AND COVERING AT

THE FIRE PROTECTION CONTRACTOR'S EXPENSE.

101. CUTTING AND PATCHING OF ANY CONDITIONS, INCLUDING FLOORS, WALLS AND CEILINGS REQUIRED FOR

THE INSTALLATION OF FIRE PROTECTION SYSTEMS IS THE RESPONSIBILITY OF THE GENERAL

CONTRACTOR. ALL WORK SHALL BE COORDINATED WITH THE GENERAL CONTRACTOR AND ALL OTHER

TRADES.

102. THIS CONTRACTOR IS RESPONSIBLE FOR SUBMISSION OF CONTRACTOR'S MATERIAL AND TEST CERTIFICATE FOR ABOVEGROUND PIPING MEETING NFPA 13, FIGURE 28.1 TO THE VA COR AND THE

ENGINEER OF RECORD FOR REVIEW AND COMMENT. ALL CONTRACTORS' MATERIAL AND TEST

CERTIFICATE FOR ABOVEGROUND PIPING MUST BE DATED, PRINTED NAME OF INDIVIDUALS WHO SIGNED

THE CONTRACTOR'S MATERIAL AND TEST CERTIFICATE AND SIGNATURES. ALL TEST MUST BE

COORDINATED WITH THE VA COR, VA FIRE SAFETY OFFICIAL AND THE ENGINEER OF RECORD. SIGNATURES BY NON VA FIRE OFFICIALS WILL NOT BE ACCEPTED. AND SIGNATURES. ALL TEST MUST BE COORDINATED WITH THE VA COR, VA FIRE SAFETY OFFICIAL AND THE ENGINEER OF RECORD. SIGNATURES BY NON VA

FIRE OFFICIALS WILL NOT BE ACCEPTED.

103. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE ALL NECESSARY OFFSETS, RISES AND DROPS IN PIPING, AND AUXILIARY DRAINS AS REQUIRED BY THE VA FIRE PROTECTION DESIGN MANUAL AND NFPA 13, WHETHER SHOWN ON PLANS OR NOT.

104. INDIVIDUAL BRANCH LINES TO A SINGLE SPRINKLER SHALL COMPLY WITH NFPA 13, SECTION 28.2.1.2 WHICH STATES, "PIPE SIZES SHALL BE NO LESS THAN 1-INCH (25 MM) NOMINAL FOR BLACK OR GALVANIZED STEEL PIPING AND 3/4-INCH (20 MM) NOMINAL FOR COPPER TUBING OR BRASS, STAINLESS STEEL OR NONMETALLIC PIPING LISTED FOR FIRE SPRINKLER SERVICE UNLESS PERMITTED BY SECTIONS 30.4 AND

30.6 OF NFPA 13."

105. ALL NEW EXPOSED PIPING MUST BE PAINTED IN COMPLIANCE WITH PROJECT SPECIFICATION 09 91 00, PAINTING.

106. WHERE SPRINKLER PIPING IS INSTALLED BELOW DUCTWORK, PIPING SHALL BE SUPPORTED

FROM THE BUILDING STRUCTURE OR FROM THE DUCTWORK SUPPORTS; PROVIDED SUCH

SUPPORTS ARE CAPABLE OF HANDLING THE LOAD OF THE LOAD OF THE DUCTWORK AND THE

LOADS SPECIFIED IN NFPA 13, SECTION 17.4.1.3 ARE MET. IF THE CONTRACTOR DECIDES TO

SUPPORT THE FIRE PROTECTION PIPING FROM THE DUCTWORK SUPPORTS; THE FIRE

PROTECTION CONTRACTOR SHALL SUBMIT CALCULATIONS SIGNED AND SEALED BY A SOUTH

CAROLINA LICENSED FIRE PROTECTION ENGINEER VALIDATING COMPLIANCE WITH NFPA 13.

FIRE PROTECTION ABBREVIATIONS

WET PIPE

WIREGUARD

WELDED

WATER FLOW SWITCH

VOLTS

VALVE

US DEPT OF VETERANS AFFAIRS

UNDERGROUND

UNLESS NOTED OTHERWISE

UPRIGHT

UNDERWRITERS LABORATORY

TO BE DETERMINED

TYPICAL

TAMPER SWITCH

THREADED

TOP OF STEEL

TOP OF CONCRETE

STEEL

SQUARE FEET

SPECIAL

SPECIFICATION

SIDEWALL

SCREWED

SCHEDULE

ROOM

RESIDUAL

REDUCER

POUNDS PER SQUARE INCH

PRESSURE SWITCH

POST INDICATING VALVE

PHASE

PLUMBING

PENDANT

PLUMBING CONTRACTOR

PRE-ACTION VALVE

PRE-ACTION

ORDINARY HAZARD 2

ORDINARY HAZARD I

OUTSIDE SCREW AND YOKE

NATIONAL PIPE THREAD

NOT TO SCALE

NON RISING STEM

NOT APPLICABLE

NOT IN CONTRACT

NORMALLY OPENED

NORMALLY CLOSED

NATIONAL FIRE PROTECTION ASSOCIATION

MALLEABLE IRON

MEZZANINE

MECHANICAL JOINT

LEVEL

LIGHT HAZARD

LIGHTING

INSPECTOR TEST CONNECTION

INSPECTOR

INTERIOR

HEATING VENTING AND AIR CONDITIONING

HOSE CABINET

HOSE VALVE

HOSE REEL

WP

WG

WLD

FS

V

VAL

VA

UNO

UPR

UL

UG

TBD

TYP

TS

THRD

TOS

TOC

STL

SF

SP

SPEC

SW

SCR

SCH

RM

RES

RED

PSI

PS

PIV

PH

PLB

PEND

PC

PAV

PA

OH2

OH1

OS&Y

NPT

NTS

NRS

NA

NIC

NO

NC

NFPA

MI

MEZZ

MJ

LVL

LH

LTG

ITC

INSP

INT

HVAC

HC

HV

HR

HORSEPOWER

HYDRANT

GROOVED

GALLONS PER MINUTE

GROUND

GRADE

GENERAL CONTRACTOR

GALVANIZED

GAUGE

GALLONS

FLOW SWITCH

FIRE PROTECTION

FLOOR

FIRE ALARM

FLANGE

FINISH

FIRE HOSE VALVE

FIRE DEPARTMENT CONNECTION

FIRE ALARM

FACTORY MUTUAL GLOBAL

EXTINGUISHER

EXTERIOR

EXISTING

EXTRA HAZARD 2

EXTRA HAZARD 1

ELEVATION

ELECTRIC

ECCENTRIC

EXTENDED COVERAGE

ELBOW

EACH

EXISTING

DUCTILE IRON

DRY PIPE

DEPT OF DEFENSE

DEPARTMENT

DRAWING

DEGREE

DIAMETER

DRY

DOWN

CONCENTRIC

CONCRETE

CONTINUATION

CHECK

CEILING

CLASS

CAST IRON

BLACK

BUILDING

BOTTOM OF BEAM

BASEMENT

BACKFLOW PREVENTER

BELOW FINISH FLOOR

BELOW

ABOVE FINISHED GRADE

ABOVE FINISHED FLOOR

ABOVE CONCRETE

AUTOMATIC

AUTHORITY HAVING JURISDICTION

AMERICANS WITH DISABILITIES ACT

ABOVE

HP

HYD

GVD

GPM

GND

GR

GC

GALV

GA

GAL

FS

FP

FL

FA

FLG

FIN

FHV

FDC

FA

FM

EXT

EX

EXIST

EH2

EH1

EL

ELEC

ECC

EC

EL

EA

(E)

DI

DP

DOD

DEPT

DWG

DEG

DIA

D

DN

CON

CR

CONT

CHK

CLG

CL

CI

BLK

BLDG

BOB

BSMT

BFP

BFF

BEL

AFG

AFF

A/CONC

AUTO

AHJ

ADA

ABV

FIRE PROTECTION DESIGN CRITERIA

LIGHT HAZARD - PATIENT CARE, OFFICES, TREATMENT AND

CUSTOMARY ACCESS AREAS, RESTROOMS, X-RAY ROOMS AND IT

& COMMUNICATION ROOMS

DESIGN DENSITY: 0.10GPM/SQ.FT

HYDRAULICALLY MOST DEMANDING AREA: 1,500SQ.FT

SPRINKLER ORIFICE: 1/2INCH

MAXIMUM COVERAGE/SPRINKLER HEAD: 225SQ.FT

HOSE STREAM ALLOWANCE INSIDE/OUTSIDE: 100GPM

K FACTOR: 5.6GPM/(PSI)

½

ORDINARY HAZARD GROUP I - LABORATORIES, MECHANICAL

ROOMS, JANITORS CLOSETS, LAUNDRY ROOMS, AND

ELECTRICAL ROOMS

DESIGN DENSITY: 0.15GPM/SQ.FT

HYDRAULICALLY MOST DEMANDING AREA: 1,500SQ.FT

SPRINKLER ORIFICE: 1/2INCH

MAXIMUM COVERAGE/SPRINKLER HEAD: 130SQ.FT

HOSE STREAM ALLOWANCE INSIDE/OUTSIDE: 250GPM

K FACTOR: 5.6GPM/(PSI)

½

DESIGN DENSITY: 0.020GPM/SQ.FT.

HYDRAULICALLY MOST DEMANDING AREA: 1,500SQ.FT.

SPRINKLER ORIFICE: 3/4INCH

MAXIMUM COVERAGE/SPRINKLER HEAD: 130SQ.FT.

HOSE STREAM ALLOWANCE INSIDE/ OUTSIDE: 250GPM

K FACTOR: 8.0GPM/(PSI)1/2

ORDINARY HAZARD GROUP 2 - OCCUPANCY OR PORTIONS

OF OTHER OCCUPANCIES WHERE THE QUANTITY AND

COMBUSTIBILITY OF CONTENTS ARE MODERATE RATES TO

HIGH, STOCKPILES OF CONTENTS WITH MODERATE RATES OF

HEAT RELEASE DO NOT EXCEED 12 FEET AND STOCKPILES

OF CONTENTS WITH HIGH RATES OF HEAT RELEASE DO NOT

EXCEED 8 FEET.

SITE INSPECTION NOTE:

A CONTRACTOR SHALL PROVIDE THE ENGINEER FIVE(5) WORKING DAYS

NOTICE FOR ALL REQUESTED REVIEWS OF THE WORK. AS A MINIMUM THE

FOLLOWING REVIEWS SHALL BE CONDUCTED PRIOR TO COVERING UP ANY

CONCEALED WORK:

1. INSTALLATION OF TAMPER AND FLOW SWITCHES ON FIRE SERVICE FOR

ELECTRONIC SUPERVISION SHALL BE FURNISHED & INSTALLED BY THE

FIRE SUPPRESSION CONTRACTOR WHERE INSPECTION SHALL BE

COMPLETED AND PASSED INSPECTION.

2. IN-WALL ROUGH-IN WORK SHALL BE VISIBLE. FIRE PROTECTION

INSPECTIONS SHALL BE COMPLETE AND PASSED.

3. ABOVE CEILING WORK AN ABOVE CEILING WORK SHALL BE COMPLETE

INCLUDING PIPING, VALVES, SPRINKLER HEADS, HANGERS, SUPPORTS

AND SEISMIC RESTRAINS, ETC. FIRE PROTECTION INSPECTIONS SHALL BE

COMPLETED AND PASSED.

RE-REVIEW SHALL BE REQUIRED IF THE WORK IS COMPLETE OR NOT

INSTALLED PER THE CONTRACT DOCUMENTS.

SPRINKLER NOTE:

SPRINKLER PLANS AS SHOWN ARE FOR BIDDING PURPOSES

ONLY. SPRINKLER CONTRACTOR IS TO OBTAIN CURRENT

HYDRANT TEST DATA AND PROVIDE HYDRAULIC CALCULATIONS

FOR SYSTEM PIPE SIZING IN ACCORDANCE WITH NFPA 13 &

NFPA 291 FOR DESIGN INPUT INTO THE CONTRACTOR'S

HYDRAULIC CALCULATIONS. CONTRACTOR IS TO SUBMIT SHOP

DRAWINGS INDICATING HYDRAULIC CALCULATIONS, PIPING

LAYOUT & SIZING. SHOP DRAWINGS AND CALCULATIONS ARE

TO BE SIGNED & SEALED BY A LICENSED FIRE PROTECTION

PROFESSIONAL ENGINEER WHERE THE WORK SHALL OCCUR

OR NICET LEVEL III OR IV IN WATER BASED SYSTEMS LAYOUT.

ALL WORK IS TO BE DONE IN ACCORDANCE WITH ALL VA FIRE

PROTECTION DESIGN MANUAL AND NFPA CODES.

THE FOLLOWING PUBLICATIONS AND AUTHORITIES HAVING JURISDICTION SHALL BE REFERENCED FOR THE

DESIGN OF THE FIRE PROTECTION SYSTEM ON THIS PROJECT:

1. ANSI, A117.1 STANDARD, ACCESSIBLE AND USABLE BUILDINGS AND FACILITIES. 2017 EDITION

2. NFPA 1 - FIRE CODE, 2024 EDITION

3. NFPA 13 - STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS, 2022 EDITION

4. NFPA 24 - STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICE MAINS AND THEIR

APPURTENANCES, 2025 EDITION

5. NFPA 25 - INSPECTION, TESTING, AND MAINTENANCE OF WATER-BASED FIRE PROTECTION SYSTEMS, 2023

EDITION

6. NFPA 101 - LIFE SAFETY CODE, 2024 EDITION

7. NFPA 170 - LIFE SAFETY CODE, 2024 EDITION

8. NFPA 241 - STANDARD FOR SAFEGUARDING CONSTRUCTION, ALTERNATION AND DEMOLITION

OPERATIONS, 2022 EDITION

9. NFPA 291 - RECOMMENDED PRACTICE FOR WATER FLOW TESTING AND MARKING OF HYDRANTS, 2025

EDITION

10. VA FIRE PROTECTION DESIGN MANUAL, NINTH EDITION, NOVEMBER 1, 2023

11. VA SEISMIC DESIGN REQUIREMENTS, REVISED JULY 1, 2023 EDITION

12. VA FIRE SAFETY

DESIGN CODES, STANDARDS & PARTIES OF REFERENCE

FIRE SUPPRESSION LEGEND

UPRIGHT SPRINKLER HEAD

PENDENT SPRINKLER HEAD

CONCEALED PENDENT SPRINKLER & COVER PLATE

SIDEWALL SPRINKLER HEAD

RECESSED PENDENT SPRINKLER WITH CONCEALED ESCUTCHEON

RECESSED SIDEWALL SPRINKLER & ESCUTCHEON

CONCEALED SIDEWALL SPRINKLER & COVER PLATE

NEW INSTITUTIONAL / SECURITY TYPE LIGATURE RESISTANT,

PENDENT SPRINKLER HEAD. PROVIDE TYCO RAVEN INSTITUTIONAL

SPRINKLER HEAD, MODEL TY3281.

SPRINKLER PIPING

ELBOW TURNED DOWN

ELBOW TURNED UP

TEE TURNED DOWN

TEE TURNED UP

FIRE PROTECTION PIPING

DRAIN

DRY PIPE

F

FD

DP

OS & Y CHECK VALVE

WORK AREAS OUTSIDE OF A RATED

CONSTRUCTION BARRIER

CONTRACTOR SHALL BE REQUIRED TO PROVIDE/INSTALL THE

REPLACEMENT OF CEILING TILES AT THE END OF EACH SHIFT

FOR WORK AREAS OUTSIDE A RATED CONSTRUCTION BARRIER.

IF THE TILES CAN NOT BE REPLACED THE SPRINKLER SYSTEM

MAY BE CONSIDERED OUT OF SERVICE IN THESE AREAS AND A

1-HOUR FIRE RATED SEPARATION WILL BE REQUIRED BETWEEN

THE CONSTRUCTION AREA AND THE OCCUPIED PORTION OF

THE BUILDING.

REFERENCE NFPA 1, PARAGRAPH 13.3.3.3

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

A

100% BID DOCUMENTS

FOR CONSTRUCTION

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT

GMK Associates, Inc.

1201 Main Street, Suite 2100 Columbia, SC 29201 803-256-0000 Thomas M. Weiland, AIA

STAMPPROGRAM MANAGER

321 4 5 6 7 8 9 10

Odell International 129 Fast Lane, Suite 200 Mooresville, NC 28117 704-401-2040 C. Harmon Reed, Jr. AIA

CONSULTANT

Charlotte Engineers, LLP 5838 Monroe Road Charlotte, NC 28212 704-531-3000 Michael Eaves FULLY SPRINKLERED

Approved:

U A

C a lla h a n \L o c a l R e v it \R

\4

C

E C e n tr a l M o d e l.

rv t

/9 /2

:3

:3

A

M

FX001

FIRE SUPPRESSION - GENERAL

NOTES AND LEGENDS

EHRM - RENOVATE B3 FOR EHRM

ADMIN AND TRAINING

COLUMBIA, SC

544-22-703

B3

07/15/2025 GAT JRC

FIRE SUPPRESSION - DRAWING INDEX

Sheet Number Sheet Name

FX001 FIRE SUPPRESSION - GENERAL NOTES AND LEGENDS

FX002 FIRE SUPPRESSION - DETAILS

FX003 FIRE SUPPRESSION - FIRE PUMP TEST RESULTS AND SEISMIC

DETAILS

FX004 FIRE SUPPRESSION - IMPAIRMENT & INTERIM REQUIREMENTS

FX100 FIRE SUPPRESSION - LEVEL 03 - DEMOLITION

FX101 FIRE SUPPRESSION - LEVEL 03 - NEW WORK

Rev. No. Revisions: Date:

METAL PIPE THROUGH 2-HR. GYPSUM WALL

METAL PIPE THROUGH 1-HR. GYPSUM WALL

STEEL/COPPER PIPE THROUGH CONCRETE OR

CONCRETE BLOCK WALL

STEEL PIPE THROUGH CONCRETE FLOOR OR WALL

TYPICAL UPRIGHT HEAD DETAILSPRINKLER HEAD LOCATION 4

BEAM PIPE HANGER 1

PIPE SLEEVE THROUGH WALL DETAIL 5

PIPE SLEEVE THROUGH FLOOR DETAIL 3

PER

MANUFACTURER

S

INSTRUCTIONS

UPRIGHT SPRINKLER

HEAD

QUICK RESPONSE

VARIES

** FOR USE IN AREAS WITHOUT LAY-IN/GYPBOARD CEILINGS

** FOR USE IN AREAS OPEN TO STRUCTURE **

NTS

3. MINIMUM 1-1/4" DEPTH HILTI FS 601 FIRESTOP SEALANT.

OR 4" DIA. (OR SMALLER) COPPER PIPE, EMT OR STEEL CONDUIT.

2. 10" DIA. (OR SMALLER) STEEL PIPE (SCHEDULE 10 OR HEAVIER),

1. 2-HR. FIRE-RATED GYPSUM WALL ASSEMBLY.

HILTI, INC. TULSA, OK 1-800-879-8000

SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS

2. ANNULAR SPACE = MIN. 1/4" TO MAX. 1".

NOTES : 1. MAXIMUM DIAMETER OF OPENING = 12-1/2".

U.L. SYSTEM NO. WL1054

T RATING = 0-HR.

F RATING = 2-HR.

HILTI, INC. TULSA, OK 1-800-879-8000

2. 10" DIA. (OR SMALLER) STEEL PIPE, 4" DIA. (OR SMALLER)

SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS

3. MIN. 5/8" DEPTH HILTI FS 601.

COPPER PIPE, EMT OR CONDUIT.

1. 1-HR. FIRE-RATED GYPSUM WALL ASSEMBLY.

NOTE : NOMINAL ANNULAR SPACE OF 1/4" TO 1" REQUIRED.

A

A

U.L. SYSTEM NO. WL1052

T RATING = 0-HR.

F RATING = 1-HR.

FRONT VIEW

A 2

SECTION A-A

A

FRONT VIEW

HILTI, INC. TULSA, OK 1-800-879-8000

6. 1/2" BEAD HILTI FS 605 SEALANT AT POINT OF CONTACT.

5. MINIMUM 1/4" DEPTH HILTI FS 605 FIRESTOP SEALANT.

4. MINIMUM 4-1/2" THICKNESS FLEXIBLE URETHANE SHEET, (MIN. 4 PCF DENSITY).

HOLLOW BLOCK WALLS ONLY).

3. NO. 8 STEEL WIRE MESH RECESSED 1/8" BELOW EACH WALL SURFACE (FOR

COPPER PIPE.

2. 17-1/4" DIA. (OR SMALLER) STEEL PIPE OR 4" DIA. (OR SMALLER)

B. ANY U.L. CLASSIFIED CONCRETE BLOCK WALL.

A. MINIMUM 5" THICK CONCRETE WALL.

1. WALL ASSEMBLY :

SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS

NOTES : 1. ANNULAR SPACE = MIN. 0", MAX. 2-3/4".

2. T RATING = 1/4-HR. WHEN STEEL PIPE IS USED.

A

HILTI, INC. TULSA, OK 1-800-879-8000

HOLLOW BLOCK WALLS, USE STEEL WIRE MESH OR STEEL SLEEVE

3. MIN. 2" THICKNESS MINERAL WOOL (MIN. 4 PCF DENSITY) TIGHTLY PACKED.

A. MIN. 4-1/2" THICK LIGHTWEIGHT OR NORMAL WEIGHT CONCRETE.

3. WALLS REQUIRE 3/4" DEPTH OF HILTI FS 605 ON BOTH SIDES. IN

SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS.

4. A. MIN. 3/4" DEPTH HILTI FS 605.

2. 21" DIA. (OR SMALLER) STEEL PIPE.

TO AID INSTALLATION.

NOTES : 1. MAXIMUM DIAMETER OF OPENING 27".

B. MIN. 1/2" BEAD HILTI FS 605 AT POINT OF CONTACT.

B. MIN. 8" CONCRETE BLOCK WALL.

2. ANNULAR SPACE 0" TO MAXIMUM 3".

1. FLOOR OR WALL ASSEMBLY :

A

FRONT VIEW

SECTION A-A

U.L. SYSTEM NO. WJ1021

T RATING = 0 AND 1/4-HR.

A

F RATING = 2-HR.

SECTION A-A

SECTION A-ATOP VIEW

A

4a1

U.L. SYSTEM NO. CAJ1156

T RATING = 0-HR.

F RATING = 3-HR.

4b

NTS

NTS

LC

1'-0"

8" MIN

PART'L ACOUSTIC

CEILING TILE.

PENDANT TYPE

SP. HEAD

2'x2' ACOUSTIC

CEILING TILE.

SP. HEAD

PENDANT TYPE

2'x4' ACOUSTIC

CEILING TILE.

PENDANT TYPE

SP. HEAD

SP. HEAD

PENDANT TYPE

CEILING TILE.

2'x4' ACOUSTIC

1'-0"

1'-0"

1'-0"

2'-0"

1'-0"

1'-0"

R C

A B

-1

/2

Components:

1. Hex Nut

2. Lock Washer

3. Hanger Rod

4. Adjustable Hanger

Ring

5. Steel Beam or Bar Joist inches inches inches

Nominal

Pipe

Size

Minimum

A Dimension

Hanger

Takeout

Rod

Diameter

1/2 3 +1/4 3/8

3/4 3 +1/4 3/8

1 3 +1/4 3/8

1 1/4 3 1/4 +0 3/8

1 1/2 3 1/2 +0 3/8

2 3 3/4 -1/4 3/8

2 1/2 4 3/4 -3/4 3/8

3 5 1 3/8

4 5 3/4 -1 1/2 3/8

5 6 1/2 -2 1/4 1/2

6 7 1/2 -3 1/2

8 9 -4 1/2 1/2

DESIGN DATA FOR BEAM HANGER

NTS

PIPE

NOTES:

1. FOR INTERIOR WALLS

AND BELOW GRADE

GROUND TO GROUND

WALLS

CUT OPENING IN

EXISTING MASONRY

WALL LARGER THAN

SLEEVE AND FORM &

FILL WITH

EXPANSIVE

TYPE GROUT

FIRE

RESISTANT

SILICONE FOAM

SEALER

ESCUTCHEON PLATE

ON ONE OR BOTH

SIDES WHERE PIPING

IS EXPOSED

PIPE SLEEVE

EXISTING POURED

CONCRETE OR

C.M.U. WALL.

ANCHOR

LUGS

(MIN. 3 REQ'D)

PIPE

INSULATION

(WHERE REQ'D)

NTS

PIPE

PIPE

INSULATION

(WHERE REQ'D)

WATERPROOF CAULK

(WATER PROOF

FLOORS

ONLY

METAL

DECK

PIPE

SLEEVE

CONTINUOUSLY WELDED WATER

STOP & ANCHOR COLLAR,

WATERPROOF FLOORS

MIN. 1" ALL OTHERS TO HAVE

ANCHOR LUGS (MIN. 3 REQ'D).

FIRE RESISTANT

SILICONE FOAM

SEALER

CONCRETE FLOOR SLAB

NOTES:

1.

2.

3.

4.

5.

DETAILS SHOWN ARE TYPICAL DETAILS. IF FIELD CONDITIONS DO NOT MATCH THE

REQUIREMENTS OF THE TYPICAL DETAILS, APPROVED ALTERNATE DETAILS

SHALL BE UTILIZED. FIELD CONDITIONS AND DIMENSION NEED TO BE VERIFIED

FOR COMPLIANCE WITH THE DETAILS, INCLUDING BUT NOT LIMITED TO THE

FOLLOWING:

A. MINIMUM AND MAXIMUM WIDTH OF JOINTS.

B. TYPE AND THICKNESS OF FIRE-RATED CONSTRUCTION. THE

MINIMUM ASSEMBLY RATING OF THE FIRE STOP ASSEMBLY

SHALL MEET OR EXCEED THE HIGHEST RATING OF THE

ADJACENT CONSTRUCTION.

IF ALTERNATE DETAILS MATCHING THE FIELD CONDITIONS ARE NOT AVAILABLE,

MANUFACTURER'S ENGINEERING JUDGEMENT DRAWINGS ARE ACCEPTABLE,

DRAWINGS SHALL FOLLOW THE INTERNATIONAL FIRESTOP COUNCIL (IFC)

GUIDELINES FOR EVALUATING FIRESTOP SYSTEM ENGINEERING JUDGEMENTS.

REFERENCES:

A. 2013 UNDERWRITER'S LABORATORIES FIRE RESISTANCE

DIRECTORY, VOLUME 2

B. NFPA 101, LIFE SAFETY CODE

C. ALL GOVERNING LOCAL AND REGIONAL BUILDING CODES

FIRESTOP SYSTEM INSTALLATION MUST MEET THE REQUIREMENTS OF ASTM

E-814 (UL 1479) TESTED ASSEMBLIES THAT PROVIDE A FIRE RATING EQUAL TO

THAT OF THE CONSTRUCTION BEING PENETRATED.

ALL RATED THROUGH-PENETRATIONS SHALL BE PROMINENTLY LABELED WITH

THE FOLLOWING INFORMATION:

A. ATTENTION: FIRE RATED ASSEMBLY

B. UL SYSTEM #

C. PRODUCT(S) USED

D. HOURLY RATING (F-RATING)

E. INSTALLATION DATE

QUICK RESPONSE RECESSED DRY PENDENT FOR ALL DRY SPRINKLER

AREAS OR AS NOTED. PROVIDE CHROME HEAD AND CHROME ESCUTCHEON.

VARIES

VARIES

VARIES

TYPICAL RETURN BEND DETAIL 6

CEILING

1"

PER

MANUFACTURER'

S

INSTRUCTIONS

VARIES

VARIES

VARIES

CEILING

1"

PER

MANUFACTURER'

S

INSTRUCTIONS

VARIES

VARIES

VARIES

CEILING

1"

PER

MANUFACTURER'

S

INSTRUCTIONS

VARIES

VARIES

VARIES

CEILING

1"

PER

MANUFACTURER'S

INSTRUCTIONS

NTS

7UNDER DUCT SPRINKLER DETAIL

D R

O P

48" OR LARGER DUCT

VARIES

NTS

1"

3/4"

PLUG

1"x 3/4"x 1" TEE

BRANCHLINE

UPRIGHT

SPRINKLER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

A

100% BID DOCUMENTS

FOR CONSTRUCTION

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT

GMK Associates, Inc.

1201 Main Street, Suite 2100 Columbia, SC 29201 803-256-0000 Thomas M. Weiland, AIA

STAMPPROGRAM MANAGER

321 4 5 6 7 8 9 10

Odell International 129 Fast Lane, Suite 200 Mooresville, NC 28117 704-401-2040 C. Harmon Reed, Jr. AIA

CONSULTANT

Charlotte Engineers, LLP 5838 Monroe Road Charlotte, NC 28212 704-531-3000 Michael Eaves FULLY SPRINKLERED

Approved:

U A

C a lla h a n \L o c a l R e v it \R

\4

C

E C e n tr a l M o d e l.

rv t

/9 /2

:3

:3

A

M

FX002

FIRE SUPPRESSION - DETAILS EHRM - RENOVATE B3 FOR EHRM

ADMIN AND TRAINING

COLUMBIA, SC

544-22-703

B3

07/15/2025 GAT JRC

DIESEL FIRE PUMP

1. PUMP:

A. PUMP MANUFACTURER: PATTERSON

B. MODEL NUMBER: 6X5X17

C. SERIAL NUMBER: FP-CO4875

D. TYPE: HORIZONTAL SPLIT-CASE

E. GPM: 1000

F. RPM: 1750

G. SUCTION: 8 INCHES

H. DISCHARGE: 6 INCHES

2. DIESEL ENGINE:

A. MANUFACTURER: CLARK

B. MODEL: JU4H-UF50

C. SERIAL NUMBER: PE4045T504320

D. TYPE: DIESEL

3. PUMP CONTROLLER:

A. MANUFACTURER: FIRETROL

B. MODEL NO.: FAT1100-JL12N

C. SERIAL NO.: 308886-01RE

4. JOCKEY PUMP CONTROLLER:

A. MANUFACTURER: FIRETROL

B. MODEL NO.: FTA1100-JL12N

C. SERIAL NO.: 308886-01RE

FIRE PUMP YEARLY TEST AND FIRE HYDRANT FLOW TEST

DIESEL FIRE PUMP TEST

DATE: 04/10/2024

PERFORMED BY:

PALMETTO AUTOMATIC SPRINKLER COMPANY, INC.

PO BOX 29127

CAYCE-WEST COLUMBIA, SOUTH CAROLINA 29171

RESULT:

GPM: 0 1000 1440

SUCTION PSI: 46 25 6

DISCHARGE PSI: 140 101 60

CITY WATER FIRE HYDRANT FLOW TEST:

DATE PERFORMED: 04/10/2024

PERFORMED BY: PALMETTO AUTOMATIC SPRINKKLER COMPANY, INC.

RESULTS:

STATIC PRESSURE: 101 PSI

NOTE: CONTRACTOR SHALL BE REQUIRED TO PERFORM THERE OWN DIESEL

FIRE PUMP AND CITY WATER FIRE HYDRANT FLOW TESTS FOR THEIR DESIGN

INPUTS FOR THEIR FIRE PROTECTION HYDRAULIC CALCULATIONS AND PIPE

SIZING.

PIPE SUPPORT AND SEISMIC RESTRAINT -

HORIZONTAL PIPING

SEISMIC RESTRAINT COMPONENTS

(TYPICAL APPLICATIONS)

CLAMP

BAR JOISTS

(AT 45 )

SEISMIC

TRANSVERSE

BRACE

PIPE

CLEVIS HANGER

NOTE:

ON WOOD ROOF

TRUSSES - USE

A CEILING FLANGE

OR ANGLE BRACKET

PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:

1" & 1-1/2" PIPES: 20 FT. ON CENTER

3/8" THREADED

ROD

BAR JOISTS

2" & 2-1/2" PIPES: 30 FT. ON CENTER

3" , 4" & 6" PIPES: 40 FT. ON CENTER

TOLCO BAND HANGERS FIG. 200, 2NFPA,

TOLCO FIG. 25 SURGE RESTRAINER

TYPE 1- FOR USE WITH 1" AND 1 1/4"

PIPE AND HANGER.

TYPE 2- FOR USE WITH 1 1/2" AND 2"

PIPE AND HANGER

TOLCO FIG. 25 IS DESIGNED TO BE USED ONLY

TO RESTRICT UPWARD MOVEMENT OF PIPE WITHIN

THE HANGER AS IT OCCURS DURING SPRINKLER

HEAD ACTIVATION OR EARTHQUAKE TYPE ACTIVITY

TOLCO FIG.

909 OR 910

TOLCO U.L. LISTED ATTACHMENTS.

TOLCO FIG. 1000 FAST CLAMPS UNDERWRITERS

LBORATORIES LISTED, MUST BE USED WITH

PROVIDE TOLCO RESTRAINTS OR APPROVED

EQUAL AS REQUIRED.

SHOWN FLAT

TORQUE-TIGHTEN HEX

MINIMUM REQUIRED

NUTS UNTIL LEAF

NOTE: TO ASSURE

SPRING IS FLAT

NOTE:

BAND HANGER

TOLCO

USED IN LONGITUDINAL BRACE

PIPE CLAMP (TOLCO FIG. 4A)

(OPTIONAL METHOD)

LATERAL (TRANSVERSE)

BRACE

TOLCO

TOLCO FIG. 1000

LEAF SPRING

FAST CLAMP

FIG. 1000

909 OR 908

TOLCO FIG.

909 OR 910

TOLCO FIG.

CONFIGURATION AND

NUTS ARE TIGHTENED

ORIENTATION BEFORE

LEAF SPRING

LATERAL (TRANSVERSE) BRACE

FAST CLAMP

TOLCO FIG. 1000

LONGITUDINAL/4 WAY BRACE

(OPTIONAL METHOD)

909 OR 910

TOLCO FIG.

TOLCO FIG. 907

MAX.

TOLCO FIG. 1000

909 OR 910

TOLCO FIG.

3"

(2) FAST CLAMP

TOLCO FIG. 1000

TOLCO FIG. 1000

FASTCLAMP RISER BRACE

TOLCO FIG.

909 OR 910

CLAMP

BAR JOISTS

(AT 45 )

SEISMIC

TRANSVERSE

BRACE

PIPE

CLEVIS HANGER

ON WOOD ROOF

TRUSSES - USE

A CEILING FLANGE

OR ANGLE BRACKET

PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:

1" & 1-1/2" PIPES: 20 FT. ON CENTER

3/8" THREADED

ROD

BAR JOISTS

2" & 2-1/2" PIPES: 30 FT. ON CENTER

3" , 4" & 6" PIPES: 40 FT. ON CENTER

WITH TOLCO BAND HANGERS FIG. 200, 2NFPA,

TOLCO FIG. 25 SURGE RESTRAINER

TYPE 1- FOR USE WITH 1" AND 1 1/4"

PIPE AND HANGER.

TYPE 2- FOR USE WITH 1 1/2" AND 2"

PIPE AND HANGER

TO RESTRICT UPWARD MOVEMENT OF PIPE WITHIN

THE HANGER AS IT OCCURS DURING SPRINKLER

HEAD ACTIVATION OR EARTHQUAKE TYPE ACTIVITY

TOLCO FIG.

909 OR 910

TOLCO U.L. LISTED ATTACHMENTS.

TOLCO FIG. 1000 FAST CLAMPS UNDERWRITERS

LBORATORIES LISTED, MUST BE USED WITH

PROVIDE TOLCO RESTRAINTS OR APPROVED

EQUAL AS REQUIRED.

SHOWN FLAT

TORQUE-TIGHTEN HEX

BAND HANGER

TOLCO

USED IN LONGITUDINAL BRACE

PIPE CLAMP (TOLCO FIG. 4A)

(OPTIONAL METHOD)

LATERAL (TRANSVERSE)

BRACE

TOLCO

TOLCO FIG. 1000

LEAF SPRING

FAST CLAMP

FIG. 1000

909 OR 908

TOLCO FIG.

909 OR 910

TOLCO FIG.

CONFIGURATION AND

NUTS ARE TIGHTENED

ORIENTATION BEFORE

LEAF SPRING

LATERAL (TRANSVERSE) BRACE

FAST CLAMP

TOLCO FIG. 1000

LONGITUDINAL/4 WAY BRACE

(OPTIONAL METHOD)

909 OR 910

TOLCO FIG.

TOLCO FIG. 907

MAX.

TOLCO FIG. 1000

909 OR 910

TOLCO FIG.

3"

(2) FAST CLAMP

TOLCO FIG. 1000

TOLCO FIG. 1000

FASTCLAMP RISER BRACE

TOLCO FIG.

909 OR 910

NTS

NTS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

A

100% BID DOCUMENTS

FOR CONSTRUCTION

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT

GMK Associates, Inc.

1201 Main Street, Suite 2100 Columbia, SC 29201 803-256-0000 Thomas M. Weiland, AIA

STAMPPROGRAM MANAGER

321 4 5 6 7 8 9 10

Odell International 129 Fast Lane, Suite 200 Mooresville, NC 28117 704-401-2040 C. Harmon Reed, Jr. AIA

CONSULTANT

Charlotte Engineers, LLP 5838 Monroe Road Charlotte, NC 28212 704-531-3000 Michael Eaves FULLY SPRINKLERED

Approved:

U A

C a lla h a n \L o c a l R e v it \R

\4

C

E C e n tr a l M o d e l.

rv t

/9 /2

:3

:3

A

M

FX003

FIRE SUPPRESSION - FIRE PUMP

TEST RESULTS AND SEISMIC

DETAILS

EHRM - RENOVATE B3 FOR EHRM

ADMIN AND TRAINING

COLUMBIA, SC

544-22-703

B3

PROCEDURES FOR DRAINING WET PIPE SYSTEM

1. TO DRAIN A WET PIPE SYSTEM THE PROCEDURE TO BE PERFORMED AND SUBMITTED TO THE

ARCHITECT, ENGINEER, AND OWNER'S REPRESENTATIVE SHOULD INCLUDE BUT NOT LIMITED TO THE

FOLLOWING.

1.1. CLOSE ALL SPRINKLER CONTROL VALVES.

1.2. TAG ALL CLOSED VALVES.

1.3. OPEN MAIN DRAIN VALVES AND AUXILIARY DRAINS ALLOWING THE SYSTEM FOR 100%

COMPLETE DRAINAGE.

1.4. WHEN THE WATER HAS BEEN COMPLETELY DRAINED, CLOSE THE MAIN DRAIN AND AUXILIARY

DRAIN VALVES. WHEN THE WATER HAS STOPPED FLOWING, CHECK ALL CONTROL VALVES TO

BE SURE THEY ARE TIGHTLY SHUT; ANY MALFUNCTION CONTROL VALVES SHOULD BE

REPAIRED AND/OR REPLACED IMMEDIATELY AS DEEMED APPLICABLE.

1.5. CHECK FOR WATER TRAPPED AT ALL LOW POINTS IN PIPING THAT LACK AUXILIARY DRAINS;

REMOVE DRAIN AND REPLACE SUCH PIPING.

1.6. ONCE ABOVE ITEM ARE CONFIRMED WITH 100% CERTAINTY THE CONTRACTOR SHALL

PERFORM ALL NEW INSTALLATIONS.

1. MINIMUM REQUIREMENTS

A. THE CONTRACTOR SHALL ENACT MEASURES THAT SHALL BE TAKEN DURING THE IMPAIRMENT

TO ENSURE THAT INCREASED RISKS ARE MINIMIZED AND THE DURATION OF THE IMPAIRMENT IS

LIMITED.

B. THE CONTRACTOR SHALL NOTIFY IN WRITING TO THE ARCHITECT, ENGINEER, VA COR, AND VA

FIRE OFFICIAL OF THE PLANNED IMPAIRMENT, PROCEDURES DURING THE IMPAIRMENT,

TESTING RE-COMMISSIONING OF THE FIRE PROTECTION/FIRE ALARM SYSTEMS FOR

PROTECTION OF THE AFFECTED LOCATIONS WITHIN THE SCOPE OF WORK SUITE.

C. THE CONTRACTOR THROUGH THE VA COR SHALL PREPARE AND SUBMIT TO THE VA COR FOR

OWNER'S DISTRIBUTION TO THE EMPLOYEES IN THE AREA OF THE IMPAIRMENT SHALL BE

PROVIDED WITH INFORMATION ON ALTERNATE FIRE PROTECTION THAT WILL BE AVAILABLE.

D. THE SUSPENSION OF ALL NON-ESSENTIAL HOT WORK PERMITS UNTIL THE CONCLUSION AND

REACTIVATION OF THE FIRE SUPPRESSION SYSTEM AND INTERFACING FIRE DETECTION

SYSTEM.

2. FIRE PROTECTION IMPAIRMENT PLAN

A. A FIRE PROTECTION IMPAIRMENT PLAN SHOULD BE DEVELOPED AND IMPLEMENTED BEFORE

AUTHORIZATION IS GIVEN, THE IMPAIRMENT COORDINATOR SHOULD VERIFY THAT THE

FOLLOWING PROCEDURES HAVE BEEN IMPLEMENTED:

• THE EXTENT AND EXPECTED DURATION OF THE IMPAIRMENT THAT HAS BEEN DETERMINED.

• THE AREA OF THE BUILDING THAT WILL BE AFFECTED HAS BEEN INSPECTED AND THE

INCREASED RISKS DETERMINED.

• RECOMMENDATIONS HAVE BEEN SUBMITTED TO THE ARCHITECT, ENGINEER AND VA COR

REPRESENTATIVE TO MITIGATE ANY INCREASED RISKS.

• WHERE A REQUIRED FIRE PROTECTION SYSTEM IS OUT OF SERVICE FOR MORE THAN FOUR

(4) HOURS IN A 24 HOUR PERIOD THE CONTRACTOR & OWNER SHALL ARRANGE FOR THE

FOLLOWING:

• AN APPROVED FIRE WATCH.

• ESTABLISHMENT AND IMPLEMENTATION OF AN APPROVED PROGRAM TO ELIMINATE

POTENTIAL IGNITION SOURCES AND LIMIT OF THE AMOUNT OF COMBUSTIBLES IN THE

AREA OF CONSTRUCTION.

• ASSIGN PERSONNEL TO TRANSMIT FIRE ALARMS TO THE OWNER'S HOSPITAL

COORDINATOR WHERE THE MAIN FIRE ALARM PANEL IS BEING MONITORED FOR 24/7

COVERAGE.

3. TAG IMPAIRMENT SYSTEM

A. A TAG SHALL BE USED TO INDICATE THAT A SYSTEM OR PART THERE OF, HAS BEEN REMOVED

FROM SERVICE. THE CONTRACTOR SHALL PLACE TAGS ON ALL AFFECTED COMPONENTS, E.G.,

TAMPER SWITCHES, VALVES, FIRE ALARM ANNUNICATOR DEVICES, ETC., PRIOR TO THE

COMMENCEMENT OF ANY WORK.

B. THE TAG SHALL BE POSTED AT EACH FIRE PROTECTION CONNECTION AND SYSTEM CONTROL

VALVE AND OTHER LOCATION REQUIRED BY THE VA COR, VA FIRE OFFICIAL OR THE ENGINEER

OF RECORD, INDICATING WHICH SYSTEM, OR PART THERE OF, HAS BEEN REMOVED FROM

SERVICE.

• THE SUPERVISORS IN THE AREA TO THE AFFECTED AREA HAS BEEN NOTIFIED.

• THE FIRE DEPARTMENT HAS BEEN NOTIFIED.

• A TAG IMPAIRMENT SYSTEM HAVE BEEN IMPLEMENTED.

• ALL NECESSARY TOOLS, EQUIPMENT, MATERIAL AND APPURTENANCES ARE LOCATED AND

ASSEMBLED ON THE IMPAIRMENT SITE.

4. RESTORING SYSTEMS TO SERVICE

A. WHEN ALL IMPAIRED EQUIPMENT IS RESTORED TO NORMAL WORKING ORDER, THE VA COR, VA

FIRE OFFICIAL AND ENGINEER OF RECORD SHALL VERIFY THAT THE CONTRACTOR HAS

IMPLEMENTED THE FOLLOWING PROCEDURES:

• ALL NECESSARY INSPECTION HAVE BEEN CONDUCTED FOLLOWING NFPA 13, 25 AND 72

REQUIREMENTS IN ORDER TO…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .