S02-RFP Attachment 8- Fire Sup Drawings-COL.pdf
PDF 3 MB Posted
- Solicitation number
- 36C77626R0032_2
About this file
This document is a comprehensive set of fire protection system design and construction specifications for the renovation of Building 3 (EHRM Admin and Training) at the VA Dorn Veterans Affairs Medical Center in Columbia, South Carolina. The project involves modifications to the existing wet-pipe fire sprinkler system, including demolition of outdated components and installation of new fire suppression infrastructure to support renovated spaces and new mechanical equipment.
The specifications establish detailed requirements for system design, installation, testing, and commissioning. The fire protection contractor must design a complete system in accordance with NFPA 13 (2022 Edition), NFPA 25, and the VA Fire Protection Design Manual, with hydraulic calculations based on current fire hydrant flow test data (dated 04/10/2024 showing static pressure of 101 PSI). The system utilizes the existing diesel fire pump (Patterson model 6X5X17, 1000 GPM at 1750 RPM) and incorporates design densities of 0.10 GPM/sq.ft. for light hazard areas and 0.15-0.20 GPM/sq.ft. for ordinary hazard areas, with maximum sprinkler head coverage of 130-225 sq.ft. depending on occupancy classification. All shop drawings and calculations must be sealed by a licensed professional engineer registered in South Carolina or a NICET Level III/IV sprinkler designer. The contractor bears responsibility for coordination with other trades, all cutting and patching, through-penetration firestop assemblies meeting UL standards, pipe support and seismic restraints per VA Seismic Design Requirements, and comprehensive testing with final certification of approval from the VA fire official and engineer of record prior to project acceptance. Interim fire protection measures including fire watches, temporary heat detectors interfaced with the fire alarm system, and fire extinguishers are required during system impairments exceeding four hours, with minimum one-week advance notice to the VA Contracting Officer's Representative.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FIRE PROTECTION GENERAL NOTES
1. THE ADDITIONS TO THE EXISTING NEW SPRINKLER SYSTEM SHALL BE SIZED IN ACCORDANCE WITH NFPA
13 AND SHALL BE HYDRAULICALLY CALCULATED TO MEET THE REQUIREMENTS OF NFPA 13 AND
APPROVED BY THE VA FIRE SAFETY OFFICIAL HAVING JURISDICTION, THE ENGINEER, AND THE ARCHITECT. THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING FLOW TEST DATA TO PERFORM
AS A BASIS OF THEIR CALCULATIONS.
2. THE SYSTEM SHALL BE DESIGNED AND BUILT IN A WORKMANLIKE MANNER, IN ACCORDANCE WITH DETAILED DRAWINGS TO BE SUBMITTED FOR APPROVAL. THE WORK SHALL INCLUDE ALL COMPONENTS
REQUIRED TO PROVIDE A COMPLETE SYSTEM.
3. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE A SET OF SHOP DRAWINGS THAT INCLUDE ALL PIPE SIZES, ELEVATIONS, HEAD LOCATIONS, DIMENSIONS, VALVES, INSPECTOR TESTS, FLOW SWITCHES, TAMPER SWITCHES, ETC.
4. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE SPRINKLER LAYOUT INCLUDING LOCATION OF
PENDANT HEADS FOR ALL LOCATION IN THIS SCOPE OF WORK.
5. THE SHOP DRAWINGS AND CALCULATIONS IF REQUIRED, SHALL BE SUBMITTED TO VA'S FIRE OFFICIAL AND VA ’ S ENGINEER AND THESE CALCULATIONS AND DRAWINGS SHALL BE SUBMITTED TO ALL
AUTHORITIES HAVING JURISDICTIONS.
6. SPRINKLER HEADS AND ASSOCIATED MAIN/BRANCH PIPING SHALL BE PROVIDED AND LOCATED IN
ACCORDANCE WITH NFPA 13 AND THE VA FIRE PROTECTION DESIGN MANUAL.
7. THE FIRE PROTECTION CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS AT THE PROJECT SITE.
8. SPRINKLER PIPING SHOULD BE ROUTED AS HIGH AS POSSIBLE WHILE STILL COORDINATING WITH OTHER
TRADES. ELEVATION OF SPRINKLER PIPING AND HEAD MUST BE DETERMINED BY PROPOSED OR
EXISTING CEILING HEIGHTS.
9. ALL MATERIAL AND ITS INSTALLATION SHALL BE IN COMPLETE COMPLIANCE WITH ALL APPLICABLE SECTIONS OF THE LATEST EDITION OF NFPA. AND FACTORY MUTUAL GUIDELINES. THE FIRE PROTECTION CONTRACTOR SHALL BE REQUIRED TO COMPLY WITH ALL SPECIAL CONDITIONS SET FORTH BY THE VA
FIRE MARSHAL , VA FIRE PROTECTION DESIGN MANUAL AND THE PROJECT SPECIFICATIONS.
10. THE FIRE PROTECTION CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL AND EQUIPMENT; AND, PERFORM ALL OPERATIONS NECESSARY FOR THE INSTALLATION OF A COMPLETE FIRE PROTECTION SYSTEM THAT IS READY FOR USE WITHIN THE INTENT OF AND AS INDICATED ON THE DRAWINGS, SPECIFICATIONS AND AS HEREIN SPECIFIED.
11. PROVIDE CUTTING AND PATCHING OF BUILDING AS REQUIRED TO INSTALL NEW WORK.
12. SMALL ITEMS NOT SHOWN OR SPECIFIED, BUT OBVIOUSLY REQUIRED BY GOOD GENERAL PRACTICE TO
COMPLETE THE WORK SHALL BE FURNISHED AND INSTALLED THE SAME AS IF BOTH SHOWN AND
SPECIFIED.
13. BY SUBMITTING A PROPOSAL FOR THIS WORK, THE CONTRACTOR WILL BE HELD TO HAVE EXAMINED THE SITE AND SATISFIED THEMSELVES AS TO EXISTING CONDITIONS UNDER WHICH THEY WILL BE OBLIGED
TO OPERATE OR THAT WILL IN ANY MANNER AFFECT THEIR WORK UNDER THIS CONTRACT. NO
ALLOWANCES SHALL BE MADE SUBSEQUENTLY IN THIS CONTRACT IN BEHALF OF CONTRACTOR OF ANY
ERROR OR NEGLIGENCE ON THEIR PART
14. FIRE PROTECTION CONTRACTOR SHALL MAKE CONNECTION INTO THE EXISTING WET-PIPE FIRE
SPRINKLER SERVICE FOR THIS SCOPE OF WORK.
15. THE FIRE PROTECTION CONTRACTOR SHALL SCHEDULE WITH THE VA COR ALL TIE-INS TO EXISTING
SYSTEMS AND PERFORM REQUIRED SHUTDOWN AND RE-INITIALIZATION OF THE EXISTING FIRE
SPRINKLER SYSTEM; THESE SERVICES WILL INCLUDE DRAIN AND REFILL OF THE FIRE SPRINKLER
SYSTEMS IN THE AFFECTED AREAS OF THIS PROJECT WORK SCOPE.
16. ALL FIRE PROTECTION WORK SHALL BE MADE IN ACCORDANCE WITH RULES AND REGULATIONS OF VA FIRE PROTECTION DESIGN MANUAL, PROJECT SPECIFICATIONS, NFPA 13 AND NFPA 25. THE ENTIRE FIRE PROTECTION SYSTEM FOR THE WORK SCOPE SHOWN ON THESE DESIGN DRAWINGS SHALL BE MADE BY THIS CONTRACTOR IN THE PRESENCE OF AN INSPECTOR FROM THE VA FIRE OFFICIAL, VA COR AND THE VA'S ENGINEER. THE FIRE PROTECTION SYSTEM SHALL BE TESTED AS REQUIRED BY NFPA 13.
17. THROUGH PENETRATION ASSEMBLIES SHALL BE PROVIDED AT EACH OPENING WHERE EXPOSED SPRINKLER PIPING PASS THROUGH RATED WALLS, FLOORS AND PARTITIONS. ALL PIPING PENETRATIONS MUST BE SEALED IN ACCORDANCE WITH “ UL ” LISTING SEALING METHOD AND/OR AS DETAILED IN THESE
CONTRACT DRAWINGS OR SPECIFICATIONS.
18. ALL APPLIANCES AND APPURTENANCES SHALL BEAR LABEL OF UL/FM APPROVED AND LABELED FOR ITS
INTENDED USE.
19. ALL MATERIALS AND EQUIPMENT SHALL BE INSTALLED AND COMPLETED IN A FIRST-CLASS
WORKMANLIKE MANNER AND IN ACCORDANCE WITH THE BEST MODERN METHODS AND PRACTICES.
ANY MATERIALS WHICH SHALL NOT PRESENT AN ORDERLY AND REASONABLY NEAT AND/OR
WORKMANLIKE APPEARANCE SHALL BE REMOVED AND REPLACED WHEN SO DIRECTED BY THE VA COR, VA FIRE OFFICIAL, THE ARCHITECT OR ENGINEER OF RECORD. THE REMOVAL AND REPLACEMENT OF THIS WORK SHALL BE DONE WHEN DIRECTED IN WRITING BY THE VA COR, AT THE CONTRACTOR ’ S
EXPENSE.
20. SUPPLY ALL SPRINKLER EQUIPMENT ACCESSORIES AS REQUIRED.
21. ALL HANGERS SHALL BE FASTENED BY MEANS OF BEAM CLAMPS, CONCRETE INSERTS OR OTHER
APPROVED DEVICES INSTALLED BY THIS CONTRACTOR.
22. SPRINKLER HEAD RATINGS, SPRAY TYPE, AND FINISH SHALL BE AS SPECIFIED ON PROJECT PLANS.
WHERE NOT SPECIFICALLY IDENTIFIED ON PLANS, SPRINKLER HEADS SHALL QUICK RESPONSE TYPE UPRIGHT PENDANT WITH PAINTED COVER PLATE OR AS REQUIRED BY THE VA COR. REGULAR PENDANT HEADS IN FINISHED SPACES SHALL BE CHROME PLATED WITH CHROME PLATED CEILING PLATES UNLESS
OTHERWISE NOTED. NEW HEADS SHALL MATCH EXISTING.
23. THE FIRE PROTECTION CONTRACTOR WILL BE REQUIRED TO COORDINATE ACCEPTANCE FOR VARIATION OF EQUIPMENT LOCATIONS AND EQUIPMENT CONFIGURATIONS WITH THE FIRE MARSHAL, THE LOCAL
JURISDICTION, THE OWNER, AND THE GENERAL CONTRACTOR.
24. THE FIRE PROTECTION CONTRACTOR IS RESPONSIBLE FOR COORDINATING CHANGES IN ELECTRICAL
REQUIREMENTS WITH THE ELECTRICAL CONTRACTOR.
25. VARIATION FROM SPECIFIED PHYSICAL EQUIPMENT APPEARANCE WILL NEED TO BE APPROVED
THROUGH THE ARCHITECT.
26. SYSTEM PIPING WILL BE SUPPORTED AND BRACED WITH HANGERS AND LISTED EARTHQUAKE BRACE ASSEMBLIES IN ACCORDANCE WITH THE VA SEISMIC DESIGN REQUIREMENTS MANUAL AND NFPA 13.
27. ONE SET OF STAMPED, APPROVED DRAWINGS SHALL BE ON SITE AT ALL TIMES AND MADE AVAILABLE TO
THE INSPECTOR AND/OR ARCHITECT/OWNER UPON DEMAND.
28. FIRE PROTECTION SYSTEMS SHALL BE INSTALLED BY A CONTRACTOR LICENSED TO PERFORM SUCH
WORK IN THE PROJECT JURISDICTION.
29. AVOID DAMAGING EXISTING SURFACES AND EQUIPMENT AND ASSOCIATED MATERIALS FROM THE SITE.
REPAIR ANY DAMAGE CAUSED DURING WORK AT NO EXTRA COST TO THE VA.
30. REPAIR FIRE AND SMOKE RATED PARTITIONS SURROUNDING FIRE ALARM WORK AS SPECIFIED. REFER
TO ARCHITECTURE PLANS FOR LOCATIONS OF SMOKE AND FIRE PARTITIONS.
31. THREADED BUSHING SHALL NOT BE USED.
32. ANY SPRINKLER REMOVED FROM SERVICE FOR ANY REASON (E.G., REMOVED, RELOCATED, ETC.) SHALL BE REPLACED WITH A NEW SPRINKLER HEAD IN ACCORDANCE WITH NFPA 25, SECTION 5.4.1.1.
33. NEW ARMOVERS SHALL BE PROVIDED TO EITHER RELOCATED OR NEW SPRINKLERS AS REQUIRED BY
NFPA 13.
34. SPRINKLER SYSTEM SHOP DRAWINGS SHALL INCLUDE ALL MATERIALS REQUIRED BY NFPA 13 CHAPTER 27.
35. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CUTTING AND PATCHING OF WALLS AND CEILING AS
MAY BE REQUIRED FOR THE INSTALLATION OF THE NEW FIRE SUPPRESSION SYSTEM.
36. INTERRUPTIONS IN OPERATION OF THE FIRE SUPPRESSION SYSTEM MUST BE SCHEDULED WITH THE VA COR AT LEAST ONE(1) WEEK IN ADVANCE; WITH PROPER NOTICE PROVIDED TO THE EMERGENCY
RESPONSE TEAMS - BOTH INSIDE AND OUTSIDE OF THE VA DORN CAMPUS.
37. WHEN WORK IS BEING PERFORMED IN AREAS THAT MUST CONTINUE OPERATION, CONTRACTOR SHALL KEEP THE AREAS CLEAN AND CLEAR OF OBSTRUCTIONS, AS MUCH AS POSSIBLE, PROVIDE WARNING
SIGNS AS NECESSARY FOR PROTECTION OF OCCUPANTS FROM ASSOCIATED RISKS. REMOVE ALL
DEBRIS AS WORK PROGRESSES.
38. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE VA COR WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE VA COR, VA FIRE OFFICIAL AND VA'S
ENGINEER OF RECORD WILL BE REQUIRED PRIOR TO FINAL ACCEPTANCE OF THE PROJECT.
39. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE
SPRINKLER SYSTEM PER NFPA 13 AND VA FIRE PROTECTION DESIGN MANUAL REQUIREMENTS.
40. LIGHT FIXTURES AND HVAC DIFFUSERS TAKE SPACE PREFERENCE, ADD ADDITIONAL SPRINKLER HEADS AS REQUIRED TO MEET "COVERAGE REQUIREMENTS" OF NFPA 13 AND THE VA FIRE PROTECTION DESIGN
MANUAL
41. COORDINATE PLACEMENT OF SPRINKLER HEADS WITH ALL MECHANICAL DUCTS, DIFFUSERS AND
ELECTRICAL LIGHT FIXTURES.
42. THE FIRE PROTECTION CONTRACTOR SHALL INDICATE ON THEIR SHOP DRAWINGS; CEILING TILE
LOCATIONS WITH ALL CEILING MOUNTED FIRE PROTECTION DEVICES.
43. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH A NON-SHRINKING
GROUT OR CAULKING MATERIAL.
44. THE FIRE PROTECTION SYSTEM / AREA OF PROTECTION INDICATED ON THE PLANS IS FOR COORDINATION AND BIDDING PURPOSES ONLY. THE FIRE PROTECTION CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COMPLETE DESIGN
45. ALL PIPING SYSTEMS THAT ARE NOT INTENDED TO BE REUSED SHALL BE REMOVED AND PIPES SHALL BE
CAPPED AS CLOSE TO MAINS AS POSSIBLE.
46. IT IS THE INTENTION OF THE SPECIFICATION AND DRAWINGS TO CALL FOR A COMPLETE AND FUNCTIONAL SYSTEM, INSTALLED AS PER THE APPLICABLE CODES WITH ALL FINISHED WORK TESTED AND READY FOR
OPERATION.
47. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE VA COR, VA FIRE OFFICIAL, VA'S ENGINEER OF RECORD, FIRE ALARM CONTRACTOR, AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN
OR INTERRUPTION OF SERVICE.
48. ALL MATERIALS, PIPING, FITTINGS, VALVES, AND APPLIANCES HEREINAFTER SPECIFIED AND THOSE WHICH ARE ESSENTIAL BUT HAVE NOT BEEN SPECIFIED SHALL BE NEW AND OF THE HIGHEST GRADE AND
QUALITY, FREE FROM DEFECTS AND SUCH AS BREAKS, FLAWS, AND IMPERFECTIONS.
49. CORE DRILL MASONRY WALLS FOR NEW PIPING. SEAL PENETRATIONS AS NECESSARY TO MAINTAIN
INTEGRITY OF EXISTING WALLS.
50. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL CUTTING AND PATCHING OF WALLS AND CEILING AS MAY
BE REQUIRED FOR THE INSTALLATION OF THE NEW FIRE SUPPRESSION SYSTEM.
51. ALL APPLIANCES AND APPURTENANCES SHALL BEAR LABEL OF UL LISTED, / FM APPROVED AND LABELED
FOR ITS INTENDED USE.
52. LONG RUNS OF PIPE SHALL BE PROVIDED WITH A SUITABLE MEANS TO PERMIT FREE MOVEMENT RESULTING FROM EXPANSION AND CONTRACTION OF PIPE. REDUCTION IN PIPE SIZES SHALL BE MADE
WITH ONE-PIECE REDUCTION FITTINGS.
53. THE FIRE PROTECTION CONTRACTOR IS TO MAINTAIN A SET OF UP TO DATE CONSTRUCTION DOCUMENTS AVAILABLE AT THE PROJECT SITE AT ALL TIMES DURING CONSTRUCTION. THE FIRE PROTECTION CONTRACTOR IS TO INSTRUCT THE VA'S REPRESENTATIVE(S) IN THE OPERATION AND MAINTENANCE REQUIREMENTS OF THE COMPLETED BUILDING FIRE PROTECTION SYSTEM AT A TIME AGREED ON BY THE OWNER. THE OWNER’S REPRESENTATIVE(S) SHALL BE PROVIDED WITH AN UP TO DATE CONSTRUCTION
DOCUMENTS AND A COPY OF NFPA 25 PRIOR TO INSTRUCTION BY THIS CONTRACTOR.
54. COORDINATE WITH OTHER WORK, INCLUDING HVAC, PLUMBING PIPING, ELECTRICAL AS NECESSARY TO INTERFACE COMPONENTS OF FIRE SPRINKLER PIPING PROPERLY WITH OTHER WORK. SYSTEM PIPING WILL BE SUPPORTED AND BRACED WITH HANGERS AND LISTED EARTHQUAKE BRACE ASSEMBLIES IN ACCORDANCE WITH THE VA SEISMIC DESIGN MANUAL, VA FIRE PROTECTION DESIGN MANUAL AND NFPA 13.
55. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO REMOVE AND LEGALLY DISPOSE OF
DEMOLISHED MATERIALS UNLESS NOTED OTHERWISE IN THE DRAWINGS.
56. ALL WALL AND FLOOR PENETRATIONS SHALL BE CORE-DRILLED AND SLEEVED.
57. UNLESS INDICATED OTHERWISE IN THE DRAWINGS OR SPECIFICATIONS, FIRE SUPPRESSION CONTRACTOR IS RESPONSIBLE FOR SEALING ALL FIRE RATED WALL PARTITIONS WITH UL LISTED MATERIAL AND
METHODS.
58. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH A NON-SHRINKING
GROUT OR CAULKING MATERIAL AND APPROVED ASSEMBLY.
59. BEFORE SUBMITTING A PROPOSAL FOR THE WORK, EACH BIDDER WILL BE HELD RESPONSIBLE TO HAVE EXAMINED THE EXISTING SITE CONDITIONS FOR THE WORK INCLUDED UNDER THIS CONTRACT. NO ALLOWANCE WILL BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR
ANY ERROR OR NEGLIGENCE ON HIS PART.
60. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE COMPLETE DESIGN OF THE FIRE PROTECTION SYSTEM AND SHALL PROVIDE SEALED SHOP DRAWINGS. SPRINKLER SYSTEM PLANS AND CALCULATIONS SHALL BE SEALED BY AN PROFESSIONAL ENGINEER REGISTERED IN THE STATE WHERE THE WORK IS TO OCCUR, OR SEALED BY A NICET LEVEL III OR LEVEL IV SPRINKLER DESIGNER CERTIFIED IN "WATER BASED SYSTEMS LAYOUT". DRAWINGS SHALL BE SEALED IN ACCORDANCE WITH REQUIREMENTS
OF THE VA COR, VA FIRE OFFICIAL AND THE ENGINEER OF RECORD.
61. THE FIRE SUPPRESSION SYSTEM AREA OF PROTECTION INDICATED ON THE PLANS IS FOR COORDINATION AND BIDDING PURPOSES ONLY. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COMPLETE DESIGN.
62. ALL HANGERS MUST BE FM APPROVED, UL LISTED AND THE TYPE APPROVED BY NFPA 13. NO SPRINKLER PIPING IS TO BE SUPPORTED FROM ANY MECHANICAL OR ELECTRICAL DEVICES. ALL PIPE SHALL BE SUPPORTED FROM THE BUILDING STRUCTURE IN A NEAT AND WORKMANLIKE MANNER. VERTICAL RISERS SHOULD BE SUPPORTED AT EACH FLOOR LEVEL WITH STEEL PIPE CLAMPS. HANGING PIPES FROM OTHER PIPES WILL BE NOT PERMITTED. PIPING SHALL BE CAREFULLY COORDINATED BEFORE INSTALLATION WITH OTHER SYSTEMS AND EQUIPMENT IN CHASES AND OTHER CONGESTED AREAS. MAXIMUM DISTANCES BETWEEN PIPE SUPPORTS SHALL MEET THE REQUIREMENT STATED IN NFPA 13, SECTION 17.4.2.1 AND TABLE 17.4.2.1(a). TITLED "MAXIMUM DISTANCE BETWEEN HANGERS (FT-IN)."
63. MAINTAINABILITY
A. EXTERNAL AND INTERNAL PARTS SHALL BE ARRANGED SO THAT WHEN INSTALLED, ALL PARTS REQUIRING MANIPULATION, OBSERVATION, AND/OR MAINTENANCE ARE READILY ACCESSIBLE AND
SAFE FOR OPERATION AND MAINTENANCE PERSONNEL. WHEREVER PRACTICAL, VALVES AND
INSTRUMENTS SHALL BE LOCATED SUCH THAT THEY CAN BE OPERATED AND EASILY ACCESSED FROM
GRADE LEVEL.
B. MAINTAINABILITY SHALL BE INCORPORATED INTO THE DESIGN OF ALL CONTRACTOR SUPPLIED EQUIPMENT. THE PRIMARY MAINTAINABILITY OBJECT SHALL BE TO MINIMIZE THE COMPLEXITY AND TIME REQUIRED FOR MAINTENANCE. THE FOLLOWING GENERAL CRITERIA SHALL BE FOLLOWED TO
ACHIEVE THIS OBJECTIVE:
a. CONTRACTOR SUPPLIED EQUIPMENT SHALL BE LOW MAINTENANCE DESIGN AND SHALL BE EASILY
MAINTAINABLE.
b. CONTRACTOR SUPPLIED EQUIPMENT SHALL BE DESIGNED TO BE MAINTAINED IN PLACE, IF
POSSIBLE, WITH MINIMUM DISASSEMBLY OF SURROUNDING EQUIPMENT AND MINIMUM USAGE OF
TEMPORARY SCAFFOLDING AND HANDLING EQUIPMENT.
64. DEVICES SHOWN ON THIS PLAN ARE NEW, UNLESS OTHERWISE NOTED.
65. DRAWING ARE DIAGRAMMATIC AND ARE NOT INTENDED TO SHOW EACH AND EVERY SPRINKLER HEAD, BRANCH PIPING, DEVICES, FITTINGS, VALVES OR COMPLETE DETAIL OF ALL THE WORK TO BE PERFORMED, BUT ARE FOR THE PURPOSES OF ILLUSTRATING THE TYPE OF SYSTEM AND CONDITIONS NECESSARY FOR AN EXPERIENCED TRADESMAN TO LAYOUT HIS WORK. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING SUCH SITE OBSERVATIONS AND MEASUREMENTS AS NECESSARY TO PROPERLY COMPLETE THE
WORK.
66. WALL PENETRATIONS THROUGH NON-RATED PARTITIONS SHALL BE PROVIDED WITH NON-SHRINKING
GROUT OR CAULKING MATERIAL AND APPROVED ASSEMBLY.
67. SPRINKLER SHOP DRAWINGS SHALL INDICATE THE FOLLOWING:
A. CEILING TYPES AND GRIDS.
B. ALL CEILING MOUNTED DEVICES (LIGHTS, DIFFUSERS AND SPECIAL ELECTRICAL SYSTEMS.
68. THE FIRE SUPPRESSION CONTRACTOR SHALL LOCATE SPRINKLER HEADS IN CEILINGS AS FOLLOWS. ALL HEADS SHALL BE LOCATED IN THE CENTER OF TILES (2' X 2') OR IN THE CENTER OF ONE QUADRANT (2' X 4') IN GYP. BOARD CEILING SPRINKLER HEADS SHALL BE LOCATED IN SYMMETRICAL PATTERN RELATIVE TO
OTHER DEVICES LOCATED IN THE CEILING.
69. ADEQUATE HOUSING SHALL BE PROVIDED FOR ALL MATERIAL STORED ON THE JOB. ALL MATERIALS FURNISHED FOR THE PROJECT SHALL BE NEW WITH LISTINGS AND LABELS BY A TESTING AGENCY
APPROVED BY THE STATE OF WHERE THE WORK IS TO BE PERFORMED.
70. WHERE WORK IS BEING PERFORMED IN AREAS THAT MUST CONTINUE NORMAL OPERATION, CONTRACTOR SHALL KEEP THE AREAS CLEAN AND CLEAR OF OBSTRUCTIONS, AND AS MUCH AS POSSIBLE, PROVIDE WARNING SIGNS AS NECESSARY FOR PROTECTION OF OCCUPANTS FROM ASSOCIATED RISKS. REMOVE
ALL DEBRIS AS WORK PROGRESSES.
71. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE VA COR, VA FIRE OFFICIAL AND VA'S ENGINEER OF RECORD WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE VA FIRE OFFICIAL AND VA'S ENGINEER OF RECORD WILL BE REQUIRED PRIOR TO FINAL
ACCEPTANCE OF THE PROJECT.
72. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE SPRINKLER
SYSTEM PER NFPA 13 AND A FIRE PROTECTION DESIGN MANUAL REQUIREMENTS.
73. REFER TO ARCHITECTURAL REFLECTED CEILING PLAN FOR COORDINATION OF SPRINKLER LOCATIONS WITH CEILING HEIGHTS AND TYPES. LOCATE SPRINKLER HEADS THROUGHOUT ALL AREAS AS REQUIRED BY NFPA 13 AND VA FIRE PROTECTION DESIGN MANUAL. COORDINATE SPRINKLER HEAD LOCATIONS WITH ALL OTHER TRADES BUT NOT LIMITED TO THE FOLLOWING: LIGHTS, STRUCTURAL SUPPORTS, BOOM, SPECIAL SYSTEMS, SMOKE DETECTORS,FIRE ALARM INDICATION DEVICES, HVAC DIFFUSERS, ETC. OBTAIN
ARCHITECT'S, ENGINEER AND/OR APPROVAL OF ALL SPRINKLER HEAD LOCATIONS.
74. ALL SPRINKLER HEAD PIPE ROUTING AND ELEVATIONS SHALL BE COORDINATED WITH ALL OTHER TRADES INCLUDING BUT NOT LIMITED TO THE FOLLOWING: CEILINGS, STRUCTURAL STEEL AND SUPPORTS, HVAC
DUCTWORK, CABLE TRAYS, CONDUIT, SPECIAL SYSTEMS, CONTROLS, ETC.
75. THE AUTOMATIC SPRINKLER CONTRACTOR IS TO PROVIDE ALL NECESSARY OFFSETS, RISES OR DROPS IN THE PIPING AND AUXILIARY DRAINS AS REQUIRED TO INSTALL COMPLETELY COORDINATED SPRINKLER SYSTEM. HYDRAULIC CALCULATIONS SHALL BE ORIGINATED AT THE FIRE PUMP AS A MINIMUM FOR
FACILITIES THAT POSSES A FIRE PUMP OR AT LOCATION OF FIRE HYDRANT FLOW TEST.
76. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF TWO (2) FOOT DISTANCE FROM A SIDE WALL- MOUNTED OR CEILING MOUNTED DIFFUSER USING AN ORDINARY TEMPERATURE SPRINKLER HEAD.
SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF THREE (3) FOOT DISTANCE FROM THE FRONT OF A
WALL-MOUNTED HOT AIR DIFFUSER.
77. SPRINKLER HEADS SHALL BE LOCATED A MINIMUM OF 18 INCHES FROM ANY LIGHT FIXTURE USING AN ORDINARY TEMPERATURE SPRINKLER HEAD. IT IS PREFERRED THAT THE CONTRACTOR MAINTAINS A TWO
(2) FOOT SPACING BETWEEN THE LIGHT FIXTURE AND SPRINKLER HEAD.
78. SPRINKLER PLANS AS SHOWN ARE FOR BIDDING PURPOSES ONLY. SPRINKLER CONTRACTOR IS TO OBTAIN CURRENT HYDRANT TEST DATA AND PROVIDE HYDRAULIC CALCULATIONS FOR SYSTEM PIPE SIZING IN ACCORDANCE WITH NFPA 13 AND THE VA FIRE PROTECTION DESIGN MANUAL. CONTRACTOR IS TO SUBMIT SHOP DRAWINGS INDICATION HYDRAULIC CALCULATIONS, PIPING LAYOUT & SIZING. ALL WORK IS TO BE DONE IN ACCORDANCE WITH NFPA 1, NFPA 13, NFPA 241, NFPA 291 AND THE VA FIRE PROTECTION DESIGN
MANUAL.
79. SPRINKLER CONTRACTOR SHALL MAINTAIN SUPERVISION OF EXISTING SPRINKLER SYSTEM AT ALL TIMES
AND SHALL COORDINATE TRANSFER OF SYSTEM WITH OWNER AND ENGINEER OF RECORD.
80. PIPE SUPPORTS:
A. ALL HANGERS MUST BE FM APPROVED, UL LISTED AND MEET THE REQUIREMENTS OF NFPA 13. NO
SPRINKLER PIPE IS TO BE SUPPORTED FROM ANY MECHANICAL OR ELECTRICAL DEVICE, SPECIFICALLY, DUCTWORK.
B. ALL PIPE SHALL BE SUPPORTED FROM THE BUILDING STRUCTURE IN A NEAT AND WORKMANLIKE MANNER. VERTICAL RISERS SHOULD BE SUPPORTED AT EACH FLOOR LEVEL WITH STEEL PIPE CLAMPS.
THE USE OF WORE OR STRAP METAL HANGERS TO SUPPORT PIPES WILL NOT BE PERMITTED. HANGING
PIPES FROM OTHER PIPES WILL NOT BE PERMITTED. CAREFULLY COORDINATED BEFORE
INSTALLATION WITH OTHER SYSTEMS AND EQUIPMENT IN CHASES AND OTHER CONGESTED AREAS.
C. MAXIMUM DISTANCES BETWEEN PIPE SUPPORTS SHALL MEET THE REQUIREMENTS STATED IN NFPA 13, SECTION 17.4.3.2 AND TABLE 17.4.2.1(a), TITLED, "MAXIMUM DISTANCE BETWEEN HANGERS (FT.-IN.).
81. ALL WALL AND FLOOR PENETRATIONS SHALL BE CORE-DRILLED AND SLEEVED THIS IS A VA DORN
REQUIREMENT, NO EXCEPTIONS.
82. NEW ARMOVERS SHALL BE PROVIDED TO NEW SPRINKLERS FOR COMPLIANCE WITH NFPA 13.
83. INDIVIDUAL BRANCH LINES TO A SINGLE SPRINKLER SHALL COMPLY WITH NFPA 13, SECTION 28.2.1.2 WHICH STATES, "PIPE SIZES SHALL BE NO LESS THAN 1-INCH (25 MM) NOMINAL FOR BLACK OR GALVANIZED STEEL PIPING AND 3/4-INCH (20 MM) NOMINAL FOR COPPER TUBING OR BRASS, STAINLESS STEEL OR NONMETALLIC PIPING LISTED FOR FIRE SPRINKLER SERVICE UNLESS PERMITTED BY SECTIONS 30.4 AND
30.6 OF NFPA 13."
84. ALL NEW EXPOSED PIPING MUST BE PAINTED IN COMPLIANCE WITH PROJECT SPECIFICATION 09 91 00, PAINTING.
85. THE SHOP DRAWINGS AND CALCULATIONS SHALL BE SUBMITTED TO THE ARCHITECT, ENGINEER AND VA
FIRE MARSHAL AND VA COR FOR REVIEW AND COMMENT.
86. IT IS THE INTENTION OF THE SPECIFICATION AND DRAWINGS TO CALL FOR A COMPLETE AND FUNCTIONAL SYSTEM, INSTALLED AS PER NFPA AND THE VA FIRE PROTECTION DESIGN MANUAL WITH ALL FINISHED
WORK TESTED AND READY FOR OPERATION.
87. THE FIRE PROTECTION CONTRACTOR SHALL NOTIFY THE VA COR, VA FIRE MARSHAL, VA'S ENGINEER OF RECORD, FIRE ALARM CONTRACTOR, AND GENERAL CONTRACTOR ONE WEEK PRIOR TO ANY SHUTDOWN
OR INTERRUPTION OF SERVICE.
88. ALL MATERIALS, PIPING, FITTINGS, VALVES, AND APPLIANCES HEREINAFTER SPECIFIED AND THOSE WHICH ARE ESSENTIAL BUT HAVE NOT BEEN SPECIFIED SHALL BE NEW AND OF THE HIGHEST GRADE AND
QUALITY, FREE FROM DEFECTS AND SUCH AS BREAKS, FLAWS, AND IMPERFECTIONS.
89. THROUGH PENETRATION ASSEMBLIES SHALL BE PROVIDED AT EACH OPENING WHERE EXPOSED SPRINKLER PIPING PASS THROUGH RATED WALLS, FLOORS AND PARTITIONS. ALL PIPING PENETRATIONS MUST BE SEALED IN ACCORDANCE WITH “UL” LISTING SEALING METHOD AND/OR AS DETAILED IN THESE
CONTRACT DRAWINGS OR SPECIFICATIONS.
90. BEFORE SUBMITTING A PROPOSAL FOR THE WORK, EACH BIDDER WILL BE HELD RESPONSIBLE TO HAVE EXAMINED THE EXISTING SITE CONDITIONS FOR THE WORK INCLUDED UNDER THIS CONTRACT. NO ALLOWANCE WILL BE MADE SUBSEQUENTLY IN THIS CONNECTION ON BEHALF OF THE CONTRACTOR FOR
ANY ERROR OR NEGLIGENCE ON HIS PART.
91. THE FIRE SUPPRESSION CONTRACTOR SHALL BE RESPONSIBLE FOR THE COMPLETE DESIGN OF THE FIRE PROTECTION SYSTEM AND SHALL PROVIDE SEALED SHOP DRAWINGS. SPRINKLER SYSTEM PLANS AND CALCULATIONS SHALL BE SEALED BY AN PROFESSIONAL ENGINEER REGISTERED IN THE STATE OF SOUTH
CAROLINA OR A NICET LEVEL III OR LEVEL IV SPRINKLER DESIGNER.
92. DRAWING ARE DIAGRAMMATIC AND ARE NOT INTENDED TO SHOW EACH AND EVERY SPRINKLER HEAD, BRANCH PIPING, DEVICES, FITTINGS, VALVES OR COMPLETE DETAIL OF ALL THE WORK TO BE PERFORMED, BUT ARE FOR THE PURPOSES OF ILLUSTRATING THE TYPE OF SYSTEM AND CONDITIONS NECESSARY FOR AN EXPERIENCED TRADESMAN TO LAYOUT HIS WORK. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAKING SUCH SITE OBSERVATIONS AND MEASUREMENTS AS NECESSARY TO PROPERLY COMPLETE THE
WORK.
93. UPON COMPLETION OF THE WORK, THE CONTRACTOR SHALL PRESENT THE OWNER WITH A REPORT CONFIRMING PROPER TESTING OF ALL NEW AND EXISTING DEVICES IN THE PROJECT ZONE; ALONG WITH APPROPRIATE SELECTED TESTING OF THE MAIN FIRE SUPPRESSION SYSTEM TO CONFIRM CONTINUED PROPER OPERATION. A CERTIFICATE OF APPROVAL FROM THE APPROPRIATE AGENCY INSPECTION AGENT
WILL BE REQUIRED PRIOR TO FINAL ACCEPTANCE OF THE PROJECT.
94. THE PIPING SCHEMATIC INDICATED BY THE DRAWINGS REPRESENTS THE SCOPE AND INTENT OF THE FIRE PROTECTION SYSTEM; HOWEVER THE SPRINKLER CONTRACTOR SHALL PROVIDE A COMPLETE SPRINKLER
SYSTEM PER NFPA 13 AND VA FIRE PROTECTION DESIGN REQUIREMENTS.
95. ALL SPRINKLER HEAD PIPE ROUTING AND ELEVATIONS SHALL BE COORDINATED WITH ALL OTHER TRADES INCLUDING BUT NOT LIMITED TO THE FOLLOWING: CEILINGS, STRUCTURAL STEEL AND SUPPORTS, HVAC
DUCTWORK, CABLE TRAYS, CONDUIT, SPECIAL SYSTEMS, CONTROLS, ETC.
96. HYDRAULIC CALCULATIONS SHALL BE ORIGINATED AT THE LOCATION OF FIRE HYDRANT FLOW TEST.
97. THE FIRE PROTECTION CONTRACTOR SHALL FURNISH ALL LABOR, MATERIAL, EQUIPMENT AND SERVICES NECESSARY FOR ANY REASONABLY INCIDENTAL TO FURNISHING A FIRE PROTECTION SYSTEM, AS INDICATED ON THE CONTRACT DRAWINGS AND / OR SPECIFIED IN THE PROJECT SPECIFICATIONS.
98. THE FIRE PROTECTION CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION WITH OTHER TRADES TO ELIMINATE CONFLICT WITH OTHER TRADES. ANY WORK INSTALLED BY THIS CONTRACTOR THAT RESULTS IN CONFLICT, DUE TO LACK OF COORDINATION BETWEEN TRADES, SHALL BE CHANGED AS DIRECTED BY THE ARCHITECT /ENGINEER WITHOUT ADDITIONAL COMPENSATION TO THE CONTRACTOR.
99. THE FIRE PROTECTION CONTRACTOR SHALL COORDINATE ROUTING OF SPRINKLER LINES TO ENSURE
PIPING DOES NOT PASS OVER ELECTRICAL PANELS.
100. ANY NEW PIPE OR DUCTWORK INSULATION THAT IS DAMAGED DURING CONSTRUCTION SHALL BE REMOVED AND REPLACED WITH NEW INSULATION TO MATCH ADJACENT INSULATION AND COVERING AT
THE FIRE PROTECTION CONTRACTOR'S EXPENSE.
101. CUTTING AND PATCHING OF ANY CONDITIONS, INCLUDING FLOORS, WALLS AND CEILINGS REQUIRED FOR
THE INSTALLATION OF FIRE PROTECTION SYSTEMS IS THE RESPONSIBILITY OF THE GENERAL
CONTRACTOR. ALL WORK SHALL BE COORDINATED WITH THE GENERAL CONTRACTOR AND ALL OTHER
TRADES.
102. THIS CONTRACTOR IS RESPONSIBLE FOR SUBMISSION OF CONTRACTOR'S MATERIAL AND TEST CERTIFICATE FOR ABOVEGROUND PIPING MEETING NFPA 13, FIGURE 28.1 TO THE VA COR AND THE
ENGINEER OF RECORD FOR REVIEW AND COMMENT. ALL CONTRACTORS' MATERIAL AND TEST
CERTIFICATE FOR ABOVEGROUND PIPING MUST BE DATED, PRINTED NAME OF INDIVIDUALS WHO SIGNED
THE CONTRACTOR'S MATERIAL AND TEST CERTIFICATE AND SIGNATURES. ALL TEST MUST BE
COORDINATED WITH THE VA COR, VA FIRE SAFETY OFFICIAL AND THE ENGINEER OF RECORD. SIGNATURES BY NON VA FIRE OFFICIALS WILL NOT BE ACCEPTED. AND SIGNATURES. ALL TEST MUST BE COORDINATED WITH THE VA COR, VA FIRE SAFETY OFFICIAL AND THE ENGINEER OF RECORD. SIGNATURES BY NON VA
FIRE OFFICIALS WILL NOT BE ACCEPTED.
103. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE ALL NECESSARY OFFSETS, RISES AND DROPS IN PIPING, AND AUXILIARY DRAINS AS REQUIRED BY THE VA FIRE PROTECTION DESIGN MANUAL AND NFPA 13, WHETHER SHOWN ON PLANS OR NOT.
104. INDIVIDUAL BRANCH LINES TO A SINGLE SPRINKLER SHALL COMPLY WITH NFPA 13, SECTION 28.2.1.2 WHICH STATES, "PIPE SIZES SHALL BE NO LESS THAN 1-INCH (25 MM) NOMINAL FOR BLACK OR GALVANIZED STEEL PIPING AND 3/4-INCH (20 MM) NOMINAL FOR COPPER TUBING OR BRASS, STAINLESS STEEL OR NONMETALLIC PIPING LISTED FOR FIRE SPRINKLER SERVICE UNLESS PERMITTED BY SECTIONS 30.4 AND
30.6 OF NFPA 13."
105. ALL NEW EXPOSED PIPING MUST BE PAINTED IN COMPLIANCE WITH PROJECT SPECIFICATION 09 91 00, PAINTING.
106. WHERE SPRINKLER PIPING IS INSTALLED BELOW DUCTWORK, PIPING SHALL BE SUPPORTED
FROM THE BUILDING STRUCTURE OR FROM THE DUCTWORK SUPPORTS; PROVIDED SUCH
SUPPORTS ARE CAPABLE OF HANDLING THE LOAD OF THE LOAD OF THE DUCTWORK AND THE
LOADS SPECIFIED IN NFPA 13, SECTION 17.4.1.3 ARE MET. IF THE CONTRACTOR DECIDES TO
SUPPORT THE FIRE PROTECTION PIPING FROM THE DUCTWORK SUPPORTS; THE FIRE
PROTECTION CONTRACTOR SHALL SUBMIT CALCULATIONS SIGNED AND SEALED BY A SOUTH
CAROLINA LICENSED FIRE PROTECTION ENGINEER VALIDATING COMPLIANCE WITH NFPA 13.
FIRE PROTECTION ABBREVIATIONS
WET PIPE
WIREGUARD
WELDED
WATER FLOW SWITCH
VOLTS
VALVE
US DEPT OF VETERANS AFFAIRS
UNDERGROUND
UNLESS NOTED OTHERWISE
UPRIGHT
UNDERWRITERS LABORATORY
TO BE DETERMINED
TYPICAL
TAMPER SWITCH
THREADED
TOP OF STEEL
TOP OF CONCRETE
STEEL
SQUARE FEET
SPECIAL
SPECIFICATION
SIDEWALL
SCREWED
SCHEDULE
ROOM
RESIDUAL
REDUCER
POUNDS PER SQUARE INCH
PRESSURE SWITCH
POST INDICATING VALVE
PHASE
PLUMBING
PENDANT
PLUMBING CONTRACTOR
PRE-ACTION VALVE
PRE-ACTION
ORDINARY HAZARD 2
ORDINARY HAZARD I
OUTSIDE SCREW AND YOKE
NATIONAL PIPE THREAD
NOT TO SCALE
NON RISING STEM
NOT APPLICABLE
NOT IN CONTRACT
NORMALLY OPENED
NORMALLY CLOSED
NATIONAL FIRE PROTECTION ASSOCIATION
MALLEABLE IRON
MEZZANINE
MECHANICAL JOINT
LEVEL
LIGHT HAZARD
LIGHTING
INSPECTOR TEST CONNECTION
INSPECTOR
INTERIOR
HEATING VENTING AND AIR CONDITIONING
HOSE CABINET
HOSE VALVE
HOSE REEL
WP
WG
WLD
FS
V
VAL
VA
UNO
UPR
UL
UG
TBD
TYP
TS
THRD
TOS
TOC
STL
SF
SP
SPEC
SW
SCR
SCH
RM
RES
RED
PSI
PS
PIV
PH
PLB
PEND
PC
PAV
PA
OH2
OH1
OS&Y
NPT
NTS
NRS
NA
NIC
NO
NC
NFPA
MI
MEZZ
MJ
LVL
LH
LTG
ITC
INSP
INT
HVAC
HC
HV
HR
HORSEPOWER
HYDRANT
GROOVED
GALLONS PER MINUTE
GROUND
GRADE
GENERAL CONTRACTOR
GALVANIZED
GAUGE
GALLONS
FLOW SWITCH
FIRE PROTECTION
FLOOR
FIRE ALARM
FLANGE
FINISH
FIRE HOSE VALVE
FIRE DEPARTMENT CONNECTION
FIRE ALARM
FACTORY MUTUAL GLOBAL
EXTINGUISHER
EXTERIOR
EXISTING
EXTRA HAZARD 2
EXTRA HAZARD 1
ELEVATION
ELECTRIC
ECCENTRIC
EXTENDED COVERAGE
ELBOW
EACH
EXISTING
DUCTILE IRON
DRY PIPE
DEPT OF DEFENSE
DEPARTMENT
DRAWING
DEGREE
DIAMETER
DRY
DOWN
CONCENTRIC
CONCRETE
CONTINUATION
CHECK
CEILING
CLASS
CAST IRON
BLACK
BUILDING
BOTTOM OF BEAM
BASEMENT
BACKFLOW PREVENTER
BELOW FINISH FLOOR
BELOW
ABOVE FINISHED GRADE
ABOVE FINISHED FLOOR
ABOVE CONCRETE
AUTOMATIC
AUTHORITY HAVING JURISDICTION
AMERICANS WITH DISABILITIES ACT
ABOVE
HP
HYD
GVD
GPM
GND
GR
GC
GALV
GA
GAL
FS
FP
FL
FA
FLG
FIN
FHV
FDC
FA
FM
EXT
EX
EXIST
EH2
EH1
EL
ELEC
ECC
EC
EL
EA
(E)
DI
DP
DOD
DEPT
DWG
DEG
DIA
D
DN
CON
CR
CONT
CHK
CLG
CL
CI
BLK
BLDG
BOB
BSMT
BFP
BFF
BEL
AFG
AFF
A/CONC
AUTO
AHJ
ADA
ABV
FIRE PROTECTION DESIGN CRITERIA
LIGHT HAZARD - PATIENT CARE, OFFICES, TREATMENT AND
CUSTOMARY ACCESS AREAS, RESTROOMS, X-RAY ROOMS AND IT
& COMMUNICATION ROOMS
DESIGN DENSITY: 0.10GPM/SQ.FT
HYDRAULICALLY MOST DEMANDING AREA: 1,500SQ.FT
SPRINKLER ORIFICE: 1/2INCH
MAXIMUM COVERAGE/SPRINKLER HEAD: 225SQ.FT
HOSE STREAM ALLOWANCE INSIDE/OUTSIDE: 100GPM
K FACTOR: 5.6GPM/(PSI)
½
ORDINARY HAZARD GROUP I - LABORATORIES, MECHANICAL
ROOMS, JANITORS CLOSETS, LAUNDRY ROOMS, AND
ELECTRICAL ROOMS
DESIGN DENSITY: 0.15GPM/SQ.FT
HYDRAULICALLY MOST DEMANDING AREA: 1,500SQ.FT
SPRINKLER ORIFICE: 1/2INCH
MAXIMUM COVERAGE/SPRINKLER HEAD: 130SQ.FT
HOSE STREAM ALLOWANCE INSIDE/OUTSIDE: 250GPM
K FACTOR: 5.6GPM/(PSI)
½
DESIGN DENSITY: 0.020GPM/SQ.FT.
HYDRAULICALLY MOST DEMANDING AREA: 1,500SQ.FT.
SPRINKLER ORIFICE: 3/4INCH
MAXIMUM COVERAGE/SPRINKLER HEAD: 130SQ.FT.
HOSE STREAM ALLOWANCE INSIDE/ OUTSIDE: 250GPM
K FACTOR: 8.0GPM/(PSI)1/2
ORDINARY HAZARD GROUP 2 - OCCUPANCY OR PORTIONS
OF OTHER OCCUPANCIES WHERE THE QUANTITY AND
COMBUSTIBILITY OF CONTENTS ARE MODERATE RATES TO
HIGH, STOCKPILES OF CONTENTS WITH MODERATE RATES OF
HEAT RELEASE DO NOT EXCEED 12 FEET AND STOCKPILES
OF CONTENTS WITH HIGH RATES OF HEAT RELEASE DO NOT
EXCEED 8 FEET.
SITE INSPECTION NOTE:
A CONTRACTOR SHALL PROVIDE THE ENGINEER FIVE(5) WORKING DAYS
NOTICE FOR ALL REQUESTED REVIEWS OF THE WORK. AS A MINIMUM THE
FOLLOWING REVIEWS SHALL BE CONDUCTED PRIOR TO COVERING UP ANY
CONCEALED WORK:
1. INSTALLATION OF TAMPER AND FLOW SWITCHES ON FIRE SERVICE FOR
ELECTRONIC SUPERVISION SHALL BE FURNISHED & INSTALLED BY THE
FIRE SUPPRESSION CONTRACTOR WHERE INSPECTION SHALL BE
COMPLETED AND PASSED INSPECTION.
2. IN-WALL ROUGH-IN WORK SHALL BE VISIBLE. FIRE PROTECTION
INSPECTIONS SHALL BE COMPLETE AND PASSED.
3. ABOVE CEILING WORK AN ABOVE CEILING WORK SHALL BE COMPLETE
INCLUDING PIPING, VALVES, SPRINKLER HEADS, HANGERS, SUPPORTS
AND SEISMIC RESTRAINS, ETC. FIRE PROTECTION INSPECTIONS SHALL BE
COMPLETED AND PASSED.
RE-REVIEW SHALL BE REQUIRED IF THE WORK IS COMPLETE OR NOT
INSTALLED PER THE CONTRACT DOCUMENTS.
SPRINKLER NOTE:
SPRINKLER PLANS AS SHOWN ARE FOR BIDDING PURPOSES
ONLY. SPRINKLER CONTRACTOR IS TO OBTAIN CURRENT
HYDRANT TEST DATA AND PROVIDE HYDRAULIC CALCULATIONS
FOR SYSTEM PIPE SIZING IN ACCORDANCE WITH NFPA 13 &
NFPA 291 FOR DESIGN INPUT INTO THE CONTRACTOR'S
HYDRAULIC CALCULATIONS. CONTRACTOR IS TO SUBMIT SHOP
DRAWINGS INDICATING HYDRAULIC CALCULATIONS, PIPING
LAYOUT & SIZING. SHOP DRAWINGS AND CALCULATIONS ARE
TO BE SIGNED & SEALED BY A LICENSED FIRE PROTECTION
PROFESSIONAL ENGINEER WHERE THE WORK SHALL OCCUR
OR NICET LEVEL III OR IV IN WATER BASED SYSTEMS LAYOUT.
ALL WORK IS TO BE DONE IN ACCORDANCE WITH ALL VA FIRE
PROTECTION DESIGN MANUAL AND NFPA CODES.
THE FOLLOWING PUBLICATIONS AND AUTHORITIES HAVING JURISDICTION SHALL BE REFERENCED FOR THE
DESIGN OF THE FIRE PROTECTION SYSTEM ON THIS PROJECT:
1. ANSI, A117.1 STANDARD, ACCESSIBLE AND USABLE BUILDINGS AND FACILITIES. 2017 EDITION
2. NFPA 1 - FIRE CODE, 2024 EDITION
3. NFPA 13 - STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS, 2022 EDITION
4. NFPA 24 - STANDARD FOR THE INSTALLATION OF PRIVATE FIRE SERVICE MAINS AND THEIR
APPURTENANCES, 2025 EDITION
5. NFPA 25 - INSPECTION, TESTING, AND MAINTENANCE OF WATER-BASED FIRE PROTECTION SYSTEMS, 2023
EDITION
6. NFPA 101 - LIFE SAFETY CODE, 2024 EDITION
7. NFPA 170 - LIFE SAFETY CODE, 2024 EDITION
8. NFPA 241 - STANDARD FOR SAFEGUARDING CONSTRUCTION, ALTERNATION AND DEMOLITION
OPERATIONS, 2022 EDITION
9. NFPA 291 - RECOMMENDED PRACTICE FOR WATER FLOW TESTING AND MARKING OF HYDRANTS, 2025
EDITION
10. VA FIRE PROTECTION DESIGN MANUAL, NINTH EDITION, NOVEMBER 1, 2023
11. VA SEISMIC DESIGN REQUIREMENTS, REVISED JULY 1, 2023 EDITION
12. VA FIRE SAFETY
DESIGN CODES, STANDARDS & PARTIES OF REFERENCE
FIRE SUPPRESSION LEGEND
UPRIGHT SPRINKLER HEAD
PENDENT SPRINKLER HEAD
CONCEALED PENDENT SPRINKLER & COVER PLATE
SIDEWALL SPRINKLER HEAD
RECESSED PENDENT SPRINKLER WITH CONCEALED ESCUTCHEON
RECESSED SIDEWALL SPRINKLER & ESCUTCHEON
CONCEALED SIDEWALL SPRINKLER & COVER PLATE
NEW INSTITUTIONAL / SECURITY TYPE LIGATURE RESISTANT,
PENDENT SPRINKLER HEAD. PROVIDE TYCO RAVEN INSTITUTIONAL
SPRINKLER HEAD, MODEL TY3281.
SPRINKLER PIPING
ELBOW TURNED DOWN
ELBOW TURNED UP
TEE TURNED DOWN
TEE TURNED UP
FIRE PROTECTION PIPING
DRAIN
DRY PIPE
F
FD
DP
OS & Y CHECK VALVE
WORK AREAS OUTSIDE OF A RATED
CONSTRUCTION BARRIER
CONTRACTOR SHALL BE REQUIRED TO PROVIDE/INSTALL THE
REPLACEMENT OF CEILING TILES AT THE END OF EACH SHIFT
FOR WORK AREAS OUTSIDE A RATED CONSTRUCTION BARRIER.
IF THE TILES CAN NOT BE REPLACED THE SPRINKLER SYSTEM
MAY BE CONSIDERED OUT OF SERVICE IN THESE AREAS AND A
1-HOUR FIRE RATED SEPARATION WILL BE REQUIRED BETWEEN
THE CONSTRUCTION AREA AND THE OCCUPIED PORTION OF
THE BUILDING.
REFERENCE NFPA 1, PARAGRAPH 13.3.3.3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
100% BID DOCUMENTS
FOR CONSTRUCTION
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT
GMK Associates, Inc.
1201 Main Street, Suite 2100 Columbia, SC 29201 803-256-0000 Thomas M. Weiland, AIA
STAMPPROGRAM MANAGER
321 4 5 6 7 8 9 10
Odell International 129 Fast Lane, Suite 200 Mooresville, NC 28117 704-401-2040 C. Harmon Reed, Jr. AIA
CONSULTANT
Charlotte Engineers, LLP 5838 Monroe Road Charlotte, NC 28212 704-531-3000 Michael Eaves FULLY SPRINKLERED
Approved:
U A
C a lla h a n \L o c a l R e v it \R
\4
C
E C e n tr a l M o d e l.
rv t
/9 /2
:3
:3
A
M
FX001
FIRE SUPPRESSION - GENERAL
NOTES AND LEGENDS
EHRM - RENOVATE B3 FOR EHRM
ADMIN AND TRAINING
COLUMBIA, SC
544-22-703
B3
07/15/2025 GAT JRC
FIRE SUPPRESSION - DRAWING INDEX
Sheet Number Sheet Name
FX001 FIRE SUPPRESSION - GENERAL NOTES AND LEGENDS
FX002 FIRE SUPPRESSION - DETAILS
FX003 FIRE SUPPRESSION - FIRE PUMP TEST RESULTS AND SEISMIC
DETAILS
FX004 FIRE SUPPRESSION - IMPAIRMENT & INTERIM REQUIREMENTS
FX100 FIRE SUPPRESSION - LEVEL 03 - DEMOLITION
FX101 FIRE SUPPRESSION - LEVEL 03 - NEW WORK
Rev. No. Revisions: Date:
METAL PIPE THROUGH 2-HR. GYPSUM WALL
METAL PIPE THROUGH 1-HR. GYPSUM WALL
STEEL/COPPER PIPE THROUGH CONCRETE OR
CONCRETE BLOCK WALL
STEEL PIPE THROUGH CONCRETE FLOOR OR WALL
TYPICAL UPRIGHT HEAD DETAILSPRINKLER HEAD LOCATION 4
BEAM PIPE HANGER 1
PIPE SLEEVE THROUGH WALL DETAIL 5
PIPE SLEEVE THROUGH FLOOR DETAIL 3
PER
MANUFACTURER
S
INSTRUCTIONS
UPRIGHT SPRINKLER
HEAD
QUICK RESPONSE
VARIES
** FOR USE IN AREAS WITHOUT LAY-IN/GYPBOARD CEILINGS
** FOR USE IN AREAS OPEN TO STRUCTURE **
NTS
3. MINIMUM 1-1/4" DEPTH HILTI FS 601 FIRESTOP SEALANT.
OR 4" DIA. (OR SMALLER) COPPER PIPE, EMT OR STEEL CONDUIT.
2. 10" DIA. (OR SMALLER) STEEL PIPE (SCHEDULE 10 OR HEAVIER),
1. 2-HR. FIRE-RATED GYPSUM WALL ASSEMBLY.
HILTI, INC. TULSA, OK 1-800-879-8000
SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS
2. ANNULAR SPACE = MIN. 1/4" TO MAX. 1".
NOTES : 1. MAXIMUM DIAMETER OF OPENING = 12-1/2".
U.L. SYSTEM NO. WL1054
T RATING = 0-HR.
F RATING = 2-HR.
HILTI, INC. TULSA, OK 1-800-879-8000
2. 10" DIA. (OR SMALLER) STEEL PIPE, 4" DIA. (OR SMALLER)
SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS
3. MIN. 5/8" DEPTH HILTI FS 601.
COPPER PIPE, EMT OR CONDUIT.
1. 1-HR. FIRE-RATED GYPSUM WALL ASSEMBLY.
NOTE : NOMINAL ANNULAR SPACE OF 1/4" TO 1" REQUIRED.
A
A
U.L. SYSTEM NO. WL1052
T RATING = 0-HR.
F RATING = 1-HR.
FRONT VIEW
A 2
SECTION A-A
A
FRONT VIEW
HILTI, INC. TULSA, OK 1-800-879-8000
6. 1/2" BEAD HILTI FS 605 SEALANT AT POINT OF CONTACT.
5. MINIMUM 1/4" DEPTH HILTI FS 605 FIRESTOP SEALANT.
4. MINIMUM 4-1/2" THICKNESS FLEXIBLE URETHANE SHEET, (MIN. 4 PCF DENSITY).
HOLLOW BLOCK WALLS ONLY).
3. NO. 8 STEEL WIRE MESH RECESSED 1/8" BELOW EACH WALL SURFACE (FOR
COPPER PIPE.
2. 17-1/4" DIA. (OR SMALLER) STEEL PIPE OR 4" DIA. (OR SMALLER)
B. ANY U.L. CLASSIFIED CONCRETE BLOCK WALL.
A. MINIMUM 5" THICK CONCRETE WALL.
1. WALL ASSEMBLY :
SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS
NOTES : 1. ANNULAR SPACE = MIN. 0", MAX. 2-3/4".
2. T RATING = 1/4-HR. WHEN STEEL PIPE IS USED.
A
HILTI, INC. TULSA, OK 1-800-879-8000
HOLLOW BLOCK WALLS, USE STEEL WIRE MESH OR STEEL SLEEVE
3. MIN. 2" THICKNESS MINERAL WOOL (MIN. 4 PCF DENSITY) TIGHTLY PACKED.
A. MIN. 4-1/2" THICK LIGHTWEIGHT OR NORMAL WEIGHT CONCRETE.
3. WALLS REQUIRE 3/4" DEPTH OF HILTI FS 605 ON BOTH SIDES. IN
SEE HILTI FIRESTOP INSTALLATION MANUAL FOR ADDITIONAL INSTRUCTIONS.
4. A. MIN. 3/4" DEPTH HILTI FS 605.
2. 21" DIA. (OR SMALLER) STEEL PIPE.
TO AID INSTALLATION.
NOTES : 1. MAXIMUM DIAMETER OF OPENING 27".
B. MIN. 1/2" BEAD HILTI FS 605 AT POINT OF CONTACT.
B. MIN. 8" CONCRETE BLOCK WALL.
2. ANNULAR SPACE 0" TO MAXIMUM 3".
1. FLOOR OR WALL ASSEMBLY :
A
FRONT VIEW
SECTION A-A
U.L. SYSTEM NO. WJ1021
T RATING = 0 AND 1/4-HR.
A
F RATING = 2-HR.
SECTION A-A
SECTION A-ATOP VIEW
A
4a1
U.L. SYSTEM NO. CAJ1156
T RATING = 0-HR.
F RATING = 3-HR.
4b
NTS
NTS
LC
1'-0"
8" MIN
PART'L ACOUSTIC
CEILING TILE.
PENDANT TYPE
SP. HEAD
2'x2' ACOUSTIC
CEILING TILE.
SP. HEAD
PENDANT TYPE
2'x4' ACOUSTIC
CEILING TILE.
PENDANT TYPE
SP. HEAD
SP. HEAD
PENDANT TYPE
CEILING TILE.
2'x4' ACOUSTIC
1'-0"
1'-0"
1'-0"
2'-0"
1'-0"
1'-0"
R C
A B
-1
/2
Components:
1. Hex Nut
2. Lock Washer
3. Hanger Rod
4. Adjustable Hanger
Ring
5. Steel Beam or Bar Joist inches inches inches
Nominal
Pipe
Size
Minimum
A Dimension
Hanger
Takeout
Rod
Diameter
1/2 3 +1/4 3/8
3/4 3 +1/4 3/8
1 3 +1/4 3/8
1 1/4 3 1/4 +0 3/8
1 1/2 3 1/2 +0 3/8
2 3 3/4 -1/4 3/8
2 1/2 4 3/4 -3/4 3/8
3 5 1 3/8
4 5 3/4 -1 1/2 3/8
5 6 1/2 -2 1/4 1/2
6 7 1/2 -3 1/2
8 9 -4 1/2 1/2
DESIGN DATA FOR BEAM HANGER
NTS
PIPE
NOTES:
1. FOR INTERIOR WALLS
AND BELOW GRADE
GROUND TO GROUND
WALLS
CUT OPENING IN
EXISTING MASONRY
WALL LARGER THAN
SLEEVE AND FORM &
FILL WITH
EXPANSIVE
TYPE GROUT
FIRE
RESISTANT
SILICONE FOAM
SEALER
ESCUTCHEON PLATE
ON ONE OR BOTH
SIDES WHERE PIPING
IS EXPOSED
PIPE SLEEVE
EXISTING POURED
CONCRETE OR
C.M.U. WALL.
ANCHOR
LUGS
(MIN. 3 REQ'D)
PIPE
INSULATION
(WHERE REQ'D)
NTS
PIPE
PIPE
INSULATION
(WHERE REQ'D)
WATERPROOF CAULK
(WATER PROOF
FLOORS
ONLY
METAL
DECK
PIPE
SLEEVE
CONTINUOUSLY WELDED WATER
STOP & ANCHOR COLLAR,
WATERPROOF FLOORS
MIN. 1" ALL OTHERS TO HAVE
ANCHOR LUGS (MIN. 3 REQ'D).
FIRE RESISTANT
SILICONE FOAM
SEALER
CONCRETE FLOOR SLAB
NOTES:
1.
2.
3.
4.
5.
DETAILS SHOWN ARE TYPICAL DETAILS. IF FIELD CONDITIONS DO NOT MATCH THE
REQUIREMENTS OF THE TYPICAL DETAILS, APPROVED ALTERNATE DETAILS
SHALL BE UTILIZED. FIELD CONDITIONS AND DIMENSION NEED TO BE VERIFIED
FOR COMPLIANCE WITH THE DETAILS, INCLUDING BUT NOT LIMITED TO THE
FOLLOWING:
A. MINIMUM AND MAXIMUM WIDTH OF JOINTS.
B. TYPE AND THICKNESS OF FIRE-RATED CONSTRUCTION. THE
MINIMUM ASSEMBLY RATING OF THE FIRE STOP ASSEMBLY
SHALL MEET OR EXCEED THE HIGHEST RATING OF THE
ADJACENT CONSTRUCTION.
IF ALTERNATE DETAILS MATCHING THE FIELD CONDITIONS ARE NOT AVAILABLE,
MANUFACTURER'S ENGINEERING JUDGEMENT DRAWINGS ARE ACCEPTABLE,
DRAWINGS SHALL FOLLOW THE INTERNATIONAL FIRESTOP COUNCIL (IFC)
GUIDELINES FOR EVALUATING FIRESTOP SYSTEM ENGINEERING JUDGEMENTS.
REFERENCES:
A. 2013 UNDERWRITER'S LABORATORIES FIRE RESISTANCE
DIRECTORY, VOLUME 2
B. NFPA 101, LIFE SAFETY CODE
C. ALL GOVERNING LOCAL AND REGIONAL BUILDING CODES
FIRESTOP SYSTEM INSTALLATION MUST MEET THE REQUIREMENTS OF ASTM
E-814 (UL 1479) TESTED ASSEMBLIES THAT PROVIDE A FIRE RATING EQUAL TO
THAT OF THE CONSTRUCTION BEING PENETRATED.
ALL RATED THROUGH-PENETRATIONS SHALL BE PROMINENTLY LABELED WITH
THE FOLLOWING INFORMATION:
A. ATTENTION: FIRE RATED ASSEMBLY
B. UL SYSTEM #
C. PRODUCT(S) USED
D. HOURLY RATING (F-RATING)
E. INSTALLATION DATE
QUICK RESPONSE RECESSED DRY PENDENT FOR ALL DRY SPRINKLER
AREAS OR AS NOTED. PROVIDE CHROME HEAD AND CHROME ESCUTCHEON.
VARIES
VARIES
VARIES
TYPICAL RETURN BEND DETAIL 6
CEILING
1"
PER
MANUFACTURER'
S
INSTRUCTIONS
VARIES
VARIES
VARIES
CEILING
1"
PER
MANUFACTURER'
S
INSTRUCTIONS
VARIES
VARIES
VARIES
CEILING
1"
PER
MANUFACTURER'
S
INSTRUCTIONS
VARIES
VARIES
VARIES
CEILING
1"
PER
MANUFACTURER'S
INSTRUCTIONS
NTS
7UNDER DUCT SPRINKLER DETAIL
D R
O P
48" OR LARGER DUCT
VARIES
NTS
1"
3/4"
PLUG
1"x 3/4"x 1" TEE
BRANCHLINE
UPRIGHT
SPRINKLER
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
100% BID DOCUMENTS
FOR CONSTRUCTION
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT
GMK Associates, Inc.
1201 Main Street, Suite 2100 Columbia, SC 29201 803-256-0000 Thomas M. Weiland, AIA
STAMPPROGRAM MANAGER
321 4 5 6 7 8 9 10
Odell International 129 Fast Lane, Suite 200 Mooresville, NC 28117 704-401-2040 C. Harmon Reed, Jr. AIA
CONSULTANT
Charlotte Engineers, LLP 5838 Monroe Road Charlotte, NC 28212 704-531-3000 Michael Eaves FULLY SPRINKLERED
Approved:
U A
C a lla h a n \L o c a l R e v it \R
\4
C
E C e n tr a l M o d e l.
rv t
/9 /2
:3
:3
A
M
FX002
FIRE SUPPRESSION - DETAILS EHRM - RENOVATE B3 FOR EHRM
ADMIN AND TRAINING
COLUMBIA, SC
544-22-703
B3
07/15/2025 GAT JRC
DIESEL FIRE PUMP
1. PUMP:
A. PUMP MANUFACTURER: PATTERSON
B. MODEL NUMBER: 6X5X17
C. SERIAL NUMBER: FP-CO4875
D. TYPE: HORIZONTAL SPLIT-CASE
E. GPM: 1000
F. RPM: 1750
G. SUCTION: 8 INCHES
H. DISCHARGE: 6 INCHES
2. DIESEL ENGINE:
A. MANUFACTURER: CLARK
B. MODEL: JU4H-UF50
C. SERIAL NUMBER: PE4045T504320
D. TYPE: DIESEL
3. PUMP CONTROLLER:
A. MANUFACTURER: FIRETROL
B. MODEL NO.: FAT1100-JL12N
C. SERIAL NO.: 308886-01RE
4. JOCKEY PUMP CONTROLLER:
A. MANUFACTURER: FIRETROL
B. MODEL NO.: FTA1100-JL12N
C. SERIAL NO.: 308886-01RE
FIRE PUMP YEARLY TEST AND FIRE HYDRANT FLOW TEST
DIESEL FIRE PUMP TEST
DATE: 04/10/2024
PERFORMED BY:
PALMETTO AUTOMATIC SPRINKLER COMPANY, INC.
PO BOX 29127
CAYCE-WEST COLUMBIA, SOUTH CAROLINA 29171
RESULT:
GPM: 0 1000 1440
SUCTION PSI: 46 25 6
DISCHARGE PSI: 140 101 60
CITY WATER FIRE HYDRANT FLOW TEST:
DATE PERFORMED: 04/10/2024
PERFORMED BY: PALMETTO AUTOMATIC SPRINKKLER COMPANY, INC.
RESULTS:
STATIC PRESSURE: 101 PSI
NOTE: CONTRACTOR SHALL BE REQUIRED TO PERFORM THERE OWN DIESEL
FIRE PUMP AND CITY WATER FIRE HYDRANT FLOW TESTS FOR THEIR DESIGN
INPUTS FOR THEIR FIRE PROTECTION HYDRAULIC CALCULATIONS AND PIPE
SIZING.
PIPE SUPPORT AND SEISMIC RESTRAINT -
HORIZONTAL PIPING
SEISMIC RESTRAINT COMPONENTS
(TYPICAL APPLICATIONS)
CLAMP
BAR JOISTS
(AT 45 )
SEISMIC
TRANSVERSE
BRACE
PIPE
CLEVIS HANGER
NOTE:
ON WOOD ROOF
TRUSSES - USE
A CEILING FLANGE
OR ANGLE BRACKET
PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:
1" & 1-1/2" PIPES: 20 FT. ON CENTER
3/8" THREADED
ROD
BAR JOISTS
2" & 2-1/2" PIPES: 30 FT. ON CENTER
3" , 4" & 6" PIPES: 40 FT. ON CENTER
TOLCO BAND HANGERS FIG. 200, 2NFPA,
TOLCO FIG. 25 SURGE RESTRAINER
TYPE 1- FOR USE WITH 1" AND 1 1/4"
PIPE AND HANGER.
TYPE 2- FOR USE WITH 1 1/2" AND 2"
PIPE AND HANGER
TOLCO FIG. 25 IS DESIGNED TO BE USED ONLY
TO RESTRICT UPWARD MOVEMENT OF PIPE WITHIN
THE HANGER AS IT OCCURS DURING SPRINKLER
HEAD ACTIVATION OR EARTHQUAKE TYPE ACTIVITY
TOLCO FIG.
909 OR 910
TOLCO U.L. LISTED ATTACHMENTS.
TOLCO FIG. 1000 FAST CLAMPS UNDERWRITERS
LBORATORIES LISTED, MUST BE USED WITH
PROVIDE TOLCO RESTRAINTS OR APPROVED
EQUAL AS REQUIRED.
SHOWN FLAT
TORQUE-TIGHTEN HEX
MINIMUM REQUIRED
NUTS UNTIL LEAF
NOTE: TO ASSURE
SPRING IS FLAT
NOTE:
BAND HANGER
TOLCO
USED IN LONGITUDINAL BRACE
PIPE CLAMP (TOLCO FIG. 4A)
(OPTIONAL METHOD)
LATERAL (TRANSVERSE)
BRACE
TOLCO
TOLCO FIG. 1000
LEAF SPRING
FAST CLAMP
FIG. 1000
909 OR 908
TOLCO FIG.
909 OR 910
TOLCO FIG.
CONFIGURATION AND
NUTS ARE TIGHTENED
ORIENTATION BEFORE
LEAF SPRING
LATERAL (TRANSVERSE) BRACE
FAST CLAMP
TOLCO FIG. 1000
LONGITUDINAL/4 WAY BRACE
(OPTIONAL METHOD)
909 OR 910
TOLCO FIG.
TOLCO FIG. 907
MAX.
TOLCO FIG. 1000
909 OR 910
TOLCO FIG.
3"
(2) FAST CLAMP
TOLCO FIG. 1000
TOLCO FIG. 1000
FASTCLAMP RISER BRACE
TOLCO FIG.
909 OR 910
CLAMP
BAR JOISTS
(AT 45 )
SEISMIC
TRANSVERSE
BRACE
PIPE
CLEVIS HANGER
ON WOOD ROOF
TRUSSES - USE
A CEILING FLANGE
OR ANGLE BRACKET
PROVIDE SEISMIC RESTRAINTS FOR PIPING AS FOLLOWS:
1" & 1-1/2" PIPES: 20 FT. ON CENTER
3/8" THREADED
ROD
BAR JOISTS
2" & 2-1/2" PIPES: 30 FT. ON CENTER
3" , 4" & 6" PIPES: 40 FT. ON CENTER
WITH TOLCO BAND HANGERS FIG. 200, 2NFPA,
TOLCO FIG. 25 SURGE RESTRAINER
TYPE 1- FOR USE WITH 1" AND 1 1/4"
PIPE AND HANGER.
TYPE 2- FOR USE WITH 1 1/2" AND 2"
PIPE AND HANGER
TO RESTRICT UPWARD MOVEMENT OF PIPE WITHIN
THE HANGER AS IT OCCURS DURING SPRINKLER
HEAD ACTIVATION OR EARTHQUAKE TYPE ACTIVITY
TOLCO FIG.
909 OR 910
TOLCO U.L. LISTED ATTACHMENTS.
TOLCO FIG. 1000 FAST CLAMPS UNDERWRITERS
LBORATORIES LISTED, MUST BE USED WITH
PROVIDE TOLCO RESTRAINTS OR APPROVED
EQUAL AS REQUIRED.
SHOWN FLAT
TORQUE-TIGHTEN HEX
BAND HANGER
TOLCO
USED IN LONGITUDINAL BRACE
PIPE CLAMP (TOLCO FIG. 4A)
(OPTIONAL METHOD)
LATERAL (TRANSVERSE)
BRACE
TOLCO
TOLCO FIG. 1000
LEAF SPRING
FAST CLAMP
FIG. 1000
909 OR 908
TOLCO FIG.
909 OR 910
TOLCO FIG.
CONFIGURATION AND
NUTS ARE TIGHTENED
ORIENTATION BEFORE
LEAF SPRING
LATERAL (TRANSVERSE) BRACE
FAST CLAMP
TOLCO FIG. 1000
LONGITUDINAL/4 WAY BRACE
(OPTIONAL METHOD)
909 OR 910
TOLCO FIG.
TOLCO FIG. 907
MAX.
TOLCO FIG. 1000
909 OR 910
TOLCO FIG.
3"
(2) FAST CLAMP
TOLCO FIG. 1000
TOLCO FIG. 1000
FASTCLAMP RISER BRACE
TOLCO FIG.
909 OR 910
NTS
NTS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
VA FORM 08 - 6231
A
100% BID DOCUMENTS
FOR CONSTRUCTION
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT
GMK Associates, Inc.
1201 Main Street, Suite 2100 Columbia, SC 29201 803-256-0000 Thomas M. Weiland, AIA
STAMPPROGRAM MANAGER
321 4 5 6 7 8 9 10
Odell International 129 Fast Lane, Suite 200 Mooresville, NC 28117 704-401-2040 C. Harmon Reed, Jr. AIA
CONSULTANT
Charlotte Engineers, LLP 5838 Monroe Road Charlotte, NC 28212 704-531-3000 Michael Eaves FULLY SPRINKLERED
Approved:
U A
C a lla h a n \L o c a l R e v it \R
\4
C
E C e n tr a l M o d e l.
rv t
/9 /2
:3
:3
A
M
FX003
FIRE SUPPRESSION - FIRE PUMP
TEST RESULTS AND SEISMIC
DETAILS
EHRM - RENOVATE B3 FOR EHRM
ADMIN AND TRAINING
COLUMBIA, SC
544-22-703
B3
PROCEDURES FOR DRAINING WET PIPE SYSTEM
1. TO DRAIN A WET PIPE SYSTEM THE PROCEDURE TO BE PERFORMED AND SUBMITTED TO THE
ARCHITECT, ENGINEER, AND OWNER'S REPRESENTATIVE SHOULD INCLUDE BUT NOT LIMITED TO THE
FOLLOWING.
1.1. CLOSE ALL SPRINKLER CONTROL VALVES.
1.2. TAG ALL CLOSED VALVES.
1.3. OPEN MAIN DRAIN VALVES AND AUXILIARY DRAINS ALLOWING THE SYSTEM FOR 100%
COMPLETE DRAINAGE.
1.4. WHEN THE WATER HAS BEEN COMPLETELY DRAINED, CLOSE THE MAIN DRAIN AND AUXILIARY
DRAIN VALVES. WHEN THE WATER HAS STOPPED FLOWING, CHECK ALL CONTROL VALVES TO
BE SURE THEY ARE TIGHTLY SHUT; ANY MALFUNCTION CONTROL VALVES SHOULD BE
REPAIRED AND/OR REPLACED IMMEDIATELY AS DEEMED APPLICABLE.
1.5. CHECK FOR WATER TRAPPED AT ALL LOW POINTS IN PIPING THAT LACK AUXILIARY DRAINS;
REMOVE DRAIN AND REPLACE SUCH PIPING.
1.6. ONCE ABOVE ITEM ARE CONFIRMED WITH 100% CERTAINTY THE CONTRACTOR SHALL
PERFORM ALL NEW INSTALLATIONS.
1. MINIMUM REQUIREMENTS
A. THE CONTRACTOR SHALL ENACT MEASURES THAT SHALL BE TAKEN DURING THE IMPAIRMENT
TO ENSURE THAT INCREASED RISKS ARE MINIMIZED AND THE DURATION OF THE IMPAIRMENT IS
LIMITED.
B. THE CONTRACTOR SHALL NOTIFY IN WRITING TO THE ARCHITECT, ENGINEER, VA COR, AND VA
FIRE OFFICIAL OF THE PLANNED IMPAIRMENT, PROCEDURES DURING THE IMPAIRMENT,
TESTING RE-COMMISSIONING OF THE FIRE PROTECTION/FIRE ALARM SYSTEMS FOR
PROTECTION OF THE AFFECTED LOCATIONS WITHIN THE SCOPE OF WORK SUITE.
C. THE CONTRACTOR THROUGH THE VA COR SHALL PREPARE AND SUBMIT TO THE VA COR FOR
OWNER'S DISTRIBUTION TO THE EMPLOYEES IN THE AREA OF THE IMPAIRMENT SHALL BE
PROVIDED WITH INFORMATION ON ALTERNATE FIRE PROTECTION THAT WILL BE AVAILABLE.
D. THE SUSPENSION OF ALL NON-ESSENTIAL HOT WORK PERMITS UNTIL THE CONCLUSION AND
REACTIVATION OF THE FIRE SUPPRESSION SYSTEM AND INTERFACING FIRE DETECTION
SYSTEM.
2. FIRE PROTECTION IMPAIRMENT PLAN
A. A FIRE PROTECTION IMPAIRMENT PLAN SHOULD BE DEVELOPED AND IMPLEMENTED BEFORE
AUTHORIZATION IS GIVEN, THE IMPAIRMENT COORDINATOR SHOULD VERIFY THAT THE
FOLLOWING PROCEDURES HAVE BEEN IMPLEMENTED:
• THE EXTENT AND EXPECTED DURATION OF THE IMPAIRMENT THAT HAS BEEN DETERMINED.
• THE AREA OF THE BUILDING THAT WILL BE AFFECTED HAS BEEN INSPECTED AND THE
INCREASED RISKS DETERMINED.
• RECOMMENDATIONS HAVE BEEN SUBMITTED TO THE ARCHITECT, ENGINEER AND VA COR
REPRESENTATIVE TO MITIGATE ANY INCREASED RISKS.
• WHERE A REQUIRED FIRE PROTECTION SYSTEM IS OUT OF SERVICE FOR MORE THAN FOUR
(4) HOURS IN A 24 HOUR PERIOD THE CONTRACTOR & OWNER SHALL ARRANGE FOR THE
FOLLOWING:
• AN APPROVED FIRE WATCH.
• ESTABLISHMENT AND IMPLEMENTATION OF AN APPROVED PROGRAM TO ELIMINATE
POTENTIAL IGNITION SOURCES AND LIMIT OF THE AMOUNT OF COMBUSTIBLES IN THE
AREA OF CONSTRUCTION.
• ASSIGN PERSONNEL TO TRANSMIT FIRE ALARMS TO THE OWNER'S HOSPITAL
COORDINATOR WHERE THE MAIN FIRE ALARM PANEL IS BEING MONITORED FOR 24/7
COVERAGE.
3. TAG IMPAIRMENT SYSTEM
A. A TAG SHALL BE USED TO INDICATE THAT A SYSTEM OR PART THERE OF, HAS BEEN REMOVED
FROM SERVICE. THE CONTRACTOR SHALL PLACE TAGS ON ALL AFFECTED COMPONENTS, E.G.,
TAMPER SWITCHES, VALVES, FIRE ALARM ANNUNICATOR DEVICES, ETC., PRIOR TO THE
COMMENCEMENT OF ANY WORK.
B. THE TAG SHALL BE POSTED AT EACH FIRE PROTECTION CONNECTION AND SYSTEM CONTROL
VALVE AND OTHER LOCATION REQUIRED BY THE VA COR, VA FIRE OFFICIAL OR THE ENGINEER
OF RECORD, INDICATING WHICH SYSTEM, OR PART THERE OF, HAS BEEN REMOVED FROM
SERVICE.
• THE SUPERVISORS IN THE AREA TO THE AFFECTED AREA HAS BEEN NOTIFIED.
• THE FIRE DEPARTMENT HAS BEEN NOTIFIED.
• A TAG IMPAIRMENT SYSTEM HAVE BEEN IMPLEMENTED.
• ALL NECESSARY TOOLS, EQUIPMENT, MATERIAL AND APPURTENANCES ARE LOCATED AND
ASSEMBLED ON THE IMPAIRMENT SITE.
4. RESTORING SYSTEMS TO SERVICE
A. WHEN ALL IMPAIRED EQUIPMENT IS RESTORED TO NORMAL WORKING ORDER, THE VA COR, VA
FIRE OFFICIAL AND ENGINEER OF RECORD SHALL VERIFY THAT THE CONTRACTOR HAS
IMPLEMENTED THE FOLLOWING PROCEDURES:
• ALL NECESSARY INSPECTION HAVE BEEN CONDUCTED FOLLOWING NFPA 13, 25 AND 72
REQUIREMENTS IN ORDER TO…