S02-RFP Attachment 11-Specifications-Columbia_Part1.pdf

PDF 2 MB Posted

Attached to
Y1DZ--Renovate B3-EHRM Training and Admin Space Project 544 22 703 EHRM Construction 6439 Garner's Ferry Rd. Columbia VAMC Columbia, SC 29209
Solicitation number
36C77626R0032_2
Issued by

About this file

This file is a comprehensive set of 100% Bid Documents and Master Specifications for the renovation of Building 3 at the Columbia VA Medical Center in Columbia, South Carolina. The project (544-22-703) involves interior renovations of the third floor to create EHRM (Electronic Health Records Management) administrative and training space, with an estimated magnitude between $2,000,000 and $5,000,000. The work includes general construction, mechanical, electrical, plumbing, fire protection, and interior finishes, along with commissioning of HVAC, plumbing, electrical, fire suppression, communications, and security systems. The project is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) and is administered by the Department of Veterans Affairs Technology Acquisition Center.

The specifications establish extensive contractual requirements covering project scheduling using Critical Path Method (CPM) techniques with activity durations not exceeding 20 workdays, quality control with a three-phase inspection system (Preparatory, Initial, Follow-Up), construction waste management targeting a minimum 50% diversion rate, comprehensive commissioning procedures including pre-functional checklists and systems functional performance testing, and detailed safety requirements including fall protection at 6 feet, confined space entry, electrical lockout/tagout procedures, and lead-based paint removal using only chemical (non-mechanical) methods. Additional requirements include monthly progress reporting, as-built drawing submission, warranty management with equipment tagging and a one-year construction warranty period, testing and commissioning compliance, COVID-19 safety protocol adherence per Executive Order 14042, operations and maintenance training for facility personnel, and submission of submittals through the Submittal Exchange electronic platform. The contractor must designate a full-time project superintendent, establish a Quality Control organization with qualified engineers and specialists, maintain security procedures and document control within the VA facility, coordinate with VA staff to minimize operational disruptions, and prepare detailed plans for demolition, lead-based paint abatement, construction sequencing, and systems commissioning prior to commencement of work.

View the file

Other files

File Type Posted
S06-Amendment 0006-Att 1-SF30-Columbia.pdf PDF
S06 - Amendment 0006-Att 2-Tech Questions-Columbia.pdf PDF
S06 - Amendment 0005-Att 1-Tech Questions-Columbia.pdf PDF
S06-Amendment 0005-Att 2-SF30-Columbia.pdf PDF
S06-Amendment 0004-Att 1- BLDG 3 EHRM - DIV 23 Specs Combined.pdf PDF
S06-Amendment 0004-Att 3-HL100.pdf PDF
S06-Amendment 0004-Att 2 - Lim. AB LBP Report - Bld3 EHRM.pdf PDF
S06-Amendment 0004-Att 5- SF30-Columbia.pdf PDF
S06 -Amendment 0004-Att 4- Tech Questions-Columbia.pdf PDF
S06-36C77626R0032-Amendment 0003.pdf PDF
S06-36C77626R0032 Amendment 0002.pdf PDF
S04- Pre Bid Conference - Columbia.pptx PPTX presentation
S06-36C77626R0032 0001.pdf PDF
S06-Site Visit Sign-In Sheet 03062026-Columbia.pdf PDF
S06-RFP Attachment 17-Spce Update for 01321615-2025-12.pdf PDF
S02-RFP Attachment 15-Specifications-Columbia_Part5.pdf PDF
S02-RFP Attachment 8- Fire Sup Drawings-COL.pdf PDF
S02-RFP Attachment 5- ARCH Drawings-COL.pdf PDF
S02-RFP Attachment 4-Campus Map-Columbia.pdf PDF
S02-36C77626R0032-Columbia.pdf PDF
S02-RFP Attachment 12-Specifications-Columbia_Part2.pdf PDF
S02-RFP Attachment 10- Plumbing Drawings-COL.pdf PDF
S02-RFP Attachment 16-Final SOW-Col.pdf PDF
S02-RFP Attachment 14-Specifications-Columbia_Part4.pdf PDF
S02-RFP Attachment 7- Fire Alarm Drawings-COL.pdf PDF
S02-RFP Attachment 2 Site Visit Information-Columbia.pdf PDF
S02-RFP Attachment 13-Specifications-Columbia_Part3.pdf PDF
S02-RFP Attachment 9- Mechanical Drawings-COL.pdf PDF
S02-RFP Attachment 6- Electrical Drawings-COL.pdf PDF
S02 - RFP Attachment 3 - Limitations on Subcontracting - Columbia.docx DOCX document
S02-RFP Attachment 1-Wage Rates-Col.txt TXT text file
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W.J.B. DORN VAMC

RENOVATE BUILDING 3 FOR EHRM ADMIN & TRAINING

COLUMBIA, SC

544-22-703

100% BID DOCUMENTS

FOR CONSTRUCTION

JULY 15, 2025

TWeiland SC Corporate

TWeiland TW SC Signed

VAMC Columbia Bldg. 3 VA Project 544-22-703

Renovate B3 for EHRM Admin & Training 07-15-2025

100% Bid Documents

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 – SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 00 10 Covid Safety Protocols For Federal Contractors 05-22

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21

01 33 23 Shop Drawings, Product Data, and Samples 09-22

01 33 30 Electronic Submittal Procedures 05-22

01 35 26 Safety Requirements 10-22

01 45 00 Quality Control 02-21

01 74 19 Construction Waste Management 04-22

01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

Attachment Limited Asbestos & Lead-Based Paint

Assessment

Building 3 – Third Floor Renovations

DIVISION 04 – MASONRY – NOT USED

DIVISION 05 – METALS – NOT USED

05 50 00 Metal Fabrications 02-21

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES – NOT USED

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21

07 84 00 Firestopping 01-21

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 14 00 Interior Wood Doors 01-21

08 71 00 Door Hardware 05-22

08 90 00 Louvers and Vents 01-21

100% Bid Documents

00 01 10-2

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 51 00 Acoustical Ceilings 12-18

09 65 13 Resilient Base and Accessories 01-21

09 65 19 Resilient Tile Flooring 05-18

09 68 00 Carpeting 01-21

09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21

10 26 00 Wall and Door Protection 01-21

10 44 16 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT – NOT USED

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 08-17

12 24 21 Lightproof Shades 01-21

12 32 00 Manufactured Wood Casework 01-21

12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components

01-21

DIVISION 14– CONVEYING EQUIPEMENT – NOT USED

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 11-16

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23

22 05 23 General-Duty Valves for Plumbing Piping 09-20

22 07 11 Plumbing Insulation 09-19

22 08 00 Commissioning of Plumbing Systems 11-16

22 11 00 Facility Water Distribution 05-21

22 13 00 Facility Sanitary and Vent Piping 09-20

22 40 00 Plumbing Fixtures 12-22

100% Bid Documents

00 01 10-3

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment

03-23

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 08 00 Commissioning of HVAC Systems 03-23

23 09 23 Direct-Digital Control System for HVAC 09-11

23 21 13 Hydronic Piping 03-23

23 23 00 Refrigerant Piping 02-20

23 25 00 HVAC Water Treatment 03-23

23 31 00 HVAC Ducts and Casings 03-23

23 34 00 HVAC Fans 03-23

23 36 00 Air Terminal Units 03-23

23 37 00 Air Outlets and Inlets 03-23

23 40 00 HVAC Air Cleaning Devices 03-23

23 73 00 Indoor Central-Station Air-Handling Units 03-23

23 81 00 Decentralized Unitary HVAC Equipment 03-24

DIVISION 25 – INTEGRATED AUTOMATION - NOT USED

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 05 33 Raceway and Boxes for Electrical Systems 11-22

26 08 00 Commissioning of Electrical Systems 11-16

26 09 23 Lighting Controls 11-22

26 24 16 Panelboards 11-22

26 27 26 Wiring Devices 11-22

26 29 11 Motor Controllers 11-22

26 29 21 Enclosed Switches and Circuit Breakers 11-22

26 51 00 Interior Lighting 11-22

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 05 36 Cable Trays for Communications Systems 12-22

27 05 53 Identification for Communications Systems 12-22

27 08 00 Commissioning of Communications Systems 11-16

27 10 00 Control, Communication and Signal Wiring 06-15

27 11 19 Communication Termination Blocks and Patch Panels 12-22

27 11 26 Communications Back Mounted Power Protection and Power

Strips

12-22

100% Bid Documents

00 01 10-4

SECTION NO. DIVISION AND SECTION TITLES DATE

27 13 13.13 Communications Copper Cable Splicing Terminations 12-22

27 15 13 Communications Copper Horizontal Cabling 12-22

27 16 19 Communications Patch Cords, Station Cords, and Cross

Connect Wire

12-22

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18

28 05 13 Conductors and Cables for Electronic Safety and

Security

10-18

28 05 26 Grounding and Bonding for Electronic Safety and

Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security

09-11

28 08 00 Commissioning of Electronic Safety and Security Systems 11-16

28 13 00 Physical Access Control System 10-11

28 23 00 Video Surveillance 09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK – NOT USED

DIVISION 32 – EXTERIOR IMPROVEMENTS – NOT USED

DIVISION 33 – UTILITIES – NOT USED

DIVISION 34 – TRANSPORTATION – NOT USED

DIVISION 48 – Electrical Power Generation – NOT USED

100% Bid Documents

Version 05-01-20

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWINGS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

SITE PLANNING

G0.0 COVER SHEET

ARCHITECTURAL

AE001 ARCHITECTURAL – LIFE SAFETY PLAN

AE002 ARCHITECTURAL – STANDARDS, NOTES, & DETAILS

AE114 ARCHITECTURAL – CONSTRUCTION OPERATAIONS,

STAGING, AND LAYDOWN AREA

AD101 ARCHITECTURAL – LEVEL 02 – DEMOLITION RCP

AD102 ARCHITECTURAL - LEVEL 03 – DEMOLITION FLOOR

PLAN

AD103 ARCHITECTURAL - LEVEL 03 – DEMOLITION RCP

HL100 ARCHITECTURAL – HAZARDOUS MATERIALS LEAD

AE112 ARCHITECTURAL – LEVEL 03 – NEW WORK

AE113 ARCHITECTURAL – LEVEL 03 – NEW WORK – FURNITURE

PLAN

AE115 ARCHITECTURAL – SAFETY LADDER DETAILS

AE401 ARCHITECTURAL – ELEVATIONS AND DETAILS

AE601 ARCHITECTURAL – DOOR SCHEDULE, WALL TYPES, ROOM

FINISH

AE701 ARCHITECTURAL – LEVEL 02 – RENOVATION RCP AND

DETAILS

AE702 ARCHITECTURAL – LEVEL 03 – NEW WORK – RCP AND

DETAILS

AE901 ARCHITECTURAL – MILLWORK SECTIONS & DETAILS

FIRE PROTECTION

FA001 FIRE ALARM - SYMBOLS, NOTES & DRAWING INDEX

FA002 FIRE ALARM - DETAILS

FA003 FIRE ALARM - INPUT/OUTPUT MATRIX

FA004 FIRE ALARM – INTERIM FIRE & MISC. REQUIREMENTS

00 01 15 - 2

FA100 FIRE ALARM – LEVEL 03 - DEMOLITION

FA101 FIRE ALARM – LEVEL 03 – NEW WORK

FA111 FIRE ALARM - NEW WORK

FX001 FIRE SUPPRESSION – GENERAL NOTES AND LEGENDS

FX002 FIRE SUPPRESSION - DETAILS

FX003 FIRE SUPPRESSION – FIRE PUMP TEST RESULTS AND

SEISMIC DETAILS

FX004 FIRE ALARM – IMPARIEMENT & INTERIM REQUIREMENTS

FX100 FIRE SUPPRESSION – LEVEL 03 - DEMOLITION

FX101 FIRE SUPPRESSION – LEVEL 03 - NEW WORK

PLUMBING

P001 PLUMBING - SYMBOLS, NOTES, DETAILS AND DRAWING

INDEX

PP100 PLUMBING - LEVEL 03 – NEW WORK –SANITARY

PP101 PLUMBING - LEVEL 03 – NEW WORK – DOMESTIC

MECHANICAL

M001 MECHANICAL - SYMBOLS, NOTES AND DRAWING INDEX

M002 MECHANICAL - DETAILS

M003 MECHANICAL - SCHEDULES

M004 MECHANICAL – AHU CONTROL SCHEMATICS

MD100 MECHANICAL – LEVEL 03 – DEMOLITION - DUCTWORK

MH100 MECHANICAL - LEVEL 03 – NEW WORK - DUCTWORK –

OVERALL

MH100A MECHANICAL - LEVEL 03 – NEW WORK - DUCTWORK –

AREA A

MH100B MECHANICAL - LEVEL 03 – NEW WORK – DUCTWORK -

AREA B

MP100 MECHANICAL - LEVEL 03 – NEW WORK - PIPING

ELECTRICAL

E001 ELECTRICAL – SYMBOLS, NOTES & DRAWING INDEX (1

OF 2)

E002 ELECTRICAL - SYMBOLS, NOTES & DRAWING INDEX (1

OF 2)

00 01 15 - 3

E003 ELECTRICAL – DETAILS

E004 ELECTRICAL – PANEL SCHEDULES

E005 ELECTRICAL – POWER RISER AND LUMINARE SCHEDULE

ED100 ELECTRICAL – LEVEL 03 - DEMOLITION

EL100 ELECTRICAL - LEVEL 03 – NEW WORK – LIGHTING –

OVERALL

EL100A ELECTRICAL - LEVEL 03 – NEW WORK – LIGHTING –

AREA A

EL100B ELECTRICAL - LEVEL 03 – NEW WORK – LIGHTING –

AREA B

EP100 ELECTRICAL - NEW WORK – POWER - OVERALL

EP100A ELECTRICAL - NEW WORK – POWER – AREA A

EP100B ELECTRICAL - NEW WORK – POWER – AREA b

EY100 ELECTRICAL – NEW WORK – TELECOMMUNICATIONS

OVERALL

EY100A ELECTRICAL – NEW WORK – TELECOMMUNICATIONS –

AREA A

EY100B ELECTRICAL – NEW WORK – TELECOMMUNICATIONS –

AREA B

- - - E N D - - -

01 00 00 -1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the renovations to the 3rd floor of building 3 at WBJ Dorn Medical Center in

Columbia, SC, as required by drawings and specifications.

B. Normal working hours for this contract will be from 7:00AM to

4:30PM (local time) Monday through Friday except for weekends and established Federal Holidays.

C. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.

D. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the

Contracting Officer.

E. Offices of O’Dell International, GMK Associates, and Charlotte

Engineers, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

F. Refer to individual specification sections for any testing requirements. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans

01 00 00 -2

Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

G. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID: Work includes interior renovations work including (but not limited to) general construction, alterations, ,necessary removal and/or replacement of existing construction, new construction, mechanical, electrical, plumbing, fire protection, interior finishes and certain other items.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at

Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

01 00 00 -3

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the

Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall install all permanent cores at completion of the work turn over all permanent lock cylinders to the VA locksmith for permanent installation.

D. Document Control:

1. Before starting any work, the General Contractor/Sub

Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or

“Sensitive Unclassified”. Secure such information in separate

01 00 00 -4 containers and limit the access to only those who will need it for the project. Return the information to the Contracting

Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of

Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the

VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an

Engineering Document Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted

24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of permits shall be issued for General

Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility

Manager.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved

01 00 00 -5 by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the

Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the

Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the

Contracting Officer, use only established roadways.. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR .

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

01 00 00 -6

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by

Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to

Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR .

All such actions shall be coordinated with the COR or Utility

Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

01 00 00 -7

J. The entire building, except within the areas of construction, will be occupied during performance of work ; but immediate areas of alterations will be vacated.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by

Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

2. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.

01 00 00 -8

L. When a building and/or construction site is turned over to

Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of (65 degrees

F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company

(Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for

Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR.

Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the

Medical Center Director’s prior knowledge and written approval.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

01 00 00 -9

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center

. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

01 00 00 -

VAMC Columbia Bldg. 3 VA Project 544-22-703

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting

Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled

"DIFFERING SITE CONDITIONS" and "CHANGES".

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

01 00 00 -10

1. Re-survey report shall also list any damage caused by

Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by

COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract

01 00 00 -11 shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The

Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or

01 00 00 -12 specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems

(including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price.

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

01 00 00 -13

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the CORwithin

15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.12 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to Warranty of

Construction at least 30 days before the planned pre-warranty conference, submit two paper sets and a electronic set (.PDF searchable format and original file format) of the warranty management plan to the COR. Scanned or other non-searchable files will not be acceptable formats. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period.

B. The contractor shall be responsible for completing and submitting all warranty initiation and registration paperwork, forms, data, photos, reports, or any other kind of required documentation to each manufacturer, supplier, vendor, or contractor needed to establish the warranty.

01 00 00 -14

C. All warranties shall by fully established and commence at the time of project acceptance. Contact the COR if government signatures are required for initiating any specific warranty.

D. The contractor shall be fully and financially responsible for any and all denied warranty claims, including the associated repair and impact costs, resulting from improper warranty registration.

E. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer Representative.

F. Organize the warranty management plan in three sections as shown below: Section 1, Section 2, Section 3.

G. Include in the warranty management plan, but not limited to, the following:

1. Section 1 –

1. A cover page that contains a heading stating, “Warranty

Management Plan”, and project number, and project title, Prime Contractor Company with point of contact information, project acceptance date, and the warranty start date.

2. The warranty management process in terms of who to call during the first-year post construction acceptance and following extended warranty. Include language and requirements as indicated in section “Contractor’s

Response to Construction Warranty Service Requirements.”

3. A summary table of contents of all warrantied equipment that includes the Equipment name, specification division, page number location of the equipment sheet.

Separate and organize the table of contents by specification division.

4. Floor plans indicating the location of all warrantied items.

01 00 00 -15

5. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the

Contractor, subcontractors, manufacturers, or suppliers involved.

6. A warranty initiation form that will be submitted by the government to the contractor upon initiation of a warranty action.

7. A warranty action status sheet that shows the nature of the warranty action, the date of the notification, the date of the contractor’s response, a “responded by” field to indicate the contractor’s point of contact, an area for capturing notes, and the warranty completion date.

8. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

9. Listing and status of delivery of all Certificates of

Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

2. Section 2 - An individual equipment sheet for each item of warranted equipment, feature of construction or system.

Each individual equipment sheet shall include:

1. The equipment name of item.

2. The model and serial numbers.

3. The location where installed to include building number, room number, and special location such as above ceiling or otherwise not directly visible area.

01 00 00 -16

4. A picture of each individual piece of equipment indicating the location in the area with the intent to be able to quickly identify and access the location upon entering the room.

5. A picture of each equipment tag associated with each item of equipment.

6. The name and phone numbers of manufacturers or suppliers.

7. The names, addresses and phone numbers of sources of spare parts.

8. The warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

9. The starting point and duration of warranty period.

10. The summary of maintenance procedures required to continue the warranty in force.

11. The cross-reference to specific pertinent Operation and

Maintenance manuals.

12. The organizations, names and phone numbers of persons to call for warranty service.

13. The typical response time and repair time expected for various warranted equipment.

3. Section 3 –

1. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

2. Section 3 - Procedure and status of tagging of all equipment covered by extended warranties.

01 00 00 -17

3. Section 3 - Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

4. Separate all sections and individual equipment sheets by tabbed dividers for all paper copies of warranty management plans. Collect and organize all paper files in three-ring binders sized to hold 8.5-inch by 11-inch paper size. Oversized paper must be neatly folded to within the

8.5 inch by 11-inch paper size such that no paper protrudes outside the binder.

5. Separate all sections and individual equipment sheets by bookmarks labeled by the equipment name for all electronic versions of the warranty management plan. Electronic files shall be provided through the contractor’s electronic file transfer system and two copies on DVD medium mailed or hand delivered to the COR.

H. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall

01 00 00 -18 respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the

Contractor.

I. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response for items not identified in section F, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the

Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

J. Contractor’s Response to Construction Warranty Service

Requirements: Following oral or written notification by the

Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report

01 00 00 -19 on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the

Government will perform the work and back charge the construction warranty payment item established.

1. Code Emergency - Perform onsite inspection to evaluate situation, and determine course of action within 2 hours, initiate work within 4 hours and work continuously to completion or relief.

2. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within

4 hours, initiate work within 6 hours and work continuously to completion or relief.

3. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within

8 hours, initiate work within 24 hours and work continuously to completion or relief.

4. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

5. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Windows

Broken or missing glazed panel.

b) Code 2-Windows

Water infiltration.

Air infiltration

c) Code 3-Windows

Window blinds failure

K. Warranty Tags:

01 00 00 -20

1. At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the

Contracting Officer Representative. Attach each tag with a copper wire and spray with a silicone waterproof coating.

2. Install each tag in a highly visible location as approved by the Contracting Officer Representative.

3. Submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Tags

Warranty Contact

Address

Telephone number

Warranty response time priority code

01 00 00 -21

1.13 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on

Medical Center property. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

1.14 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.

Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned.

Vibrations must be eliminated.

01 00 00 -22

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.

1.15 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevators for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition.

2. Contractor covers and provides maximum protection of following elevator components:

a) Entrance jambs, heads soffits and threshold plates.

b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c) Finish flooring.

01 00 00 -23

3. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.

4. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.

5. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.16 TEMPORARY TOILETS

A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.

1.17 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the

Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the

01 00 00 -20 temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install any required meters at Contractor's expense and furnish the Medical Center a monthly record of the

Contractor's usage of electricity as hereinafter specified.

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for any electrical devices required.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical…