This document is a Request for Proposal (RFP) for a Sterile Processing Services (SPS) addition at the Sioux Falls VA Health Care System in South Dakota. The project involves constructing approximately 8,916 square feet of new space and renovating 2,730 square feet of existing space in Building 5, located at 2501 West 22nd Street. The new addition will include an interstitial/mechanical space with the same footprint as the SPS area and is designed to be adjacent to the existing operating room addition.
The comprehensive technical specifications cover multiple construction divisions, including site work, demolition, concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, furnishings, and building systems. The project will require extensive coordination, with specific attention to safety requirements, environmental controls, waste management, and sustainable construction practices. The technical documents include detailed drawings, specifications for materials and installation, and requirements for quality control, commissioning, and final documentation. The solicitation indicates the project is part of VA Project Number 438-460, with Anderson Engineering of Minnesota, LLC serving as the primary design consultant.
View the file
Other files
Show 40 more
Latest 50 of 61 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anderson Engineering of Minnesota, LLC 13605 1st Avenue North
Plymouth, MN 55441 Phone: 763-412-4000 Fax: 763-412-4090
Prepared in association with the following:
IMEG CORPERATION ENGINEERING
VAMC SIOUX FALLS
CONSTRUCT NEW STERILE PROCESSING
SERVICES (SPS)
VA PROJECT NUMBER: 438-460
2501 WEST 22ND STREET
SIOUX FALLS, SD. 57105
TECHNICAL SPECIFICATIONS VOL I
ANDERSON ENGINEERING OF MN, LLC
Project Number: 16584
Issue for Bid Documents
14, February 2025
Sioux Falls VAHCS, Sioux Falls, SD VA Project 438-460 Construct Sterile Processing Service Addition 02/14/2025 2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 10-1 Table of Contents
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS VOLUME 1
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 06-21 01 35 26 Safety Requirements 11-21 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 11-21 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 01-21 02 41 00 Demolition 08-17 02 82 11 Traditional Asbestos Abatement 01-21 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 01-21 04 05 13 Masonry Mortaring 10-17 04 20 00 Unit Masonry 08-17 04 72 00 Cast Stone Masonry 01-21
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18 05 36 00 Composite Metal Decking 01-21
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 10-2 Table of Contents
SECTION NO. DIVISION AND SECTION TITLES DATE
05 40 00 Cold-Formed Metal Framing 01-21 05 50 00 Metal Fabrications 08-18 05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 08 00 Facility Exterior Closure Commissioning 01-21 07 13 52 Modified Bituminous Sheet Waterproofing 01-21 07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21 07 40 00 Siding Panels 01-21 07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 71 00 Roof Specialties 01-21 07 72 00 Roof Accessories 01-21 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 21 00 Impact Resistant Doors 08 22 00 Fiberglass Reinforced Plastic (FRP) Doors and Frames 08 31 13 Access Doors and Frames 01-21 08 44 13 Glazed Aluminum Curtain Walls 04-20 08 51 13 Aluminum Windows 01-21 08 71 00 Door Hardware 01-21 08 71 13 Automatic Door Operators 01-21 08 80 00 Glazing 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 30 00 Specialty Moldings and Trims 09 30 13 Ceramic/Porcelain Tiling 01-21 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 05-18 09 67 00 Architectural Solid Coatings 12-21
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 10-3 Table of Contents
SECTION NO. DIVISION AND SECTION TITLES DATE
09 67 23.30 Resinous (Epoxy Base) High Performance Flooring 01-21 09 67 26 Methyl-methacrylate Based Self-leveling Flooring
System with a Decorative Flake Broadcast 01-21
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES
10 21 13 Toilet Compartments 01-21 10 26 00 Wall and Door Protection 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21 10 44 13 Fire Extinguisher Cabinets 08-18 10 51 16 HDPE Lockers
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 12 31 00 Manufactured Metal Casework 12 32 00 Manufactured Wood Casework 01-21 12 36 00 Countertops 12-18
Appendix A Geotechnical Engineering Report Appendix B Hazardous Materials Inspection Report
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 15 - 1
LIST OF DRAWING SHEETS
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GI000 COVER SHEET
GI001 SHEET INDEX
GI002 ABBREVIATIONS
GI101 GROUND LEVEL LIFE SAFETY PLAN
GI111 INTERSTITIAL/FIRST LEVEL LIFE SAFETY PLAN
GC101 GROUND LEVEL INFECTION CONTROL & LIFE SAFETY
PLAN
GC111 FIRST LEVEL INFECTION CONTROL & PHASING PLAN
VB101 SITE SURVEY & MAPPING
CD101 DEMOLITION PLAN
CS101 SITE LAYOUT PLAN
CG101 GRADING PLAN
CG102 EROSION CONTROL PLAN
CU101 UTILITY PLAN
CU103 SANITARY SEWER PLAN AND PROFILE
CU104 STORM SEWER PLAN AND PROFILE
CU105 STORM SEWER PLAN AND PROFILE
CU106 WATER LINE PLAN AND PROFILE
CP101 PAVING & JOINT LAYOUT PLAN
C-501 RAMP SITE DETAILS
C-502 STAIRS SITE DETAILS
C-503 RETAINING WALL SITE DETAILS
C-504 CIVIL DETAILS
C-505 CIVIL DETAILS
C-506 CIVIL DETAILS
C-507 CIVIL DETAILS
LP101 PLANTING PLAN
LP501 PLANTING DETAILS
LF101 SITE FURNISHINGS PLAN
LF501 SITE FURNISHINGS DETAILS
LF502 SITE FURNISHINGS DETAILS
IR101 IRRIGATION PLAN
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 15 - 2
LIST OF DRAWING SHEETS
IR501 IRRIGATION DETAILS
IR502 IRRIGATION DETAILS
IR503 IRRIGATION DETAILS
IR504 IRRIGATION DETAILS
SG000 GENERAL NOTES
SG001 TESTING SCHEDULES
SB100 PARTIAL BASEMENT FOUNDATION PLAN
SB101 GROUND LEVEL FOUNDATION PLAN
SB102 GROUND LEVEL COLUMN LOADS
SB103 ENLARGED PLANS AND SECTIONS
SB200 SECTIONS - FOUNDATION
SB201 SECTIONS - FOUNDATION
SF102 FIRST FLOOR & ROOF FRAMING PLAN
SF103 ROOF FRAMING PLAN
SF210 SECTIONS - FLOOR
SF220 SECTIONS - ROOF
SF221 SECTIONS - ROOF
SF230 BRACE FRAME ELEVATIONS & SECTIONS
HA101 ASBESTOS CONTAINING MATERIALS
HA102 LEAD CONTAINING MATERIAL
AD101 GROUND LEVEL DEMOLITION PLAN
AD111 INTERSTITIAL/FIRST LEVEL DEMOLITION PLAN
AD520 DEMOLITION WALL SECTIONS AND DETAILS
AE101 GROUND LEVEL FLOOR PLAN
AE102 GROUND LEVEL DIMENSION PLAN
AE111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN
AE112 INTERSTITIAL/FIRST LEVEL DIMENSION PLAN
AC101 GROUND LEVEL REFLECTED CEILING PLAN
AC111 INTERSTITIAL/FIRST LEVEL REFLECTED CEILING PLAN
AE121 ROOF PLAN
AE201 EXTERIOR ELEVATIONS
AE211 INTERIOR ELEVATIONS
AE212 INTERIOR ELEVATIONS
AE301 BUILDING SECTIONS
AE302 BUILDING SECTIONS
AE311 WALL SECTIONS
AE312 WALL SECTIONS
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 15 - 3
LIST OF DRAWING SHEETS
AE313 WALL SECTIONS
AE314 WALL SECTIONS
AE320 STAIR SECTIONS AND ENLARGED PLANS
AE321 STAIR SECTIONS AND ENLARGED PLANS
AE322 STAIR SECTIONS - PARTITIONS AT EXISTING STAIR
AE411 ENLARGED PLANS & INTERIOR ELEVATIONS
AE412 ENLARGED PLANS & INTERIOR ELEVATIONS
AE413 ENLARGED PLAN, SECTIONS AND DETAILS - CART WASH
AE501 EXTERIOR PLAN DETAILS
AE502 EXTERIOR PLAN DETAILS
AE503 EXTERIOR PLAN DETAILS
AE520 EXTERIOR SECTION DETAILS
AE521 EXTERIOR SECTION DETAILS
AE530 ROOF DETAILS
AE531 ROOF DETAILS
AE540 INTERIOR PLAN DETAILS
AE541 INTERIOR PLAN DETAILS
AE542 INTERIOR PLAN DETAILS
AE543 INTERIOR PLAN DETAILS
AE550 INTERIOR SECTION DETAILS
AE551 INTERIOR SECTION DETAILS
AE552 INTERIOR SECTION DETAILS
AE560 CEILING DETAILS
AE601 INTERIOR PARTITION TYPES AND DETAILS
AE602 DOOR SCHEDULE AND ELEVATIONS, CAST STONE
PROFILES AND WINDOW TYPES
AE640 MOUNTING HEIGHTS
AF101 FINISH PLANS
AF102 GROUND LEVEL WALL PROTECTION PLAN
AF600 ROOM FINISH SCHEDULE AND INTERIOR FINISH DETAILS
AW101 GROUND LEVEL WAYFINDING PLAN
AW601 WAYFINDING MESSAGE SCHEDULES & SIGNAGE DETAILS
QH101 GROUND LEVEL EQUIPMENT PLAN & SCHEDULE
QH411 ENLARGED EQUIPMENT PLAN & SCHEDULE
FP000 FIRE PROTECTION COVERSHEET
FPD101 GROUND LEVEL DEMOLITION PLAN - FIRE PROTECTION
FP101 GROUND LEVEL FLOOR PLAN - FIRE PROTECTION
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 15 - 4
LIST OF DRAWING SHEETS
FP111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - FIRE
PROTECTION
FP400 FIRE PROTECTION DETAILS
M000 MECHANICAL COVERSHEET
MC000 CONTROLS COVER SHEET
MC101 GROUND LEVEL FLOOR PLAN - CONTROLS
MC102 FIRST LEVEL FLOOR PLAN - ROOM PRESSURIZATION
PLAN
MC111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - CONTROLS
MC121 ROOF PLAN - CONTROLS
MC400 CONTROL DIAGRAMS
MC401 CONTROL DIAGRAMS
MC402 CONTROL DIAGRAMS
MC403 CONTROL DIAGRAMS
MC404 CONTROL DIAGRAMS
MP000 PIPING COVERSHEET
MPD091 PIPE BASEMENT DEMOLITION PLAN - PIPING
MPD101 GROUND LEVEL FLOOR DEMOLITION PLAN - PIPING
MPD111 FIRST LEVEL DEMOLITION PLAN - PIPING
MPD151 FIFTH LEVEL DEMOLITION PLAN - PIPING
MP091 PIPE BASEMENT FLOOR PLAN - PIPING
MP101 GROUND LEVEL FLOOR PLAN - PIPING
MP111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - PIPING
MP121 ROOF PLAN - PIPING
MP400 PIPING DETAILS
MP401 PIPING DETAILS
MP500 STEAM FLOW DIAGRAM
MP501 HEATING WATER FLOW DIAGRAM
MP502 CHILLED WATER FLOW DIAGRAM
MP600 PIPING SCHEDULES
MV000 VENTILATION COVERSHEET
MVD091 PIPE BASEMENT DEMOLITION PLAN - VENTILATION
MVD102 GROUND LEVEL FLOOR DEMOLITION PLAN - VENTILATION
MVD112 FIRST LEVEL DEMOLITION PLAN - VENTILATION
MV091 PIPE BASEMENT FLOOR PLAN - VENTILATION
MV101 GROUND LEVEL FLOOR PLAN - VENTILATION
MV111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN -
VENTILATION
MV121 ROOF PLAN - VENTILATION
MV300 VENTILATION ENLARGED PLANS
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 15 - 5
LIST OF DRAWING SHEETS
MV301 VENTILATION ENLARGED PLANS
MV400 VENTILATION DETAILS
MV401 VENTILATION DETAILS
MV402 VENTILATION DETAILS
MV600 VENTILATION SCHEDULES
PL000 PLUMBING COVERSHEET
PLD100 PIPE BASEMENT DEMOLITION PLAN - PLUMBING
PLD101 GROUND LEVEL FLOOR DEMOLITION PLAN - PLUMBING
PLD111 FIRST LEVEL DEMOLITION PLAN - PLUMBING
PL100 PIPE BASEMENT AND UNDERFLOOR - PLUMBING
PL101 GROUND LEVEL FLOOR PLAN - PLUMBING
PL111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - PLUMBING
PL121 ROOF PLAN - PLUMBING
PL300 PLUMBING ENLARGED PLANS
PL400 PLUMBING DETAILS
PL401 PLUMBING DETAILS
PL500 PLUMBING FLOW DIAGRAMS
PL600 PLUMBING MATERIAL LISTS
E000 ELECTRICAL COVERSHEET
FA001 ELECTRICAL FIRE-ALARM COVERSHEET
ES-100 NEW ELECTRICAL SITE PLAN
ED101 GROUND LEVEL FLOOR DEMOLITION PLAN - ELECTRICAL
ED121 ROOF DEMOLITION PLAN - ELECTRICAL
EL101 GROUND LEVEL FLOOR PLAN - LIGHTING
EL111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - LIGHTING
EP101 GROUND LEVEL FLOOR PLAN - POWER
EP102 PARTIAL GROUND LEVEL FLOOR PLAN - POWER
EP111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - POWER
EP121 ROOF PLAN - POWER
EP151 FIFTH LEVEL FLOOR PLAN - POWER
FA101 GROUND LEVEL FLOOR PLAN - FIRE ALARM
FA111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN - FIRE ALARM
E400 ELECTRICAL DETAILS
E401 ELECTRICAL DETAILS
E402 ELECTRICAL DETAILS
E500 ELECTRICAL ONE-LINE DIAGRAMS
E501 ELECTRICAL ONE-LINE DIAGRAMS
E600 ELECTRICAL SCHEDULES
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
00 01 15 - 6
LIST OF DRAWING SHEETS
E601 ELECTRICAL SCHEDULES
T000 TECHNOLOGY COVERSHEET
T001 GROUND LEVEL OVERALL PLAN -TECHNOLOGY
T002 LEVEL 01 OVERALL PLAN -TECHNOLOGY
TD101 GROUND LEVEL FLOOR DEMOLITION PLAN - TECHNOLOGY
T101 GROUND LEVEL FLOOR PLAN - TECHNOLOGY
T111 INTERSTITIAL/FIRST LEVEL FLOOR PLAN -TECHNOLOGY
T300 TECHNOLOGY ROOM ENLARGEMENTS
T400 TECHNOLOGY DETAILS
T500 TECHNOLOGY RISER DIAGRAMS
T600 TECHNOLOGY SCHEDULES
- - - END - - -
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -1
GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of portions of existing structure, site construction and furnish labor and materials, equipment, management, supervision, tools and all other necessary resources and perform work to construct a Sterile Processing Service Addition to Building 5 of approximately 8,916 SF and renovate approximately 2,730 SF of existing Building 5 ground level Microbiology Lab, complete with landscaping, parking and roadwork as required by drawings and specifications.
B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.
C. Offices of Anderson Engineering of MN. and IMEG Engineers, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -2
GENERAL REQUIREMENTS
D. Work subject to tests by testing laboratory retained by
General Contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
F. Normal working hours for this contract will be from 7:00 AM to 4:30 PM (local time) Monday through Friday except for weekends and established Federal Holidays. Performing on-site work outside normal working hours will require approval from the Contracting Officer and the Contracting
Officer’s Representative (COR). Request shall be submitted at least 72 hours prior to the requested date and at no additional cost to the Government. Approvals are subject to the availability of on-site staff.
G. Prior to commencing work, general contractor shall provide proof that an OSHA certified “competent Person” (CP) (29
CFR 1928.20.(b) (2) shall maintain a presence at the work site at any time work is being performed.
H. Training: All on site workers of the prime and subcontractors shall have completed and received a certificate of completion of the 10 hour OSHA certified
Construction Safety course or other equivalent competent
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -3
GENERAL REQUIREMENTS
training. The Construction Superintendent shall have completed and received a certification of completing the 30 hour OSHA Construction Safety course. Submit OSHA certification for all on-site workers to the COR prior to any worker beginning on-site work.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID : Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items including demolition, new site utilities, relocation of existing utilities, civil, landscape, architectural, structural, mechanical, plumbing, fire protection, electrical and telecommunications work.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -4
GENERAL REQUIREMENTS
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees.
This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The
General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation . See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -5
GENERAL REQUIREMENTS
1. Before starting any work, the General Contractor/Sub
Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or
“Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of
“sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an
Engineering Document Management Software (EDMS).
a) Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -6
GENERAL REQUIREMENTS
b) “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.
Access shall be restricted to picking up and dropping off materials and supplies.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The
Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the
Contracting Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the
Contracting Officer, use only established roadways, or use
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -7
GENERAL REQUIREMENTS
temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and
Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -8
GENERAL REQUIREMENTS
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of
Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
G. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
The work to be outlined shall include, but not be limited to:
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -9
GENERAL REQUIREMENTS
To ensure such executions, Contractor shall furnish the
COR with a schedule of approximate, phasing and dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing and dates to ensure accomplishment of this work in successive phases mutually agreeable to the COR. Access to occupied spaces will be limited. This may require the sequencing of the Work in many rooms on multiple occasions, potentially requiring completion during hours outside of normal business hours when spaces are occupied. The sequencing of access to spaces will be coordinated with the COR.
H. Part of Building #5 will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to Proceed and turned over to
Contractor.
1. OR Suite will be occupied during the performance of work.
Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -10
GENERAL REQUIREMENTS
access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by
Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
I. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade.
Remove the fence when directed by COR.
J. When a building and/or construction site is turned over to
Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -11
GENERAL REQUIREMENTS
Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
K. Utilities Services: Maintain existing utility services for
Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems
(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR [Chief Engineer] [Chief of Facilities
Management]. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center
Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK
RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -12
GENERAL REQUIREMENTS
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center . Interruption time approved by
Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the
Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -13
GENERAL REQUIREMENTS
shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions;
so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of
VA Supply Service, of buildings areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the
Contracting Officer. This report shall list by rooms and spaces:
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -14
GENERAL REQUIREMENTS
1. Existing condition and types of flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by
Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING
SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-
4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved.
They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -15
GENERAL REQUIREMENTS
surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by
Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the
Government are identified by attached tags or noted on drawings or in specifications as items to be stored.
Items that remain property of the Government shall be
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -16
GENERAL REQUIREMENTS
removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the
Contractor and be removed by Contractor from Medical
Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government.
When rooms and spaces are vacated by the Department of
Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the
Government in advance of work to avoid interfering with
Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS (FAR 52.236-9)
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -17
GENERAL REQUIREMENTS
limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting
Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The
Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL
CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage
Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -18
GENERAL REQUIREMENTS
it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by
Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA – SOIL CONDITIONS
A. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -19
GENERAL REQUIREMENTS
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by GEOTEK ENGINEERING & TESTING SERVICES, INC.
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings.
Logs of subsurface exploration are shown diagrammatically in the Geotechnical Report.
C. A copy of the soil report, is an appendix to these specifications and will be made available for inspection by bidders upon request to the Contracting Officer and COR at the VA Medical Center, Sioux Falls, SD and shall be considered part of the contract documents.
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the
Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -20
GENERAL REQUIREMENTS
a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting
Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, are in accordance with lines and elevations shown on contract drawings.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -21
GENERAL REQUIREMENTS
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer.
Furnish such certification to the COR before any work
(such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.
Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -22
GENERAL REQUIREMENTS
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty-foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying
Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -23
GENERAL REQUIREMENTS
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21
Warranty of Construction at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting
Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the
Contactor and the Contracting Officer. Include in the
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -24
GENERAL REQUIREMENTS
warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the
Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of
Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -25
GENERAL REQUIREMENTS
have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and
Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment
Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the
2501 West 22nd St. Bid Documents Sioux Falls, SD 57105
01 00 00 -26
GENERAL REQUIREMENTS
work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the
Government at the contractor’s expenses, the Contracting
Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .