This document is a First Level Infection Control and Construction Barrier & Phasing Plan drawing for a VA project to construct a new Sterile Processing Services (SPS) space at the Sioux Falls VA Health Care System. The drawing provides detailed infection control requirements and construction phasing guidelines for the project, which involves approximately 8,500 square feet of new construction and 2,300 square feet of renovation adjacent to the operating room in Building 5.
The plan includes comprehensive Infection Control Risk Assessment (ICRA) details, specifying construction activity types (Type A-D), risk groups (Group 1-4), and control procedure classes (I-IV). Key requirements include maintaining negative air pressure, using HEPA filtration, establishing construction barriers, controlling dust migration, and ensuring continuous hospital operations during construction. The document outlines specific protocols for different construction activities, emphasizing patient safety and minimizing infection risks during the renovation and expansion process.
View the file
Other files
Show 40 more
Latest 50 of 61 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
121A
STAIR #5
TOILET
WORK
ROOM
PROCEDURE
ROOM
TOILET
CORRIDOR
MECH
SOILED
CLEAN
M.H.
ELEC
WORK
ROOM
WAITING128
RECEPTION
129A
HAC
STAIR #4 131
Room
131A Room
120A Room
126B
STAIR
TELECOM
111A
MECHANICAL
INTERSTITIAL
SPACE
126A
MECHANICAL
CONSTRUCTION / ICRA BARRIER
CONSTRUCTION / ICRA BARRIER
1 HOUR ICRA/CONSTRUCTION BARRIER.
1 HOUR ICRA/CONSTRUCTION BARRIER DOOR.
LIMITS OF CONSTRUCTION
CONSTRUCTION /
ICRA BARRIER.
CONTRACTOR TO
COORDINATE
INTERIM LIFE
SAFETY WITH
COR.
NOTE:
PROVIDE 1 HOUR FIRE RATED, STARC SYSTEMS FIREBLOCK WALL PANELS OR
APPROVED EQUAL FOR ALL ICRA/CONSTRUCTION BARRIERS.
WHERE CEILING IS COMPLETELY REMOVED, MODIFY SPRINKLER SYSTEM SO HEADS ARE
UPTURNED AND EXTENDED TO 18" OF STRUCTURE. REPLACE HEAD(S) TYPE AS REQUIRED.
SPRINKLER SYSTEM, WHERE EXISTING, ARE TO REMAIN IN SERVICE THROUGHOUT
CONSTRUCTION. CONTRACTOR MUST INSTALL FIRE PROTECTION SYSTEM AS
CONSTRUCTION PROGRESSES. ONCE INSTALLED SYSTEM MUST BE ACTIVATED EVEN IF
PENDING ACCEPTANCE.
PROVIDE MOBILE ICRA CARTS AS NEEDED TO ACCOMPLISH WORK OR AS DIRECTED BY COR.
PHASE - ALL:
CONSTRUCTION PROJECT ACTIVITY TYPE - D
INFECTION CONTROL RISK GROUP - GROUP 4: HIGH RISK
CONTROL PROCEDURE CLASS - IV
INFECTION CONTROL RISK ASSESSMENT (ICRA) BY
PROJECT AREA USE AND PHASE
CONSTRUCTION INFECTION CONTROL RISK ASSESSMENT (ICRA)
TYPE A
TYPE B
TYPE C
TYPE D
INSPECTIONS AND NON-INVASIVE ACTIVITIES. INCLUDES, BUT NOT
LIMITED TO, REMOVAL OF CEILING TILES FOR VISUAL INSPECTION
LIMITED TO 1 TILE PER 50 SQUARE FEET, PAINTING BUT NOT SANDING
WALL COVERING, ELECTRICAL TRIM WORK, MINOR PLUMBING, AND
ACTIVITIES WHICH DO NOT GENERATE DUST OR REQUIRE CUTTING OF
WALLS OR ACCESS TO CEILINGS OTHER THAN FOR VISUAL INSPECTION.
SMALL SCALE, SHORT DURATION ACTIVITIES WHICH CREATE MINIMAL
DUST. INCLUDES, BUT IS NOT LIMITED TO, INSTALLATION OF TELEPHONE
AND COMPUTER CABLING, ACCESS TO CHASE SPACES, CUTTING OF
WALLS OR CEILING WHERE DUST MIGRATION CAN BE CONTROLLED.
FLOOR COVERING REMOVAL (WITHOUT SANDING OR GRINDING).
ANY WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR
REQUIRES DEMOLITION OR REMOVAL OF ANY FIXED BUILDING
COMPONENTS OR ASSEMBLIES. INCLUDES, BUT IS NOT LIMITED TO,
SANDING OF WALL FOR PAINTING OR WALLCOVERING, REMOVAL OF
FLOOR COVERINGS, CEILING TILES AND CASEWORK, NEW WALL
CONSTRUCTION, MINOR DUCTWORK OR ELECTRICAL WORK ABOVE
CEILINGS, MAJOR CABLING ACTIVITIES, AND ANY ACTIVITY WHICH
CANNOT BE COMPLETED WITHIN A SINGLE WORK SHIFT. FLOOR
COVERING REMOVAL (WITH SANDING OR GRINDING).
MAJOR DEMOLITION AND CONSTRUCTION PROJECTS. INCLUDES, BUT IS
NOT LIMITED TO, ACTIVITIES WHICH REQUIRE CONSECUTIVE WORK
SHIFTS, REQUIRE HEAVY DEMOLITION OR REMOVAL OF A COMPLETE
CEILING SYSTEM, FLOORING AND NEW CONSTRUCTION.
GROUP 1
LOW RISK
• MECHANICAL SPACES: AREAS NOT DIRECTLY ADJACENT TO PATIENT
CARE, INCLUDING INTERSTITIAL SPACES.
• ENGINEERING OR EMS OFFICE/WORK AREAS
• OFFICE AREAS: AREAS NOT ATTACHED TO/ADJOINING PATIENT CARE
AREAS, NOT USED FOR PATIENT INTERVIEWS, EVALUATIONS OR
EXAMINATIONS.
• PUBLIC CORRIDORS: SPACES NOT ON OR DIRECTLY ATTACHED TO
PATIENT UNITS OR TREATMENT LOCATIONS.
GROUP 2
MEDIUM
RISK
• OUTPATIENT AREAS:
1. PRIMARY CARE OR SPECIALTY CARE CLINIC AREAS
2. BEHAVIORAL/MENTAL HEALTH AREAS
3. EXTENDED CARE / REHAB CLINIC AREAS
4. COMMUNITY BASED OUT PATIENT CLINICS (CBOC’S)
GROUP 3
HIGH RISK
• IN-PATIENT UNITS:
1. INCLUDING, BUT NOT LIMITED TO: EMERGENCY DEPT.; NURSING
UNITS; RADIOLOGY/MRI/CT/ULTRASOUND; NUCLEAR MEDICINE;
CAFETERIA/KITCHEN/CANTEEN; LABORATORIES; RADIATION /
ONCOLOGY; DIALYSIS
GROUP 4
HIGHEST
RISK
• ICU/SICU
• OR/PACU/ENDOSCOPY
• GI
• STERILE PROCESSING SERVICES (SPS)
• PHARMACY
• CATH LAB
CLASS
I
KEEP AREAS FREE OF DEBRIS, TRASH
EXECUTE WORK TO MINIMIZE OF DUST MIGRATION (E.G. WET MOPPING, HEPA VACUUM)
IMMEDIATELY REPLACE ANY CEILING TILE DISPLACED FOR VISUAL INSPECTION
(INVOLVING MINOR DEMOLITION IN MAINTENANCE OR REMODELING.)
CLASS
II
SAME AS CLASS I PLUS:
1. ESTABLISH MATERIAL AND DEBRIS ROUTE USING NON-PATIENT/VISITOR PATHWAY
2. WATER MIST WORK SURFACE TO CONTROL DUST WHILE CUTTING OR DRILLING.
3. BLOCK OFF AND SEAL AIR VENTS
4. SEAL UNUSED DOORS WITH PLASTIC SHEATHING AND DUCT TAPE.
5. CREATE BARRIERS AS DEFINED BY INFECTION PREVENTION
6. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY COVERED CONTAINER; TAPE COVERING UNLESS SOLID LID.
7. WET MOP AND/OR VACUUM WITH HEPA FILTERED VACUUM BEFORE LEAVING WORK AREA.
8. PLACE STICKY MAT AT ALL WORK AREA ENTRANCES AND EXITS.
9. REMOVE OR ISOLATE HVAC SYSTEM IN CONSTRUCTION AREA
CLASS
III
SAME AS CLASS I AND II PLUS:
1. ISOLATE HVAC SYSTEM IN CONSTRUCTION AREA TO PREVENT DUCT SYSTEM CONTAMINATION
2. COMPLETE CRITICAL BARRIERS (I.E. SHEETROCK, PLYWOOD, PLASTIC) AT ALL CONSTRUCTION ENTRIES AND EXITS; MONITOR FOR SEAL AND TAKE IMMEDIATE
CORRECTIVE ACTION AS NEEDED
3. MAINTAIN AND MONITOR NEGATIVE AIR PRESSURE WITHIN CONSTRUCTION SITE UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS.
4. REMOVE OR ISOLATE HVAC SYSTEMS IN AREA WHERE WORK IS BEING PERFORMED.
5. CHECK AND REPLACE AIR FILTERS AS NEEDED REGULARLY
6. DO NOT REMOVE BARRIERS FROM WORK SITE UNTIL PROJECT IS COMPLETE & HAS BEEN THOROUGHLY CLEANED; REMOVE BARRIERS CAREFULLY TO MINIMIZE
SPREADING DUST. DEBRIS.
7. VACUUM WORK WITH HEPA FILTERED VACUUM.
8. WET MOP AREA WITH CLEANER/DISINFECTANT.
9. MITIGATE VIBRATION AND NOISE TO LOWEST IMPACT WHERE POSSIBLE.
10. DISPLAY ICRA AT SITE
11. SEAL HOLES, PIPES, CONDUITS AND PUNCTURES.
CLASS
IV
SAME AS CLASS I, II AND III PLUS:
1. INSPECT ADJACENT AREAS FOR DUST MIGRATION; TAKE IMMEDIATE CORRECTIVE AS NEEDED
2. USE HEPA VACUUM IN AREA PRIOR TO START OF CONSTRUCTION
3. CONSTRUCT ANTE ROOM; ALL PERSONNEL MUST ENTER THROUGH IT TO BE VACUUMED USING HEPA VACUUM BEFORE LEAVING OR TO DON/DOFF PPE
INFECTION CONTROL &
CONSTRUCTION BARRIER
GENERAL NOTES
1. SEE SPEC SECTION 01 35 26 SAFETY REQUIREMENTS FOR ADDITIONAL
INFORMATION
2. THE INTENT OF INFECTION CONTROL ISOLATION IS TO CONTAIN DUST AND
PARTICULATE MATTER TO THE CONSTRUCTION AREA. CONSTRUCTION AREA
PERIMETER NEEDS TO BE SEALED COMPLETELY WITH SHEET PLASTIC AS
SPECIFIED AND DUCT TAPE DURING OPERATIONS, WHERE PERMITTED BY CLASS.
ICRA - CONSTRUCTION BARRIER TO BE PROVIDED AS SPECIFIED AND LISTED IN
ICRA CLASS.
3. PROVIDE NEGATIVE PRESSURE MONITORS DURING CONSTRUCTION OPERATIONS
AS SPECIFIED. MONITOR TO MEASURE PRESSURE DIFFERENTIAL BETWEEN
CONSTRUCTION AREA AND ADJACENT CORRIDOR OR ROOM AS DIRECTED BY VA.
4. AS CONSTRUCTION PROGRESSES, FROM TYPE D TO TYPE C AND THEREON,
PROVIDE A REQUEST VIA "INFECTION CONTROL CONSTRUCTION PERMIT" TO THE
VA INFECTION CONTROL NURSE. UPON AUTHORIZATION, PROCEED TO NEXT TYPE
OF CONSTRUCTION. PROVIDE AT LEAST TEN (10) WORKING DAYS NOTICE FOR
EACH PERMIT.
5. CONSTRUCT IC (INFECTION CONTROL) CONSTRUCTION BARRIER(S) FROM FLOOR
TO DECK/FLOOR ABOVE. EXCEPTION. IF BARRIER IS ADJACENT TO SMOKE, FIRE,
OR EXISTING WALL CONSTRUCTION WHICH WILL NOT BE DEMOLISHED AND
TERMINATES TO FLOOR/DECK ABOVE, THEN CONSTRUCT DUST PROOF IC
BARRIER, SEE DETAIL(S). TAPE, MUD, SAND JOINTS AND PAINT ON NON-
CONSTRUCTION SIDE OF BARRIER.
6. CONTROL BARRIERS ARE TO BE INSTALLED AND REMOVED ONLY BEFORE 7:00 AM
AND AFTER 8:00 PM OR DIRECTED BY COR
7. DURING CONSTRUCTION OPERATIONS IN EACH ENCLOSED AREA PROVIDE
NEGATIVE PRESSURE MONITORS, MINIMUM (1) ONE IN AREAS LESS THAN 1000 SF,
(2) TWO MINIMUM IN AREAS BETWEEN 1000 SF AND 5000 SF, AND (3) THREE FOR
AREAS BETWEEN 5000 SF AND 10000 SF.
8. LIFE SAFETY EGRESS IS TO BE MAINTAINED AT ALL TIMES.
9. THE CONTRACTOR SHALL PROVIDE ENOUGH NEGATIVE AIR MACHINES TO
COMPLETELY EXCHANGE THE REGULATED AREA AIR VOLUME (4) FOUR ACTUAL
TIMES PER HOUR. THE COMPETENT PERSON SHALL DETERMINE THE NUMBER OF
UNITS NEEDED FOR EACH REGULATED AREA BY DIVIDING THE CUBIC FEET IN THE
REGULATED AREA BY (15) FIFTEEN AND THEN DIVIDING THAT RESULT BY THE
ACTUAL CUBIC FEET PER MINUTE (CFM) FOR EACH UNIT TO DETERMINE THE
NUMBER OF UNITS NEEDED TO EFFECT (4) FOUR AIR CHANGES PER HOUR.
PROVIDE A STANDBY UNIT IN THE EVENT OF MACHINE FAILURE AND/OR
EMERGENCY IN AN ADJACENT AREA.
10. PRIOR TO ANY REMOVAL OF SMOKE BARRIER FIRE RATED PARTITIONS,
CONSTRUCT NEW SMOKE BARRIER/APPROPRIATE FIRE RATED PARTITIONS PER
PLANS OR CONSTRUCT INFECTION CONTROL BARRIER TO ACT AS SMOKE
BARRIER.
CONSTRUCTION PHASING
GENERAL NOTES
1. THE WORK UNDER THIS CONTRACT SHALL BE DIVIDED INTO PHASES. A PHASE
CAN INVOLVE MULTIPLE LOCATION AREAS. SEE SPECIFICATIONS SECTION 01 00 00
1.6.G PHASING.
2. THE GENERAL CONTRACTOR SHALL COORDINATE ALL PHASING AND SEQUENCING
WITH ALL TRADES AND THE OWNER. THE GENERAL CONTRACTOR SHALL PROVIDE
A WRITTEN NARRATIVE TO OUTLINE CONSTRUCTION PHASING AND SEQUENCE
PLANS, VALIDATING AND ELABORATING ON THIS PHASING DESCRIPTION.
3. THE GENERAL CONTRACTOR SHALL COOPERATE FULLY WITH THE OWNER SO
WORK MAY BE CARRIED OUT SMOOTHLY, WITHOUT INTERFERING WITH OR
DELAYING WORK UNDER THIS CONTRACT, OR OTHER CONTRACTS ON THE
PROJECT SITE OR WORK BY OWNER.
4. THE GENERAL CONTRACTOR'S CONSTRUCTION SCHEDULE SHALL INDICATE THE
SEQUENCE, COMMENCEMENT AND COMPLETION DATES, OWNER INSPECTION AND
APPROVAL DATES AND MOVE-OUT AND MOVE-IN DATES OF OWNER'S PERSONNEL
FOR ALL PHASES OF THE WORK.
5. THE GENERAL CONTRACTOR SHALL PERFORM THE WORK IN EACH PHASE IN THE
SEQUENCE SHOWN ON THE PHASING PLAN DRAWING(S) AND CONSTRUCTION
PHASING DESCRIPTION.
6. THE GENERAL CONTRACTOR MUST COMPLETE ALL WORK IN EACH PHASE WITH
THE VA INSPECTING AND ACCEPTING THE WORK PRIOR TO VA OCCUPANCY AND
THE CONTRACTOR PROCEEDING TO THE NEXT SCHEDULED PHASE. UPON
COMPLETION OF A PARTICULAR PHASE, THE ENTIRE AREA COVERED BY THAT
PHASE CAN BE OCCUPIED BY THE VA PERSONNEL WITH ALL SYSTEMS
FUNCTIONING PROPERLY.
7. BEFORE COMMENCING WORK ON EACH SUCCESSIVE PHASE, THE GENERAL
CONTRACTOR SHALL SUBMIT AN UPDATED COPY OF THE SCHEDULE.
8. ANY ICRA / CONSTRUCTION BARRIERS CONSTRUCTED BY THE CONTRACTOR
PRIOR TO THE START OF DEMOLITION MUST REMAIN IN PLACE UNTIL THE
COMPLETION OF THAT PHASE OR SUBSEQUENT PHASE WHERE REQUIRED.
9. THE CONTRACTOR SHALL PERFORM ALL WORK ADJACENT TO VA OCCUPIED
AREAS IN SUCH A MANNER TO ENSURE THE CONTINUOUS AND UNINTERRUPTED
USE OF ALL OCCUPIED AREAS, INCLUDING THE APPLICABLE MECHANICAL AND
ELECTRICAL SYSTEMS SERVING THESE AREAS.
10. FOR ADDITIONAL NOTES AND INFORMATION REFER TO INFECTION CONTROL
DRAWING(S) AND DEMOLITION PLANS.
11. ANY INFORMATION REGARDING SEQUENCING PROVIDED IN THE DOCUMENTS IS
FOR ARCHITECT-OWNER PLANNING PURPOSES ONLY.
12. THE CONTRACTOR DURING CONSTRUCTION SHALL MAINTAIN REQUIRED MEANS
OF EGRESS THROUGHOUT ALL PHASING.
13. THE CONTRACTOR SHALL PLAN FOR A MINIMUM OF 4 WEEKS' TIME BETWEEN
PHASES TO ALLOW THE VA TO OCCUPY THE NEWLY ACCEPTED SPACE AND
VACATE THE FOLLOW-ON PHASES. THE VA WILL ACCELERATE THIS TIME WHEN
POSSIBLE AND WILL NOTIFY THE CONTRACTOR IF THIS OCCURS.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly Licensed Architect under the laws of the State of Minnesota.
Name:
Tom Olesak
Date: 02/14/2025
License Number: 18157
2882 106th St, Urbandale, IA 50322
C U s e rs
\g b a rb a ri
\D o c u m e n ts \1
-R
G io v a n n i- B a rb a ri .r v t
/2
/2
:4
:0
P
M
GC111
FIRST LEVEL INFECTION
CONTROL & PHASING PLAN
CONSTRUCT NEW SPS
Sioux Falls, SD.
438-460
02/14/2025 LA GJB16584
1/8" = 1'-0"
FIRST LEVEL ICRA, CONSTRUCTION BARRIER & PHASING PLAN
0 8' 16'4'
Revisions: Date:
ADDENDUM 1 (AD-1) 03/28/2025
ADDENDUM 3 (AD-3) 05/20/2025
AD-1
AD-3
| Sheets |
| AC101 - GROUND LEVEL REFLECTED CEILING PLAN |
| AD111 - INTERSTITIAL/FIRST LEVEL DEMOLITION PLAN |
| AE111 - INTERSTITIAL/FIRST LEVEL FLOOR PLAN |
| GC111 - FIRST LEVEL INFECTION CONTROL & PHASING PLAN |